Hand Over Check List
Hand Over Check List
Closed
1 HANDOVER PROCEDURES
Have you read the Contract handover requirements and conditions? Detailed strategy for operation of Mall to allow necessary construction &
1.1 Operational strategy requirements not detailed. P&T
commissioning work to proceed to be developed and agreed
If a phased handover is required, will operation of plant be affected? Permit to Work procedures for handed over plant areas to be established and
1.2 Permit to Work strategy to be developed. P&T
Client/FM Staff to be briefed on Construction Permit to Work procedures
Is specific provision made within Contract for beneficial use? Marked up drawings detailing proposed areas and systems that will be available
1.3 Reference made to Sectional completion only AACD
for use to be produced & issued.
Have principle systems required for beneficial use been identified? Details & strategy for priority systems that are required that will enable safe
1.4 Extent of commissioned systems to be defined. AACD/P&T
building usage to be established and milestone dates applied.
Is there an adequate scheme of maintenance during beneficial use proposed? Maintenance schedule to be produced and maintenance logs strategy to be
1.5 AACD plan of action required AACD
submitted for agreement
Has procedure been agreed for phased removal of site temporary facilities? Details of what temporary supplies will be in operation at ‘soft’ opening and
1.6 AACD plan of action required AACD
programme for transferral to permanent to be established.
Is there a programme for preparation and delivery of handover information? Milestone Programme to be produced for all systems inspections,
1.7 AACD plan of action required AACD
demonstrations and training (preliminary & Final)
Are Procedures and timescales for document approvals agreed with the Engineer & Client? Insufficient time is available prior to ‘soft’ opening to review all documentation.
1.8 AACD plan of action required AACD/P&T
Minimum requirement to be established
Has all protection been removed? On establishment of marked up drawings in 1.3 above, final inspection to be
2.1 Work in Progress P&T
carried out by Engineer
Has a final clean been done? After Builders Clean has been carried out, Specialist to be employed to clean all
2.2 Work in Progress AACD
areas. Full scope & requirements to be established. (Fabric & MEP)
Is all plant and equipment labelling satisfactory? Regular QA inspections to be carried out by AACD & Engineer to ensure
2.3 Work in Progress AACD/P&T
compliance with Specification requirements
Are all hazard labels present especially to plant areas? On establishment of marked up drawings in 1.3 above, final inspection to be
2.4 Work in Progress P&T
carried out by Engineer
Is access to enclosed equipment satisfactory? Review of Maintainability report to be carried out and recommendation
2.5 Maintainability Report required from Engineer P&T
implemented as applicable
Have ceiling tiles been identified for access to services and recorded? Ceiling access to be part of Maintainability review
2.6 Work in Progress AACD
Are all sealed notices or framed wall charts etc, approved and installed? On establishment of marked up drawings in 1.3 above, final inspection to be
2.7 Work in Progress P&T
carried out by Engineer
3 SNAGGING
Closed
STATUTORY INSPECTIONS
4
Utility way leaves and lease agreements signed off? Update required on when energisation of substations are planned
4.1 Y P&T Construction are dealing with FEWA P&T
Utility supplies inspected and signed off? Programme for Substations completion to be advised
4.2 N Work in Progress AACD
Have all fire barriers, fire dampers and fire stopping been signed off by Statutory Authorities? Schedule of dampers & Fire stopping to be installed and inspected to be
4.3 N Work in Progress AACD
produced.
Civil Defence Authority’s requirements met (fire alarms & interfaces, emergency lighting etc.)? Cause & Effect matrix to be developed & issued for ‘soft’ & ‘hard’ opening
4.4 N Cause & Effect strategy & matrix to be developed P&T
dates
Has Occupation Certificate been issued? Drawings marked up in 1.3 to be approved
4.5 N Areas for Occupation to be advised P&T
Has Public Health consent been signed off (including drainage testing, water quality etc.)? Detailed Commissioning Strategy & programme incorporating key
4.6 N AACD plan of action required AACD
milestones required.
Has means of escape been signed off? Detailed Commissioning Strategy & programme incorporating key
4.7 N AACD plan of action required AACD
milestones required.
Has fire alarm system been signed off and Fire Certificate issued? Detailed Commissioning Strategy & programme incorporating key
4.8 N AACD plan of action required AACD
milestones required.
Have fire fighting systems and appliances been signed off? Detailed Commissioning Strategy & programme incorporating key
4.9 N AACD plan of action required AACD
milestones required.
Are there any special emergency services requirements? Updated Operational Strategy & Overall Fire Strategy to be issued
4.10 N Operational requirements to be advised P&T
Is all Commissioning and interface testing complete? Detailed Commissioning Strategy & programme incorporating key
5.1 N AACD plan of action required AACD
milestones required.
Has Performance Testing of Cooling, Controls, Acoustics etc been signed off? Detailed Commissioning Strategy & programme incorporating key
5.2 N AACD plan of action required AACD
milestones required.
Is date for chlorination (potable water available) agreed? Detailed Commissioning Strategy & programme incorporating key
5.3 N AACD plan of action required AACD
milestones required.
DOCUMENTATION
6
Is a progress sheet being used to track documentation preparation, approval and issue? Schedule of all O & M manuals & Drawings that are to be produced to be
6.1 N AACD plan of action required AACD
advised c/w proposed submission dates
Has Phased/Practical Completion Certificate been issued? Clarification on whether Sectional completion certificates will be issued and
6.2 N AACD plan of action required P&T
impact on Defects Liability Periods
Have meter and fuel readings been recorded? Clarification on who will be responsible for Fuel usage for ‘soft’ and ‘hard’
6.3 N AACD plan of action required P&T
openings
Have maintenance logs for plant during Commissioning/beneficial use been kept? Maintenance schedule to be produced and maintenance logs strategy to be
6.4 N AACD plan of action required AACD
submitted for agreement
Have regular water sample analyses been taken and recorded? Maintenance schedule to be produced and maintenance logs strategy to be
6.5 N AACD plan of action required AACD
submitted for agreement
TRAINING
7
Have Engineers produced a narrative detailing the overview of the design philosophy for the client training? Updated narratives for inclusion within O & M and Training manuals to be
7.1 N Extent of training to be developed P&T
issued.
Is a full schedule of training requirements in place? Schedule of planned training sessions together with agendas to be produced
7.2 N AACD plan of action required AACD
for review and approval
Has the Client defined the full scope of work for the FM operator? Responsibility demarcation to be established with Intercontinental to enable
7.3 N Discussions to be held with Intercontinental P&T
budgets to be finalised
Have we and the Client got sufficient resources for training in all systems? Requirements dependant on resolution of items 7.2 & 7.3 above
7.4 N Discussions to be held with Intercontinental P&T
Are our personnel available at installation/commissioning? Requirements dependant on resolution of items 7.2 & 7.3 above
7.5 Y RAK FM
Is videotaping of interest to the client for specialist systems (professionally done)? As there will be a progressive handover of areas, videotaping would be
7.6 - Discussions to be held with Intercontinental P&T
beneficial. RAK FM can arrange as necessary
Closed
TRAINING (cont)
7
Has the training been accepted by the client? Dependant on resolution of 7.2
7.7 N AACD plan of action required P&T
Have spares been itemised and handed over? Storage locations, environmental conditions and logistical management
8.1 N AACD plan of action required AACD/P&T
system to be determined for spares
Have all keys been labelled and handed over including special keys? Schedule and dates for handover aligned with ‘soft’ and ‘hard’ openings to be
8.2 N AACD plan of action required AACD/P&T
established
Have all specialists’ tools been itemised and handed over? Schedule and dates for handover aligned with ‘soft’ and ‘hard’ openings to be
8.3 N AACD plan of action required AACD/P&T
established
Are measures in place for protecting loose equipment from theft? Security measures during period up to Practical Completion to be established
8.4 N Discussions to be held with Intercontinental P&T
MAINTENANCE
9
Have all maintenance contracts been put in place by the Client/RAK FM Schedule of all systems that will require specialist maintenance agreements to
9.1 N Discussions to be held with Intercontinental P&T
be established
Are procedures in place for emergency call outs? P&T Operational Strategy/Procedures to be issued
9.2 N Discussions to be held with Intercontinental P&T
Are licenses in place for storing and disposal of controlled chemicals? Schedule of all chemicals that will require licences to be established
9.3 N Discussions to be held with Intercontinental P&T
Are licenses in place for storing of gases? Schedule of all gases that will require licences to be established
9.4 N Discussions to be held with Intercontinental P&T
Are there any special warranties which require specific Client maintenance? Summary list of special maintenance issues required in the period up to
9.5 N Discussions to be held with Intercontinental AACD
Practical Completion to be collated & issued
Have procedures for Post-Handover works been agreed with Client? To be advised
10.1 N Discussions to be held with Intercontinental P&T
Is a resourced programme in place for Post-Handover works? To be advised
10.2 N Discussions to be held with Intercontinental P&T
Are contractors’ staff briefed on occupied Permit to Work procedures within the occupied building? P&T Permit to Work procedures to be issued
10.3 N Discussions to be held with Intercontinental P&T
Are arrangements in place for system fine tuning/adjustment? To be advised
10.4 N Discussions to be held with Intercontinental P&T
Is any Post-handover training required? Discussions to be held with Intercontinental to To be advised
10.5 Y P&T
ascertain scope of training required
Is Transition Management service required to facilitate smooth handover to RAK FM Discussions to be held with Intercontinental to Discussion ongoing
10.6 Y P&T
ascertain scope of service