Production Schedule

Please include location, time of film, what you are filming and team members including
actors
A = Animation
SF= Short film

Date Plan of action Team Members

Mon 7th Dec A Build set for animation, including characters. Josh
Tue 8th Dec A Film Opening sequence of animation and get the Josh
music for it and make the logo.
Wed 9th Dec A Film animation Josh
Thurs 10th Dec A Film animation Josh
Fri 11th Dec A Record Foley sounds for my animation and find Josh
the ones I’m not able to record
Mon 14th Dec A Record all dialogue for my animation Josh, Craig, Bilal
Tue 15th Dec SF Record House scene for short film Josh, Bilal
Wed 16th Dec SF Record flashback scene Josh, Bilal
Thurs 17th Dec SF Record the ally way scenes Josh, Bilal, Craig
Fri 18th Dec SF Record any needed Foley sound for my short Josh
film. Watch over all footage and see if I need any
reshoots.