Professional Documents
Culture Documents
Pre-Commissioning: Appita Journal April 2013
Pre-Commissioning: Appita Journal April 2013
net/publication/298152201
Pre-commissioning
CITATIONS READS
0 5,203
1 author:
Geoff Covey
retired
71 PUBLICATIONS 322 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Geoff Covey on 01 March 2019.
PRELIMINARIES
Keywords: Commissioning, Pre-commissioning
Even before pre-commissioning begins there are
INTRODUCTION some tasks to be performed to ensure that the plant
It is not always easy to make a precise definition of is ready for pre-commissioning. The general
pre-commissioning, but broadly it covers the objective here is to check that the plant has been
activities between the mechanical completion of a assembled as intended.
plant and the when process fluids are first fed into
Typical functions at this stage will include:
the plant with the intent of making product.
‘Walking all lines’ – tracing the route of
The stage is usually characterised by the use of
all pipework to see that it runs between the
water and air (or occasionally steam) in place of
vessels it is supposed to connect. At the
process fluids, but sometimes it is more appropriate
same time look for errors in construction
to use other fluids if water in the equipment is
e.g. open flanges on spare “T’s”, pipe run
unacceptable.
in a manner inappropriate for its duty.
There are several objectives in pre-commissioning: Although there will be resistance to
changes at this stage it is better to fix the
Removing foreign material and problem now than to wait until the plant is
construction debris from the process. being commissioned and confirm an
Testing that drives and instruments are already identified fault then. Example:
functioning correctly (to the extent that is process engineer’s inspection of a plant
practical). shortly before pre-commissioning found
Checking that lines are connected properly lines for fast settling slurry rising at 45°-
and that they can accommodate an rising slurry lines will block rapidly unless
acceptable flow. they are vertical. The fault was corrected
Testing that valves function correctly while the plant was still at the end of the
For plant that will regularly be dismantled construction phase and operational
and re-assembled, to familiarise crews difficulties in this area were avoided.
with how this is done and to identify any Check that plant really is mechanically
difficulties in undertaking these tasks so complete. This includes ensuring that all
that corrective measures can be taken construction tools and accessories have
before the plant becomes live. been removed. Example: start-up of a high
temperature fluid bed had been delayed
There is also the benefit of enabling everyone who several times. At last it was possible to
will be involved in commissioning and operating start heating it for the first time. When the
the plant to gain familiarity with the details of its bed reached incandescent temperature,
construction and layout. looking through the viewing point
revealed an aluminium ladder propped
It is obvious that it is better to undertake these tasks inside.
before corrosive, toxic, flammable or expensive Confirm that all lines have been pressure
materials are introduced to the plant. This is why tested – this is a better way of finding
water is usually used at this stage. leaks than waiting until pre-
commissioning. It is important to note that
Often time, cost or inconvenience will prevent all
although pressure testing involves filling
of the proper steps in pre-commissioning from
lines with water, it is a static process and
does not avoid the need for line flushing.
Vessels have been water filled – looking
for leaks, flexible flanges etc.
Rotation direction of all motors and driven
equipment – remember that some
gearboxes will reverse the turning
direction as well as altering shaft speed.
Example: this is particularly important
with screw conveyor. A piece of equipment
had multiple screws which conveyed
material in a zig-zag manner. One of the
screws should have run in the opposite
direction to the rest. This was not picked Figure 2 Typical debris found in pre-
up before the first material was put commissioning
through the plant and the screw jammed
(fortunately without significant damage). Water flushing
CONCLUSIONS