284 Calendar Days: 12th Dec. 2008
284 Calendar Days: 12th Dec. 2008
Ditto but exceeding 1500mm but not exceeding 3000mm m3 52.69 52.16 43.59 2,296.76 2,273.65
1.07 Trench excavation for masonry foundation m3 43.95 42.79 23.64 1,038.98 1,011.56
1.08 Fill around foundation and building in non expansive material 80%
from the site and 20% selected materials. m3 182.54 194.88 46.83 8,548.35 9,126.23
1.09 Fill under hard core with imported selected materials .
m3 189.09 94.94 101.12 19,120.78 9,600.33
1.10 Caraway surplus excavated material to appropriate tip m3 642.81 578.89 32.7 21,019.89 18,929.70
1.11 250mm thick basaltic stone hardcore. m2 227.77 237.51 44.40 10,112.99 10,545.44
2. CONCRETE WORK
2.01 50mm lean concrete quality C-5, 150 kg of cement/m3,
a) Under footing m2 68.10 59.32 35.09 2,389.63 2,081.54
b) Under floor slab & beams m2 279.65 286.96 35.09 9,812.92 10,069.43
C)Under Masonry foundation m2 30.99 35.09 1,087.44
2.02 Reinforced concrete quality C-25:
a) In footing m3 24.93 24.70 1,126.21 28076.42 27,817.39
b) In Foundation column m3 3.30 3.31 1,126.21 3716.49 3,727.76
c) In grade beam m3 23.70 24.99 1,126.21 26691.18 28,143.99
d) In Steps m3 0.13 1,126.21 146.41 -
e) In 100mm thick ground floor slab m2 227.77 237.51 112.62 25651.4574 26,748.38
2.03 Formwork
a)To Footing pad m2 80.04 61.88 54.08 4,328.56 3,346.47
b) To Foundation column m2 49.68 49.68 54.08 2,686.69 2,686.69
c)To Grade beam m2 154.37 164.31 54.08 8,348.33 8,885.88
d) To Steps m2 1.02 54.08 55.16 -
2.04 Mild steel bar reinforcement, labour only. -
a) Dia.6 Plain bar kg 53.00 56.17 2.42 128.26 135.93
b) Dia.8 deformed bar kg 1,302.00 1,409.69 2.42 3,150.84 3,411.45
c) Dia.10 deformed bar kg 462.00 423.3 2.42 1,118.04 1,024.39
d) Dia.12 deformed bar kg 305.00 381.52 1.89 576.43 721.07
e) Dia.14 deformed bar kg 1,308.00 1332.74 1.89 2,472.12 2,518.88
f) Dia.16 deformed bar kg 1,027.00 838.16 1.89 1,941.03 1,584.12
2.05 10mm thick 100mm deep Styrofoam expansion joint filler. ml 227.56 233.88 15 3,413.40 3,508.20
-
Total Carried to Summary 124,703.37 127,499.00
3. MASONRY WORK
3.01 400 mm thick basaltic or equivalent type stone masonry below
ground surface.. m3 19.53 19.43 472.26 9,223.24 9,176.01
3.02 400 mm thick basaltic or equivalent type stone masonrye above
ground surface. m3 9.77 6.53 497.20 4,857.64 3,246.72
1.03 Ribbed slab for suspended floor slab, 60 mm thick all according to
the detail structural drawing. m2 479.01 402.09 225.22 107,206.97 90,558.71
1.04
Pre-cast element (PB1) to the size of 4770x120x80mm . pcs 180.00 150 151.36 27,244.80 22,704.00
1.05 Pre-cast element (PB2) to the size of 2970x120x80mm. pcs 14.00 14 92.24 1,319.36 1,291.36
1.06 Sawn zigba wood or steel formwork. -
a) To elevation columns m2 225.50 225.5 61.82 13,940.41 13,940.41
b) To floor beams m2 216.36 210.7 61.82 13,375.38 13,025.47
c) To top tie beams m2 101.28 127.33 61.82 6,261.13 7,871.54
d) To suspended slab m2 75.79 61.82 4,685.34
1.07 Mild steel reinforcement , Labor cost only. -
a) Dia. 6 Plain bar kg 7,108.00 946.88 2.42 17,201.36 2,291.45
b) Dia. 8 deformed bar kg 615.00 630.68 2.42 1,488.30 1,526.25
c) Dia. 10 deformed bar kg 1,041.00 1655.44 2.42 2,519.22 4,006.16
d) Dia. 12 deformed bar kg 3,670.00 2000.14 1.89 6,936.30 3,780.26
e) Dia. 14 deformed bar kg 7,000.00 1980.04 1.89 13,230.00 3,742.28
f) Dia. 16 deformed bar kg 2,522.00 2421.2 1.89 4,766.58 4,576.07
g) Dia. 20 deformed bar kg 1,403.00 1336.23 1.89 2,651.67 2,525.47
2. BLOCK WORK
2.01 Class C, 190mm thick HCB wall m2 1,077.52 1296.6 140.58 151,477.76 182,276.03
2.02 Ditto item 2.01 but 90mm thick m2 142.28 94.18 113.75 16,184.35 10,712.98
3. ROOFING
48,400.92 50,505.54
CONTRACT NO: 0117/08- UCBP - DM -3B-700 CONTRACT TIME: 284 Calendar days
CLIENT: Ministry of Education COMMENCEMENT DATE: 12th Dec. 2008
CONSULTANT: MH Engineering & Architect PLC TIME ELAPSED:
CONTRACTOR: Inter Continental Construction PLC Block No. T2-611
Item Contract Executed Unit Contract Executed
No Description Unit Qty Qty Price Amount Amount
4. CARPENTRY & JOINERY
4.01
Supply and fix 8 mm thick chip wood ceilings. Price include 40 x 50
mm zigba wood battens with c/c spacing of 600 mm both ways,
corner list and all other necessary accessories to complete the work. m2 243.26 243.3 110.73 26,936.18 26,940.61
4.02 Supply and fix 300x25mm zigba wood fascia board price include
three coats of oil paint m 86.42 67.14 47.61 4,114.46 3,196.54
4.03 Supply and fix flush type wooden doors of 40mm thick both side
covered with 4mm thick ply wood and RHS steel frame price
includes approved quality cylindrical lock, hinges, three coats of
varnish paint, metal louver and all other necessary accessories to
complete the work.
- -
D5 size 807x2745mm pcs 30.00 30 2,033.57 61,007.10 61,007.10
D5' size 807x2545mm pcs 6.00 6 2,033.57 12,201.42 12,201.42
4.04 Supply, fabricate and mount wood truss according to the structural
drawing. Price shall include two coats of anti-termite treatment and
all other necessary accessories. The connection joints shall be
approved by the responsible engineer.
- -
4.04.1 Eucalyptus wood upper & lower members.Dia. 100mm. ml 508.35 491.5 13.56 6,893.23 6,664.74
4.04.2 Eucalyptus wood vertical & diagonal members.Dia. 100mm. ml 461.11 436.5 13.56 6,252.65 5,918.94
4.04.3 Sawn Zigba wood roof purlins50x70mm placed at c/c 1200mm.
ml 332.70 320.7 24.80 8,250.96 7,953.36
125,655.99 123,882.70
5. METAL WORK
5.01
Metal window and doors made of 38x1.5mm LTZ profiles shown on
the drawings, price include approved quality locks and all iron
mongry works, two coats of anti rust, three coats of synthetic paint,
1mm thick ribbed sheet and door stopper. All according to detail
drawing.
Doors
D6 size 580x1735mm covered with 1mm thick ribbed sheet pcs 30.00 30 339.59 10,187.58 10,187.58
5.02
Supply, assemble & erect steel structure fire escape spiral stair case
manufactured from CHS, RHS Profile & checkered plate treads
including RHS, CHS balustrade & hand rail in accordance with
detail drawing. price includes one coat of anti rust, two coats of
syntetic enamel paint and the necessary accessories and related
works to complete the work. pcs 1.00 36,636.00 36,636.00 -
Size : Dia. 2200mm, Height 6180mm
Total Carried to Summary 73,272.00 36,636.00
7.FINISHING
7.01 Apply three coats of plastering in cement mortar
a)To internal wall surface. m² 1,896.94 1959.52 51.67 98,014.89 101,248.40
- -
b)To external wall surface. m² 666.74 837.4 53.76 35,843.94 45,018.62
- -
c)To concrete ceiling. m² 475.10 502.57 61.82 29,370.68 31,068.88
7.05 Two coats of plastering in 1:3 ratio cement mortar to
receive ceramic wall tiles m² 382.54 173.50 36.47 13,951.23 6,327.55
7.06 Supply and lay terrazzo tile flooring. The pattern of the tile and the
entire work shall be approved by the engineer. Price shall include
cement mortar (1:3) bed and grouting. m² 103.80 84.67 149.71 15,539.90 12,675.95
7.07 Supply and fix 6 mm thick & 150x150mm white glazed ceramic wall
tiles with cement mortar (1:2) backing with 5mm joints to be grouted
with white cement. m² 382.54 111.9 42,806.23 -
7.08 50 mm thick smooth finished cement screed(1:3) floor finish with
glass crack protection. Price include glass. All as per engineers
instruction. m² 612.97 604.51 61.38 37,624.10 37,104.82
7.09
Supply and fix 30mm thick and 300mm wide edge chamfered and
with water drip grooved terrazzo window sill with a minimum slope.
Quality of terrazzo shall be approved by the engineer. ml 59.40 57.00 67.5 4,009.50 3,847.50
7.10
Supply and fix 30 x 30 x 3 mm angle iron corner protection up to a
height of 1500mm from floor finish level, flushed to walls. No 24.75 23.00 60 1,485.00 1,380.00
7.11 1200mm wide stone pavement around the building. Price shall
includes red ash or equivalent bedding material as per the detail
drawing and the engineers direction. m² 103.42 101.44 99.26 10,265.47 10,068.93
7.12 Cement wash plastering to receive oil paint. m²
2. CONCRETE WORK
2.01 50mm lean concrete quality C-5, 150 kg of cement/m3,
3. MASONRY WORK
3.01 400 mm thick basaltic or equivalent type stone masonry
below ground surface.. m3 19.53 19.61 472.26 9,223.24 9,261.02
3.02 400 mm thick basaltic or equivalent type stone masonrye
above ground surface. m3 9.77 6.73 497.20 4,857.64 3,346.16
2. BLOCK WORK
2.01 Class C, 190mm thick HCB wall m2 1,077.52 1296.6 140.58 151,477.76 182,276.03
2.02 Ditto item 2.01 but 90mm thick m2 142.28 94.18 113.75 16,184.35 10,712.98
3. ROOFING
4.01
Supply and fix 8 mm thick chip wood ceilings. Price
include 40 x 50 mm zigba wood battens with c/c spacing of
600 mm both ways, corner list and all other necessary
accessories to complete the work. m2 243.26 243.3 110.73 26,936.18 26,940.61
4.02 Supply and fix 300x25mm zigba wood fascia board price
include three coats of oil paint m 86.42 47.61 4,114.46 -
4.03 Supply and fix flush type wooden doors of 40mm thick
both side covered with 4mm thick ply wood and RHS steel
frame price includes approved quality cylindrical lock,
hinges, three coats of varnish paint, metal louver and all
other necessary accessories to complete the work.
- -
D5 size 807x2745mm pcs 30.00 30 2,033.57 61,007.10 61,007.10
D5' size 807x2545mm pcs 6.00 6 2,033.57 12,201.42 12,201.42
4.04 Supply, fabricate and mount wood truss according to the
structural drawing. Price shall include two coats of anti-
termite treatment and all other necessary accessories. The
connection joints shall be approved by the responsible
engineer.
- -
4.04.1 Eucalyptus wood upper & lower members.Dia. 100mm.
ml 508.35 491.5 13.56 6,893.23 6,664.74
4.04.2 Eucalyptus wood vertical & diagonal members.Dia.
100mm. ml 461.11 436.5 13.56 6,252.65 5,918.94
4.04.3 Sawn Zigba wood roof purlins50x70mm placed at c/c
1200mm. ml 332.70 320.7 24.80 8,250.96 7,953.36
125,655.99 120,686.17
5. METAL WORK
5.01
D6 size 580x1735mm covered with 1mm thick ribbed sheet pcs 30.00 30 339.59 10,187.58 10,187.58
5.02
Metal window doors made of 38x1.5mm LTZ profiles
shown on the drawings, price include approved quality
locks and all iron mongry works, two coats of anti rust,
three coats of synthetic paint,and door stopper. All
according to detail Arch. drawings.
Window doors
a) WD1 size 1580x2545mm pcs 4.00 4 1,185.86 4,743.45 4,743.45
b) MD1 size 2765x2790mm pcs 1.00 2,275.04 2,275.04 -
5.03
6.06
TMS 022/ 136 IC +1xTLD 36W/840 lamp. NO. 164 102 396.75 65,067.00 40,468.50
11.11 Lightning Protection System
11.11.01 Air termination copper rod of 1.5m with roof mounting
bracket. NO. 1 2400 2,400.00 -
11.11.02 1x25mm sq. bare copper down conductor inside PVC
conduit of 25mm diameter from roof bond to junction box.
M 60 86 5,160.00 -
11.11.03 Testing junction boxes at 1.5m above ground level.
NO. 6 700 4,200.00 -
11.11.04 1x25mm sq. bare copper earth conductor inside PVC
conduit of 25mm diameter from junction box to earthling
rod. M 12 86 1,032.00 -
11.11.05 1500x16mm copper bond earthling rod inside
500x500x700mm pit (measured elsewhere) including all
connecting accessories. NO. 6 1200 7,200.00 -
11.11.06 Bonding down conductor with metal roof and roof support
members. Ls. 1 1311 1,311.00 -
2. CONCRETE WORK
2.01 50mm lean concrete quality C-5, 150 kg of cement/m3,
a) Under footing m2 68.10 59.32 35.09 2,389.63 2,081.54
b) Under floor slab & beams m2 279.65 286.96 35.09 9,812.92 10,069.43
C)Under Masonry foundation m2 30.99 35.09 1,087.44
2.02 Reinforced concrete quality C-25:
a) In footing m3 24.93 24.70 1,126.21 28076.42 27,817.39
b) In Foundation column m3 3.30 3.31 1,126.21 3716.49 3,727.76
c) In grade beam m3 23.70 24.49 1,126.21 26691.18 27,580.88
d) In Steps m3 0.13 1,126.21 146.41 -
e) In 100mm thick ground floor slab m2 227.77 237.51 112.62 25651.4574 26,748.38
2.03 Formwork
a)To Footing pad m2 80.04 61.88 54.08 4,328.56 3,346.47
b) To Foundation column m2 49.68 49.68 54.08 2,686.69 2,686.69
c)To Grade beam m2 154.37 164.31 54.08 8,348.33 8,885.88
d) To Steps m2 1.02 54.08 55.16 -
2.04 Mild steel bar reinforcement, labour only. -
a) Dia.6 Plain bar kg 53.00 56.17 2.42 128.26 135.93
b) Dia.8 deformed bar kg 1,302.00 1,409.69 2.42 3,150.84 3,411.45
c) Dia.10 deformed bar kg 462.00 423.3 2.42 1,118.04 1,024.39
d) Dia.12 deformed bar kg 305.00 381.52 1.89 576.43 721.07
e) Dia.14 deformed bar kg 1,308.00 1332.74 1.89 2,472.12 2,518.88
f) Dia.16 deformed bar kg 1,027.00 838.16 1.89 1,941.03 1,584.12
-
2.05 10mm thick 100mm deep Styrofoam expansion joint filler. ml 227.56 233.88 15 3,413.40 3,508.20
-
Total Carried to Summary 124,703.37 126,935.90
3. MASONRY WORK
3.01 400 mm thick basaltic or equivalent type stone masonry below
ground surface.. m3 19.53 19.77 472.26 9,223.24 9,336.58
3.02 400 mm thick basaltic or equivalent type stone masonrye above
ground surface. m3 9.77 6.79 497.20 4,857.64 3,375.99
2. BLOCK WORK
2.01 Class C, 190mm thick HCB wall m2 1,077.52 1296.6 140.58 151,477.76 182,276.03
2.02 Ditto item 2.01 but 90mm thick m2 142.28 94.18 113.75 16,184.35 10,712.98
3. ROOFING
4.01
Supply and fix 8 mm thick chip wood ceilings. Price include 40 x 50
mm zigba wood battens with c/c spacing of 600 mm both ways,
corner list and all other necessary accessories to complete the work. m2 243.26 243.3 110.73 26,936.18 26,940.61
4.02 Supply and fix 300x25mm zigba wood fascia board price include
three coats of oil paint m 86.42 67.14 47.61 4,114.46 3,196.54
4.03 Supply and fix flush type wooden doors of 40mm thick both side
covered with 4mm thick ply wood and RHS steel frame price
includes approved quality cylindrical lock, hinges, three coats of
varnish paint, metal louver and all other necessary accessories to
complete the work.
- -
D5 size 807x2745mm pcs 30.00 30 2,033.57 61,007.10 61,007.10
D5' size 807x2545mm pcs 6.00 6 2,033.57 12,201.42 12,201.42
4.04 Supply, fabricate and mount wood truss according to the structural
drawing. Price shall include two coats of anti-termite treatment and
all other necessary accessories. The connection joints shall be
approved by the responsible engineer.
- -
4.04.1 Eucalyptus wood upper & lower members.Dia. 100mm. ml 508.35 491.5 13.56 6,893.23 6,664.74
4.04.2 Eucalyptus wood vertical & diagonal members.Dia. 100mm. ml 461.11 436.5 13.56 6,252.65 5,918.94
4.04.3 Sawn Zigba wood roof purlins50x70mm placed at c/c 1200mm.
ml 332.70 320.7 24.80 8,250.96 7,953.36
125,655.99 123,882.70
5. METAL WORK
5.01
Metal window and doors made of 38x1.5mm LTZ profiles shown on
the drawings, price include approved quality locks and all iron
mongry works, two coats of anti rust, three coats of synthetic paint,
1mm thick ribbed sheet and door stopper. All according to detail
drawing.
Doors
D6 size 580x1735mm covered with 1mm thick ribbed sheet pcs 30.00 30 339.59 10,187.58 10,187.58
5.02
Metal window doors made of 38x1.5mm LTZ profiles shown on the
drawings, price include approved quality locks and all iron mongry
works, two coats of anti rust, three coats of synthetic paint,and door
stopper. All according to detail Arch. drawings.
Window doors
a) WD1 size 1580x2545mm pcs 4.00 4 1,185.86 4,743.45 4,743.45
b) MD1 size 2765x2790mm pcs 1.00 2,275.04 2,275.04 -
5.03
Windows are manufactured from 38x1.5mm LTZ frame profile all as
per the engineers approval and window door schedule. Unit price
includes one coat of antirust and two coats of synthetic enamel
paint, best quality lock with hand type windows as per detail
drawing.
Window
a) W1 size 1180x1505mm pcs 30.00 30 793.21 23,796.30 23,796.30
b) W2 size 1580x1505mm pcs 2.00 2 1062.09 2,124.18 2,124.18
Top Window
c) TW1 size 580x505mm pcs 6.00 6 130.82 784.92 784.92
d) TW2 size 1940x505mm pcs 6.00 6 439.39 2,636.34 2,636.34
5.04
Φ 50mm,2.5mm thick furniture pipe hand rail fixed to metal
balustrade with welding and all other necessary accessories for
completing the work. All according drawing and shall be approved
by the engineer. m 58.20 52.3 360.00 20,952.00 18,828.00
6.06
Supply, fabricate and erect steel staircase according to the structural
drawing .Price shall include one coat of antirust and two coats of
syntactic enamel painting and all other necessary accessories. pcs 1.00 1 36,636.00 36,636.00 36,636.00
6.07
Supply, assemble & erect steel structure fire escape spiral stair case
manufactured from CHS, RHS Profile & checkered plate treads
including RHS, CHS balustrade & hand rail in accordance with
detail drawing. price includes one coat of anti rust, two coats of
syntetic enamel paint and the necessary accessories and related
works to complete the work. pcs 1.00 36,636.00 36,636.00 -
Size : Dia. 2200mm, Height 6180mm
7.FINISHING -
7.01 Apply three coats of plastering in cement mortar -
a)To internal wall surface. m² 1,896.94 1959.52 51.67 98,014.89 101,248.40
- -
b)To external wall surface. m² 666.74 837.4 53.76 35,843.94 45,018.62
- -
c)To concrete ceiling. m² 475.10 502.57 61.82 29,370.68 31,068.88
7.05 Two coats of plastering in 1:3 ratio cement mortar to
receive ceramic wall tiles m² 382.54 173.50 36.47 13,951.23 6,327.55
7.06 Supply and lay terrazzo tile flooring. The pattern of the tile and the
entire work shall be approved by the engineer. Price shall include
cement mortar (1:3) bed and grouting. m² 103.80 84.67 149.71 15,539.90 12,675.95
7.07 Supply and fix 6 mm thick & 150x150mm white glazed ceramic wall
tiles with cement mortar (1:2) backing with 5mm joints to be grouted
with white cement. m² 382.54 111.9 42,806.23 -
7.08 50 mm thick smooth finished cement screed(1:3) floor finish with
glass crack protection. Price include glass. All as per engineers
instruction. m² 612.97 604.51 61.38 37,624.10 37,104.82
7.09
Supply and fix 30mm thick and 300mm wide edge chamfered and
with water drip grooved terrazzo window sill with a minimum slope.
Quality of terrazzo shall be approved by the engineer. ml 59.40 57.00 67.5 4,009.50 3,847.50
7.10
Supply and fix 30 x 30 x 3 mm angle iron corner protection up to a
height of 1500mm from floor finish level, flushed to walls. No 24.75 23.00 60 1,485.00 1,380.00
7.11 1200mm wide stone pavement around the building. Price shall
includes red ash or equivalent bedding material as per the detail
drawing and the engineers direction. m² 103.42 101.44 99.26 10,265.47 10,068.93
7.12 Cement wash plastering to receive oil paint. m²
8. PAINTING
Apply three coats of plastic emulsion paint. Price shall include pre -
cleaning & preparation of the surface.
8.01
To internal plastered wall surface. m2 1,896.94 1959.52 10.99 20,847.37 21,535.12
8.02
To internal pointed wall surface. m2
8.03
To external plastered wall surface. m2 666.74 837.39 14.37 9,581.05 12,033.29
8.04 2
To external grooved wall surface. m
8.05
To exposed beam and column m2
8.06
To RC ceiling. m2 475.10 502.57 14.37 6,827.19 7,221.93
8.07
To chip wood ceiling. m2 243.26 240.7 13.27 3,228.06 3,194.09
8.08 2
Oil paint to cement wash wall surface m
2. CONCRETE WORK
2.01 50mm lean concrete quality C-5, 150 kg of cement/m3,
a) Under footing m2 68.10 59.32 35.09 2,389.63 2,081.54
b) Under floor slab & beams m2 279.65 286.96 35.09 9,812.92 10,069.43
C)Under Masonry foundation m2 30.99 35.09 1,087.44
2.02 Reinforced concrete quality C-25:
a) In footing m3 24.93 24.70 1,126.21 28076.42 27,817.39
b) In Foundation column m3 3.30 3.31 1,126.21 3716.49 3,727.76
c) In grade beam m3 23.70 24.99 1,126.21 26691.18 28,143.99
d) In Steps m3 0.13 1,126.21 146.41 -
e) In 100mm thick ground floor slab m2 227.77 237.51 112.62 25651.4574 26,748.38
2.03 Formwork
a)To Footing pad m2 80.04 61.88 54.08 4,328.56 3,346.47
b) To Foundation column m2 49.68 49.68 54.08 2,686.69 2,686.69
c)To Grade beam m2 154.37 164.31 54.08 8,348.33 8,885.88
d) To Steps m2 1.02 54.08 55.16 -
2.04 Mild steel bar reinforcement, labour only. -
a) Dia.6 Plain bar kg 53.00 56.17 2.42 128.26 135.93
b) Dia.8 deformed bar kg 1,302.00 1,409.69 2.42 3,150.84 3,411.45
c) Dia.10 deformed bar kg 462.00 423.3 2.42 1,118.04 1,024.39
d) Dia.12 deformed bar kg 305.00 381.52 1.89 576.43 721.07
e) Dia.14 deformed bar kg 1,308.00 1332.74 1.89 2,472.12 2,518.88
f) Dia.16 deformed bar kg 1,027.00 838.16 1.89 1,941.03 1,584.12
-
2.05 10mm thick 100mm deep Styrofoam expansion joint filler. ml 227.56 233.88 15 3,413.40 3,508.20
-
Total Carried to Summary 124,703.37 127,499.00
3. MASONRY WORK
3.01 400 mm thick basaltic or equivalent type stone masonry below
ground surface.. m3 19.53 19.43 472.26 9,223.24 9,176.01
3.02 400 mm thick basaltic or equivalent type stone masonrye above
ground surface. m3 9.77 5.98 497.20 4,857.64 2,973.26
2. BLOCK WORK
2.01 Class C, 190mm thick HCB wall m2 1,077.52 1296.6 140.58 151,477.76 182,276.03
2.02 Ditto item 2.01 but 90mm thick m2 142.28 94.18 113.75 16,184.35 10,712.98
3. ROOFING
48,400.92 50,505.54
CONTRACT NO: 0117/08- UCBP - DM -3B-700 CONTRACT TIME: 284 Calendar days
CLIENT: Ministry of Education COMMENCEMENT DATE: 12th Dec. 2008
CONSULTANT: MH Engineering & Architect PLC TIME ELAPSED:
CONTRACTOR: Inter Continental Construction PLC Block No. T2-614
Item Contract Executed Unit Contract Executed
No Description Unit Qty Qty Price Amount Amount
4. CARPENTRY & JOINERY
4.01
Supply and fix 8 mm thick chip wood ceilings. Price include 40 x
50 mm zigba wood battens with c/c spacing of 600 mm both
ways, corner list and all other necessary accessories to complete
the work. m2 243.26 243.3 110.73 26,936.18 26,940.61
4.02 Supply and fix 300x25mm zigba wood fascia board price include
three coats of oil paint m 86.42 67.14 47.61 4,114.46 3,196.54
4.03 Supply and fix flush type wooden doors of 40mm thick both side
covered with 4mm thick ply wood and RHS steel frame price
includes approved quality cylindrical lock, hinges, three coats of
varnish paint, metal louver and all other necessary accessories to
complete the work.
- -
D5 size 807x2745mm pcs 30.00 30 2,033.57 61,007.10 61,007.10
D5' size 807x2545mm pcs 6.00 6 2,033.57 12,201.42 12,201.42
4.04 Supply, fabricate and mount wood truss according to the
structural drawing. Price shall include two coats of anti-termite
treatment and all other necessary accessories. The connection
joints shall be approved by the responsible engineer.
- -
4.04.1 Eucalyptus wood upper & lower members.Dia. 100mm.
ml 508.35 491.5 13.56 6,893.23 6,664.74
4.04.2 Eucalyptus wood vertical & diagonal members.Dia. 100mm.
ml 461.11 436.5 13.56 6,252.65 5,918.94
4.04.3 Sawn Zigba wood roof purlins50x70mm placed at c/c 1200mm.
ml 332.70 320.7 24.80 8,250.96 7,953.36
125,655.99 123,882.70
5. METAL WORK
5.01
Metal window and doors made of 38x1.5mm LTZ profiles shown
on the drawings, price include approved quality locks and all iron
mongry works, two coats of anti rust, three coats of synthetic
paint, 1mm thick ribbed sheet and door stopper. All according to
detail drawing.
Doors
D6 size 580x1735mm covered with 1mm thick ribbed sheet pcs 30.00 30 339.59 10,187.58 10,187.58
5.02
Metal window doors made of 38x1.5mm LTZ profiles shown on
the drawings, price include approved quality locks and all iron
mongry works, two coats of anti rust, three coats of synthetic
paint,and door stopper. All according to detail Arch. drawings.
Window doors
a) WD1 size 1580x2545mm pcs 4.00 4 1,185.86 4,743.45 4,743.45
b) MD1 size 2765x2790mm pcs 1.00 2,275.04 2,275.04 -
5.03
Windows are manufactured from 38x1.5mm LTZ frame profile all
as per the engineers approval and window door schedule. Unit
price includes one coat of antirust and two coats of synthetic
enamel paint, best quality lock with hand type windows as per
detail drawing.
Window
a) W1 size 1180x1505mm pcs 30.00 30 793.21 23,796.30 23,796.30
b) W2 size 1580x1505mm pcs 2.00 2 1062.09 2,124.18 2,124.18
Top Window
c) TW1 size 580x505mm pcs 6.00 6 130.82 784.92 784.92
d) TW2 size 1940x505mm pcs 6.00 6 439.39 2,636.34 2,636.34
5.04
Φ 50mm,2.5mm thick furniture pipe hand rail fixed to metal
balustrade with welding and all other necessary accessories for
completing the work. All according drawing and shall be approved
by the engineer. m 58.20 52.3 360.00 20,952.00 18,828.00
6.06
Supply, fabricate and erect steel staircase according to the
structural drawing .Price shall include one coat of antirust and
two coats of syntactic enamel painting and all other necessary
accessories. pcs 1.00 1 ### 36,636.00 36,636.00
6.07
Supply, assemble & erect steel structure fire escape spiral stair
case manufactured from CHS, RHS Profile & checkered plate
treads including RHS, CHS balustrade & hand rail in accordance
with detail drawing. price includes one coat of anti rust, two coats
of syntetic enamel paint and the necessary accessories and
related works to complete the work. pcs 1.00 ### 36,636.00 -
Size : Dia. 2200mm, Height 6180mm
7.FINISHING -
7.01 Apply three coats of plastering in cement mortar -
a)To internal wall surface. m² 1,896.94 1959.52 51.67 98,014.89 101,248.40
- -
b)To external wall surface. m² 666.74 837.4 53.76 35,843.94 45,018.62
- -
c)To concrete ceiling. m² 475.10 502.57 61.82 29,370.68 31,068.88
7.05 Two coats of plastering in 1:3 ratio cement mortar to
receive ceramic wall tiles m² 382.54 173.50 36.47 13,951.23 6,327.55
7.06 Supply and lay terrazzo tile flooring. The pattern of the tile and the
entire work shall be approved by the engineer. Price shall include
cement mortar (1:3) bed and grouting. m² 103.80 84.67 149.71 15,539.90 12,675.95
7.07 Supply and fix 6 mm thick & 150x150mm white glazed ceramic
wall tiles with cement mortar (1:2) backing with 5mm joints to be
grouted with white cement. m² 382.54 111.9 42,806.23 -
7.08 50 mm thick smooth finished cement screed(1:3) floor finish with
glass crack protection. Price include glass. All as per engineers
instruction. m² 612.97 604.51 61.38 37,624.10 37,104.82
7.09
Supply and fix 30mm thick and 300mm wide edge chamfered and
with water drip grooved terrazzo window sill with a minimum
slope. Quality of terrazzo shall be approved by the engineer. ml 59.40 57.00 67.5 4,009.50 3,847.50
7.10
Supply and fix 30 x 30 x 3 mm angle iron corner protection up to a
height of 1500mm from floor finish level, flushed to walls. No 24.75 23.00 60 1,485.00 1,380.00
7.11 1200mm wide stone pavement around the building. Price shall
includes red ash or equivalent bedding material as per the detail
drawing and the engineers direction. m² 103.42 101.44 99.26 10,265.47 10,068.93
7.12 Cement wash plastering to receive oil paint. m²
8. PAINTING
Apply three coats of plastic emulsion paint. Price shall include pre
- cleaning & preparation of the surface.
8.01
To internal plastered wall surface. m2 1,896.94 1959.52 10.99 20,847.37 21,535.12
8.02 2
To internal pointed wall surface. m
8.03
To external plastered wall surface. m2 666.74 837.39 14.37 9,581.05 12,033.29
8.04
To external grooved wall surface. m2
8.05
To exposed beam and column m2
8.06
To RC ceiling. m2 475.10 502.57 14.37 6,827.19 7,221.93
8.07
To chip wood ceiling. m2 243.26 240.7 13.27 3,228.06 3,194.09
8.08
Oil paint to cement wash wall surface m2
1.08 Fill around foundation and building in non expansive material 80%
from the site and 20% iselected materials. m3 542.92 574.27 46.83 25,424.94 26,893.06
1.09 Fill under hard core with imported selected materials . m3 529.00 268.24 101.12 53,492.48 27,124.43
1.10 Caraway surplus excavated material to appropriate tip m3 3,094.05 2814.4 32.7 101,175.44 92,030.88
1.11 250mm thick basaltic stone hardcore. m2 668.45 687.80 44.40 29,679.18 30,538.32
2. CONCRETE WORK
2.01 50mm lean concrete quality C-5, 150 kg of cement/m3,
a) Under footing m2 214.32 191.70 35.09 7,520.49 6,726.75
b) Under floor slab & beams m2 799.25 820.33 35.09 28,045.68 28,785.38
c) Under Masonry Foundation m2 103.42 78.04 35.09 3,629.01 2,738.42
2.02 Reinforced concrete quality C-25:
a) In footing m3 84.39 84.39 1,126.21 95,040.86 95,040.86
b) In Foundation column m3 8.69 9.56 1,126.21 9,786.76 10,766.57
c) In grade beam m3 65.42 67.76 1,126.21 73,676.66 76,311.99
d) In Steps m3 1,126.21
e) In 100mm thick ground floor slab m2 668.45 687.80 112.62 75,280.84 77,460.04
2.03 Formwork
a)To Footing pad m2 185.52 185.52 54.08 10,032.92 10,032.92
b) To Foundation column m2 130.32 128.4 54.08 7,047.71 6,943.87
c)To Grade beam m2 440.68 467.27 54.08 23,831.97 25,269.96
d) To Steps m2
2.04 Mild steel bar reinforcement, labour only.
a) Dia.6 Plain bar kg 9.00 121.31 2.42 21.78 293.57
b) Dia.8 deformed bar kg 3,887.00 3500.28 2.42 9,406.54 8,470.68
c) Dia.10 deformed bar kg 631.00 582.93 2.42 1,527.02 1,410.69
d) Dia.12 deformed bar kg 1,892.00 1893.57 1.89 3,575.88 3,578.85
e) Dia.14 deformed bar kg 3,940.00 3604.59 1.89 7,446.60 6,812.68
f) Dia.16 deformed bar kg 2,333.00 2062.84 1.89 4,409.37 3,898.77
2.05 10mm thick 100mm deep Styrofoam expansion joint filler. ml 621.40 935.82 15 9,321.00 14,037.30
3. MASONRY WORK
3.01 400 mm thick basaltic or equivalent type stone masonry below
ground surface.. m3 49.64 41.45 472.26 23,442.99 19,575.18
3.02 400 mm thick basaltic or equivalent type stone masonrye above
ground surface. m3 24.82 14.49 497.20 12,340.50 7,204.43
B. SUPERSTRUCTURE
1. CONCRETE WORK
1.01 C-25 reinforced concrete
a) In elevation columns m3 40.09 40.09 1137.93 45,619.61 45,619.61
b) In floor beams m3 83.42 72.82 1137.93 94,926.12 82,864.06
c) In top tie beam m3 23.02 28.27 1137.93 26,195.15 32,169.28
d) In 150mm thick suspended slab m2 232.71 170.69 39,721.27
1.02 150*200 precast lintel ml 93.60 27.18 60 5,616.00 1,630.80
-
1.03 Ribbed slab for suspended floor slab, 60 mm thick all according to
the detail structural drawing. m2 1,317.72 1110.65 225.22 296,776.90 250,140.59
1.04 Pre-cast element (PB1) to the size of 4770x120x80mm . pcs 528.00 436 151.36 79,918.08 65,992.96
-
1.06 Sawn zigba wood or steel formwork. -
a) To elevation columns m2 601.34 601.35 61.82 37,174.84 37,175.46
b) To floor beams m2 562.97 578.47 61.82 34,802.81 35,761.02
c) To top tie beams m2 299.91 365.9 61.82 18,540.44 22,619.94
d) To suspended slab m2 232.71 61.82 14,386.13
-
1.07 Mild steel reinforcement , Labor cost only. -
a) Dia. 6 Plain bar kg 10,758.00 2543.34 2.42 26,034.36 6,154.88
b) Dia. 8 deformed bar kg 3,676.00 1992.99 2.42 8,895.92 4,823.04
c) Dia. 10 deformed bar kg 1,587.00 4533.04 2.42 3,840.54 10,969.96
d) Dia. 12 deformed bar kg 5,565.00 6156.7 1.89 10,517.85 11,636.16
e) Dia. 14 deformed bar kg 10,245.00 3008.51 1.89 19,363.05 5,686.08
f) Dia. 16 deformed bar kg 24,459.00 11340.62 1.89 46,227.51 21,433.77
g) Dia. 20 deformed bar kg 2,760.00 3754.95 1.89 5,216.40 7,096.86
2. BLOCK WORK
2.01 Class C, 190mm thick HCB wall m2 3,286.64 3360.26 140.58 462,035.85 472,385.35
2.02 Ditto item 2.01 but 90mm thick m2 142.28 248.9 113.75 16,184.35 28,312.38
Total Carried to Summary 478,220.20 500,697.73
3. ROOFING
3.01
Roof cover in precoated or galvanized EGA - 400, 0.4mm thick
fixed to zigba purlins,price shall include ridge cap, UV resistance
washers and G-28 flat sheet dev. Length 330 mm Ridge cap.
(Purlins measured separately and roof measured in horizontal
projection). m2 994.28 906.35 107.63 107,014.36 97,550.45
3.02
a) G-28 Galvanized sheet metal gutter of dev. Length 700mm
price includes two coats of anti-rust and synthetic paint ml 203.00 157.11 67.55 13,712.65 10,612.78
5. METAL WORK
5.01
Metal window and doors made of 38x1.5mm LTZ profiles shown
on the drawings, price include approved quality locks and all iron
mongry works, two coats of anti rust, three coats of synthetic
paint, 1mm thick ribbed sheet and door stopper. All according to
detail drawing.
Doors
D6 size 580x1735mm covered with 1mm thick ribbed sheet pcs 72.00 72 509.33 36,671.76 36,671.76
5.02
6.06
Supply, fabricate and erect steel staircase according to the
structural drawing .Price shall include one coat of antirust and two
coats of syntactic enamel painting and all other necessary
accessories. pcs 2.00 2 36,636.00 73,272.00 73,272.00
6.07
Supply, assemble & erect steel structure fire escape spiral stair
case manufactured from CHS, RHS Profile & checkered plate
treads including RHS, CHS balustrade & hand rail in accordance
with detail drawing. price includes one coat of anti rust, two coats
of syntetic enamel paint and the necessary accessories and
related works to complete the work. pcs 1.00 36,636.00 36,636.00 -
Size : Dia. 2200mm, Height 6180mm
Total Carried to Summary 109,908.00 73,272.00
CONTRACT NO: 0117/08- UCBP - DM -3B-700 CONTRACT TIME: 284 Calendar days
CLIENT: Ministry of Education COMMENCEMENT DATE: 12th Dec. 2008
CONSULTANT: MH Engineering & Architect PLC TIME ELAPSED:
CONTRACTOR: Inter Continental Construction PLC Block No. T6, 616
Item Contract Executed Unit Contract Executed
No Description Unit Qty Qty Price Amount Amount
7.FINISHING
7.01 Apply three coats of plastering in cement mortar
a)To internal wall surface. m² 5,152.47 5595.33 51.67 266,228.12 289,110.70
- -
b)To external wall surface. m² 1,645.56 1994.84 53.76 88,465.31 107,242.60
- -
c)To concrete ceiling. m² 2,925.76 1344.08 61.82 180,870.48 83,091.03
9. GLAZING
9.01 Supply and fix 4 mm thick clear sheet glass to metal beads and
puttied with approved quality of putty. m2 278.51 160.56 100.8 28,073.81 16,184.45
Unit
No Description Unit Qty Price Amount
A. SUBSTRUCTURE
1.01 Site clearing to the depth 200 mm thick. m2 97.20 22.33 2,170.48
1.02 Bulk excavation in ordinary soil to a depth of 500 mm m3 52.50 218.14 11,452.35
1.03 Trench Excavation m3 36.30 204.50 7,423.35
1.04 Pit Excavation m3 0 251.70 -
1.05 backfill and Compaction m3 36.80 835.48 30,745.66
1.06
3
Caraway surplus excavated material to average distance of 1km m 45.60 214.99 9,803.54
1.07 25cm thick basaltic hard core or equivalent stone hard core m2 70.00 189.48 13,263.60
2. CONCRETE WORK
2.01 50mm lean concrete quality C-5, 150 kg of cement/m3, m2
A) Under grade beams m2 30.20 85.72 2,588.74
B) Under footing pad m2 - 85.72 -
2.02 Reinforced concrete quality C-25:
a)Footing pad m3 - 2,791.43 -
b) footing column m3 - 2,791.43 -
c) In grade beam m3 12.00 2,791.43 33,497.16
d) In 100mm thick ground floor slab m2 - 279.14 -
2.03 Formwork
a)Footing pad m2 - 383.87 -
b) footing column m2 - 404.71 -
c)To Grade beam m2 25.00 493.95 12,348.75
2.04 mild steel bar reinforcement ,price includes cutting,bending,
placeing in position and tying.
a) Dia 6 Plain bar kg 100.00 70.91 7091
b) Dia.10 Plain bar kg - 67.39 0
c) Dia.12 deformed bar kg 289.50 66.14 19147.53
d) Dia.14 Plain bar kg - 65.57 0
e) Dia.16Plain bar kg - 65.39 0
f) Dia.24 Plain bar kg 65.71
Unit
No Description Unit Qty Price Amount
Total Carried to Summary 56,939.46
PROJECT ; RESIDENCE(VILLA)
LOCATION ; DEBRE MARKOS
OWNER :አቶ መንገሻ እንዳለው ዘሪሁን
Unit
No Description Unit Qty Price Amount
2. BLOCK WORK
2.01 20cm thick HCB wall class C m2 168.96 433.71 73,279.64
2.02 Class C, 150mm thick HCB wall m2 147.89 405.23 59,929.46
2.03 Class C, 100mm thick HCB wall m2 0.60 -
Total Carried to Summary 133,209.11
3. ROOFING
3.01 EGA roofing m2 135.50 692.24 42,235.20
3.02
Supply & fix G-28 Galvanized sheet metal down pipe of dev. Length
700mm price includes two coats of anti-rust and synthetic paint ml 40.50 404.58 16,385.49
Eqauluptes purlin
m2 - -
4.01
Supply and fix Gypsem board. price include 40 x 50 mm zigba
wood battens with c/c spacing of 600 mm both ways, corner list
and all other necessary accessories to complete the work. m2 70.00 349.92 24,494.40
4.03 vertical and diagonal members ml 78.50 87.45 6,864.83
4.04 horizontal and diagonal members ml 70.00 483.88 33,871.60
4.05 Equaluptes roof purlins50x70mm placed at c/c 1200mm. ml 90.00 146.49 13,184.10
Total Carried to Summary 78,414.93
5. METAL WORK
5.01
Metal window and doors made of 38x1.5mm Aluminium Emitation
profiles shown on the drawings, price include approved quality
locks and all iron mongry works, two coats of anti rust, three coats
of synthetic paint, 1mm thick ribbed sheet and door stopper. All
according to detail drawing.
Doors
D size800X800 covered with 1.5mm thick ribbed sheet no 8.00 5,831.07 46,648.56
D size 1200X1200mmdoor no - 5,831.07 -
D size 800x2100mmdoor pcs - -
internal tamburata door pcs - 5,831.07 -
5.02
Windows are manufactured from 38x1.5mm LTZ frame profile all
as per the engineers approval and window door schedule. Unit
price includes one coat of antirust and two coats of synthetic
enamel paint, best quality lock with hand type windows as per
detail drawing.
Window
W size 120X120cm no 7.00 2,048.86 14,342.02
W size 150X150cm no - 2,135.46 -
W size 150x200cm pcs - -
W size 80x65cm/top window/ pcs - 2,048.86 -
Total Carried to Summary 60,990.58
6.FINISHING
6.01 plastering
a)To internal and external wall surface. m² 68.23 134.66 9,187.85
6.02 for floor ceramic tiling 56.30 757.28 8,231.00
6.03 for wall ceramic tiling m² 32.00 642.53 20,560.96
6.04 for ceramic scarting m² 56.20 127.21 1,428.57
Total Carried to Summary 92,723.91
PROJECT ; RESIDENCE(VILLA)
LOCATION ; DEBRE MARKOS
OWNER :አቶ መንገሻ እንዳለው ዘሪሁን
Unit
No Description Unit Qty Price Amount
7. PAINTING
Apply three coats of plastic emulsion paint. Price shall include pre -
cleaning & preparation of the surface.
To internal plastered wall surface.
7.01 To internal wall surface m2 100.00 69.59 6,959.00
7.02 To external plasterd wall surface quartize paint m2 50.00 215.44 10,772.00
7.06 To filling paint m2 130.50 59.32 7,741.26
Total Carried to Summary 25,472.26
8. GLAZING
Supply and fix 4 mm thick clear sheet glass to metal beads and
puttied with approved quality of putty. m2 25.50 796.91 20,321.21
Supply and fix 4 mm thick froasted glass to metal beads and
puttied with approved quality of putty. m2 14.50 767.21 11,124.55
Total Carried to Summary 31,445.75
9. SANITARY INSTALLATION
SEPTIC TANKER no - 0.00 -
WASTE, VENT AND STORM WATER PIPES AND
ACCESSORIES
Supply and lay internal UPVC waste and vent pipes
9.01 according to where shown on the drawings. Complete with
all the necessary fittings.
Dia. 50 mm no - 63.75 -
" 80 " ml - 91.38 -
" 110 " ml - 212.50 -
9.05 paper holder - 204.00 -
9.06 man hole - 305.19 -
9.08 turkish type WC no - 1,020.00 -
9.11 soap holder - 531.25 -
9.12 Fix hand wash basin complete with all the necessary accessories
and fitting no 2.00 1,487.50 2,975.00
9.13 Shower trey 70x70cm with all accesary no 1.00 977.50 977.50
Total Carried to Summary 3,952.50
3. MASONRY WORK
3.01
400 mm thick basaltic or equivalent type
stone masonry bedded in cement
mortar(1:3) mix below ground surface.
price shall include cement mortar bed. m3 56.77 11.81 472.26 26,810.20 5,577.39
3.02
m2 - - - -
2.04 400mm deep Vertical Sun breaker of 190
mm Class C HCB wall between 150mm
reinforced slab (horizontal sun breakers)
m2 - - - -
2.06 Supply and install inclined type louvers
wall 190mm thick with horizontally fixed
mosquito mesh . The work shall be done
as per the detail drawing. Price includes
mosquito mesh.price shall include wire
mesh between HCB and angle iron.
ml - 67.55 - -
b) G-28 Galvanized sheet metal gutter of
dev. Length 620mm price includes two
coats of anti-rust and synthetic paint
ml 80.76 59.83 4,831.87 -
3.03 G-28 Galvanized sheet metal valley gutter ml - 0 - -
of dev. Length 700mm price includes two
3.04 a) Ditto item 3-2 but copping with flashing ml - 0 - -
coats of anti-rust and synthetic paint
dev. length 1000mm.
b) Ditto item 3-2 but fleshing copping dev. ml 62.02 86.33 5,354.19 -
length 880mm.
3.05
a) Ditto item 3-2 but dev. length. of
330mm for flashing ml - - - -
b) Ditto item 3-2 but flashing dev. length
650mm.
ml 16.04 63.77 1,022.87 -
3.06 2000mm wide sun shading fabric element
m2 - - - -
3.07 Supply and fix wire mesh ventilation size
60x60mm (in flat metal frames) under m2 31.98 150.00 4,797.00 -
eave with combination of ribbed sheet
size 120x60mm nailed to zigba wood
Total Carried
battens size40x50mm. Price to Summary
include three - - 60,830.59 43,656.88
coats of oil paint and all other necessary
accessories to complete the work.
CONTRACT NO: 0117/08- UCBP - DM -3B-700 CONTRACT TIME: 284 Calendar days
CLIENT: Ministry of Education COMMENCEMENT DATE: 12th Dec. 2008
CONSULTANT: MH Engineering & Architect PLC TIME ELAPSED:
CONTRACTOR: Inter Continental Construction PLC Block: No. DM -LH -D4 -XX- 609
Item Contract Executed Unit Contract Executed
No Description Unit Qty Qty Price Amount Amount
- - - -
4. CARPENTRY & JOINERY - - - -
4.01 Supply and fix 8 mm thick chip wood
ceilings. Price include 40 x 50 mm zigba
wood battens with c/c spacing of 600 mm
both ways, corner list and all other
necessary accessories to complete the
work.
ml - 0 - -
4.04.3
Sawn Zigba wood roof purlins50x70mm
placed at c/c 1200mm. ml - 0.00 - -
5.01 Doors
D1 size 870x2545mm covered with 1mm
thick ribbed sheet pcs 3.00 3 1120.67 3,362.01 3,362.01
D3 size 1180x2285mm covered with 1mm
thick ribbed sheet pcs 4.00 4 1364.71 5,458.84 5,458.84
D4 size 1180x3545mm partally covered
with 1mm thick ribbed sheet pcs 2.00 2 2117.23 4,234.46 4,234.46
5.02 Window
W1 size 780x2206mm pcs 8.00 8 818.80 6,550.40 6,550.40
W2 size 780x1335mm pcs 2.00 2 495.51 991.02 991.02
W3 size 580x580mm pcs 4.00 4 160.08 640.32 640.32
Window doors
CONTRACT NO: 0117/08- UCBP - DM -3B-700 CONTRACT TIME: 284 Calendar days
CLIENT: Ministry of Education COMMENCEMENT DATE: 12th Dec. 2008
CONSULTANT: MH Engineering & Architect PLC TIME ELAPSED:
CONTRACTOR: Inter Continental Construction PLC Block: No. DM -LH -D4 -XX- 609
Item Contract Executed Unit Contract Executed
No Description Unit Qty Qty Price Amount Amount
5.03
WD1 size (1580x2545)+(680x1335)mm pcs 3.00 3 2,201.49 6,604.47 6,604.47
5.06
8.08
Oil paint to cement wash wall surface m2 - 16 - -
RHS rafter
a)70X50x3mm. kg 1,073.65 560.14 36.95 39,671.37 20,697.17
4.02 RHS Purlins - -
a)60X40x3mm. kg 616.60 610.56 36.95 22,783.37 22,560.19
4.03 Metal plates
a)2(200x100x4 mm) Pcs 36.00 12.00 61.18 734.16
4.04 Bolts with nuts
c)Dia 12 mm bolt .Dev length =100 mm pcs 144.00 10.1 1,454.40 -
b)Dia 16 mm bolt .Dev length =110 mm with washer
and nut pcs 24.00 16.87 404.88 -
5.05 Angle Iron support
a)25 X 25 x 4 mm Length 40 mm pcs 72.00 72 7.32 527.04 527.04
b)50x50x4mm length 50mm pcs 12.00 36 12.17 146.04 438.12
6.05
4 .SANITARY INSTALLATION
4.01 WATER SUPPLY PIPES, VALVES AND
ACCESSARIES
4.1 Supply and install smoothly finished Cast insitu
concrete washing basin according to the detail
drawing , price shall include form work steel
reinforcement and all necessary accessories such as
smell traps ,floor drains, chain plugs , drain pipe and
water tap
No 64 64 1345.45 86,108.80 86,108.80
4.20 supply and install galvanized steel pipe to water
distribution system - -
Dia. 15Mm Ml 18.72 36.48 85 1,591.20 3,100.80
Dia . 20Mm Ml 21.65 9.6 103.96 2,250.73 998.02
Dia.25mm Ml 35.52 19.2 146.99 5,221.08 2,822.21
Dia.32mm Ml 0.51 59.3 109.76 55.98 6,508.77
4.30 Supply and fix approved quality bronze gate valve
- -
working pressure or 50 meters head, which ever is
greater at - -
Dia. 15Mm pcs 6 16 249.49 1,496.94 3,991.84
Dia . 20Mm pcs 10 16 323 3,230.00 5,168.00
Dia.25mm pcs 16 32 458.18 7,330.88 14,661.76
Dia.32mm pcs 2 4 602.88 1,205.76 2,411.52
4.2 WASTE ,VENT AND STORM WATER PIPE
AND ACCESSORIES - -
Supply and lay internal upvc (pn4 ) wast and
4.21 vent pipie - -
Dia. 50'' Ml 11.1 25.6 152.77 1,695.75 3,910.91
Dia 80'' Ml 9.16 19.6 132.64 1,214.98 2,599.74
Dia.110'' Ml 9.88 84 134.93 1,333.11 11,334.12
Total Carried to Summary 112735.21 143616.49
CONTRACT NO: 0117/08- UCBP - DM -3B-700 CONTRACT TIME: 284 Calendar days
CLIENT: Ministry of Education COMMENCEMENT DATE: 12th Dec. 2008
CONSULTANT: MH Engineering & Architect PLC TIME ELAPSED:
CONTRACTOR: Inter Continental Construction PLC Block: No. DM -LN -T2 -XX- 817
Item Contract Executed Unit Contract Executed
No Description Unit Qty Qty Price Amount Amount
A. SUBSTRUCTURE
1. EXCAVATION AND EARTH WORK
1.01
Site clearing and removing the top 200 mm thick soil m2 144.00 144 4.57 658.08 658.08
1.02 Bulk excavation in ordinary soil to a depth of 1500 mm
from reduced level. m3 144.00 7.20 31.73 4,569.12 228.46
1.03
Cartaway surplus excavated material to appropriate tip m3 115.20 36 41.61 4,793.47 1,497.96
1.04 Gravel fill m3 1.73 3.58 274.22 474.40 981.71
1.05 Fill under hard core with imported selected materials
from out side well rolled and compacted in layers not
exceeding 200 mm thick. m3 57.60 20.43 118.69 6,836.54 2,424.84
1.06 250mm thick basaltic stone hardcore well rolled,
consolidated and blinded with crushed stone . m2 15.27 136.17 41.61 635.38 5,666.03
RHS rafter
a)70X50x3mm. kg 1,073.65 560.14 36.9 39,617.69 20,669.17
4.02 RHS Purlins - -
a)60X40x3mm. kg 616.60 610.56 36.9 22,752.54 22,529.66
4.03 Metal plates
a)2(200x100x4 mm) Pcs 36.00 12.00 62.5 750.00
4.04 Bolts with nuts
c)Dia 12 mm bolt .Dev length =100 mm pcs 144.00 10.1 1,454.40 -
b)Dia 16 mm bolt .Dev length =110 mm with washer and
nut pcs 24.00 16.87 404.88 -
5.05 Angle Iron support
a)25 X 25 x 4 mm Length 40 mm pcs 72.00 72 7.32 527.04 527.04
b)50x50x4mm length 50mm pcs 12.00 36 12.17 146.04 438.12
6.05
4 .SANITARY INSTALLATION
4.01 WATER SUPPLY PIPES, VALVES AND
ACCESSARIES
4.1 Supply and install smoothly finished Cast insitu concrete
washing basin according to the detail drawing , price
shall include form work steel reinforcement and all
necessary accessories such as smell traps ,floor drains,
chain plugs , drain pipe and water tap
S U M M A R Y
ITEM
NO DESCRIPTION AMOUNT ( Birr )
A. SUB - STRUCTURE
1 Excavation and Earth Work 74,858.98
2 Concrete Work 74,673.18
3 Stone Masonry 40,621.04
Sub - Tota (A ) 149,532.17
B. SUPER STRUCTURE
1 Concrete Work 56,939.46
2 Block Work 133,209.11
3 Roofing 58,620.69
4 Carpentry & Joinery 78,414.93
5 Metal Work 60,990.58
6 Finishing 92,723.91
7 Painting 25,472.26
8 Glazing 31,445.75
Sub - Total ( B ) 537,816.68
C. UTILITIES / FACILITIES
9 Sanitary Installation 3,952.50
10 Electrical Installation 20,748.76
Sub total C 24,701.26
TOTAL ( A + B +C ) 712,050.11
TOTAL (A+B) 712,050.11
OWNER :አቶ እንዳልካቸው ሙሉ ታደሠ
1. Fance work
1.01 site clearing to 200mm thickness m2 12.12 19.31 234.04
1.02 Treanch excavation m3 8.60 152.25 1,309.35
1.03 backfill and compaction m3 6.13 517.08 3,169.70
1.04 masonry work m3 7.14 1,345.60 9,607.58
1.05 20CM HCB Wall m2 20.08 406.50 8,162.52
1.06 reandering, dressing and plastering
for fance wall m2 45.12 201.69 9,100.25
1.07 painting for fance wall m2 41.35 60.05 2,483.07
1.1. Concrete work
2.01 elevation column m3 3.02 2,898.58 8,753.71
2.02 gread beam m3
1.52 2,898.58 4405.8416
1.2. Metal work -
3.01 diameter 6 plian bar kg 32.12 82.59 2,652.79
3.02 diameter 10 deformed bar kg 64.32 81.00 5,209.92
3.03 fance door by LTZ Ribed sheet no 3.00 5,617.77 16,853.31