MSOG-M2014-C-JMS-001 - For Grating Cover Installation
MSOG-M2014-C-JMS-001 - For Grating Cover Installation
PROJECT TITLE:
Grating Cover Installation, Pasir Gudang Johor
DOCUMENT TITLE:
JOB METHOD STATEMENT FOR
MSOG-M2014-C-JMS-001
CONTRACTOR SHELL
Rev Date Status
Prepared By Checked By Approved By Acknowledged By
02 September
A Issued for Approval KKL Raseen MRH SYAFIQ
2020
Corresponding Permit to Work
No.
Method Statement Rev 0
The Permit Issuer, when developing the respective Permit forms, will use the Method Statement supplied.
1. Description of works
What does the work entails? The following are the work scope: -
Mobilize of personnel and tools to work site
Site work preparation
Install prefabricated gratings in specified location
Housekeeping
How is the work going to be completed / commissioned?
Mobilize of personnel and tools to work site
Prior to mobilize personnel and tools to work site, the following activity shall take place,
Site Safety Supervisor shall screen all workers dossier and conduct safety induction.
PTW Applicant, Site Safety Supervisor and Site Supervisor shall visit the work site to
familiarize themselves with the area and any potential issues.
Site Safety Supervisor and Site Supervisor shall carry out tools and equipment
inspection prior to mobilize to work site.
PTW applicant shall apply and ensure PTW is based on work scope.
Mobilize personnel and tools to work site.
Site Supervisor (SS) and Client Representative to verify location where gratings are to
be installed prior to start works.
Site Supervisor (SS) shall direct workers unload the gratings from the lorry in specified
location manually.
Site Supervisor (SS) shall direct workers to hack drainage structure as per grating
dimension using hammer if the concrete structure is uneven.
Site Supervisor (SS) direct the workers to Install the gratings manually.
Repeat the steps for other locations.
Corresponding Permit to Work
No.
Method Statement Rev 0
Housekeeping
Site Supervisor shall direct workers to remove barricade, safety signage and
housekeeping.
Site Safety Supervisor, Site Supervisor and PTW Applicant ensure work site
housekeeping completed and accepted by Client representative.
Will the scope of work/commissioning affect the operations of the live gantry/tank farm? No
If yes, how?
What will be affected? No
Duration of the work? 8 Hour
Calendar / work days – (0830 to 1730)- Total Working Time 8 hours
Any shift works? No
Site location drawings attached? YES (refer attachment)
Usage of mobile Gas Testing equipment available? YES How many units required and where
will it/they be positioned?
1-unit personal gas detector
Are process safety equipment’s required in this project? Pressure Safety Valve (PSV)? Thermal
Corresponding Permit to Work
No.
Method Statement Rev 0
Relief Valve (TRV)? Pressure Vacuum Relief Valve (PVRV)? Others? N/A
Radiographic Testing (RT) to be done at worksite have to be highlighted to Worksite. Are they
informed 5 days in advance? NO
For HT of the tank, ensure that water is being released into the worksite drain and interceptors.
(Yes/No) NO
For HT of piping/pipelines performed in the worksite, are all pressure HT equipment’s in good
conditions? N/A
Underwater equipment’s in good operation? Airline from air source on top deck/jetty?
N/A
Qualified and certified divers? State what certification. Required 2 divers at any one time.
Acknowledged? N/A SCUBA not permitted. Acknowledged? N/A
Temporary supports to be used within Worksite? Attached sketches for the supports?
NA.
Are there any other works taking place near this area of concern? (To be filled by TOS/M)
N/A
What other works which are going on at other location of the terminals? (To be filled by TOS/M)
N/A
Safety Checks
Safety walkabout to be performed with Shell Terminal Operations? YES
Safety walkabout to be performed with Vendor/Contractor Top Management? YES
Unsafe Act Audit/ Unsafe Condition Audit to be performed? YES
Near-miss list recorded, updated and reviewed? YES
Workers’ PPE sufficient? YES
Reminder to comply to Golden Rules, Comply, Intervene, Respect. Acknowledged? YES
Reminder to achieve Shell Goal Zero targets? Acknowledged? YES
- NO FATALITY
- NO PFA (Potential Fatality Accident)
- NO SPILLAGE
- NO LSR NON-COMPLIANCE
- NO PQ (incl. CO) (Product Quality)
- NO TRC (Total Recordable Case)
- LINE OF FIRE
Reminder to comply to all the 12 Shell Life Saving Rules (LSR) at all times. Acknowledged?
YES