EARNED VALUE:
EV = BAC X % Complete
SV = EV – PV
SPI = EV / PV
CV = EV – AC
CPI = EV / AC
TCPI = (BAC – EV) / (BAC – AC) or (BAC – EV) / (EAC – AC)
BOTTOM-UP FORECASTING:
ETC = New Estimate
EAC = AC + ETC
COMMUNICATION CHANNELS:
N(N-1)/2
PERT/3-POINT:
(O+4(M)+P)/6