Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

Design Flood Estimation-Hydro Meteorological Approach

By

N.N.Rai
Director, Hydrology (S)
Central Water Commission

1.0 Introduction

For any hydraulic structure the design flood of a selected return period, Standard
Project Flood or Probable maximum Flood depending upon the size of structure is
required to be estimated. The designer is mainly cocerened with the peak value of
the flood for many structures like bridges, barrage/weirs, cross drainage
structures and small storage structures. On the other hand the volume of flood as
well as the shape of the flood hydrograph are also needed while designing
major/intermediate storage structures. The following two approaches are very
commonly adopted for estimating design flood.

1. Statistical approach commonly known as flood frequency analysis


2. Hydro meteorological approach commonly known as unit hydrograph
approach

In both of the above approaches, adequate data inputs are required for processing
and obtaining the design flood outputs. The inputs are generally the long term and
short term rainfall and runoff records, annual flood peaks series, catchment or
physiographic characteristics etc. The detailed methodology to be adopted in a
particular case depends upon the data availability.

2.0 Inflow Design Flood for the safety of the dam

The inflow design flood for safety of the dam is selected on the basis of the
classification of the dam as follow:

Classification Gross storage (Mm3) Hydraulic head Design flood

(m)

Small Between 0.5 and 10 Between 7.5 and 12 100 yr flood

Intermediate Between 10 and 60 Between 12 and 30 SPF

Large Greater than 60 Greater than 30 PMF


3.0 Hydro Meteorological Approach

In the hydro meteorological approach attempt is made to analyse the causative


factors responsible for production of severe floods. The design flood computation
mainly involves estimation of a design storm hyetograph and derivation of
catchment response function (unit hydrograph). The catchment response function
used can be either a lumped system model or a distributed lumped system
model. In the former the unit hydrograph is assumed to represent the entire
catchment area. In the distributed model the catchment is divided into smaller
sub-catchments, and the unit hydrograph of each sub-catchment applied with
channel and reservoir routing will define the catchment response. The main
advantage of the hydro meteorological approach is that it gives a complete flood
hydrograph and this allows making a realistic determination of its moderating
effect while passing through a reservoir or a river reach. This approach however
subjected to certain limitations such as:

 Requirement of long term hydro meteorological data for estimation of


design storm parameters
 Availability of SRRG data
 Assumptions in unit hydrograph theory

3.1 Data for storm studies

The basic data required in storm studies are (i) daily rainfall records of all
raingauge stations in and around the region under study, (ii) rainfall data of self
recording raingauges (iii) data of storm dew point and maximum dew point
temperature. The IMD publications are important source of these data.

3.2 Design storm duration

For all practical purposes the unit hydrograph base governs the duration of of the
storm depth. For unit hydrograph having a base of 24 hours or less, the design
storm of one day is considered appropriate and sufficient. In case the UG base is
more than 24 hours and less than 48 hours 2 day design storm should be
considered sufficient. For basins having UG base of more than 48 hours a design
storm of 3 days should be considered. Storms of periods exceeding 72 hours are
not generally required to be considered in the design flood estimation.

3.3 Estimating Probable Maximum Storm (PMS)

The most common method of estimating PMS for a project basin is the one
involving the transposition of selected major storms to the project basin and its
maximization there. The three main steps of the transposition and maximization
method are (i) selection and analysis of past major storms on record considered
transposable to the project basin, (ii) Adjustment of these transposed storms for
maximum moisture that could occur over the project basin, iii) envelopment of
the transposed adjusted storms
3.3.1 Storm Transposition

Storm transposition means application of a storm from one rea to another area
within the same meteorologically homogenous region. Further the orientation of
the storm should not be adjusted by more than 20 degree. The transposition
should not be attempted if it involves crossing a barrier or change in elevation of
800 m. No storm should be transposed in general beyond 2 degrees latitude or
longitude from place of its occurrence.

3.3.2 Maximisation of selected storms

The maximaisation of selected storms is carried out by multiplying the


transposed storm rainfall depths (obtained by Depth Area Duration analysis)
with a factor. This factor is called moisture adjustment factor MAF).

MAF = maximum precipitable water over basin/storm precipitable water

3.3.3 Envelopment of transposed adjusted storms

The last step in the estimation of the probable maximum storm for a basin is to
envelop the transposed adjusted storm depths. Assuming that the storm isohyetal
pattern will fit perfectly over the basin, the maximum average depths of rainfall
for various durations are first read of the DAD curves, of each of the transposable
storms for an area equal to the drainage area of the project. These values in
respect of each storm are then adjusted for maximum moisture by multiplying
them with respective MAF. The adjusted data are plotted on a graph and smooth
envelope curve drawn through the highest values. This envelop curve furnishes
the probable maximum rainfall depths for the basin.

3.4 Generalised PMP Atlases

Generalised PMP atlases were published by Central Water Commission during


the year 2014-15 for the different river basins of the country. These atlases
available on downloadable PDF format on CWC web site, aid as a ready reckoner
for arriving at a first hand estimate of design storm depths for any project,
existing or being planned in the respective region. From these atlases the 1-day, 2-
day, 3-day PMP depth for a particular catchment area of the project can be
directly obtained. The 1-day PMP depth is converted to 24-hour PMP depth by
multiplying it with a factor of 1.15 known as clock hour correction. The increase
in 1-day rainfall may however be limited to 50 mm. The Standard Project Storm
depth of different durations can be read from the relevant DAD curve of the PMP
atlases. The 24 hour PMP/SPS depth as obtained after clock hour correction is
further distributed in two bells of 12 hours each. The hourly distribution
coefficients of the rainfall are also given in PMP Atlas and the same should be
used to get the hourly rainfall. From the hourly rainfall increments the hourly
loss as per relevant Flood Estimation Report of CWC should be deducted to get
the hourly effective rainfall increments.
3.5 Basin response characteristics (Unit Hydrograph)

The catchment response function used can be either a lumped system model or a
distributed lumped system model. In the former, a unit hydrograph is assumed to
represent the entire catchment area. In the distributed model, the catchment is
divided into smaller sub-regions, and the unit hydrographs of each sub-regions
applied with channel and/or reservoir routing will define the catchment response.
Hydro-meteorological Approach

3.5.1 Definition of Unit Hydrograph

A Unit Hydrograph is the runoff hydrograph that results from one cm of excess
precipitation distributed uniformly over the watershed at a uniform rate during
the specific period/ unit period /unit duration.A unit hydrograph, thus, has a
duration and that duration represents the duration of the excess precipitation that
generates the unit graph. For example, when one speaks of a one-hour unit
hydrograph, they are talking about the runoff resulting from a one-hour storm that
produces one cm of excess precipitation. The duration, being a very important
characteristic, is used as a prefix to a specific unit hydrograph. The duration of
unit hydrograph may be 1 hr, 2 hr or 3 hr or so depending upon the size of
catchment and storm characteristics. However, the unit duration should be
preferably equal or less than 1/3rd of the time of concentration/basin lag /the
period of rise.

3.5.2 Derivation of Unit Hydrograph

The unit hydrograph is best derived from the observed hydrograph resulting from
a storm which fulfills the two basic conditions i.e. the rainfall is more or less
uniformly distributed over the basin and has a reasonably uniform intensity. Such
a hydrograph will generally form a singly and sharp peak. In case, such a
hydrograph is not available then the unit hydrograph has to be derived from the
analysis of an observed complex event. When observed discharge and rainfall data
at short interval are not available, then synthetic unit hydrographs are derived
with the help of basin characteristics.

Synthetic Unit Hydrograph (SUG)

Synthetic unit hydrographs are often required at the locations where hydrologic
records are not available and also as a means of correlating and supplementing
observed data. SUG are derived based on relationships found between various
characteristics of a standard unit hydrograph and descriptors of basin
morphology. These relations are applicable only to the specific regions in which
they are developed.
Where adequate rainfall-runoff data are lacking, a synthetic unit hydrograph may
be developed based on known physical characteristics of the basin. Some of the
methods for derivation of synthetic unit hydrograph for a basin are:

a. Snyder’s method
b. Transposition of unit hydrograph
c. Formulae developed by CWC as adopted in the Flood Estimation
Reports of various sub-zones of India

Snyder’s method

Among several known methods for development of synthetic unit hydrographs,


the one developed by Snyder is most commonly referred to. Snyder analysed a
large number of hydrographs from drainage basins in the Appalachian Mountain
region in United States ranging in area from 25 Sq km to 25,000 Sq km and
developed the following relations.

tp = Ct(LLc)0.3
tr = tp/5.5
qp = Cp/tp
T = 3(1+tp/24)

where, tp = lag time from mid-point of effective rainfall duration to peak of a unit
hydrograph,in hours;

tr = standard duration of effective rainfall in hours;


qp = peak discharge per unit discharge area of unit hydrograph for
standardized duration, tr in cumecs/Sq. km;
T = base length of the unit hydrograph for standard duration tr, in days
Ct and Cp are coefficients

The value of Snyder’s coefficient Ct and Cp are found to vary considerably


depending upon the topography, geology and climate. Snyder indicated that C t is
affected by basin slope S. Linsley, Kohler and Paulhus have suggested an
expression for tp in which the basin slope S has been considered

2
 LL 
t p  Ct  c 
 S

Snyder’s method is not advocated to be used due to obvious reasons.

Transposition of Unit Hydrograph

If unit hydrograph is available for several areas adjacent to a basin for which a unit
hydrograph is required but for which necessary data are lacking, then
transposition of available unit hydrograph will ordinarily give better results than
resorting to a wholly synthetic procedure. One of the commonly used procedures
is to derive a dimensionless unit hydrograph and then use the same for deriving
unit hydrograph for the ungauged basin

Flood estimation reports of CWC

The Central Water Commission (CWC) in association with Indian Meteorological


Department (IMD), Ministry of Railway and Ministry of Surface Transport have
prepared Flood Estimation Reports for small and medium catchments. However,
these reports are finding use even for large catchments. In such a case the large
catchment is subdivided into sub catchments and these reports can be
conveniently used for each sub-catchment individually and the total effect of the
entire catchment can be studied along with other principles of Hydrology such as
channel routing etc.

For this purpose of publication of these reports, the country has been divided into
26 hydro-meteorologically homogenous sub-zones. Theoretically the sub zones are
considered to be hydro meteorologically homogeneous but some of the parameters
such as the slope of the river, land use etc vary with in these sub zones. In each of
the sub-zones, data at sufficient number of sites is available. The data at these
stations are helpful in studying the variability of hydrologic and physiographic
properties with in the catchment.

Unit Hydrograph from a Hydrograph with Isolated Peak

The various steps involved in derivation of unit hydrograph from the analysis of
the flood hydrograph with a single and sharp peak are as follows.

(a) Inspection of discharge record and identification of events with isolated,


well defined and single peak with considerable runoff volume.
(b) Processing of hourly gauge data and converting them in discharge with the
help of rating curve corresponding to each of the identified flood
hydrograph.
(c) Separation of bases flow and computation of direct runoff hydrograph
ordinates by deducting base flow ordinates from the corresponding
observed flood hydrograph ordinates.
(d) Determination of the volume of the rainfall data of all the raingauge station
in and around the basin with a view to:
(i) Ensure that uniform rain has occurred over the entire basin: and
(ii) Estimation of the duration of the effective rainfall.

(e) Estimation of the ordinates of the unit hydrograph by dividing the


ordinates of the direct runoff hydrograph by effective rainfall.

The unit duration of the unit hydrograph will be the duration of the effective
rainfall as worked out at step (e). It is desirable that the amount of direct runoff
(or the effective rainfall) is more than 10mm.
Unit Hydrograph from Complex Flood Hydrograph

Very few flood hydrographs with single and sharp peak resulting from an intense
& uniform rainfall in relatively very short interval of time are available. In most of
the cases the effective rainfall duration is relatively large with varying intensity of
rainfall with time resulting in complex event. Nash model and Clark Model base
on Instantaneous Unit Hydrograph (IUH) are commonly used one to derive the
UH from complex flood hydrograph.

Instantaneous unit hydrograph

Instantaneous Unit Hydrograph (IUH) is defined as a unit hydrograph of


infinitesimally small duration. In other words, IUH is the direct runoff
hydrograph at the outlet of the catchment resulting from 1 unit (1 cm) of rainfall
falling over the catchment in no time. Of course, this is only a fictitious situation
and a concept to be used in hydrograph analysis.

Nash model

Nash proposed a conceptual model for deriving IUH by routing unit impulse
input through a number of “n” identical linear reservoirs in series of equal storage
coefficient; K. Nash gave method of moment to derive the parameter nand K from
the historical rainfall-runoff of flood events. The shape of IUH was derived to be
two parameter Gamma function. The ordinate of the IUH at time t is given by,

n 1
1  t  -t
U(t)    e K
K n - 1!  K 
Where, n = no. of reservoirs; and

K = a reservoir constant, called storage coefficient.

The values of ‘K’ and ‘n’ in Nash model can be evaluated by the method of
moments using the following relations:

MDRH1-MERH1 = nK

MDRH2-MERH2 = n(n+1)K2 + 2nK MERH1

where,

MDRH1 = first moment arm of DRH

MERH1 = first moment arm of ERH

MDRH2 = second moment arm of DRH


MERH2 = second moment arm of ERH

The unit of the ordinate of IUH is per sec. (sec -1). When the ordinates are
multiplied by the total volume of runoff (in cubic meters) resulting from 1 mm of
rainfall over the catchment area, the unit will be cumec.

Clark model

Clark method assumes that the rainfall first undergoes pure translation and then
attenuation. The translation is achieved by a travel time-area histogram and
attenuation by routing results of above through a linear reservoir at the catchment
outlet. Clark suggested that IUH could be derived by routing time area
concentration curve trough a single linear reservoir.

The Clark model uses two parameters, time of concentration and storage constant.
The first parameter, time of concentration is the time taken by a water particle
from hydraulically most distant point to the basin outlet. The estimate of this lag
time is time from the end of effective rainfall over the basin to point of inflection
on the recession limb of the direct surface runoff hydrograph. The second
parameter storage constant, K, which has dimension of time, represents the rate of
withdrawal of water from storage in the channel system. This parameter can be
estimated by dividing the flow at point of inflection of the surface runoff
hydrograph by rate of change of discharge at the same time. The other necessary
item to compute IUH is the time area relation. For this purpose, the catchment area
is divided to sub areas by various isochrones

The Clark method translates incremental runoff from sub areas with in the
catchment to the outfall point according to the travel times and then routes this
runoff through linear reservoir in order to account for the storage effects of the
basin and channels.

Time of concentration (tc) is defined as the travel time of water particles from the
most upstream point (timewise) in the basin to the outflow location. This lay may
be estimated by measuring the time between the end of effective rainfall over the
catchment and the inflection point on the recessions limb of the surface runoff
hydrograph when the time of concentration has been determined, the basin is
divided into incremental runoff producing areas that have equal travel time in the
outflow location. The distance from the most upstream point in the basin is
measured along the main watercourse to the outflow location. Dividing this
distance by tc gives the rate of travel or distance traveled in unit time.

Preliminary estimates of time of concentration can be done using California


formulae. In MKS units the formula is as under

L3
t c  (0.87 )
H
and in FPS units the formula is

L3
t c  (11.9 )
H
Where

L= length of mainstream in km or miles

H = Difference in elevation in m or ft.

Isochrones representing equal travel time to the outflow location are laid out
using the distance traveled per unit to establish the location of lines. The
increment of time used to subdivide the catchment need only be small enough to
adequately define the areal distribution of runoff. The area between the
isochrones are measured and tabulated with the corresponding travel time (o to tc)
for each incremental area. The time period selected as the computation in travel
should be approximately equal to unit duration of excess.

The runoff from the contributing areas (between isochrones) which has been
translated to the outflow location is in units of volume and these must be
converted to proper units of discharge. This conversion is as shown below:

0.278ai
Ii  ---------------- (1)
t
Where,

Ii = ordinate in proper unit of discharge (m3/s) of the time area runoff volume
at the end of period i.

ai = ordinates in unit of depth-area of excess (mm-Km2) of the time area runoff


at the end of the period i

t = time period of computation interval in hours

The routing of the translated runoff through storage at the outflow location is
accomplished as follows

Oi  CI i  (1  C )Oi 1 -------------------(2)

Where

Oi = Outflow from the basin at the end of period i in m3/s

Ii = Inflow or runoff from each area at the end of the period i


C = Dimensionless routing constant

The routing constant is

2 t
C --------------------(3)
2 K  t
Where

t = time period of computation interval

K = attenuation constant having dimension of time

Q
K -------------------(4)
dQ / dt
The magnitude of ‘K’ can be approximately evaluated at the point of inflection of
the recession limit of the observed surface runoff hydrograph. This ratio decreases
to a minimum at the point of inflection by the rate of change of discharge (slope) at
the same point. Another technique is to compute the volume of runoff remaining
under the recession limits of the surface runoff hydrograph following the point of
inflection and divide by the discharge at the same point. The hydrographs that
results from routing these flows from incremental areas is the instantaneous unit
hydrograph, which can be corrected to a unit hydrograph of a unit duration t.

Derivation of Unit Hydrograph from IUH

To get a t-hour unit hydrograph from IUH, the ordinates of IUH are lagged by t
hours, then the sum of IUH ordinate and t-hour lagged IUH ordinates are divided
by 2 to get the UH ordinates of t-hour duration.

3.6 Computation of design flood hydrograph

For estimation of design flood hydrograph, the effective rainfall increments of each
bell are rearranged with respect to ordinates of UH, such that the maximum
rainfall is placed against the maximum UG ordinate, next lower value of effective
rainfall against next lower value of SUG ordinate and so on. The effective rainfall
arrangement obtained are then reversed to obtain critical sequence. The sum of the
product of UG ordinates and critically sequenced effective hourly rainfall gives
total surface runoff to which base flow is added to get the ordinates of the design
flood hydrograph.

3.7 Case study-Design flood computation Gopi Krishna Sagar Project (M.P.)
by hydro-meteorological approach

The case study is enclosed as Annexure-1


4.0 Conclusion

Estimation of design flood for the design of different type of hydraulic structures
is a very significant component of hydrological studies. While a higher value
results in increase in the cost of structure, an underestimated value is likely to
place the structure and the population involved at risk. Hence proper selection of
design flood values is of great importance. Consequently the efforts should be
made to collect the adequate hydro-meteorological data to arrive at a reasonable
estimate of design flood for any hydraulic structure.
Annexure-I

Design Flood Estimation by Hydro-meteorological Approach


Case Study-Gopi Krishna Sagar Project (M.P.)

1.0 Introduction

The Gopi Krishna Sagar project is located on Chopan river in Guna district of Madhya
Pradesh. The catchment area of the project upto the dam site is 294 sq. km. The latitude
and longitude of the project site are 24032’55” N and 77014’03” E respectively. The gross
storage capacity of the reservoir is about 85.01 MCM and the height of the dam, an
earthen dam, is 30.8 m. The project completed in year 1985, was originally designed for
design flood of 3605 cumec. As per BIS criteria, the dam is classified as large dam and
therefore, qualifies for PMF as design flood. The design flood studies for the project has
been reviewed in year 2010 using hydro-meteorological approach.

2.0 Design Flood Studies

The dam was originally designed for 3605 cumec design discharge. The present design
flood studies have been carried out using hydro-meteorological approach. All the
physiographic parameters of the project catchment required for deriving the unit
hydrograph have been estimated by GIS processing of SRTM_52_08 Digital Elevation
Model. The same are given in Plate-1. The Probable Maximum Precipitation (PMP) has
been taken from the relevant PMP atlas. From the PMP atlas of Chambal, Betwa, Sone and
Mahui rivers, the 1-day areal PMP for 1000 km2 is 500 mm (Table : 14-XI of PMP atlas).
The corresponding 1-day point PMP has been calculated as 609.76 mm. The 24 hr areal
PMP corresponding to catchment area of the project has been used for the convolution
with UH taking two bells of 12 hour each. The UH parameter (Please see relevant
equations as given in Table-A) have been calculated as per FER subzone-1(b). The
notations of UH parameters are given in Plate-A. The loss rate has been adopted as 1 mm
per hour as given in sub zone 1(b) FER, considering the small catchment area as well as
PMF condition for the project. The computation in brief and the resulting design flood
hydrograph are given on subsequent pages. The PMF has been worked out as 4209 cumec.
Plate-A: Notations of UH Parameters

Table-A: Equations to calculate the UH parameters for FER Subzone-1(b)

tp= 0.339 (L/√S e)0.826 qp= 1.251/( tp)0.610 TB=6.662(tp)0.613

W50=2.215/( qp)1.034 W75=1.191/( qp)1.057 WR50=0.834/( qp)1.077

WR75=0.502/( qp)1.065
Plate-1
Design Flood Computations
Name of the project/ site: Gopi Krishna Sagar (MP)

Lat : 240 32' 50"


Long : 770 13' 55"

Table-1: Equivalent stream slope

Point Reduced Di Li (km) (Di+Di-1)Li


level (m)
(m)
1 432 0 0.00 0
2 445.30 13.30 5.00 66.5
3 465.30 33.30 6.45 300.57
4 485.30 53.30 6.80 588.88
5 505.30 73.30 6.20 784.92
6 525.30 93.30 5.60 932.96
7 545.30 113.30 1.25 258.25
ΣLi=L=31.3 km ΣLi(Di+Di-1)=2932.08 m.km
ΣLi(Di+Di-1) 2.993 m/km
Seq =
L2

Physiographic parameters

Sr. No. Parameter Value


1 Catchment Area (A) 294 km2
2 Longest river length from outlet (L) 31.3 km
3 Centroidal river length from outlet (LC) 15.7 km
4 Equivalent stream slope along longest river (Se) 2.993 m/km

Table-2: Unit Hydrograph parameters


[FER 1(b)]

tp 3.7059 say 3.7 hr


qp 0.5626 cumec/sqkm
W50 4.0145 hr
W75 2.1855 hr
WR50 1.5494 hr
WR75 0.9262 hr
TB 14.8709 hr
Tm 4.2000 hr
Qp 165.42 cumec
Table-3: Unit Hydrograph Ordinates

Time Discharge
(hr) (m3/sec)
0 0
1 30
2 64
3 120
4 165
5 136
6 98
7 64
8 46
9 34
10 24
11 16
12 11
13 6
14 3
15 0
Table-4: Rainfall Depth

Design Storm: PMP

1 day areal PMP for 1000 sq.km. from PMP altas of Chambal basin (Table-14 XI of atlas) = 500 mm
1 day point PMP = 500/0.82 = 609.75 mm
1 day areal PMP for 294 sq.km CA of project = 0.89x609.75 =542.68 mm
(Note: 0.89 is areal reduction factor as per FER-1(b) used for converting the point rainfall into areal rainfall)
24 hr areal PMP = 542.68 + 50 = 592.68, where 50 mm is the clock hour correction
Areal PMP depth for 1st 12 hr bell = 0.79x592.68 = 468.22 mm
(Note: for 1st 12 hour the rainfall depth is 79% of the 24 hour rainfall depth as per FER-1(b) Rainfall
Distribution Table)
Areal PMP depth for 2nd 12 hr bell = 0.21x592.68 = 124.46 mm

Table-5: Rainfall Distribution

Time in Normalised Cumulative Rainfall Incremental Rainfall Loss Rate Effective Rainfall
hours distribution depth (cm) depth (cm) (cm/hr) (cm)
coefficient Ist bell IInd bell Ist bell IInd bell cm/hr Ist bell IInd bell
From
FER-1(b)
1 0.16 7.49 1.99 7.49 1.99 0.1 7.39 1.89
2 0.30 14.05 3.73 6.56 1.74 0.1 6.46 1.64
3 0.46 21.54 5.73 7.49 1.99 0.1 7.39 1.89
4 0.54 25.28 6.72 3.75 1.00 0.1 3.65 0.90
5 0.63 29.50 7.84 4.21 1.12 0.1 4.11 1.02
6 0.71 33.24 8.84 3.75 1.00 0.1 3.65 0.90
7 0.76 35.58 9.46 2.34 0.62 0.1 2.24 0.52
8 0.81 37.93 10.08 2.34 0.62 0.1 2.24 0.52
9 0.86 40.27 10.70 2.34 0.62 0.1 2.24 0.52
10 0.92 43.08 11.45 2.81 0.75 0.1 2.71 0.65
11 0.96 44.95 11.95 1.87 0.50 0.1 1.77 0.40
12 1.00 46.82 12.45 1.87 0.50 0.1 1.77 0.40

Table-6: Critical sequencing of rainfall

Time U.G. Critical Arrangement of rainfall Critical 1Hr excessive Time


in Ordinate increments in 1st bell & 2nd bell Rainfall after in
hours reversing the critical hours
arrangement
1 30 2.24 0.52 1.77 0.40
2 64 3.65 0.90 1.77 0.40
3 120 6.46 1.64 2.24 0.52
4 165 7.39 1.89 2.24 0.52
5 136 7.39 1.89 2.71 0.65
6 98 4.11 1.02 3.65 0.90
7 64 3.65 0.90 4.11 1.02
8 46 2.71 0.65 7.39 1.89
9 34 2.24 0.52 7.39 1.89
10 24 2.24 0.52 6.46 1.64
11 16 1.77 0.40 3.65 0.90
12 11 1.77 0.40 2.24 0.52
13 6
14 3
15 0
Table-7: Computation of Design Flood for Gopi Krishna Project
UG Total
ordi- Rainfall excess in cm Flow
nate
Ti- (cu- Base
me mec) 1.77 1.77 2.24 2.24 2.71 3.65 4.11 7.39 7.39 6.46 3.65 2.24 0.40 0.40 0.52 0.52 0.65 0.90 1.02 1.89 1.89 1.64 0.90 0.52 DSRO Flow Cumec
(hr) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
0 0 0.00 0.00 11.760 11.76
1 30 53.19 0.00 53.19 11.760 64.95
2 64 113.46 53.19 0.00 166.65 11.760 178.41
3 120 212.75 113.46 67.23 0.00 393.44 11.760 405.20
4 165 292.53 212.75 143.43 67.23 0.00 715.93 11.760 727.69
5 136 241.11 292.53 268.93 143.43 81.28 0.00 1027.28 11.760 1039.04
6 98 173.74 241.11 369.78 268.93 173.40 109.37 0.00 1336.34 11.760 1348.10
7 64 113.46 173.74 304.79 369.78 325.12 233.33 123.42 0.00 1643.64 11.760 1655.40
8 46 81.55 113.46 219.63 304.79 447.04 437.49 263.29 221.75 0.00 2089.00 11.760 2100.76
9 34 60.28 81.55 143.43 219.63 368.47 601.55 493.68 473.06 221.75 0.00 2663.39 11.760 2675.15
10 24 42.55 60.28 103.09 143.43 265.51 495.82 678.81 886.98 473.06 193.65 0.00 3343.18 11.760 3354.94
11 16 28.37 42.55 76.20 103.09 173.40 357.28 559.50 1219.60 886.98 413.13 109.37 0.00 3969.47 11.760 3981.23
12 11 19.50 28.37 53.79 76.20 124.63 233.33 403.17 1005.25 1219.60 774.61 233.33 67.23 0.00 4239.00 11.760 4250.76
13 6 10.64 19.50 35.86 53.79 92.12 167.70 263.29 724.37 1005.25 1065.09 437.49 143.43 11.94 0.00 4030.46 11.760 4042.22
14 3 5.32 10.64 24.65 35.86 65.02 123.96 189.24 473.06 724.37 877.89 601.55 268.93 25.46 11.94 0.00 3437.88 11.760 3449.64
15 0 0.00 5.32 13.45 24.65 43.35 87.50 139.88 340.01 473.06 632.60 495.82 369.78 47.74 25.46 15.67 0.00 2714.28 11.760 2726.04
16 0.00 6.72 13.45 29.80 58.33 98.74 251.31 340.01 413.13 357.28 304.79 65.64 47.74 33.43 15.67 0.00 2036.04 11.760 2047.80
17 0.00 6.72 16.26 40.10 65.82 177.40 251.31 296.93 233.33 219.63 54.11 65.64 62.68 33.43 19.40 0.00 1542.76 11.760 1554.52
18 0.00 8.13 21.87 45.25 118.26 177.40 219.47 167.70 143.43 38.99 54.11 86.18 62.68 41.39 26.87 0.00 1211.74 11.760 1223.50
19 0.00 10.94 24.68 81.31 118.26 154.92 123.96 103.09 25.46 38.99 71.03 86.18 77.61 57.32 30.60 0.00 1004.36 11.760 1016.12
20 0.00 12.34 44.35 81.31 103.28 87.50 76.20 18.30 25.46 51.19 71.03 106.72 107.48 65.29 56.74 0.00 907.18 11.760 918.94
21 0.00 22.17 44.35 71.01 58.33 53.79 13.53 18.30 33.43 51.19 87.96 147.79 122.42 121.05 56.74 0.00 902.04 11.760 913.80
22 0.00 22.17 38.73 40.10 35.86 9.55 13.53 24.03 33.43 63.38 121.81 168.32 226.96 121.05 49.27 0.00 968.20 11.760 979.96
23 0.00 19.37 21.87 24.65 6.37 9.55 17.76 24.03 41.39 87.78 138.74 312.07 226.96 105.12 26.87 0.00 1062.52 11.760 1074.28
24 0.00 10.94 13.45 4.38 6.37 12.54 17.76 29.75 57.32 99.97 257.22 312.07 197.09 57.32 15.67 1091.85 11.760 1103.61
25 0.00 6.72 2.39 4.38 8.36 12.54 21.99 41.20 65.29 185.35 257.22 271.00 107.48 33.43 1017.35 11.760 1029.11
26 0.00 1.19 2.39 5.75 8.36 15.52 30.45 46.93 121.05 185.35 223.37 147.79 62.68 850.82 11.760 862.58
27 0.00 1.19 3.13 5.75 10.35 21.50 34.68 87.00 121.05 160.96 121.81 86.18 653.60 11.760 665.36
28 0.00 1.57 3.13 7.11 14.33 24.48 64.31 87.00 105.12 87.78 71.03 465.86 11.760 477.62
29 0.00 1.57 3.88 9.85 16.32 45.39 64.31 75.55 57.32 51.19 325.38 11.760 337.14
30 0.00 1.94 5.37 11.22 30.26 45.39 55.84 41.20 33.43 224.66 11.760 236.42
31 0.00 2.69 6.12 20.80 30.26 39.42 30.45 24.03 153.77 11.760 165.53
32 0.00 3.06 11.35 20.80 26.28 21.50 17.76 100.75 11.760 112.51
33 0.00 5.67 11.35 18.07 14.33 12.54 61.96 11.760 73.72
34 0.00 5.67 9.85 9.85 8.36 33.74 11.760 45.50
35 0.00 4.93 5.37 5.75 16.05 11.760 27.81
36 0.00 2.69 3.13 5.82 11.760 17.58
37 0.00 1.57 1.57 11.760 13.33
38 0.00 0.00 11.760 11.76
Table-8: Design Flood Hydrograph (PMF) for Gopi Krishna Sagar Project

Time Discharge
(hr) (m3/sec)
0 12
1 65
2 178
3 405
4 728
5 1039
6 1348
7 1655
8 2101
9 2675 Fig.2: Design Flood Hydrograph for Gopi Krishna Sagar
10 3355 Project
11 3981 4500
12 4251
13 4042 4000

14 3450 3500
15 2726
Discharge (cumec)

3000
16 2048
17 1555 2500
18 1223 2000
19 1016
20 919 1500

21 914 1000
22 980
500
23 1074
24 1104 0
25 1029 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38
26 863
Time (hour)
27 665
28 478
29 337
30 236
31 166
32 113
33 74
34 45
35 28
36 18
37 13
38 12

You might also like