Professional Documents
Culture Documents
Chapt6 Preliminary Gritremoval PDF
Chapt6 Preliminary Gritremoval PDF
Chapter 6
PRELIMINARY TREATMENT:-GRIT REMOVAL
Grit removal
Grit removal is accomplished in channels or retention tanks. The objective is to
settle out inorganic matter (particles with diameter above 0.2mm) whilst avoiding
deposition of putrescible organic material and during this process, the organic
matter must be kept in suspension. The average specific gravity of grit particles
and organic matter are 2.5 and 1.2 respectively and therefore grit particles have a
higher settling velocity than organic matter. The settling velocity of grit is
approximately 0.03 m/s. The horizontal flow velocities in grit channels are normally
0.3m/s and higher horizontal velocities result in scouring of the deposited material.
Grit settlement can therefore be used as a guide to the plant performance. If the
quantity of grit reduces, it may be an indication that the flow rate has increased
above 0.3 m/s or the grit is being retained in suspension. If the amount of grit
increases, there may be a new effluent discharge.
Since there is diurnal variation in flow, to control the velocity at all flow rates, the
channel should be designed so that the velocity remains constant at all depths of
flow and this can be achieved by the use of a parabolic cross-section. In this case
flow will be proportional to the cross-sectional area. A flume is incorporated at the
downstream end of the channel to maintain a constant velocity at all depths and at
the same time measuring flow (Fig. 3). The Venturi should not be drowned so that it
produces an upstream depth that is independent of conditions downstream
conditions. Usually a trapezoidal section is used instead of a parabolic for ease of
construction.
Inlet pipe
Grit chamber
A 3
C
C
v
W B
Section A-A
A Section C-C
W
v2/2g
H H
Flow, Q = vA (7)
∴ Q = vBh
v2
H = h+ (8)
2g
Q = 2 2 g (H − h ) 2 Bh
1 1
(9)
2 2
Flow in a flume is maximum when depth at throat is of the total energy (h= H)
3 3
3 3
Qmax = 1.71BH 2
or Qmax = KBH 2
(10)
3 1
dQ = KBH 2 dH (11)
2
dQ = vWdH (12)
Taking the velocity in the grit chamber to be 0.3 m/s, the above equation becomes:
3kB 1 2
W = H (14)
(0.6)
Dividing equation 10 by equation 14, the width of the channel can be computed
from:
Q
W =5 (15)
H
The settling velocity of grit is taken as 0.03m/s. Therefore the length of the grit
channel is given as:
Thus the top width of the channel is simply determined from the maximum flow and
corresponding depth. In practice. L= 20 x maximum depth of channel to
allow for turbulence and variation in settling velocity.
Grit storage is provided in the channel to reduce the frequency of manual cleaning.
The grit storage space is provided by lowering the floor of grit channel. A 1 or 2
week grit storage space may be provided and the volume of the grit storage space
may be estimated from:
Grit volume
Depth of storage required in grit channel =
Grit channel base width x length
Hydraulic grit washing within the grit chamber is provided by bottom scouring. The
scouring velocity will re-suspend the organic particles which might have settled in
the chamber while the grit remains at the bottom. The scouring reduces the volume
of grit, odour formation and flies. The critical horizontal velocity for scouring is given
by Shields equation:
8 fg (R g − 1)d
vc =
λ
Where:
f =Particle shape factor (0.04-0.06)
g =Gravitational constant
λ =Friction factor (0.03)
⎛ ρp ⎞
Rd =Relative density ⎜⎜ ⎟⎟ . The density for sand particles is 2650kg/m3 and for
⎝ ρ ⎠
suspended solids is 1150kg/m3 and ρ is the liquid density.
d =Diameter of particle, m
The critical horizontal velocity should be ≥ 0.1 m/s to ensure sufficient scouring to
re-suspend the organic solids.
Using the results in Table 1, a parabolic section is plotted and a best-fit trapezoidal
section is selected (Fig. 5).
=1.31m3
6
The grit channel should be lowered by 0.1m to provide the grit storage space.
Other specifications of the grit channel are in Fig. 6.
Key
2
b< B Hmax = max depth at measuring device
3
E = 3H max D = 3(B − b ) L = 1.5H max R = 2(B − b ) F ≥ 10 B
Example: 2
Design data
Design population = 75 000 capita
Average dry weather flow, ADWF = 6.50Ml/d
Minimum dry weather flow, MDWF = 2.70Ml/d
Peak dry weather flow, PDWF = 15.8Ml/d
Peak design flow, PDF = 16.25Ml/d
Inlet pipe invert level, I.L = 71.293m
Design data
The grit chamber is designed to cater for the following hydraulic conditions:
Maximum design flow, Qmax = 16.25Ml/d (0188m3s 1)
Minimum design flow, Qmin = 2.70Ml/d (0.0313m3s-1)
Design velocity, v = 0.3ms-1
Grit concentration = 10ml per liter of influent
Therefore grit load = 0.01m3/1000m3 of influent
8
The ratio of maximum flow to minimum flow is less than 12. Therefore the velocity in
the grit channel will be constant (Marais, 1969).
Design formulae
Free discharge flume equation, Q = cbH3/2 (1)
Where c = a constant = 1.71
b = flume throat width, m
H = upstream depth of flow, m
Inlet channel invert level, I.L = Inlet pipe I.L - Hmin (4)
From Table 3 a flume throat width of 0.225m is the optimal size for it is the smallest
size possible flume. It therefore has the minimum construction cost. Therefore a
0.225m throat width is adopted.
W = 0.97H1/2
Using above equation 7 and varying values of channel depth (H), Table 4 is
constructed.
W = 200mm
By using the line of best fit the best fit curve is: y = 0.983x - 0.15 as shown in Fig
7.
10
11
Flume dimensions
Dimension E = 3Hmax = 3 x 0.620 = 1.860m
Dimension F = 10B = 10 x 0.480 = 4.800m
Dimension D = 3(B-b) = 3(0.480-0.225) = 0.765m
Dimension R = 2(B-b) = 2(0.480-0.225) = 0.510m
Flume configuration
Grit storage
Allow a seven days grit storage space
Average daily flow, ADWF = 6500m3/d
Grit concentration = 0.01m3/1000m3 inflow
Therefore seven days grit volume = (6500 x 10-3 x 7 x 0.01) m3
= 0.455m3
Depth of storage required in grit channel = Grit volume/(Grit channel base width x
length)
= 0.455/(0.400 x 18) m3/m2
The grit storage is provided by lowering the floor of the grit channel. The floor of the
grit channel is made to fall along the floor line at a slope of say 1:60. A fall of 1:60
for 18m provides a vertical fall of 18/60 = 0.30m. The fall is provided by a screed
of minimum thickness 0.025m and a maximum thickness of 0.325m.
Grit sump
The lower end of the floor should be provided with a grit sump 0.400 x 0.300 x
0.150 meters deep to collect the grit.
Velocity control
To obtain an approximately constant velocity in the grit channel the flume should be
lowered a distance ( called the step height) below the floor of grit channel.
Downstream conditions
The downstream channel discharges into the primary settling tanks division box.
The floor level of the box is set at least half the PST inlet pipe diameter below
channel floor level to prevent drowning of the channel.
Therefore invert level of the collection chamber = 70.615 - 1/2Φ, where Φ =PST
inlet pipe diameter.
To avoid drowning of the influent pipe consider this depth (0.80m) as for a pipe
flowing at 0.8 full. Therefore pipe diameter: = 0.432m/0.8
= 0.5775m
= 600mm diameter pipe
Height of channel walls, Hw = (Pipe I.L - Channel I.L) + (Pipe diam + grit channel
storage depth ) + freeboard
Hw = 1.00m
References
1. Mara D., (1976), Sewage Treatment in Hot Climates, John Wiley, UK
2. Mara D., (1997), Design of Waste Stabilization Ponds in India, Lagoon
Technology, UK
3. Mutamba J. 1998), Design of Cowdary Park BNR, Design Project, Dept. of Civil
and Water Engineering, NUST, Zimbabwe.
4. Smith .M., (1995), Unpublished Lecture Notes in Wastewater Engineering,
Loughborough University, UK
14