Ref: AFC/PEF/AC586/L/0000
Page: 1 of 1
Dear Sir,
As advised on numerous occasions / meetings, both verbally and by Email, AFC are becoming
increasingly concerned regarding your current level of Delays in terms of Technical submittals and
approvals which are delaying following activities.
Please refer the Time line of your package works shows the delay in actions in terms of Technical submittals
and approvals. M/s Perfect Engineering FZC had sufficient time to submit all the drawings and technical
submittals to get approval from Consultant ahead of the contract programme based on the LOI issued
dated 23/07/2014.
13 Nov 2014
13 All Shop Drawings submittal Perfect Not yet started as per planned date by Perfect
Planned date
26 Dec 2014
14 Material submittal by M/s Perfect Perfect Under review by AFC submitted on 30/11/2014
Planned date
Taking into consideration of above time line M/s Perfect Engineering FZC are already in delay of 34
days in line with Contract Programme.
Further failure in meeting the dates as agreed for technical submittals, approvals and Delivery of
material will affect the overall completion of Hotel 1 at City walk Project and also leaves susceptible and
hindrances to other trades which will also create delays to other subcontractors.
Please address this issue as a matter of urgency & serious and ensure to mitigate your current delay
and complete your works as per contract programme.
Yours faithfully,
For Al Futtaim Carillion LLC
Anthony Cantwell
Project Director
AC/WM/msa
Encl: Photographs
Cc: AFC