Professional Documents
Culture Documents
CB510P Ch7b PDF
CB510P Ch7b PDF
Progress Control – Earned Value
Prof. Omar El‐Anwar
Earned Value Method
Measures performance with regards to
• Schedule
• Cost
Three Measures:
• Budgeted Cost of Work Scheduled (BCWS)
• Budgeted Cost of Work Performed (BCWP), or
Earned Value
• Actual Cost of Work Performed (ACWP)
1
12/22/2016
Budgeted Cost of Work Scheduled
(BCWS) or Planned Value (PV)
• Estimated cost of work scheduled to be
performed during a specific period of time
• Cost‐loaded schedule
Cost‐Loaded Schedule
2
12/22/2016
Budgeted Cost of Work Scheduled
(BCWS)
Cost‐Loaded Schedule:
BCWS after 3 weeks = $89,000
Budgeted Cost of Work Performed
(BCWP), or Earned Value (EV)
• BCWP or Earned Value
• Estimated cost of work actually performed
during a specific period of time
Use % complete for unfinished tasks
3
12/22/2016
Actual Cost of Work Performed
(ACWP) or Actual Value (AV)
• Actual cost of work performed during a
specific period of time
Example of Earned‐Value Method
• You are managing a design project. The initial
estimate of work hours required was 2,800.
• You have 3 engineers assigned to the project full
time (8 hours per day, 5 days per week) and one
engineer assigned to the project half‐time (4
hours per day, 5 days per week).
• Each engineer’s work is charged to the project at
$50 per hour.
• At the end of 15 weeks, 80% of the design work
has been completed at a cost of $130,000
8
4
12/22/2016
Example of Earned‐Value Method
• What would the duration of the project be
based on the original estimate of work
hours?
• Calculate BCWS, BCWP, ACWP.
Example of Earned‐Value Method
• What would the duration of the project be based on the
original estimate of work hours?
• Number of working hours/week = 3x8x5 + 1x4x5 = 140
hrs/week
• Estimated Project Duration =
initial estimate of work hours / No. of working hrs/week =
2,800/140 = 20 weeks
10
5
12/22/2016
Example of Earned‐Value Method
• Calculate BCWS, BCWP, ACWP.
• By the end of the 15th week, the number of work hours
scheduled = (15/20) x 2,800 = 2,100 hrs
• BCWS = $50/hr x 2,100 hrs = $105,000
• Work performed is 80% = 0.8 x 2,800 = 2,240 hrs
• BCWP = $50/hr x 2,240 hrs = $112,000
• ACWP = $130,000
11
Earned‐Value Method
• Measures progress of work
– Schedule Variance (SV)
– Schedule Performance Index (SPI)
• Measures control of budget
– Cost Variance (CV)
– Cost Performance Index (CPI)
• Total Estimated Cost at Completion
12
6
12/22/2016
Measure Progress of Work
• Schedule Variance (SV)
SV = BCWP – BCWS
+ve: Ahead of Schedule
–ve: Behind Schedule
• Schedule Performance Index (SPI)
SPI = BCWP/BCWS
>1 : Ahead of schedule
<1 : Behind schedule
13
Measure Control of Budget
• Cost Variance (CV)
CV = BCWP – ACWP
+ve: Under budget
–ve: Over budget
• Cost Performance Index (CPI)
CPI = BCWP/ACWP
>1 : Under budget
<1 : Over budget
14
7
12/22/2016
Total Estimated Cost at Completion
(EAC)
• Assumes current performance will
continue
Total Estimated Cost at Completion = Original
Total Estimate (BAC)/CPI
• Assumes current performance will not
continue
Total Estimated Cost at Completion = Original
Total Estimate (BAC) ‐ CV
15
Example of Earned‐Value Method
(Continued)
• Evaluate project progress to data. Is the
project behind schedule or ahead of
schedule?
• Evaluate control of project budget to date.
Is the project over budget or under
budget?
• Forecast total project cost at completion
assuming that current performance will
continue
16
8
12/22/2016
Example of Earned‐Value Method
(Continued)
• Evaluate project progress to data. Is the project
behind schedule or ahead of schedule?
SV = BCWP – BCWS
= $112,000 ‐ $105,000 = $7,000 (+ve) Ahead of
Schedule
Or
SPI = BCWP / BCWS = $112,000 / $105,000 = 1.067
(>1) Ahead of Schedule
17
Example of Earned‐Value Method
(Continued)
• Evaluate control of project budget to date. Is the
project over budget or under budget?
CV = BCWP – ACWP =
$112,000 ‐ $130,000 = $‐18,000(‐ve) Over Budget
Or
CPI = BCWP / ACWP =
$112,000 / $130,000 = 0.86(<1) Over Budget
18
9
12/22/2016
Example of Earned‐Value Method
(Continued)
• Forecast total project cost at completion
assuming that current performance will
continue
Budgeted cost at completion (BAC) =
2,800 hrs x $50/hr = $140,000
Total Estimate Cost at Completion (EAC) =
BAC/CPI = $140,000/0.86 = $162,500
19
Earned value: basic elements
Apr. Term Information
PV Planned value What is the estimated value of the work planned to be
(BCWS) done
ETC Estimate to From this point on, how much more do we expect to
completion pay until the end of the project
10
12/22/2016
Earned value: basic elements
Term Formula
CV EV –AV
Cost variance
SV EV –PV
Schedule variance
CPI EV/AV
Cost performance
index
SPI EV/PV
Schedule performance
index
EAC BAC/CPI or BAC – CV (based
Estimate at completion on assumption)
ETC EAC - AV
Estimate to completion
VAC BAC – EAC
Variance at completion
21
Questions?
11