SOK LVL A1 0.600 m d2 1.950 m 3. Further, the soil investigation report shall be reviewed by the consultant and
A2 0.841 m d3 2.000 m certification shall be obtained to ensure confirmity between assumed soil parameters
S 0.450 m SOK lvl 0.500 m and soil report values before start of construction.
0.00 LVL
G1 0.250 m P 3.400 m 4. The foundation design is applicable only when the considered NSBC is available at
(or) within the 2m depth from E.G.L. In both cases the minimum foundation depth
shall be 2m from E.G.L.
In case the required SBC is not available at/beyond 2m depth, this foundation design
does not stand applicable.
5. This foundation design shall not be used in case of organic silt, organic clay or peat
layers are found up to depth "2b" from founding level during soil investigation (where
b= pad/raft width).
6. Any discrepency in the drawing & site conditions shall be brought to the notice of
site engineer & consultant.
7. In case top of pedestal is found to be lower than the road level/ high flood level,
then base plate encasement shall be taken up in consultation with the site
-d1 LVL engineer/incharge /consultant.
8. Excavation plan & volume shown in drawing is indicative only & this is applicable
only for normal soil conditions. It, may vary as per site conditions & encountered
-d2 LVL strata.
SECTION B-B
-d3 LVL 9. This foundation design shall not be adopted at sites where soil is subjected to
ground improvements/Liquefaction. In this case special foundation shall be done.
10. In case ground water table is found within the foundation depth. This foundation
design does not stand applicable.
SECTION A-A
Grade of concrete - M20
Grade of steel - Fe500
Foundation Quantity
Concrete 3.59 cum
Lean concrete 0.45 Cum
Steel 453.3 kg
Excavation* 22.5 Cum
Shuttering 14.6 sqm
*Excavation limit is 200mm
# IMPORTANT:It is important that the cast-in part is placed in level and the cast-in
part tube is filled with concrete up to the middle of the top hole as shown on drawings
of cast-in parts.