ACTIVITY DURATION ESTIMATE

[Form 3.15]

Activity ID: A1040 Date Prepared:

Activity Name: Excavation and lean concrete Sec-AA WBS ID: 1.3.1.1

Responsibility: Activity Duration: 7


[Name/Designation/Organization] [Days]

Description of Work:
 Excavation in all kind of soil for foundation, backfilling, compacted, as required and disposal of surplus excavated material outside the site of
works, complete in all respect
 Providing and laying insitu 1:4:8 SRC in foundation using brick blast including mechanical compaction, finishing, curing, compete in all respect.
 Supply and apply approved termite proofing treatment by spray in foundation as per manufacturers recommendation to be applied as per
approved method, backed with 10 years guarantee

Res ID Resource Description Qty Unit of Rate Amount


[BOQ Item/Labor/Machine/Material] Measure

Cft 7.4
EK010 Excavation 3’ wide and 3’ in depth
8000 59200
Cft 140
CE011 Lean Concrete 1:4:8 foundation
540 75600
Sft 6.9
PN030 Termite Proofing
2500 17250

TOTAL 152050
Remarks:
ACTIVITY DURATION ESTIMATE
[Form 3.15]

Activity ID: A1050 Date Prepared:

Activity Name: Rebars and RCC Sec-AA WBS ID: 1.3.1.1

Responsibility: Activity Duration: 10


[Name/Designation/Organization] [Days]

Description of Work:
 Supplying, cutting, bending hoisting, placing in position, high yield strength steel reinforcement 60ksi, deformed bars including cost of
wastage in cutting, tying with binding wire of 18 gauge, providing and fixing steel chairs, pins, spacers complete in all respect
 Reinforced cement concrete using Portland cement in ratio 1:2:4 in following complete in all respect as per drawing. Providing, mixing, laying,
compacting and curing for 28 days

Res ID Resource Description Qty Unit of Rate Amount


[BOQ Item/Labor/Machine/Material] Measure

Cft 240
CE020 RCC 1:2:4
920 220800
Kg 160
ML010 Deformed Steel
4200 67200

TOTAL 892800
Remarks:
ACTIVITY DURATION ESTIMATE
[Form 3.15]

Activity ID: A1060 Date Prepared:

Activity Name: Brick Masonary Sec-AA WBS ID: 1.3.1.1

Responsibility: Activity Duration: 10


[Name/Designation/Organization] [Days]

Description of Work:
 Brick Masonry in foundation as per drawing with mortar of 1:5 cement sand, straight or curve at any level including all anchor, wall ties and
other fixtures required to be built in brick masonry, complete in all respect
 Double Damp Proof Course verticle and horizontal

Res ID Resource Description Qty Unit of Rate Amount


[BOQ Item/Labor/Machine/Material] Measure

Brick masonry (9” English bond) Cft 198


BK020 3000
foundation 59400
Sft 52
PN010 Double Damp proofing
1000 5200

TOTAL 646000
Remarks:
ACTIVITY DURATION ESTIMATE
[Form 3.15]

Activity ID: A1190 Date Prepared:

Activity Name: Sub Base Filling WBS ID: 1.3.1.1

Responsibility: Activity Duration: 5


[Name/Designation/Organization] [Days]

Description of Work:
 Supply of approved fill material from outside souse under flooring including breaking clod, dressing, watering, and consolidation by ramming
in layers not exceeding 6 inch thick in depth to full compaction complete in all respect

Res ID Resource Description Qty Unit of Rate Amount


[BOQ Item/Labor/Machine/Material] Measure

Cft 19
EK030 Sub Base Filling
15000 285000

TOTAL 285000
Remarks:
ACTIVITY DURATION ESTIMATE
[Form 3.15]

Activity ID: A1200 Date Prepared:

Activity Name: Brick Masonary Sec-AA WBS ID: 1.3.1.2

Responsibility: Activity Duration: 14


[Name/Designation/Organization] [Days]

Description of Work:
 Supplying, cutting, bending hoisting, placing in position, high yield strength steel reinforcement 60ksi, deformed bars including cost of
wastage in cutting, tying with binding wire of 18 gauge, providing and fixing steel chairs, pins, spacers complete in all respect
 Reinforced cement concrete using Portland cement in ratio 1:2:4 in following complete in all respect as per drawing. Providing, mixing, laying,
compacting and curing for 28 days
 Providing and laying first class burnt brick solid masonry set in cement sand mortar using clean approved quality sand in wall as per drawing
including fastening, filling the interior faces, curing and finishing etc. complete in all respect
Res ID Resource Description Qty Unit of Rate Amount
[BOQ Item/Labor/Machine/Material] Measure

Sqft 209
BK010 Brick masonry (9” English bond) 4600 961400
CE020 RCC 1:2:4 Cft 240
100 24000
Kg 160
ML010 Deformed Steel
25 4000

TOTAL 989400
Remarks:
ACTIVITY DURATION ESTIMATE
[Form 3.15]

Activity ID: A1250 Date Prepared:

Activity Name: Roof Slab Sec-AA WBS ID: 1.3.1.2

Responsibility: Activity Duration: 7


[Name/Designation/Organization] [Days]

Description of Work:
 Supplying, cutting, bending hoisting, placing in position, high yield strength steel reinforcement 60ksi, deformed bars including cost of
wastage in cutting, tying with binding wire of 18 gauge, providing and fixing steel chairs, pins, spacers complete in all respect
 Reinforced cement concrete using Portland cement in ratio 1:2:4 in following complete in all respect as per drawing. Providing, mixing, laying,
compacting and curing for 28 days

Res ID Resource Description Qty Unit of Rate Amount


[BOQ Item/Labor/Machine/Material] Measure

Kg 160
ML010 Deformed Steel
8500 1360000
CE020 RCC 1:2:4 Cft 240
2500 450000

TOTAL 1960000
Remarks:
ACTIVITY DURATION ESTIMATE
[Form 3.15]

Activity ID: A1600 Date Prepared:

Activity Name: Roof Slab Sec-AA WBS ID: 1.3.1.2

Responsibility: Activity Duration: 7


[Name/Designation/Organization] [Days]

Description of Work:
 Providing and laying water proof over RCC roof Slab consisting of two coats of hot SI bitumen over one prime coat of bitumen one layer of
100gm/m2 with end overlapped 6” and jointed with Samad bond. Laying 4” mud to proper slope and covered with 1.5” thick brick tile laid
over 1:5 ratio cement sand mortar and grouted with 1:3 cement sand mortar, curing cleaning and complete in all respect

Res ID Resource Description Qty Unit of Rate Amount


[BOQ Item/Labor/Machine/Material] Measure

Sft 90
FG040 Roof Treatment
5000 45000

TOTAL 45000