Professional Documents
Culture Documents
Procedure of Boiler Acid Cleaning: and Flushing & Passivation
Procedure of Boiler Acid Cleaning: and Flushing & Passivation
The cleaning activities will be executed after the unit has accomplished its leak
test and flushing. All utilities, instrumentation, and equipment support has been
check out and ready for the service. De-aerator is needed to heat-up the
demineralized water by contacting with auxiliary steam.
The overall cleaning procedure contains two steps as follows: Acid Cleaning
and Flushing & Passivation.
I. ACID CLEANING
1.1. Objective
1.2 Procedure
1) Run the de-aerator unit to heat up the Boiler feed water to get
120 oC of water temperature.
2) Fill up the boiler with de-aerated (hot) water to the normal
water level through the feed pipe normally used during
operation.
3) After reach the normal level, Confirm the water temperature in
the Boiler less than 98 OC, if the temperature higher than 98 C,
run the cooling system.
4) Circulate the Boiler water by (temporary) Chemical injection
system facility, provided by Nalco.
5) Add the Citric Acid and inhibitor to the mixing tank, to get the
complete circulation (by temporary Injection system).
6) Circulate the Boiler by permanent circulation pump.
7) Confirm the pH is in the range of 3 – 4, (adjust using Ammonia
to increase the pH and citric acid to reduce the pH).
2.1 Objective
The objective of this step is to avoid flash corrosion from the active
metal surface (after acid cleaning) and passivate the metal surface.
Ammonia and sodium nitrite is required in this step.
2.2 Procedure
a. After the acid cleaning finished, drain the water/acid inside
the boiler and fill the boiler with de-aerated boiler feed water
at 120 oC.
b. Circulate for 30 minutes, and check for iron concentration.
c. If the iron concentration is higher than 200 ppm make up
and blow-down the water to reduce iron concentration, after
the soluble iron is less than 200 ppm then add amonia to the
boiler to rise the pH to 9-11.
d. Add 0.5 % Sodium nitrite to the boiler, keep the water level
on the normal level.
e. Continuous circulation for 8 hours to get sufficient contact
time and satisfactory passivation step.
f. When the above step has completed, drain all the water in
the boiler.
g. Rinse the boiler using De-aerated water until all drain had
cleared.
h. The boiler is ready to be inspected.
III. WET LAY UP PROCEDURE
1. Use only high purity water (distilled or demineralized) for filling the
superheater section.
2. Treat the deionized water only with chemicals that do not leave a solid
residue when the water is evaporated.
4. Test the water each week for pH and Hydrazine content (when possible)
to make sure treatment levels are being maintained. As in the wet lay-up
procedure, the unit must be kept completely full of water to prevent air
pockets.