Professional Documents
Culture Documents
RMX Manual PDF
RMX Manual PDF
RMX Manual PDF
2.18.2 Lifting and Transporting the Iron Skid using a Winch Truck .......... 2-177
2.18.3 Lifting the Main Skid using Cranes (with the Skid Assembled)...... 2-177
2.18.4 Lifting the Main Skid using Cranes (with the Skid Disassembled) . 2-180
2.18.5 Four Point Lifting using Two Cranes (for the Iron Skid) ................. 2-187
2.19 Equipment Pressure Testing............................................................... 2-188
2.19.1 Pressure Relief Valve Adjustment & Testing ................................. 2-188
2.19.2 System Pressure Calibration ......................................................... 2-190
2.19.3 Onsite Pressure Testing ................................................................ 2-192
2.19.4 Additional Regulations for Pumping............................................... 2-194
2.20 SCM Skid Process Troubleshooting ................................................... 2-198
2.21 Top 10 Maintenance Items ................................................................. 2-204
3.0 APPENDIX A ...................................................................................3-1
3.1 MARK IV AT system description and troubleshooting (for electricians) .. 3-1
3.2 System Overview .................................................................................... 3-1
3.3 Detailed System Description................................................................... 3-2
3.4 Process Variables ................................................................................... 3-5
3.4.1 Rates ................................................................................................. 3-5
3.4.2 Pressure ............................................................................................ 3-7
3.4.3 Density .............................................................................................. 3-9
3.5 System Inputs and Outputs................................................................... 3-10
3.5.1 Inputs (PLC) .................................................................................... 3-10
3.5.2 Outputs (PLC) ................................................................................. 3-14
3.6 Miscellaneous Operator Panel Controls................................................ 3-15
3.6.1 High Pressure Return Valve ............................................................ 3-15
3.6.2 Emergency Shutdown ..................................................................... 3-15
3.6.3 Master Water Valve Open/Close ..................................................... 3-15
3.7 Miscellaneous Components.................................................................. 3-16
3.7.1 Weight Display on Surge Can (Tank) .............................................. 3-16
3.8 Cement and Mix Water Hydraulic Valve Control Components.............. 3-17
3.9 Process Ranges ................................................................................... 3-20
3.9.1 Mix Water ........................................................................................ 3-20
Cementing Services SCM W/MK IV AT Skid vi
Operator Training Manual – Version 1.1
SCM W/MK IV AT Skid Operation and Maintenance
Table of Contents
perform by the end of the unit. Upon completion of the unit you will be able to:
1.2 Introduction
The newly designed Sanjel Cyclonic Mixer with Mark IV Automation Technology (SCM
W/MK IV AT) skid is used for performing primary and remedial cementing jobs (Figure
1-1). It is a unit combining the slurry mixing system and high pressure pumping system,
which allows the operator to perform slurry mixing and pumping on the same unit. It is
offered on a oilfield skid that is capable of mixing at slurry rates up to 1.8 m3/min (11.34
• Hydraulic System
• Air System
The major components of the unit are illustrated in Figure 1-2 and Figure 1-3. The
Figure 1-2: Major Components of SCM W/MK IV AT International Skid (road side view)
Figure 1-3: Major Components of SCM W/MK IV AT International Skid (curb side view)
hydraulic system and the high pressure pumping system is driven by the two Detroit
diesel engines. Sanjel’s high energy mix head mixes pneumatically delivered bulk
cement with water and recirculated slurry to generate the quality cement slurry. The
system to the desired density. The slurry, mixed at the preset density, is transferred
continuously to the down hole high pressure Triplex pumps, and then is pumped down
cement control valve regulates the flow rate of the bulk cement flowing to the high
energy mix head. When the system is in the automatic mode, the MK IV AT system
functionally runs the bulk cement control valve and the mix water control valve to mix
water and recirculated slurry with the dry cement to produce the new slurry. The new
slurry is then discharged into the mix tank through a cyclonic mixing chamber. Once the
new slurry reaches the mix tank, it is evened out with the existing slurry in the tank by a
tank agitator and then is recirculated by the recirculation centrifugal pump back to the
mix head. The 2” Coriolis flow meter, assembled in the recirculation line, senses the
actual density and a portion of the flow rate of the recirculated slurry and sends them
When the mix tank becomes full, the slurry flows over a weir into the averaging tank in
order to be averaged and discharged to the high pressure Triplex pumps. The 3”
magnetic flow meter mounted in the mix head water line measures the mix head water
The MK IV automation system analyzes measured values of density, water rate, and the
bulk cement control valve position plus the slurry design parameters to decide the new
bulk cement control valve position, which is recalculated every second. The automation
system continually instructs the hydraulic actuator to adjust the opening of the bulk
cement control valve. As the result, the slurry density is controlled within the preset
density range.
In addition, the automation system also monitors and records the following parameters:
• Time
• Charge Pressure
• Job Total
• Stage Total
• Auxiliary Rate 3
• Auxiliary Rate 4
• Auxiliary Pressure
• Discharge Pressure
• Primary Top Skid: is composed of a hydraulic skid, a pump skid, and an engine
• Secondary Bottom Skid: provides structural support and elevation to the primary
skid. Figure 1-5 points out the location of the secondary bottom skid.
• Treating Iron Skid: carries the treating iron, surge tank, and major components of
the ground mixing system. Figure 1-6 shows the configuration of the treating iron
skid. Table 1-1 lists all the treating iron carried by the iron skid.
Description Quantity
2"x10' 1502 Weco Long Joint 30
2"x4' 1502 Weco Pup Joint 6
2" Single Wing Swivel Joint (Chicksan) 6
2" SPM Double Wing Swivel Joint (Chicksan) 4
2" 1502 Weco Jack Knife 3
2" Crossover (FxF) 2
2" Crossover (MxM) 3
2" Integral Tee (FxMxF) 2
2" Wye (FxFxM) 2
2x2 Plug Valve 6
Relief Valve 2
mounted on the engine skid via the transmissions and flexible drive lines. The engines
are remote-controlled from the operator’s control console. Sanjel’s SCM International
skids are equipped with Detroit Diesel Series 60 engines (Figure 1-7).
pumps via two transmissions (Figure 1-8) and two flexible drive lines (Figure 1-9). The
transmissions are mounted on the output side of the two engines. The drive lines are
installed between the transmissions and the Triplex pumps. The transmissions are
remote-shifted from the operator’s control console. They are equipped with power shift
and lock up mode. Sanjel’s SCM international skids are equipped with two Allison 4700
automatic transmissions.
hydraulic power to all the equipment on the skid unit that is hydraulically driven.
• Hydraulic Pumps
• Hydraulic Motors
• Relief Valves
• Control Valves
• Pre-charge Filters
pumps are shown in Figure 1-13. They are attached to the Funk gearbox.
1. Cessna Hydraulic
Pump for Bulk
Cement Valve and
Mix Water Control
Valve
2. Sundstrand
Hydraulic Pump for
Five Agitation
Paddles
3. Sauer Sundstrand
Hydraulic Pump for
Road Side Mix
Water Pump
4. Sauer Sundstrand
Hydraulic Pump for
Curb Side Mix
Water Pump
5. Sauer Sundstrand
Figure 1-13: Hydraulic Pumps Hydraulic Pump for
Recirculation
Pump
6. Sauer Sundstrand
Hydraulic Pump for
Pressurizer Pump
pump, the pressurizer pump, the mix water pumps, and the five agitation paddles, as
Figure 1-14: Sauer Danfoss Hydraulic Motor for Figure 1-15: Sauer Danfoss Hydraulic Motor for
Recirculation Pump Pressurizer Pump
Figure 1-16: Sauer Sundstrand Series 90 Hydraulic Figure 1-17: Sauer Sundstrand Series 90 Hydraulic
Motor for Mix Water Pump (road side) Motor for Mix Water Pump (curb side)
Figure 1-18: Char-Lynn Hydraulic Motor for Agitation Paddle of Mix Tank
Figure 1-19: Char-Lynn Hydraulic Motors for Agitation Paddles of Averaging Tank
Figure 1-20: Char-Lynn Hydraulic Motors for Agitation Paddles of the Displacement Tank
and displacement fluids that are pumped into the well for various purposes, and water
that is discharged into the mix head to create slurry. The system consists of the
following components:
• Plumbing System
• Fill Lines
with each having graduated markers measuring in increments of 0.08 m3 (0.5 bbl) for a
tank total volume of 4 m3 (25 bbl). The tank is constructed of stainless steel for the
purpose of carrying acid and bearing weight. Each compartment of the displacement
tank has a 152.4 mm (5") air actuated discharge port and a hydraulic driven agitation
paddle. The butterfly valves on the ports allow the operator to remove fluid from one or
both compartments.
The displacement tank is filled from an off board source through the 76.2 mm (3")
external fill line or with the mix water centrifugal pumps. The filling of the displacement
tank is controlled by the two manual valves installed on the two fill lines. The dumping of
the tank is controlled by the two air actuated valves with the control switches mounted
on the side of the tank. The process piping feed of the displacement tank is controlled
by the actuated valves whose switches are located on the lower control console. A high
pressure return line is connected from the Triplex pumps to allow the pump pressure to
Figure 1-21: Displacement Tank (road side) Figure 1-22: Displacement Tank (curb side)
The tank can be filled by the 3x2 mix water pumps from either side of the tank from an
external source via a 4" hose or from an off board source via a 3" hose. The
displacement fluid in the displacement tank is fed to the Triplex pump either by the aid
of gravity or the pressure from the pressurizer pump. The fluid used to create slurry is
Figure 1-23 to Figure 1-26 show the components of the displacement tank.
10. Agitation
Paddle (road
side
compartment)
the displacement tank. They also receive fluid from the displacement tank and
discharge to the high energy mix head, ground mixing tree, or back to the displacement
tank. The two pumps are located beneath the operator’s control console and beside the
Triplex pumps. Sanjel’s SCM skids are equipped with 3x2 mission pumps (Figure 1-27
Figure 1-27: Mission Mix Water Pump (road side) Figure 1-28: Mission Mix Water Pump (curb side)
controlled tank main valves, pneumatically and manually controlled isolation valves,
pneumatically controlled short suction and long suction valves, and pipes.
water together, with the recirculated slurry, to create slurry of a desired density. The
• Surge Tank
• Mixing Chamber
• Mix Tank
• Averaging Tank
and constant, flow of dry bulk cement and delivers the cement to the high energy mix
head, at a reduced pressure. It also acts as a buffer when changing “P” tanks. It has a
maximum volume of 2.1 m3 (75 ft3), with a minimum usable working volume of 1.2 m3
(45 ft3). It is equipped with two sight glasses, a hydraulic load cell, a remote weight
indicator, and a pressure relief valve. The pressure relief valve is used to ensure that
the surge tank is not over pressured during SCM mixing, and to make sure that the
Figure 1-29: Surge Tank Figure 1-30: Surge Tank Weight Display
A daylight readable LED display (Figure 1-30) is mounted to the leg of the surge tank.
The purpose of the display is to provide a weight indication of the product in the surge
tank. This indication will assist the operator with keeping the cement level constant
• Recirculation Line
The components of the high energy mix head assembly are illustrated in Figure 1-31
Figure 1-32: SCM High Energy Mix Head Assembly (curb side
view)
The SCM high energy mix head mixes materials from three sources (Figure 1-33):
The high energy mix head receives dry cement (pneumatically) from the surge tank and
mixes the cement with water coming from the mix water pump and also with recirculated
slurry from the recirculation pump. The recirculated slurry is drawn from the mix tank.
The delivering rate of bulk cement is metered by the bulk cement control valve located
on the top of the mix head. A portion of the recirculated slurry density is measured by
the 2" Coriolis flow meter and the water flow is measured through the 3" magnetic flow
meter. The 2" Coriolis flow meter is installed in the recirculation line and the 3" magnetic
flow meter is installed in the water line. The slurry density, and slurry mixing rate, are
controlled manually (or automatically) by rotating the bulk cement control valve and the
The bulk cement sleeve (Figure 1-33) seats on the top of the mix head and directs the
flow of bulk cement, the recirculated slurry, and the mix water towards the throat of the
mix head. The sleeve also isolates the bulk cement from the water, and recirculated
slurry, and prevents the dry cement from being “wetted” before the appropriate stage in
The mix water diffusion plate (Figure 1-33) is installed in the mix head, at the bottom of
the bulk cement sleeve. It creates high velocity water jets that will wet the bulk cement
and break up any clumps prior to the cement being introduced to the recirculated slurry
streams. The jets also induce shearing in the slurry to ensure a homogeneous mixture.
The bulk cement control valve (Figure 1-34) controls the amount of dry cement being
delivered to the mix head. Its opening is shown by the position of the indicator bonnet
located beneath the hydraulic actuator. When the system is in the automatic mode, the
Programmable Logic Controller (PLC) and is adjusted by the hydraulic actuator. When
the system is in the manual mode, the position of the bulk cement control valve can be
addition, if the hydraulic control fails, simply switching the hydraulic “Auto/Hand”
selector switch from “Auto” to “Hand” (Figure 1-35), then the position of the valve can be
The make-up water line bridges the mix head water line and the recirculation line. The
water being delivered to the recirculation line, from the make-up water line, is used for
The flow rate in the make-up water line is regulated by a hydraulically actuated water
control valve called the mix water control valve installed in the middle of the line. This
valve directs water into the circulating loop of the mixing side of the process. The
position of the valve can be changed automatically (by the PLC) or manually (by the
switches and potentiometer) on the upper control console. However, if the hydraulic
control fails, simply switching the hydraulic “Auto/Hand” selector switch from “Auto” to
“Hand” (Figure 1-35), then the valve can be controlled manually with a bar that is
The mix head water line conveys water from the mix water pump to the mix head and
the make-up water line. When the PLC is in “auto” mode, the water flow rate is enabled
or disabled by a pneumatically controlled 3" master water control valve installed in the
The master water valve is a pneumatic butterfly valve that sends an “opened” or
“closed” feedback signal to the PLC. It can be controlled automatically by the PLC or
manually via the “Open/Close” toggle switch on the operator’s upper control console.
When opened, it directs water to the high energy mix head and to the mix water valve.
The recirculation line connects the mix tank and the high energy mix head. It
recirculates the pre-mixed slurry, from the mix tank to the mix head, to mix with the new
The 3" magnetic flow meter (Figure 1-36), that is installed in the mix head water line,
measures the rate of water being pumped to the mix head and the make-up water line.
The readings of the flow meter are displayed on the HMI screen and the E&H monitor
(Figure 1-37).
Figure 1-36: 3" Magnetic Flow Meter Figure 1-37: 3" Magnetic Flow Meter Transmitter
(with local display)
The MK IV automation system is equipped with a 2" Coriolis mass flow meter, located in
the recirculation line with the function of monitoring the recirculated slurry density, flow
Density measurement is very important in the recirculation section because it allows the
MK IV automation system to modify the process inputs before slurry is pumped down
hole. By this modification, density variations can be initially corrected in the recirculation
section and any remaining variations then are dampened down in the down hole
The 2" Coriolis flow meter samples the density signal and sends it to the Programmable
Logic Controller (PLC) where the density signal is converted to the actual cement
delivery rate. Then the PLC adjusts the cement control valve according to the actual
cement delivery rate (and some control law) to maintain the cement delivery set-point;
therefore, maintaining the density set-point. The Coriolis recirculation flow meter
readings are displayed on the HMI screen and the transmitter (Figure 1-38).
The high energy mixing system is equipped with three process pressure transducers,
which include: a 2" mix head water pressure transducer, a 3" mix head recirculation
pressure transducer, and a 2" Coriolis recirculation pressure transducer (Figure 1-39).
o This transducer measures the water pressure at the high energy mix
head. The measuring range is 0 – 160 psi. It is located in the mix water
o This transducer measures the pressure in the circulating line of the mixing
side of the process. The measuring range is 0 – 160 psi. It is located in the
o This sensor measures the pressure in the 2" Coriolis flow meter. The
measuring range is 0 – 160 psi. The circulating line branches off and
directs a portion of the slurry through the 2" Coriolis flow meter and then
into the bottom of the mix tank. A bean (a fixed choke) and the 3"
recirculation valve work together to constrict flow and pressurize the slurry
going through the 2" Coriolis flow meter. A minimum of 20 psi back
transducer is located between the outlet of the Coriolis meter and the 2"
recirculation valve.
to the cyclonic mixing chamber. It is the point where the mix water, recirculated slurry,
separates the air used to deliver bulk cement, from the slurry, before the slurry goes into
the mix tank. It helps reduce the air entrainment of the slurry, and gets rid of the dust in
of the mixing chamber and cyclonic mixing chamber. When the slurry enters the mix
tank, it is blended by the agitation paddle and recirculated back to the mix head by the
recirculation pump. Then it flows over the weir into the averaging tank. The mix tank is
top of the mix tank. It is approximately 2.7 m3 (17 bbl) in volume. The small fluctuations
of density in the mix tank are averaged out by the volume of slurry in the averaging
tank. It is very important to maintain a proper fluid height in the mix tank because it
allows good mixing and permits the cyclonic mixing chamber to do its job. Proper fluid
height also reduces the possibility of entraining additional air in the slurry, as it passes
1-45) to aid in mixing and circulation. The agitation paddles push the slurry up. One
agitator turns counterclockwise and the other one turns clockwise with the flow.
Figure 1-44: Averaging Tank Agitation Paddle Figure 1-45: Averaging Tank Agitation Paddle
(road side) (curb side)
and the two Triplex pumps. One is on the road side and the other one is on the curb
side. They receive fluid from either the displacement tank or an external source
(accessed from either side). They discharge fluid either into the high energy mix head,
through a 3" magnetic flow meter, or into the displacement tank. Sanjel’s SCM
international skids are equipped with two Mission (3x2) centrifugal pumps (Figure 1-46
and Figure 1-47). The 3x2 means an outlet diameter of 2" by an inlet diameter of 3".
Figure 1-46: Mission Mix Water Pump (road side) Figure 1-47: Mission Mix Water Pump (curb side)
on the road side. This pump receives slurry from the bottom of the mix tank and
discharges it through the 2" Coriolis flow meter and to the two recirculation lines on the
high energy mix head. The two recirculation lines direct the recirculated slurry into the
new incoming water and bulk cement mixture. It is also possible for the recirculation
pump to push the slurry to the high pressure Triplex pumps, in the case where the
pressurizer pump has failed. Sanjel’s SCM international skids are equipped with two
Gardner Denver 2045 LX (6x5) centrifugal pumps. One is called the recirculation pump
(below) and the other is called the pressurizer pump. The 6x5 means an outlet
mixing on the ground. The system is used to carry out low pressure jet mixing by
connecting the jet mixing bowl, and the hopper, to the mix slurry tub via a riser hose.
For ground mixing, one of the mix water pumps will pump the pressurized mix water into
the mixing bowl, and both of the Triplex pumps will be available to pump down hole. The
• Surge Tank
• Hopper
• Mixing Bowl
• Dust Collector
• Mixing Tree
1. Surge Tank
2. Bulk Direction
Control Flow Spool
3. Hopper
4. Mixing Bowl
5. Dust Collector
6. Cement Loading
Line
7. Mix Slurry Tub
8. Metering Valve
flow of dry bulk cement and delivers the cement to the high energy mix head, at a
reduced pressure. It also acts as a buffer when changing “P” tanks. It has a maximum
volume of 2.1 m3 (75 ft3), with a minimum usable working volume of 1.2 m3 (45 ft3). It is
equipped with two sight glasses, a hydraulic load cell, a remote weight indicator, and a
pressure relief valve. The pressure relief valve is used to ensure that the surge tank is
not over pressured during mixing operations, and to make sure that the pressure in the
1.2.8.2 Hopper
The hopper, also known as a witch’s hat (Figure 1-49), is placed beneath the surge tank
and above the jet mixing bowl. It collects and transports the dry cement from the surge
from the hopper and mixes the cement with the water that comes from the 2" water line
and the 11/2" bypass water line. The outlet of the mixing bowl is connected to the mix
mixed slurry. When conducting ground mixing, the mix slurry tub will be removed from
the iron skid to be mounted on the curb side of the skid (Figure 1-50).
off the bulk cement from the surge tank. Meanwhile, it is a valve that maintains and
bowl during ground mixing. The mixing tree consists of a 2" main mixing valve, a 2" jet
1. Mixing Tree
2. 2" Main Mixing Valve
3. 2" Jet Hose Valve
4. 11/2" By-pass Valve
5. 1" Wash Up Line
When performing ground mixing, the 2" main valve is opened (and closed) to control the
total volume of water to be jetted to the mixing bowl. The 2" jet hose valve is always
wide-open to supply water, and provide the jetting power to ascend up the riser hose
into the mix slurry tub, to the mixing bowl. The 11/2" by-pass valve is adjusted to change
the density of the slurry in the mixing bowl. The 1" wash up line is used to maintain
from the averaging tank or slurry tub, or the displacement fluid from the displacement
tank and then to push the fluid down hole. This system is composed of a 4" Coriolis
mass flow meter, a centrifugal pressurizer pump, twin high pressure Triplex pumps, an
motor that is powered by a Sauer Sundstrand hydraulic pump. The pump receives fluid
from either the averaging tank, or the displacement tank, and then discharges the fluid
to the high pressure Triplex pumps. In the case of a recirculation pump failure, the
pressurizer pump can also circulate slurry from the mix tank to the mix head. Sanjel’s
SCM units are equipped with two Gardner Denver 2045 LX centrifugal pumps. One is
called the pressurizer pump (below) and the other is called the recirculation pump. The
1.2.9.2 4" Coriolis Mass Flow Meter and 4" Down Hole Pump Boost
Pressure Transducer
The 4" Coriolis mass flow meter (Figure 1-53) is installed, in the discharge line from the
averaging tank, to capture and record the density, rate and temperature of the fluids
being pumped to the Triplex pumps. The readings of the flow meter are displayed on
the HMI screen and the 4" E&H transmitter (Figure 1-54).
The 4" down hole pump boost pressure transducer (Figure 1-55) measures the boost
pressure to the high pressure pumps. The measuring range is 0 – 160 psi. This
Figure 1-53: 4" Coriolis Mass Flow Meter Figure 1-54: 4" E&H Transmitter (with local display)
single-acting horsepower pumps, with 600 maximum brake horsepower, located at the
rear of the SCM units. The two pumps have a 6" stroke length with a plunger diameter
of 31/2" on the road side and 41/2" on the curb side. Each pump consists of a fluid end
and a power end. The fluid end is where the slurry gets pressurized by the pushing of
the three plungers. The power end is connected to the drive line, through which the
Figure 1-56: High Pressure Triplex Pumps (road side and curb side)
the Triplex pumps to the wellhead. The discharge manifold of the unit forms an “H”
supplies air to the air starters to start the CAT engine and the two Detroit engines. The
Detroit engine air system provides compressed air to the Triplex pump plungers’ oiler
system (to pressurize oil being injected into the plungers), to the air actuators (to
operate the actuators), to the control console (to enable the master water valve control),
and to the Vortec air conditioner (to operate the air conditioner).
Automated Technology). The operator enters the cement blend data that the system
uses to calculate the set-points for water and bulk cement delivery. The hydraulic
actuators control the mix water control valve, and bulk cement control valve, to achieve
the set-points. Numerous process variables are monitored, and the valves are
o Slurry temperature
The core of the control system is the programmable logic controller (PLC). The PLC is
essentially a computer that runs a custom program, which analyzes the process
variables and electrical inputs, performs calculations and generates outputs. The
outputs are used to control the process, as well as provide the operator visually with the
The interface to the PLC is a Human Machine Interface (HMI). The HMI is a 15" touch
screen display that is also a computer running on Windows CE. It provides the operator
with a visual interface of the process and the ability to input data and execute functions
system to receive data from the PLC. The job data is recorded and enables the operator
to produce a graph on location for the customer. Numerous process variables are also
recorded to the data card located in the HMI. This data can be used to analyze the job,
process parameters, as well as the unit control switches. It is also equipped with a
Vortec air conditioner unit to keep the upper control console cool in hot weather. It
allows the operator to control the unit’s engines, transmissions, centrifugal pumps, a
series of valves, and the hydraulic system. The job parameters displayed by the gauges
on the control console include pressures, temperatures, and fuel levels for different
equipment. Figure 1-58 shows the layout of the upper and lower control consoles.
Figure 1-59 to Figure 1-63 show the upper and lower control consoles components.
The function of each toggle switch assembled on the upper control console is described
Figure 1-64 shows the location of the Vortec air conditioner unit. It is mounted on the
Caution
Risk of moderate equipment damage or minor personal injury
Good safety practices are critical when starting and operating the unit.
Keep the following safety precautions in mind when performing a cement job:
• Make sure to wear all the proper Personal Protective Equipment (P.P.E.)
including: steel-toed boots, hard hats, safety glasses, coveralls, gloves, or any
• If a hydraulic leak occurs, stop the unit immediately. Do not operate the unit, until
• After each cement job has been completed, flush the mixing system immediately
and ensure that the flow meters are clean and free of dirt.
• Disassemble the bulk cement control valve from the mix head after each
cementing job and flush out the inside of the head; clean the vacuum breakers.
• Do not clean the bulk cement control valve with water. Avoid water inside of the
valve.
be transported freely between the well and the unit. If a “P” tank is used to supply the
bulk cement, spot the unit to the “P” tank for a desired location. When spotting the unit,
there should be a minimum 30 meters (100 ft) between the unit and the wellhead.
Sometimes the bulk units will be used, instead of the “P” tank, to supply the bulk cement
to the SCM skid on location. When the bulk unit gets to the lease, spot the bulk unit to
of each day and (after operating it) at the end of each day. These inspections ensure
that the unit will be working properly and reliably during any job. The following items
• Check all the fluid levels, including the engine oil, coolant, hydraulic oil, lube oil,
• Check the fuel tanks. All the fuel tanks should be full.
• Check the drip pans on the primary skid and ensure they are not full.
• Air the unit up from the rig. Check for any air leaks.
• Run the CAT C9 engine and the Detroit engines and check for any abnormities.
• Engage all the centrifugal pumps and check for any abnormities.
• Function test all the air and hydraulic actuated valves. Ensure the water and bulk
control valves function from “fully open” to “fully closed” without any interference.
• Check the condition of the pressure relief valves, installed on the high pressure
• Visually inspect the metering valve of the surge tank, to make sure there is no
cement build-up.
• Inspect the rubber boots of the fluidizers for wear. If wear is detected, replace the
boots.
• Function test all the centrifugal pumps, and preset the actuated valves to the
• Preset the water valves to the desired position for mixing and taking on water.
• Close all the drain valves of the mix water pumps, recirculation pump, and
pressurizer pump.
1.4.2 Rigging In
As soon as the pre-job inspection has been finished, the operator starts rigging in.
Follow the procedures below to set up the SCM unit and connect the unit with other
associated equipment.
There are three connections on the road side that can be used to connect to the drilling
rig, or water truck, to get water. The three connections are shown in Figure 1-65.
1.4.2.2 Laying out the Treating Iron and Connecting the Unit to the
Wellhead
The treating iron is always connected to the discharge iron on the road side. Before
laying out the treating iron, check with the supervisor to see if the client has requested a
particular layout to the wellhead, and if a pump-out tee and valve are required. When
laying out the treating iron to the wellhead, the wings on the treating iron should face
towards the SCM unit. Oil the unions before joining each piece. Tighten each
connection properly (generally 4 – 5 hits with the hammer). The treating iron layout and
connections are:
• The number and configuration of iron differs from job to job, but there is a
standard configuration from the discharge of the Triplex pump down to ground
level called the “dog-leg”, which consists of three swivel joints (Chicksans) and
NOTE: The type of layout of treating iron shown in Figure 1-66 is different than
• Iron should be laid out in a box shape to prevent it from breaking during jacking
• Slings must be placed, at rear of the unit, from the discharge valve to the ground
be used. At the same time, the dust bag should be installed on the dust collector and
• Connect the cement loading line of the surge tank and the product line of the “P”
tank via a 4" bulk hose (Figure 1-68). If two tanks are to be used, a “Y” cam lock
Figure 1-68: Bulk Hose Connecting Surge Tank and P Figure 1-69: 3" Air Hose of P Tank
Tank
• Connect the 3" air hose, on the “P” tank, to a blower that is carried by another
unit (Figure 1-69). The unit with the blower should be located at a convenient
• Connect the cement loading line of the surge tank and the product line of the bulk
unit via a 4" bulk hose. A 45° cam lock can be used for proper orientation of the
hose.
NOTE: The bulk hose should be free from tight curves, or other potential bridge points,
1.4.2.4 Connecting the Mix Head to the Surge Tank for High
Energy Mixing Jobs
Connect the cement transfer line from the master bulk shut-off valve, of the bulk cement
control valve, to the metering valve of the surge tank (Figure 1-70).
Figure 1-70: Bulk Cement Transfer Line Connecting Mix Head to Surge Tank
be connected with the unit. The dust bag should be installed on the dust collector and
the fluidizer should be connected to the air line. Refer to Figure 1-67.
To connect the mixing tree to the mixing bowl, perform the following:
• Connect the 2" jet hose valve of the mixing tree with the 2" water line of the
mixing bowl via a 2" water hose (Figure 1-71 and Figure 1-72).
• Connect the 11/2" bypass valve of the mixing tree with the 11/2" bypass water line
of the mixing bowl via a 11/2" water hose (Figure 1-71 and Figure 1-72).
Figure 1-71: Connecting Mixing Tree to Mixing Figure 1-72: Connecting Mixing Tree to Mixing
Bowl Bowl (cont’d)
• Remove the mix slurry tub from the iron skid and mount the tub on the curb side
• Attach the 4" suction line to the pressurizer pump along with a 2" recirculation
• Connect the mix slurry tub to the mixing bowl via a 4" riser hose (Figure 1-73 and
Figure 1-74).
Figure 1-73: Mix Slurry Tub Connection Figure 1-74: Connecting Mix Bowl and Mix
Slurry Tub via 4" Riser Hose
2. Once the field is selected, use the number pad provided to input the information.
5. Once the recipe is updated, press “SAVE”. A confirmation screen will come up at
this time. If you want to overwrite the current recipe, press “YES”.
6. In order for the program to update a stage, press “NEXT STAGE” and then press
“PREVIOUS STAGE”.
7. Select the pump that will be used to bring on the mix water.
2. Set the centrifugal pumps’ revolutions to the optimum number – mix water pump
3. For the operation of the pressurizer pump, the minimum rpm is set to 1000. The
rpm may need to be increased during the job, to the desired back pressure on
achieve 20 psi back pressure on the 2" Coriolis flow meter. The valve is located
2. The Venturi bean (fixed choke) on the 2" recirculation side should have the
delivery, and the bulk delivery set-point, are within the proper range. Follow the
1. Properly place the recipe for the job on the PLC screen.
2. Make sure that the program mode is selected in the mixing function screen.
3. Touch either the mixing water, or the cement, to bring up a pop-up screen.
4. Enter the values for the rate and the density, and touch their correlated
simulation buttons.
NOTE: If the simulation is running, the buttons will appear yellow, and the
simulation will be seen on the mixing water and the cement screens.
6. Examine the functions of the bulk cement control valve and the mix water control
valve. Ensure there are no erratic and irregular movements of both valves.
7. Compare the actual bulk delivery and the bulk delivery set-point, making sure the
8. Associate the correlation explained in step 5, with the one explained in step 6,
and make a decision if the PLC is working properly for either of them.
NOTE: Make sure that both simulations are turned off before starting the job.
with all the personnel on location. Get a radio from the supervisor, after the safety
meeting. Using the radio, the operator is able to communicate with other crew regarding
valve, and centrifugal pumps to make sure all functions are properly working. Use the
operator, to ensure proper procedures are followed and that the SCM operator is fully
1. Check and make sure the cyclone supply valve (Figure 1-76) is closed, at all
times.
2. Air up the bulk unit, to a maximum of 40 psi, and maintain this constant pressure
for the proper pneumatic flow of bulk cement to the SCM unit.
3. Turn the canvas valves (Figure 1-77) to ¾ open to ensure proper aerating of
cement.
4. Place the top air valve (Figure 1-77) to ½ open for constant flow of bulk.
5. Check and make sure the purge valve (Figure 1-77 and Figure 1-78) is closed, at
6. To reduce bridging effects and ensure proper constant bulk flow, slowly open the
pod valve (Figure 1-78) to fully open, so that the desirable mixture of air and bulk
flow to the SCM unit can be acquired. Keep the pod valve at fully open, until
1. When there is approximately one ton of cement left in the pod, switch pods for
smooth operation of bulk cement flow. Another indication that a pod is getting
close to empty is the excessive amount of air found coming from the 4" vent line
NOTE: The bulk unit operator should let the SCM operator know when there is
only one ton of bulk cement left, to ensure that the proper slurry density is
maintained.
2. When switching the pods, fully open the pod valve on the new pod and close the
pod valve halfway on the pod that is almost empty. An indication that the pod is
NOTE: Close attention is required to ensure that the empty pod is not left open,
1. When bridging occurs, that means the bulk cement has stopped being delivered
to the SCM unit, due to insufficient pneumatic transfer. To remove the bridging,
close the pod valve and open the purge valve to allow air to push bridged off bulk
2. If this does not sufficiently push the bulk to the SCM unit then properly disengage
the PTO to the blower. Take off and clear the 8' bulk hose.
NOTE: The PTO must be disengaged to the blower. Ensure that all pressure is
bled from the plumbing before removing the 8' bulk hose.
1. Air up the “P” tank to maximum 15 psi and maintain, at all times, the proper flow
2. Turn the canvas air valve (Figure 1-80) to ¾ open to ensure proper aerating of
the cement.
3. Check, and make sure, that the purge valve (Figure 1-80) stays closed, at all
4. To reduce the possibility of bridging and ensure proper constant bulk flow, slowly
open the tank valve (Figure 1-81) to fully open, so that the desirable mixture of
air and bulk flow to the SCM unit can be acquired. Keep the pod valve fully open
1. Switch to a different tank when the tank being used is empty. An indication that
the “P” tank is getting empty is an excessive amount of air coming from the 4"
vent line (Figure 1-79) on the SCM unit. A reduction in air pressure from the “P”
2. To switch to a different “P” tank, completely open the tank valve (on the new
tank) and close the tank valve (on the empty tank). Ensure that continuous air
NOTE: The PTO must be disengaged to the blower. Ensure that all pressure is bled
1. Flip the “MASTER WATER”, “MIX WATER VALVE”, and “CEMENT VALVE”
switches, located on the upper control console, to the “AUTO” position. See
Figure 1-82.
2. With the mix water pumps’, the recirculation pump’s, and pressurizer pump’s revs
already preset, and once the curb side Triplex pump is rolling, and the circulation
NOTE: This scenario is out of the road side displacement tank with the curb side
isolated.
3. Once there is 2 m3 (12.6 bbl) of pre-flush left to pump, in the road side of the
displacement tank, press the “START MIXING” button on the HMI screen.
4. After the “START MIXING” button has been pressed, the mix water rate will
increase. The cement control will not open until the mix water rate is 100 liter/min
(25 gpm). After the cement control valve opens, with the increasing of the bulk
cement delivery, the slurry density will be increasing to the set-point. Refer to
5. Increase the bulk cement delivery so that the density of the slurry increases (as
quickly as possible).
6. After all rates are reading properly, watch the density of the 2" Coriolis flow
meter. Make sure that the bulk control valve is responding properly to the density
screen and verify that it is reading 20 psi. If there is not enough back pressure on
the meter, the density will read lower than what the actual slurry density is. To
increase the pressure, adjust the 3" recirculation line shut-off valve two notches
(Figure 1-75) to increase the back pressure to approximately 20 psi. Ensure the
7. With the valves being set, and the automation working properly, observe the
averaging tank level and adjust the rate trim to raise or lower the slurry height in
the tank.
8. When all the processes are functioning properly, stand back and watch. Make
sure that the bulk control valve is reacting properly to the density changes.
9. When there is the predetermined pre-flush pumped, and sufficient slurry in the
averaging tank, switch from the displacement tanks to the mix tank and
averaging tank.
Cementing Services SCM W/MK IV AT Skid 1-79
Operator Training Manual – Version 1.1
Unit 1
SCM W/MK IV AT Unit Operation and Maintenance
10. Always open and then close the valves. Make sure the valves are given enough
NOTE: Switching the valves too quickly will cause the pumps to suck air and
jack.
1. Flip the mix water valve to the “MANUAL” position (see Figure 1-82 for the
location of the “AUTO/MANUAL” switch) and close the bypass water. Keep the
slurry weight as consistent as possible. Make sure that the density does not get
2. Inform the bulk unit operator to “shut in” the product line. If the slurry weight is
declining to low, then flip the master water valve to the “CLOSE” position (see
4. Flip the master water valve to the “CLOSE” position, if it is still in the “OPEN”
position.
5. Once the bulk cement product line is purged, turn off the recirculation pump.
6. Flip the “X-OVER” switch (Figure 1-84) to open the mix tank to the pressurizer
pump.
7. When the mix tank, and averaging tank, are just about to suck air, shut down
pumping.
NOTE: Make sure there is constant communication, at all times, between the SCM unit
operator and the bulk unit operator. The bulk unit operator should let the SCM unit
operator know when the cement level in the pod is getting low. The indications include:
excessive air coming from the 4" vent line (Figure 1-79) on the SCM unit, a decline in
pressure on the bulk unit, or the actual bulk delivery on the HMI screen is declining
1. Once the lead is finished and the bulk unit operator has purged out the bulk line,
switch from the averaging tank to the mix tank by opening the “X-OVER” valve
(Figure 1-84) and turning the “Averaging Tank Isolation Valve” switch to “CLOSE”
(Figure 1-85).
2. Turn off the recirculation pump to allow the mix tank to drain at a quicker rate.
3. Once the mix tank is empty, switch back to the averaging tank and slow down the
4. Make sure that the “MIX WATER VALVE” and “MASTER WATER” switches are
in the “AUTO” position and press the “NEXT STAGE” button. Make sure to turn
6. When the slurry level in the averaging tank is getting low and the tail slurry is at
weight, open the “X-OVER” valve and close the “AVERAGING TANK
7. Pump out of the mix tank until the slurry is flowing over the weir and filling up the
averaging tank.
8. When the averaging tank is full enough so that the down hole pump will not suck
air, switch back from the mix tank to the averaging tank by closing the “X-OVER”
1. Flip the “MASTER WATER”, “MIX WATER VALVE”, and “CEMENT VALVE”
3. Adjust the density of the slurry with the bulk control valve. Make minor
4. Once the valve is in the “Sweet Spot”, usually only minor adjustments will be
needed.
2. Turn on the Instrumentation Power Switch. This switch turns on the PLC, HMI,
previous settings and information. This would be either US or Metric units, and
4. Simulate the cement recipe to ensure the recipe provided will give the
appropriate results.
5. Make sure that the simulation mode is turned off, immediately following this
check.
The function of each field listed previously is described in the following subsections:
The mix water control circuit consist of two paths. When the
• Calculates the mix water rate set-point for desired mixing rate.
• Shows the actual rate of mix water through the magnetic flow meter.
• Bar graphs that indicate loop status, control output and valve feedback
o LE (Load Error) displays load error between rate set-point and actual rate
10% – Red
o Green – Open
o Red – Closed
• Square background flashing “Warning” shows the water rate is too low
Pressing the bar graphs opens the Control Valve Calibration screen (Figure 1-88) in the
Flex Screen. This screen contains calibration parameters for the mix water valve.
Detailed characteristics, and settings, are accessed via the Tuning Screen.
• Bar Graphs
o LE (Load Error) displays the load error between density set-point and
actual density.
10% – Red
Pressing the bar graphs opens the Control Valve Calibration screen (Figure 1-90) in the
Flex Screen. This screen contains calibration parameters for the cement valve control.
Detailed characteristics and settings are accessed via the Tuning Screen.
Pressing the numerical value, for each pressure, opens detailed screens (Figure 1-92
and Figure 1-93) in the Flex area. To change the “Over Pressure Trip Point”, press on
the current set-point and the number pad will appear for entering the new over pressure
NOTE: When the over pressure set-point is exceeded, the throttle will go to low idle and
the transmission will shift to neutral for the associated engine, transmission or pump.
The over pressure trip point field will flash red, when active. The actual pressure must
be lower than the over pressure trip point, to be able to reset the system. Before doing
this, press the throttle in (to reset to low idle). The transmission should always be shifted
from neutral to 1st at a low idle rpm. After the system is reset, resume the normal
operations.
The screens below (Figure 1-92 and Figure 1-93 ) allow you to do the following:
This box (Figure 1-94) displays error or warning messages from the control system. The
messages only display for a few seconds and then go into the message log.
• Stage Total
• Job Total
The surge can weight indicator (Figure 1-96) provides a weight and tare function for the
vessel. The hydraulic load cell is positioned under one leg of the vessel and measures
• Tare
o The tare function provides a method of zeroing the weight of the vessel.
• Default
o If you have tared the vessel mistakenly, you can return to the default,
which will remove the tare offset and will once again display the weight of
the vessel.
• Factor
o The weight measured under the one leg represents 50% of the total
weight. The factor multiplies the weight by 2 to display the actual weight
measured.
• Rate Trim
o Initially set to the programmed rate in the current recipe stage. It is for use
during the job for adjusting the mixing rate. The down hole rate is
• Density Trim
used during mixing to adjust for the difference between the mud (or
To change the Recipe Data, press the variable you want change. The screen is a touch
screen. Once the box is selected, a number pad (Figure 1-101) will appear on the
screen. This will allow you to change the data in the input boxes. Once the data in the
input box is changed, press the “ENTER” key (Figure 1-100) and the number pad will
disappear. It will reappear every time that a variable is selected. When the new recipe
has been entered, and is correct, then press the “SAVE” button in the middle of the
A message will appear in the message window indicating that the data has been saved.
If the job has only one type of slurry, then input the recipe into the program. To do this
either a) press the “SAVE” button again and press “YES” to overwrite the data again, or
b) press the “NEXT STAGE” button on the top right corner of the screen once.
Let the 2nd recipe come up and then press the “PREVIOUS STAGE” button just below
the “NEXT STAGE” button. This inputs the data into the program by making it disregard
When there is a 2nd recipe, just press “NEXT STAGE” button on the bottom of the recipe
input box and it will read “STAGE 2” on the top of the recipe box. Enter the new recipe
for the 2nd slurry by following the same procedures as for the 1st slurry. The only thing
that will be noticed with the program is that when you press the “SAVE” button and
overwrite the previous recipe, the program automatically changes to the most current
saved stage.
So when saving the 2nd recipe, and before starting the job, make sure that on the top
right hand corner of the screen, it reads “STAGE 1” or the proper stage is needed. If the
incorrect stage is selected, press the “PREVIOUS STAGE” button or “NEXT STAGE”
button to select the desired stage. When you press the “NEXT STAGE” or “PREVIOUS
STAGE” buttons, on the upper right hand side of the screen, the recipe box on the
buttons.
• Start Mixing/Pause
• System Diagnostic
• System Tuning
• Screen Lock
• Mixing Functions
• Process Variables
• Trend Graphs
Figure 1-102:
Function Buttons
Field
This function starts mixing the slurry based on the current stage information. When
pressed, the mix water pump must be over 2000 rpm and the recirculation pump must
be over 1500 rpm. The bulk control, mix water and master water valves must be set to
“automatic” on the toggle switches on the operator panel. If they are not, a message
will appear in the message box and mixing will not start. If all the parameters are met,
and mixing starts, the button will turn green in color. Initially, to pause the process,
press the button again and it will close the water and bulk valves.
NOTE: When you engage the “Start Mixing” function after the pause has been pressed,
the program does not go to the previous position. It goes to the calculated positions and
• Mixing Function
o Master water valve switch in “AUTO” or “MAN” but valve must be open
1200)
is 1200)
Cementing Services SCM W/MK IV AT Skid 1-100
Operator Training Manual – Version 1.1
Unit 1
SCM W/MK IV AT Skid Operation and Maintenance
overridden and the system will go into the mixing mode. This is because
o With the system in “AUTO” and mixing, if the mix water rate drops below
▪ If the condition lasts more than 3 seconds, the cement valve will
close.
o After “Start Mixing” is active, the cement valve will not open until the mix
• Alarms/Notifications
o If the recirculation density is 200 kg/m3 (1.7 lb/gal) higher than the
o During mixing, if the cement valve is 100% open and the density is 30
kg/m3 (0.25 lb/gal) lower than the set-point, the bulker symbol on the
o If the down hole Triplex pump’s boost pressure is less than 30 psi, the
value flashes.
1-107) are color coded according to the amplitude of the excitation current
signal.
▪ Green (0 – 18 ma)
• The centrifugal pump symbols are color-coded dependent on the rpm. See
These buttons change the stage recipe that is read by the program. The stage recipe
that is being read is shown on the top of the stage information area. Also, the “Cement
Pressing this button opens the System Diagnostic screen (Figure 1-103), which assists
with troubleshooting problems. This screen displays raw input, and output, signals from
the system. From this screen the operator can also change units or access the
Caution
Risk of moderate equipment damage or minor personal injury
These functions should only be accessed by qualified personnel. Incorrect usage could result in
data loss or equipment malfunction.
This button brings up the screens used for system tuning. There is a system tuning
page for each of the control loops – water and cement (Figure 1-104 and Figure 1-105).
This area is for an electronic technician to view process response characteristics, while
Warning
Risk of substantial equipment damage or serious personal injury
The tuning variables should only be modified by qualified personnel. Minor changes to the
variables can have major effects on the control characteristics.
This button is pressed when you need to clean the screen. It will produce a blank
screen with a bar graph that acts as a count down timer. This allows the operator to
NOTE: When this function is used it will disable the screen for 10 seconds.
This button opens the “Mixing Functions” screen (Figure 1-106) in the Flex area. The
screen contains items that determine how some pre-mixing functions will be controlled.
These features are designed for mixing an initial batch of slurry to weight before
engaging the “Start Mixing” function. With the start tub level set at 80%, the program
would calculate the required mix water needed to have the initial batch of slurry
occupying 80% of the mix tank. The calculations are based on the data entered in the
selected stage. See below for the functions of the buttons and boxes.
“Start/Stop Water” Button – This function opens the master water valve, and the mix
water valve, fully until the required mix water (REQ) matches the actual mix water
(ACT). Once the actual mix water matches the required mix water, the valves close and
“Start Cement” Button – Once the system verifies that the required mix water has
been delivered to the mixing tank; it allows the operator to activate the “Start Cement”
button. At this point, the operator would be circulating the mix side at the specified rpm.
When the “Start Cement” function is activated, the bulk cement valve travels to 60%
open. It remains there until the density in the mixing tank equals the programmed
density set-point. Once the density is reached, it would close the valve or the operator
would press “START MIXING” and the program would take over.
“Reset Job” Button – This button resets the program for a new job, puts the program
“Water Valve Initial Position” and “Cement Valve Initial Position” Drop Boxes –
Either of the two valves can be initially set to open, to a calculated position, based on
cement blend parameters. The other method is to have the valve initially go to a
manually entered position. This manual setting is adjusted by entering the desired
percentage position in the water or bulk cement control valve position box.
“Down Hole Rate” Drop Box – The down hole rate drop box has two different options
– “Mass” and “Pumps”. This is the down hole rate that is displayed on the “Stage
Information” area of the screen. This also affects the “totalizer” with how it calculates the
total pumped. “Mass” is the 4" Coriolis mass flow meter and “Pumps” is the combined
rates of the Triplex pumps. Most often, this is set to “Mass” to read the actual flow of
fluid to the pumps. This helps the operator notice if the pumps are jacking, or partially
bridging off, by the difference in flow to the pump rate. The only time that “Pumps”
would need to be selected is if the fluid is very aerated that the Coriolis does not read
properly or if the operators are pumping through the short suction and no fluid is flowing
“Control Reference” Drop Box – This is specifically for the mixing rate. The two
choices are “Program” and “Pump” rates. “Program” rate is the rate set by the recipe or
is changed with the rate trim. “Pump” rate is the mixing rate corresponding to the rate
that is being pumped down hole. The best way to start mixing is in the “Program” rate,
because when pumping the pre-flush the operator may need to slow down the pumps
for the mixing system to build-up enough slurry in the averaging tank (to start pumping)
Pressing this button opens the “Process Variables” screen (Figure 1-107). This screen
contains all the pertinent information for the mixing system and the high pressure
o Green – Open
o Red – Closed
o Background Color
• 2" Coriolis
o Density (lb/gal)
o Rate (bbl/min)
o Temperature (Fahrenheit)
o Pressure (psi)
• 4" Coriolis
o Density (lb/gal)
o Rate (bbl/min)
o Temperature (Fahrenheit)
• Process Pressures
▪ 0 – 160 psi
▪ 0 – 160 psi
Pressing the “Calibration Data” button opens the “Calibration Data” screen (Figure
1-108). This screen allows you to enter in the calibration factors for:
Pressing the “Auxiliary Pressure Data” button opens the “Auxiliary Pressure Data”
screen (Figure 1-109). This screen allows you to enter in ranges for process pressure
• If “Zero” function is used (when the line has pressure), “Default” can be used to
o 4 – 20 ma = 0 – 160 psi
Pressing the “Aux Press Calib” button opens up the “Auxiliary Pressure” faceplate
(Figure 1-110). This faceplate is used to setup, and calibrate, the auxiliary pressure
• If either of the previous functions are used incorrectly, use the “Default Values”
o 4 – 20 ma = 0 – 15000 psi
A condensed screen (Figure 1-111) containing the two Coriolis flow meters’ main values
can be viewed by pressing the middle of the “Process Variables” screen. The screen
Figure 1-111: Condensed Screen with Coriolis Flow Meters Main Values
Pressing this button opens up the options available for viewing during the job (Figure
• Job Data – Rate, Pressures, Density, Bulk Delivery, Bulk Delivery Set-point
• Rates – Mix Water Rate, 2" Coriolis Rate, Down Hole Rate
• Process Pressure – Mix Head Water Pressure, Mix Head Recirculation Pressure,
The data viewed in Figure 1-113 to Figure 1-117 is a 15 minute history of the job. The
data is stored on a memory card in the HMI. It can be retrieved, if necessary, for
these including rigging out, cleaning up the SCM high energy mixing system, washing
the high pressure Triplex pumps, washing up the ground mixing system, greasing the
• Disconnect the water line between the drilling rig and the SCM unit.
• Disconnect the water line from the water truck to the SCM unit.
• Disconnect the bulk hose from the bulk unit to the surge tank. If the “P” tank is
used, disconnect the bulk hose from the “P” tank to the surge tank and
NOTE: Ensure that all air is bled off from the bulk system, prior to disconnecting
the hoses.
• For high energy mixing jobs, disconnect the bulk hose between the mix head and
o Disconnect the 11/2" and 2" water hoses between the mixing tree and the
mixing bowl.
o Disconnect the 4" riser hose between the mix slurry tub and the mixing
bowl.
o Disconnect the 2" recirculation line, and the 4" suction line, from the
o Dismount the mix slurry tub from the primary skid and place it back on the
iron skid.
• Connect a vacuum truck to the end of the treatment line, to suck out all the slurry
• After the Triplex pumps have been vacuumed, rig out the treatment line.
clean up, cement can build-up rapidly around various areas of the mixing system. Given
time, this build-up can cause serious restrictions in the slurry, and dry cement, flow. It
can also result in the slurry being mixed too slowly or it can cause the whole mixing
Once the cementing-mixing process has completed, immediately clean up the unit
following the procedure below. This ensures that the unit will perform properly on the
1. Turn the “MIX WATER VALVE” and “MASTER WATER” switches from the
2. Turn the mix water valve and the bulk cement valve to the “Close”.
3. Close the 2" mix water valve to the mix head. This ensures that all the water is
supplied to the wash up valve, when the master water valve is opened. Open the
NOTE: To use the wash up valve, the master water valve must be open.
5. Close the 2" mix head water line shut-off valve to the mix head. This ensures that
all the water is supplied to the wash up valve. To use the wash up valve, the
6. If possible, rinse down the mix and averaging tanks while they are still warm and
the fluid on the walls is not dried. This speeds up the wash up.
7. Open the lid of the cyclonic chamber and wash it off. Also, wash under the 180°
8. Hammer loose the union, for the mix head, and tilt it back.
10. Remove the bulk cement sleeve and wash off the bottom of the jets.
11. With the sleeve removed, check the jets to ensure that they are not plugged off
with debris. Also, check the condition of the mix water diffusion plate and make
12. Inspect the o-rings and ensure that they are not damaged or cut.
14. Drain both the mix tank and averaging tank, and rinse out the bottoms.
15. Isolate the averaging tank, by closing the “AVERAGING TANK ISOLATION
VALVE”, so that no fluid will come back through the drain and close the
16. Open the automated “WATER CONTROL VALVE” to flush the recirculation lines.
17. Once the mix tank is half full, turn on the recirculation pump.
18. Fully open, and close, the 3" recirculation line shut-off valve to flush thoroughly.
19. With the recirculation pump on, open and close the 4" isolation manual valve to
20. Shut off the recirculation pump. Open the “X-OVER VALVE”.
21. Open the recirculation line to the averaging tank, and once flowing, open the
22. The recirculation of the averaging tank may need to be flushed, a few times until
it is clean.
23. Once the mix tank and averaging tank are clean, drain the remaining water.
24. At the end of the job, hammer off the suction caps to ensure there is no slurry
debris. This will make certain that there are no restrictions or problems for the
next job.
2. Shift the transmission to the 5th gear. Flush back to the displacement tank.
3. Open the displacement side pressurizer pump isolation valve (see Figure 1-119
for the location of the switch) and the high pressure return valve (see Figure
4. Turn on the pressurizer pump. Turn on one of the Triplex pumps, returning back
5. Open the short suction valve (Figure 1-121 and Figure 1-122) for 2 to 3 seconds
and close. Repeat 6 to 8 times, ensuring that the valve is free of debris.
Figure 1-121: Short Suction Valve and 4" Suction Figure 1-122: Short Suction Valve and 4" Suction
Caps (on road side) Caps (on curb side)
8. Hammer off all the 4" suction caps (Figure 1-121 and Figure 1-122) and push the
valves of the Triplex pumps to drain all water from the pumps.
NOTE: Make sure the 2" water line and 11/2" bypass water line are cleaned, to
3. Run the 2" water line to clean all the debris up to the riser hose and into the mix
slurry tub.
4. Wash the mix slurry tub. Make sure the inside of the mix slurry tub lip, and
suction, is washed. Ensure that the mix slurry tub is cleaned outside and inside.
5. Suck out the rest of water through the pressurizer pump and hammer off the 4"
cap to drain the rest of water from the tub (Figure 1-123).
centrifugal pumps. To grease the centrifugal pumps, pump 3 to 4 shots of grease while
• Neutron valves on the mixing tree (if the ground mixing is used)
For the greasing procedure of the plug valves, refer to Section 2.10.1.2.1 Plug Valve.
• All the items that came off the unit go back onto the unit.
• All the hammers are inspected for cracks in the handles or other aspects that
• All the swivel joints have been greased (this should be done weekly).
• The unit is clean inside and outside before it is handed over to the next crew.
NOTE: If any problems are found that need to be resolved by the mechanics, report the
problems to them quickly. The mechanics can then inspect the unit, prior to the next
job.
2.2 Introduction
SCM W/MK IV AT (abbreviated as SCM) International skids are all constructed at the
Sanjel fabrication shop. These skids are operated and maintained by a supervisor and
an operator. All SCM units have been designed to operate with high efficiency and high
durability. It is important that these units are maintained following a simple maintenance
In this section, first, Sanjel’s routine maintenance schedule and general maintenance
requirements for the SCM skid will be introduced. Then the unit will be broken down into
licensed mechanic’s help, if required. This inspection report must be turned in to the
maintenance personnel and a copy should be left in the unit. Refer to Sanjel’s “250
Hour Vehicle Inspection Report” to conduct the inspection (Table 2-1 to Table 2-3).
NOTE 1: The “250 Hour Vehicle Inspection Report” sheets contain references to
may be tractors or trailers used to transport the SCM skid, at some future date.
NOTE 2: The “250 Hour Vehicle Inspection Report” sheets are provided here as
examples only. These sheets should not be used as the actual checklist forms, unless
there are no other options. In cases where there are no proper forms available, make
copies of the sheets provided here (you may have to resize the pages to fill them out).
After copying, ensure that the original pages are put back into the manual.
licensed mechanic. When performing the monthly maintenance, fill out Sanjel’s “Monthly
Maintenance Log” each time work is done. This log must be turned in to the
maintenance personnel and a copy should be left in the unit. See Table 2-4 for an
three months or 50,000 km (32,000 miles) on the unit. The inspection is carried out by a
licensed mechanic with help from the operator and supervisor. The mechanic is
responsible to insure that the inspection is done properly. The mechanic, in consultation
with the camp management, determines what course of action is taken on items
requiring major repairs. Follow Sanjel’s “Quarterly Inspection Report” sheet to perform
the maintenance. The sheet should be handed in to the maintenance personnel once
the work is done. Refer to Table 2-5 to Table 2-8 for examples of the “Quarterly
tractors or trailers used to transport the SCM skid, at some future date.
NOTE 2: The “Quarterly Inspection Report” sheets are provided here as examples
only. These sheets should not be used as the actual checklist forms, unless there are
no other options. In cases where there are no proper forms available, make copies of
the sheets provided here (you may have to resize the pages to fill them out). After
copying, ensure that the original pages are put back into the manual.
operator, if needed. The “Quarterly Inspection Report” sheet is also used as the annual
maintenance sheet.
pages).
NOTE: The checklists provided in this section are examples only. Please refer to the
Sanjel SCM Commissioning Document, which resides on Sanjel’s Intranet website, for
the proper checklists (along with a number of other forms available for download).
maintenance is always required. With regular inspection and efficient maintenance, the
Regular lubrication and inspection of the parts of a unit is the most cost effective
method of obtaining safe and reliable unit operation. Sanjel has developed a scheduled
maintenance program for all units, ensuring that every unit operates properly when
• The crew on the unit must perform a 250 hour service, assisted by a mechanic if
necessary.
inspection, with assistance from the driver, operator, and supervisor. The
• A work order (Table 2-35) is completed for every inspection, detailing actions
taken on major repairs. The maintenance department keeps the work order as a
record.
The maintenance department also ensures the inspection is properly performed and
takes follow up action on rejected items. The maintenance department updates the
maintenance log book and wall chart, and keeps the documents in the unit's file.
Modifying units is not acceptable, unless absolutely necessary for job completion.
• Modifications made to the vehicle must be properly fixed and the vehicle
duties will be reviewed and applied to all units in the fleet, if approved.
gain information about the condition of the oil itself, or the condition of the component
from which the oil was removed. This information can then be used to reduce
Engine oils are to be sampled and changed every 250 hours +/- 10%. The shop
mechanic co-ordinates the program and supervises taking the samples. An approved
sampling device should be installed on all the engines. Dates and hours (or miles) are
The "oil added box" is the total oil added between oil changes, not the amount of oil
added at the oil change. When completing the unit number, add suffixes.
NOTE: If more than 3.785L (1 gallon) of oil is added between oil changes, report this to
1. Attach the oil drain pipe from the oil pan to the oil drain pan.
2. Allow the oil to flow out of the oil drain pipe for one minute to permit the oil to
clear the drain pipe of any debris or oil left from other trucks.
3. While oil is still flowing, take the oil sample directly from the flowing hose, not
• Change the oil filters once per year. If changing for regular maintenance be sure
to cut open the filters to see if any metal is present. This could possibly tell of a
failure starting.
• Change the hydraulic oil once every other year. Filter the oil with the filter cart
• Inspect the oil and filters for contaminants, at the year when the oil is changed.
• Table 2-36 gives an example to specify the years of the oil and filters changes.
Table 2-36: Example of the Hydraulic Oil and Filters Change Schedule
• Sample oil, and change oil and filters every 250 hours.
• Change oil once per year with ATF Petro Canada – Semi Synthetic oil. Refer to
2.5.5.4 Triplex Pump – Lube Oil and Lube Tank Oil Filter
The maintenance task is as follows:
• Change the lube oil and lube tank oil filters once per year. Cut open the oil filters
There are certain components on the SCM skid unit that require routine inspection and
following order:
• Transmissions
• Drive Lines
• Iron
• Hydraulic System
• Plumbing System
engines are located at the front of the primary skid. Refer to Figure 2-1 and Figure 2-2
for the road side and curb side views of the engines. In the following subsections, the
engine components are divided into the fuel system, oil system, air system, cooling
1. Exhaust
2. Air Cleaner
Canister
3. Radiator
4. Air Kill Reset
Lever
5. Air
Compressor
6. Coolant
Inhibitor
Element
7. Primary Fuel
Filter
8. Secondary
Fuel Filter
9. Oil Filters
10. Oil Filler Cap
11. Oil Dipstick
12. Oil Pan
13. Air Starter
14. Oil Drain
Plug
Figure 2-1: Detroit Diesel Engine (road side view)
tanks are located below the two engines (see Figure 2-3 and Figure 2-4 for the major
components of the fuel tanks). Each engine is equipped with primary and secondary
fuel filters. The primary filter or fuel/water separator removes large contaminations from
1. Fuel Cap
2. Fuel Return Line
3. Fuel Suction
Lines
4. Fuel Level
Sensor
5. Fuel Vent Hose
6. Fuel Primer
Pump
7. Fuel Tank Drain
Plug (not
showing)
• Inspect the fuel lines, for fray and physical damage, daily.
Warning
Risk of substantial equipment damage or serious personal injury
Fuel is highly flammable. Always follow proper safety procedures when refueling the unit.
Always shut off the engines during refueling.
• Always fill the fuel tanks after each job. Filling the fuel tanks minimizes moisture
• During fuel refills, inspect the fuel cap gasket for a proper seal.
• There are two types of fuel caps (Figure 2-5). Always replace the existing fuel
escape.
• Change the primary fuel filter and secondary fuel filter at the 250 hour service.
The Detroit engines are equipped with spin-on primary and secondary fuel filters.
Caution
Risk of moderate equipment damage or minor personal injury
Engine exhaust is poisonous. Always operate the engine in well-ventilated area to avoid injury
from inhaling engine exhausted air.
2. When the engine reaches the ambient temperature and is cool to touch,
secondary fuel filter, turn the handle on the shutoff valve to the “Close”
position.
NOTE: Fill the replacement filters with fuel and have them ready to install
4. Remove the primary and secondary fuel filters using a band type of filter
wrench.
5. If the new replacement filters were not previously filled, fill them with clean
diesel fuel and coat the gaskets lightly with the fuel.
6. Thread the new filters onto the adaptor inserts until the gaskets make full
NOTE: Do not over tighten the filters. Over tightening the filters may
the filters.
Warning
Risk of substantial equipment damage or serious personal injury
Engine exhaust is poisonous. Always operate the engine in a well-ventilated area to avoid
injury from inhaling engine exhaust.
9. Start the engine and check for any leaks. Shut down the engine and fix
NOTE: Never use the starting motor and fuel pump to prime the fuel
filters. Excessive use of both, to prime the fuel system, will result in
10. Mark down the date of change along with the operator’s initials on the
filters.
cleans, inhibits corrosion, and cools the engine by carrying heat away from the moving
parts.
Warning
Risk of substantial equipment damage or serious personal injury
Hot oil and components can cause personal injury. Do not allow hot oil or hot components to
contact the skin.
Warning
Risk of substantial equipment damage or serious personal injury
To avoid injury from slipping and falling, clean up any spilled oil immediately.
• Check the engine oil level, daily. See Figure 2-7 and Figure 2-8 for the locations
of the engine oil filler cap and dipstick. Perform this action when the engine is
stopped and the equipment is on level ground. If the engine has just been
stopped and is warm, wait about 20 minutes to allow the oil to return back to the
oil pan before checking. Maintain the oil level within the satisfactory range on the
Figure 2-7: Engine Oil Filler Cap and Dipstick Figure 2-8: Engine Oil Filler Cap and Dipstick (curb
(road side) side)
• Visually check for oil leaks around the oil filters and the external oil lines (daily).
• All diesel engines must be on an oil analysis program. Refer to Section 2.5.3 Oil
• The engine oil must be sampled and changed at the 250 hour service. Refer to
Section 2.5.4 Obtaining an Oil Sample for the oil change information.
• Change the oil filters (Figure 2-10) at the 250 hour service. Follow the steps
Warning
Risk of substantial equipment damage or serious personal injury
Immediately clean up any spilled liquids to avoid injury from slipping and falling.
1. Place a container under the engine oil pan, remove the drain plug and
drain the engine oil. Replace the drain plug and tighten it securely.
3. Clean the filter gasket and the contact surface of the adaptor head.
4. Have the new filters filled with engine oil and lightly apply the same oil to
5. Start the new filters on the adaptor head and tighten by hand until the
gaskets touch the adaptor head. Tighten the filters an additional two thirds
NOTE: Do not over tighten. Over tightening the filter may fracture and
6. Fill the oil (as needed) to bring the oil level within the satisfactory range
7. Start and run the engine for a short period of time and check for any leaks.
Warning
Risk of substantial equipment damage or serious personal injury
Engine exhaust is poisonous. Always operate the engine in a well-ventilated area to avoid
injury from inhaling engine exhaust.
8. After all the leaks have been corrected, shut down the engine and wait
approximately 20 minutes to allow the oil to return back to the engine oil
pan, from various parts of the engine. Check the oil level again. Add oil, as
needed.
oiler system, the control console to enable the master water valve, and the Vortec air
conditioner. Refer to Figure 2-12 for a simplified diagram of the Detroit engine air
system.
Vortec Air
Conditioner
Routine maintenance needs to be performed for the air cleaner, air kill button and air kill
reset lever, air compressor, air dryer, air lubricator, and air tank. The entire air system
Caution
Risk of moderate equipment damage or minor personal injury
Never service the air cleaner element with the engine running since this will allow dirt to enter
the engine.
• The Detroit engine has one air cleaner element. The air cleaner element should
be checked at the 250 hour service. Inspect the element with a trouble light by
inserting the light into the element and scanning all the way around. If the light
penetrates the element, the element is still good. If not, the element needs to be
replaced.
NOTE 1: This is important especially when the engine is operated under severe
dust conditions.
• Mark the installation date and operator’s name on the air cleaner canister.
for runaway engines, which are caused when flammable gas enters the engine (i.e.,
methane, sour gas, propane). The air kill button (Figure 2-14) of the Detroit engines is
located on the upper control console on the operator’s platform. It is a red button
labeled as “Emergency Shutdown” at the right bottom corner of the control console. The
air kill reset lever (Figure 2-15) is mounted in the air intake line of the engine.
• Function test the air kill reset lever before each job and at the 250 hour service
(Figure 2-15). Check it with the engine at a dead idle, NOT at high rpm, to ensure
the gates will cut off the air supply. Do the test using the air kill button on the
• Move the handle back from the closed position (handle at 45°) to the opened
position (handle at 90°) and feel for smoothness of operation, or any other
obstructions, and listen for an audible clicking sound as it moves back into place
(Figure 2-15).
pressure air. It pumps the air into the air tank (reservoir). It is located on the engine’s left
side above the middle of the compartment. See Figure 2-16 for the major components
1. Discharge
Line
2. Governor
3. Coolant Line
4. Oil Line
The governor (Figure 2-16) controls the air compressor and starts or stops the air
compressor from pumping air. When the air tank pressure rises to the “cut-out”
pressure, the governor stops the compressor from pumping air. However, the
Danger
Risk of extreme equipment damage, severe personal injury or possible death
Never work on or repair compressor system when the engine is in operation.
Do not disconnect the high pressure air line unless the air tank has been drained.
Warning
Risk of substantial equipment damage or serious personal injury
• Inspect the air intake, oil suction and return lines, and coolant suction and return
hoses for tight connections and general condition. Tighten the connections, and
• If any oil is present during the draining of the air tank or slow air build-up occurs,
and vapor form) before the air is collected by the air tank. It is located between the two
Allison transmissions. The air dryer of the SCM skids is manufactured by Bendix.
Warning
Risk of substantial equipment damage or serious personal injury
Always shut off the engines prior to servicing the air dryer.
o If oil is present in the air system when draining the air tanks, check the air
dryer. The presence of oil in the air dryer will render the dryer ineffective.
o If the air dryer is continuously blowing off, check oil contaminants in the air
system.
o If there are white milky deposits on the exhaust of the air dryer, this may
be the result of water and oil mixing in the dryer. Notify the maintenance
department.
• Change the Bendix air dryer with a mechanic’s assistance once a year.
lubrication into the air system. This injection helps reduce friction between the sliding
surfaces, thus increasing the cycling speed of the components and reducing wear. It is
• Check the lubrication oil level in the air lubricator, at the 250 hour service.
and provides compressed air to the plunger packing oiler system, the air actuators, the
control console, and the Vortec air conditioner unit. It sits between the two fuel tanks of
Figure 2-19: Air Tank Figure 2-20: Air Tank Drain Valve
• The air tanks must be drained of moisture and sediment, daily (after each job).
See Figure 2-20 for the location of the drain valve. There are three reasons for
3. To inspect for oil. If oil is detected in the tanks, it indicates the air
through radiators. There are coolers attached to the radiators to cool the pressurized
Figure 2-21: Detroit Engine Radiator (road side) Figure 2-22: Detroit Engine Radiator (curb side)
• Inspect the cooling system for leaks, daily. Watch for an accumulation of coolant
• Check the coolant level daily by checking the sight glass (Figure 2-23). Add
o Cold Check
▪ Ensure that all coolant plugs at the bottom of the radiator, and on
▪ Check the coolant level. The cooling system is correctly filled when
the coolant level reaches the middle of the sight glass on the
radiator.
o Hot Check
▪ Start and run the engine for about five minutes at a moderate
speed.
Warning
Risk of substantial equipment damage or serious personal injury
Hot coolant can cause serious burns. Never remove the filler cap when the engine is under the
operating temperature. To open the radiator filler cap, stop the engine and wait until the
cooling system is cool. Wear adequate protective clothing (face shield, rubber gloves, apron,
and boots). Slowly loosen the filler cap in order to relieve the pressure.
coolant level.
• Change the coolant inhibitor elements every 500 hours (Figure 2-24 and Figure
2-25).
Figure 2-24: Coolant Inhibitor Element (road side) Figure 2-25: Coolant Inhibitor Element (curb
side)
electrical system of the skid. There are two alternators (Figure 2-29), two batteries
(Figure 2-26 shows the locations of the two battery boxes), three power switches
Figure 2-26: Battery Boxes Figure 2-27: Curb Side Battery Switches
The main skid power switch (Figure 2-27) on the curb side battery box and the night
switch (Figure 2-28) on the road side battery box are used to connect/disconnect the
batteries with the electrical system. If the road side engine fails, turn on the road/curb
side battery isolation switch (Figure 2-27) so that the curb side engine can charge the
• Check the tension of the alternator belt, daily, (Figure 2-29) and adjust when
• Clean the batteries (connections and cables) at the 250 hour service.
• Inspect the alternator for loose connections and ensure proper battery charging,
yearly.
• The engine mounting bolts, and the condition of the mounting pads, should be
2.7 Transmissions
Sanjel’s SCM skids are equipped with two Allison 4700 transmissions. These
transmissions (Figure 2-30) are located underneath the displacement tank, one on the
road side and the other one on the curb side. They transfer power from the engines, to
the drive lines, allowing the operator to select the proper gear to run the high pressure
Triplex pumps.
• Determine the transmission fluid level by performing a COLD CHECK and a HOT
CHECK. The fluid level should be inspected, daily. Report an abnormal fluid level
▪ A cold check may be made after the initial start-up and the
presence of the transmission oil has been proven (the sump fluid
Remove the dipstick and examine the fluid level. If the fluid on the
dipstick is within the COLD CHECK band, the level is suitable. If the
fluid level is not within this band, add or drain fluid as needed to
o Hot Check
Remove the dipstick and examine the fluid level. The safety
operating level should be within the HOT RUN band on the dipstick.
If the fluid level is not within this band, add or drain fluid (as
NOTE: Make sure the results of each fluid level check are
consistent. Determine the level more than once and, if readings are
and not clogged. If readings are still not consistent, report this to
• Change the transmission oil once per year with ATF Petro-Canada – Semi
synthetic.
NOTE: It is extremely important that the transmission oil is kept clean. The fluid
transmission.
• When changing the transmission oil, check the drain plug (Figure 2-31) for filings
transmissions and the Triplex pumps. They provide the torque to the power ends of the
Triplex pumps. The skid is equipped with two drive lines. One is on the road side, the
other one is on the curb side. See Figure 2-32 and Figure 2-33.
Figure 2-32: Drive Line (road side) Figure 2-33: Drive Line (curb side)
Danger
Risk of extreme equipment damage, severe personal injury or possible death
Rotating drive shafts are dangerous. You can snag clothes, skin, hair, or hands. Never use a
pipe wrench on the drive shaft, always use a strap wrench.
• Before lubricating the drive lines, visually inspect all input and end-fitting retaining
o Grasp the end fittings (yokes) and attempt to move vertically and
Figure 2-34: Rotating Drive Lines Figure 2-35: Moving Drive Lines (vertically and
horizontally)
• Add grease to the CROSS lube fitting (nipples) until lubricant exits at the
• Grease the slip yoke until grease exits the yoke plug (may require several
squirts). Cover the pressure relief hole while continuing to lubricate the yoke.
NOTE: Covering the pressure relief hole allows lubrication to the back of the
yoke.
• Replace the grease nipple, if it does not take or hold the grease.
stroke length in 6" and plunger diameter in 31/2" on the road side and 41/2" on the curb
side. These twin Triplex pumps are horizontal, single-acting horsepower pumps located
pressurized system that injects oil into the plungers’ packing as they operate. The two
pressure regulated oiler tanks (Figure 2-38 and Figure 2-39) are mounted beside the
right side of the control console on the operator’s platform. They have pressure hoses
1. Air Pressure
Gauge
2. Air Pressure
Regulator
3. Air Lines
4. Pneumatic
Pumps
5. Needle Valves
6. Oil Lines
7. Filler/Breather
Cap
8. Ball Valve
9. Bleed Valves
10. Sight Glasses
Figure 2-40: Oiler Tank Hoses and Valves to Plungers Housing (road
side)
Figure 2-41: Oiler Tank Hoses and Valves to Plungers Housing (road
side)
Warning
Risk of substantial equipment damage or serious personal injury
Prior to any maintenance on the oiler, release all pressure in the tank by opening the bleed
valves (# 9 in Figure 2-39).
• Measure the pressures and inspect the oil lines for obvious signs of leaks, or
wear, daily.
• Check the oil level in the oiler tanks during the pre-job inspection. Fill up the
oilers with Greenpatch Oil to the blue mark on the sight glasses (Figure 2-44), if
needed. If the oil level is low during a job, use any engine oil or a suitable
• Drain the plunger oiler tanks reservoirs (Figure 2-42 and Figure 2-43), daily.
150 psi. Consult with the maintenance department for proper operating requirements.
Figure 2-45 to Figure 2-51 show the major components of the lube system. All units
5. Lube Pressure
Gauge (on Triplex
pumps)
6. Lube Swivel (on
Triplex pumps)
• Check the pressure and oil lines for obvious signs of leaks and wear daily.
NOTE: If engine oil is used as an emergency lubricant, the system oil must be
• Each lube tank is equipped with a sight glass (Figure 2-47). Fill the lube tank until
the oil level reaches the blue mark on the sight glass.
• Change the lube oil and thoroughly clean the lube oil reservoir once a year.
• Check the lube oil and filter element supplies needed for frequent maintenance.
• Check all pressure, vacuum and temperature gauges and replace any defects.
suction, and discharge ends, of the Triplex pump and use springs to close the valves.
The valve of the Gardner Denver high pressure pump is shown in Figure 2-52. The
1. Valve
2. Valve Insert
3. Spring
4. Keeper
• Inspect the seals regularly to ensure the seals are working and to prevent
pumping problems.
• Remove the three springs (Figure 2-53) and compare height differences on a flat
surface. If there is a height difference between the springs, change the springs.
• Visually inspect the valve inserts for wear and surface condition. Run fingers over
the mating surface where the insert sits, and feel for surface roughness and
irregularities.
• When replacing the rubbers on the valves, ensure the mating surfaces are clean
and the rubbers are flush against the mating plate to create a perfect seal. This
prevents fluid from entering the gap and separating the seal from the seat.
approximately eight months. If less than eight months, advise maintenance. Figure 2-54
illustrates the fluid cylinder assembly. Refer to the SCM unit Parts Manual for proper
materials for the repacking. Supplies such as the o-rings, seals, packing, valves, seats,
maintenance.
1. Remove the suction cover (Figure 2-55) with tools provided for the pumps.
3. Remove the plungers (Figure 2-55) through the front of the fluid end.
5. Before repacking the pumps, check the plungers and packing brass for excessive
wear, nicks or burrs. Also, clean, grease, and inspect the packing bore in the
stuffing box.
1
Courtesy of Gardner Denver Compact Pump Service Manual.
6. Install the packing, and brass, into the stuffing box with the packing lips facing
the front of the fluid end. See Figure 2-56 and Figure 2-57 for the correct packing
sequence.
may change. Check with the maintenance department for the proper packing ring
seal components.
1. Wiper Ring
2. Lantern Ring
3. Peek Adapter
4. Double Stack
Pressure Ring
5. Header Ring
6. Adapter (with
back-up rings
and o-rings)
1. Lantern Ring
2. Double Stack
Pressure Ring
3. Single Stack
Pressure Ring
4. Header Ring
5. Adaptor
6. O-Ring
7. Back-up Ring
8. Back-up Ring
9. O-Ring
7. Install the stuffing box and hand-tighten. Slide the plunger through the suction
8. Tighten the plunger in the crosshead (350 to 400 ft-lbs). Tighten the stuffing box.
9. Replace the suction covers with new seals, if necessary, and install the suction
covers.
10. Connect the plunger oiler lines to the packing nuts (Figure 2-58) and make sure
• The key to long lasting packing is to ensure the packing rings and spacers are
• When removing the plungers, always use a strap wrench on the pump shaft to
rotate the Triplex. Do not load the plungers into the Triplex pump with any tool
Improper Crosshead
Adjustment
Low Oil Low Oil Level Check & Add Oil if Necessary
Pressure
High Oil Temperature Refer to High Oil Temperature
Contaminated Lubricant
Change Oil
Short Plunger/ Abrasives in Fluid Filter Pumped Product & Flush Fluid
Packing Life Friction Wear Lubricate with Rock Drill Oil
2.10 Iron
The intention of the iron maintenance is to ensure that all critical components, in all
services, perform safely during high pressure operations. The iron maintenance
involves routine and annual maintenance. Properly maintaining the iron carried by the
iron skid is one of the responsibilities of the operator. For the details regarding how to
• Visual Inspection
• Specific Iron
inspect the iron on a regular basis to examine for signs of cracks, washout, corrosion,
and damaged rubber inserts. Repair the iron that is not working properly, if possible. If
there are any damages that affect the performance of the iron, and the operator cannot
See Figure 2-59 and Figure 2-60 for an example of 2x1 and 2x2 plug valves.
Figure 2-59: 2x1 Plug Valve Figure 2-60: 2x2 Plug Valve
• Prior to use, the plug valves should be inspected for proper operation. Make sure
that the valves are free of contamination and should actuate from the opened to
• After each use, the bore of the plug valves should be sprayed with a light oil or
• The plug valves are required to be greased by the operators after each use on
the job site. Follow the steps below to grease the valves.
o Use a 21 MPa (3,000 psi) high pressure grease gun to grease the valve,
o Rotate the valve to the closed position to open and pump a little more
o If the valve is in line, grease the valve a moderate amount until the
2.10.1.2.2 Swages
• Before each use, clean the threads with a wire brush and apply lubricant on the
threads of the swages to prevent rust. Inspect for any thread damage.
Swivel joints are also called “Chicksans”. See Figure 2-62 and Figure 2-63 for examples
Figure 2-62: Two-way Swivel Joint Figure 2-63: Three-way Swivel Joint
• Each week, at a minimum, the swivel joints are to be greased by the operators.
• Before greasing, check all swivel joints to make sure that they can swivel without
much effort. If a swivel joint is hard to swivel, grease it. If a swivel joint cannot
swivel, and greasing does not solve the problem, flag it unusable and send it to a
• While greasing, they must be rotated to ensure proper application to all bearing
races. Do not over grease. Once grease is seen outside the dust seal on the
entire rotation, greasing is complete. Over greasing may cause the dust seal to
be extruded out. Clean off the excess grease and replace the slotted screw.
Ensure that the dust seal is in place so contamination cannot occur from the
outside.
2.10.1.2.4 Unions
See Figure 2-64 and Figure 2-65 for an example of Weco wings and Weco threads.
Figure 2-64: Weco Wing (103 MPa/15,000 psi Figure 2-65: Weco Thread (103 MPa/15,000 psi
CWP) CWP)
Warning
Risk of substantial equipment damage or serious personal injury
Remind any third party onlookers to keep clear, as bits of metal may break off when
hammering.
• Before using the hammer, ensure the wedge on the hammer is secure and the
handle has not dried out (otherwise there is a danger of the hammer head
• The threads should be visually checked for nicks or spurs after each job. If any
are observed, send the iron to a certified repair facility for repair or replacement.
If threads are in good condition, spray WD-40 (or equivalents) to prevent them
from rusting.
• Constant hammering on the wings, to tighten them, wears them to a point. They
are ground on an annual basis, but may require periodic grinding to flatten them.
Change any wings that cannot be ground to a square, with the following steps.
o Remove segments
o Reassemble
• Before each use, clean threads with a wire brush and apply lubricant on the
• The folded metal should be ground to repair the wing on the union (Figure 2-66).
daily basis.
thickness inspection, MPI (Magnetic Particle Inspection), banding, repair (if required),
inspection report is acquired from the facility after the annual maintenance has been
acts as the recirculation pump. The other acts as the pressurizer pump (also called pre-
Both the recirculation pump and the pressurizer pump are located under the averaging
tank. One is on the road side and the other one is on the curb side. The recirculation
pump is used for slurry recirculation from the averaging tank to the mix tank. The
pressurizer pump is used for pushing slurry into the high pressure Triplex pumps.
• After each job, open the drain valve to drain the remaining liquid out of the pump.
NOTE: Remember to close the drain valve before the next job.
Figure 2-67: Drain Valve of Recirculation Pump Figure 2-68: Drain Valve of Pressurizer Pump
Figure 2-69: Recirculation Pump Grease Points Figure 2-70: Pressurizer Pump Grease Points
• Grease the packing grease points (Figure 2-69 and Figure 2-70), daily, during
mixing operations.
• Grease the bearing housing grease points (Figure 2-69 and Figure 2-70), weekly.
To test the pressurizer pump and recirculation pump, follow the steps below:
1. To pressure test the recirculation pump, attach the pressure gauge to the 4"
test the pressurizer pump, attach the pressure gauge to the 4" pressurizer
3. Turn on the recirculation or pressurizer pump and record the pressure reading.
4. Open the return valve and circulate water back to the displacement tank using
5. Once the water circulation back to the displacement tank has been established,
record the pressure. Circulating to the tanks using only the recirculation or
pressurizer pump should read at 25 psi; the dead head reading should be 50 psi.
monitored on a daily basis through the use of the electronic pressure transducers
located in the process piping. The deviation from expected pressures can be an
2
Courtesy of the Gardner Denver 2045 LX Centrifugal Pump Maintenance Manual and Parts List.
1. Remove all the worn packing rings from the stuffing box and clean them
thoroughly.
2. Check all the bearings as per the manufacturer’s specifications and replace
them, if necessary.
4. Lubricate the two primary seal rings. Install and seat each seal ring separately,
with all the seal lips facing toward the impeller. Stagger the splits at the 12
o’clock and the 3 o’clock positions so that there is no direct leakage path
established.
6. Lubricate the two secondary seal rings. Install and seat each seal ring separately
a. The first secondary seal ring of this series must be installed with the lips
facing away from the impeller with splits at the 6 o’clock position. The
reverse position of this seal will prevent air from being drawn through the
b. The second secondary seal ring of this series must be installed with the
seal lips facing toward the impeller, and with the split at the 9 o’clock
position.
7. Lubricate, install, and seat the split compression packing ring with the split at the
12 o’clock position.
8. To properly preload this combination set, bottom out the flat side of the gland
side and the other one is on the curb side. The mix water pumps are used to pressurize
the water before it fills the displacement tank, feeds the high pressure mixing head or
the mixing tree. The mix water pumps are powered by the hydraulic system. Sanjel’s
skid units are equipped with two 3x2 Mission centrifugal pumps.
• Grease the packing grease point daily and the bearing lubrication points, weekly
Figure 2-75: Lubrication Points for the Mix Water Pump (road side)
Figure 2-76: Lubrication Points for the Mix Water Pump (curb side)
• Drain water from the pump volute after each job. Leave the drain valve open
(Figure 2-77 and Figure 2-78) until the next cementing job.
pumps. To test the mix water pumps, follow the steps below:
1. Stop the Detroit engines. Attach the pressure gauge to the 4" mix discharge end
2. Turn on the unit and dead head the water flow by closing the master water valve.
Warning
Risk of substantial equipment damage or serious personal injury
Do not leave the mixing water pump dead headed for long periods of time, as the pump will
heat the fluid and the pump housing will become very hot.
Figure 2-79: 4" Mix Discharge End (road side) Figure 2-80: 4" Mix Discharge End (curb side)
1. Remove the gland bolt assembly by loosening the gland bolt retaining nuts.
3. Add three to four squirts of grease. Watch for grease exiting the packing gland.
4. Add only two to three pieces at a time, between repacking intervals. If this occurs
more than twice, all the packing in the pump should be replaced.
2. Grease all the packing ropes and insert pieces into the packing housing
staggering the cut end (i.e., cut end up is inserted first, cut end down is inserted
3. Place the packing gland in position and swing the gland bolts in place.
4. Tighten the gland lightly against the packing using the gland bolt nuts.
NOTE: Tighten the gland against the packing “finger tight” only. If the packing is over
mixing system is not thoroughly cleaned after each job, cement can build-up around
various components of the unit. As a result, the build-up can cause serious restraints in
the slurry and dry cement. It can also cause the slurry to be mixed too slowly or even
To prevent these problems from occurring, the following components should be properly
maintained:
performing maintenance on the valve, remove it from the mix head first.
Figure 2-81: Bulk Cement Control Valve Figure 2-82: Union and Hinge Bolts
1. Hammer loose the union (see Figure 2-82 for the location of the union).
2. Unfasten the bolts of the hinge (see Figure 2-82 for the location of the hinge
bolts).
3. Lift the bulk cement control valve off the mix head.
If cement build-up is detected on any component of the bulk cement control valve, then
After the bulk cement control valve is removed, do the following checks:
• Push the vacuum breakers (x3) in and out to make sure it is working properly.
• Check the vacuum breaker seats for cement build-up and any damage. If the
• Check the bulk cement control valve for free valve movement and cement
build-up.
• Make sure the bulk cement control valve can be rotated smoothly. Grease the
control valve before every job. If the valve is hard to rotate, there may be cement
build-up between the plug and control valve body. Take the following steps.
o Remove the plug by loosening the clamp on top of the valve body.
o With the actuators and plug removed, clean all cement build-up, then
grease and reassemble the valve. While the control valve is disassembled,
o When the bulk cement control valve is removed, check the mix head
NOTE: While the bulk control valve is disassembled, remove all cement build-up
from the control valve body by chipping it off. Do not clean any cement build-up
in the bulk cement control valve using water. Water left inside of the valve will
mix with the dry cement creating a blockage or a closed valve condition.
2. Remove the Allen bolts on the clamp on top of the bulk control valve (Figure 2-83
Figure 2-83: Allen Bolt Removal Figure 2-84: Allen Bolt Removal (cont’d)
3. Pull up the top portion of the valve attached to the actuator (Figure 2-85).
4. When the valve shutter is free, inspect the gap between the shutter and the top
(Figure 2-86).
7. To clean out any cement that is caked on, use a buffing wheel.
8. Remove the plates, starting with the one opposite to the bulk inlet (Figure 2-88).
10. Buff up the inside of the head and clean the vacuum breaker ports.
12. When reinstalling the top, make sure the guide pin lines up to the guide hole
(Figure 2-89).
• When greasing the actuated shutter shaft, work the shutter to ensure the grease
• To work the shutter you may operate it using the hydraulics, or bypass the
NOTE 1: Greasing the shaft keeps cement out and keeps the valve from freezing.
NOTE 2: After reassembly, make sure that the bulk control valve is fully closed when
the indication pin (Figure 2-90) is lined up with “0” and make sure it is fully open when
the indicator pin is lined up with 10. Recalibration of the electronics may also be
required.
• Inspect and clean the bulk cement sleeve and water diffusion plate after each
job.
• Wash up the 3" Magnetic flow meter and 2" Coriolis flow meter, after each job.
• Perform an extra check of the top and bottom of the mix chamber, below the
water diffusion plate, for cement build-up. If build-up is observed, clean up the
mix chamber.
• Ensure the holes in the water diffusion plate are free of debris.
• Inspect the curved surface inside the cyclonic mixing chamber for cement build-
• Perform an annual thickness test for the mix chamber, especially the elbow
distributes power to the hydraulic pumps via a multi-pad Funk gearbox. Routine
maintenance for the hydraulic tank, the CAT C9 engine, and the Funk gearbox need to
be regularly performed.
Warning
Risk of substantial equipment damage or serious personal injury
Never attempt to perform work on the hydraulic system when it has operated for some time.
Hot hydraulic oil can cause severe burns.
• The oil level in the hydraulic tank (Figure 2-91) should be checked, daily, and
filled up to the blue mark on the sight glass (Figure 2-92) when the engine is off
Figure 2-91: Hydraulic Tank Sight Glass and Drain Figure 2-92: Close-up View of Sight Glass
Valve
• The hydraulic oil filters must be changed once per year. Loosen the bolts (Figure
2-93) indicated by the arrows to access the oil filter. If oil is hot, wait until it has
cooled down.
• The hydraulic oil must be changed once every other year. Filter the oil with the
• Inspect the oil and filters for contaminants, at the year when the oil is changed.
• Refer to Table 2-36 for an example in terms of the hydraulic oil and filters change
schedule.
• Liquid Teflon sealant should be used on hydraulic line pipe threads. All fittings
should be tight.
• Tiny dust particles are harmful to a hydraulic system. Every effort should be
• Change the main filters/high pressure filters (Figure 2-95) once every year.
• The hoses and other components should be checked for leaks and wear daily,
• Repairs to the system should only be made using the proper hoses and fittings.
and Figure 2-97 for the engine’s right and left side views. In the following subsections,
the engine components are divided into the air system, electrical system, cooling
system, fuel system and fuel lines, and oil system to be discussed in terms of their
maintenance.
two air starters of the Detroit engines to start the three engines. See Figure 2-98 for a
Routine maintenance needs to be performed for the air cleaner, air kill button and air kill
reset lever, air compressor, air dryer, and air tank. The entire air system should be
The air cleaner filters and silences the air, which is consumed by the engine during
running. It sits inside the air inlet canister (Figure 2-99). The CAT engine is equipped
with a dual element air cleaner, which contains a primary air filter (Figure 2-100) and a
Figure 2-100: Primary Air Filter Figure 2-101: Secondary Air Filter
Caution
Risk of moderate equipment damage or minor personal injury
Never service the air cleaner elements with the engine running since this will allow dirt to enter
the engine.
• The air filters should be checked at the 250 hour service. Inspect the filters with a
trouble light by inserting the light into the filter and scanning all the way around. If
light penetrates the filter, the filter is still good. If not, replace the filter.
NOTE: This is especially important when the engine is operated under severe
dust conditions.
• Ensure the lid-attaching latches are tightened, to ensure a proper seal between
the lid and the canister, after the air filters are in place.
• The CAT C9 engine air cleaners are equipped with two air filters. Ensure both air
• Mark the installation date and operator’s name on the air cleaner canister.
The CAT C9 engine is equipped with air kill functionality. The air kill is used for runaway
engines, which are caused when flammable gas (i.e., methane, sour gas, or propane)
enters the engine. The air kill button (Figure 2-102) of the CAT engine is located on the
It is a red button labeled as “Emergency Shutdown” at the right bottom corner of the
control console. Another air kill button (Figure 2-103) can be found on the engine gauge
panel mounted on the engine compartment. The air kill reset lever is located at the top
Figure 2-102: Air Kill Button (Emergency Shutdown on upper control console)
• Function test the air kill reset lever during the pre-job inspection. Check it with the
engine at a dead idle, NOT at high rpm, to ensure the gates will cut off the air
supply. Test using both air kill buttons on the upper control console and the
• Move the handle back from the closed position (handle at 45°, see Figure 2-104)
to the opened position (handle at 90°) and feel for smoothness of operation or
any other obstruction, and listen for an audible clicking sound as it moves back
The air compressor (Figure 2-105) is the source of air for the two air starters of the two
Detroit engines and one air starter of the CAT engine. Its function is to gather air from
the radiator and compress it into high pressure air. It is located on the engine’s left side
The air compressor pumps air into the air tank (reservoir). The governor controls the air
compressor and starts or stops the air compressor from pumping air. When the air tank
pressure rises to the “cut-out” pressure, the governor stops the compressor from
pumping air. However, the compressor runs constantly in the event of an air leak.
1. Coolant Line
2. Air Intake
3. Coolant Line
4. Governor
Line
5. Oil Feed Line
Danger
Risk of extreme equipment damage, severe personal injury or possible death
Never work on the compressor system when the engine is in operation.
Do not disconnect the high pressure air line unless the air tank has been drained.
Warning
Risk of substantial equipment damage or serious personal injury
The compressor may be too hot to touch after several hours of operation.
• Inspect the air intake, hydraulic oil suction and return lines, coolant suction and
return hoses (for tight connections) and overall general condition. Tighten the
• If any oil is present during the draining of the air tank or slow air build-up occurs,
The air dryer (Figure 2-106) collects and removes any air system contaminants (in liquid
and vapor form) before the air enters the air tank, and provides clean and dry air to the
air system. It is located on the engine’s left side beside the Funk gearbox. The air dryers,
Warning
Risk of substantial equipment damage or serious personal injury
Always shut off engines prior to servicing the air dryer.
o If oil is present in the air system, when draining the air tanks, check the air
dryer. The presence of oil in the air dryer will render the air dryer
ineffective.
o If the air dryer is continuously blowing off, check oil contaminants in the air
system.
o If ice builds up in the exhaust (bottom) of the air dryer, check the heating
o If there are white milky deposits on the exhaust of the air dryer, this may
be the result of water and oil mixing in the dryer. Notify the maintenance
department.
• Change the Bendix air dryer with a mechanic’s assistance once a year.
The air tank receives and stores compressed air from the compressor, then it supplies
the air to the air starters for all three engines. It is mounted on the hydraulic skid next to
• The air tank must be drained of moisture and sediment daily (after each job). See
Figure 2-108 for the location of the drain valve. There are three reasons for
3. To inspect for oil. If oil is detected in the tanks, it indicates the air
system of the SCM skid. There is an alternator (Figure 2-109), a battery (see Figure
2-110 for the battery box), a night switch (Figure 2-110), and the necessary wiring. The
night switch on the battery box is used to connect/disconnect the battery with the
• Check the tension of the alternator belt daily and adjust when necessary. Inspect
• Clean the batteries (connections and cables) at the 250 hour service.
• Inspect the alternator for loose connections and ensure proper battery charging
yearly.
• Check the coolant level in the radiator daily (when the engine is stopped and
Warning
Risk of substantial equipment damage or serious personal injury
Hot coolant can cause serious burns. Never remove the filler cap when the engine is under the
operating temperature. To open the radiator filler cap, stop the engine and wait until the
cooling system is cool. Slowly loosen the filler cap in order to relieve the pressure.
o Remove the cooling system filler cap (Figure 2-112) slowly to relieve
pressure.
Figure 2-112: Cooling System Filler Cap (located on the top of the
coolant tank)
o Maintain the coolant level within 13 mm (0.5 inch) of the bottom of the filler
cap.
o Clean the cooling system filler cap and check the condition of the filler cap
is located below the engine compartment. See Figure 2-113 and Figure 2-114 for the
1. Fuel Cap
2. Fuel
Return
Line
3. Fuel Suction
Line
4. Fuel Level
Sensor
5. Fuel Vent
Hose
• Inspect the fuel lines for fray and physical damage daily.
• Check for fuel leaks at all engine-mounted fuel lines and connections daily.
Warning
Risk of substantial equipment damage or serious personal injury
Fuel is highly flammable. Always follow proper safety procedures when refueling the unit.
Always shut off the engines during refueling.
• Always fill the fuel tank after each job. Filling the fuel tank minimizes moisture
• During fuel refills, inspect the fuel cap gasket for a proper seal.
• There are two types of fuel caps (Figure 2-115). Always replace the existing fuel
escape.
• Monitor the bowl of the primary fuel filter/water separator (Figure 2-116) daily for
signs of water. If water is observed, drain the water from the bowl.
• Change the primary fuel filter at the 250 hour service. Follow the steps below.
o Remove the fuel filter element from the mounting base with the bowl
attached.
o Remove the O-ring from the gland of the bowl. Clean the following
components.
▪ Bowl
necessary.
▪ Mounting base
o Install the bowl on a new element. Tighten the bowl by hand. Do not use a
o Lubricate the top seal of the element with clean diesel fuel. The element
may be filled with fuel, at this time. Install the new element on the
o Start the engine and check for leaks. Run the engine for one minute. Stop
o Mark down the date of change along with the operator’s initials on the
filter.
• Replace the secondary fuel filter (Figure 2-117) at the 250 hour service. Follow
the steps below to prime the fuel system and to change the secondary fuel filter.
o Stop the engine. Turn the ignition switch off or disconnect the battery.
o Clean the gasket sealing surface of the fuel filter base. Ensure that all of
o Install the new fuel filter. Spin the fuel filter onto the fuel filter base until the
gasket contacts the base. Use the rotation index marks on the filters as a
guide for proper tightening. Tighten the filter for an additional full turn (360
degrees) by hand.
o Mark down the date of change along with the operator’s initials on the
filter.
o Open the fuel priming pump and operate the fuel priming pump until a
o Promptly start the engine. If the engine runs rough, continue to operate
the engine at low idle. Do not raise the engine speed above idle, until the
NOTE: If the engine does not start, open the fuel priming pump and repeat
• During a filter change, match the new filter type and manufacturer with the old
filter. Ensure the old filter gasket is not left on the filter mount.
o Fill the new filter with fresh diesel fuel to prevent an air lock in the fuel
system.
▪ Remove both filters and check the fuel level. Top it off, if necessary,
▪ Unscrew the fuel primer and pump until resistance is felt. Replace
department.
Cementing Services SCM W/MK IV AT Skid 2-150
Operator Training Manual – Version 1.1
Unit 2
SCM W/MK IV AT Skid Operation and Maintenance
cleans, inhibits corrosion, and cools the engine by carrying heat away from the moving
parts.
Warning
Risk of substantial equipment damage or serious personal injury
Hot oil and components can cause burns. Do not allow hot oil or hot components to contact
the skin.
• Check the engine oil level, daily, using the engine oil dipstick (Figure 2-118).
Perform this action only when the engine is stopped. Maintain the oil level
between the “ADD” mark and the “FULL” mark on the oil level gauge (Figure
• All diesel engines must be on an oil analysis program. Refer to Section 2.5.3 Oil
• The engine oil must be sampled and changed at the 250 hour service. Refer to
Section 2.5.4 Obtaining an Oil Sample for the oil change information.
• Change the oil filter (Figure 2-121), at the 250 hour service. Follow the steps
below.
NOTE: Only use oil filters recommended by Caterpillar when changing the oil
filter.
o Clean the sealing surface of the filter mounting base. Make sure that the
o Coat the new oil filter gasket with clean engine oil.
NOTE: Do not fill oil filters with oil before installing them. This oil would not
o Install the oil filter. Tighten the oil filter until the oil filter gasket contacts the
base. Tighten the oil filter by hand according to the instructions on the oil
o Mark down the date of change along with the operator’s initials on the
filter.
• Check the gearbox oil level daily. Add oil, if necessary. See Figure 2-123 for the
location of the dipstick. See Figure 2-123 for the location of the filler cap.
• Change the oil every 1000 hours with Synthetic 50W. See Figure 2-124 for the
1. Dipstick
2. Filler Cap/Vent Cap
3. Drain Plug
• For full operation of the hydraulic pumps, the CAT engine should be operating at
of 2400 rpm.
• Pinch the rate to adjust the density and flow using valves, instead of idling down
• Do not adjust the pressure relief valves on the hydraulic system. This will heat
NOTE: The most common failure of the hydraulic system is leakage from the rubbing of
Component Specifications
4. Cessna Hydraulic Pump (for bulk cement Maximum Pressure – 3000 psi
control valve actuator, mix water control
Maximum Speed – 2400 rpm
valve actuator, and high pressure return
line control valve actuator)
Component Specifications
16. Hydraulic Pressure on Mix Water Pump Maximum Pressure – 3000 psi
system, and fluid displacement system. It is used for the conveyance of fluids including
water, slurry, and drilling mud. The main components of the system are a series of
pipes, valves with air actuators, and valves with hydraulic actuators. The configuration
The plumbing system has a total of eleven air actuators, as shown in Figure 2-126.
• Perform a weekly check of the valve air actuators (open and close) and ensure
they work properly. The yellow indicator on each air actuator shows if the air
actuator is functioning well. The two diagnosis switches of the curb side and road
side displacement tank suction valve air actuators are mounted on the rear of the
displacement tank (Figure 2-127). The diagnosis switch of the master water valve
air actuator is located on the upper control console and the other diagnosis
switches are located on the lower control console at the operator’s platform
(Figure 2-128).
• Inspect the pipes and joints for any leaks, daily. Identify the causes of leaks.
injured by an accidental explosion. The skid is equipped with four pressure relief valves.
There are two 2" SPM pressure relief valves installed on the discharge ends of the
Triplex pumps (Figure 2-129 and Figure 2-130) and one 1" Baird pressure relief valve
installed on the surge tank (Figure 2-131). Ensuring these valves operate to
Figure 2-129: 2" SPM Pressure Relief Valve (road Figure 2-130: 2" SPM Pressure Relief Valve (curb
side) side)
The configurations of the 1" and 2" pressure relief valves are illustrated in Figure 2-132
1. Valve Body
2. Spider
3. Adjusting Screw
4. Keeper
5. Cap
6. Disk Spring
7. Ball and Seat
8. Lock Nut
9. Cap Seal
10. Keep Seal
11. Seat Seal
12. Wing Nut
13. Ring Segment
14. Retainer Ring
15. Set Screw
16. Drive Screw
17. Label
18. Ring Seal
Figure 2-133: 2" SPM Pressure Relief Valve – 103 MPa (15,000 psi)
• Relief valves should be tested, on a weekly basis, and the test results recorded
in the unit maintenance manual. Recommended test dates are during crew
• If the relief valve function tests show a different pressure than what is tagged,
remove the adjustment cap, adjust and retest the relief valve. Retag the valve
• All tests should be completed, and the pressure logged, using the chart recorder.
• If slurry is pumped through the valve prior to regular service intervals, the valves
NOTE: Do not use the supplied lithium grease on the pressure relief valve spring. This
Configuration
Seat ID
Operating OD
Setting Range (mm/
# of Spring Ball Bearing OD
Unit # (MPa/psi) Type (MPa/psi) Springs Configuration inch) (mm/inch)
0-103/
35/5000 SPM 16 2x2 19/0.75 35/1.375
924501 0-15,000
924502
2-10/ 13
7/1000 Baird 18 1x1 19/0.75 23 /16/0.9375
300-1,500
reassembly, adjustment of relief valve to unit specification, bench testing with the
Haskell pressure pump to confirm pressure setting and tagging the valve to
• Instructions for unit disassembly and reassembly are listed, for both the 1" Baird
2.16.1.1 Disassembly
Warning
Risk of substantial equipment damage or serious personal injury
1. Back off the locking nut and loosen the adjusting screw.
3. Loosen the wing union and remove the valve from the discharge line tee or pump
fluid head.
4. Place the valve in a vise. Remove the valve adjusting screw, lock nut, and valve
cap. Once the valve cap is off, pull the keeper assembly out of the valve body
6. Clean the Bellville springs, keeper, ball bearing, seat, and the inside of valve
body. Visually inspect the condition of each piece for signs of wear and/or
fatigue.
7. Use a flashlight to visually inspect the condition of the ball seat inside the valve
body.
a. Baird - Place the valve in a vise and remove the seat frame from the body of
the valve. Once the seat frame has been removed, the seat can be removed
by tapping the seat from the top of the valve down and out of the bottom of
b. SPM - Turn the valve upside down after removing the ball and keeper. Use a
punch to tap the seat up and out the top of the valve.
2.16.1.2 Reassembly
The reassembly steps are:
1. Before replacing the seat, clean the seat area and apply grease liberally (refer to
Table 2-40: Unit Specifications for Pressure Relief Valve Configurations). Ensure
the seat is in place by tapping it gently with the same hammer and punch used
when removing the seat. The seat on the Baird valve is inserted from the bottom;
while the seats on the SPM valves are inserted from the top. Ensure the seat
faces the correct way; the chamfered edge should face the ball bearing.
2. On the Baird valve, apply Loctite 567 Thread Sealant to the seat frame thread,
and then screw the thread into the bottom of the valve body. This is the high
pressure side of the valve, and should be tightened with a 48" pipe wrench into
3. Lubricate the new ball bearing with grease and insert it into the valve seat.
4. Lubricate the keeper assembly with grease and place the greased springs onto
the keeper assembly in the correct configuration (refer to Table 2-40: Unit
5. Place the keeper assembly into the valve body and on top of the ball bearing.
6. Using an anti-seize compound, lubricate the threads of the valve cap, thread the
7. Using an anti-seize compound, lubricate the threads of the adjusting screw and
lock nut. Tighten the adjusting screw until contact is made with the Bellville spring
stack.
8. The unit should now be tight at every thread seal, except for the adjusting screw
The wiring of an adjustment screw cover, over the top of the adjustment screw and lock
nut, provide a visual indication of when, and at what pressure, the relieve valve was last
adjusted (Figure 2-134 and Figure 2-135). It also indicates whether the valve has been
Figure 2-134: 1" Baird Pressure Relief Valve Figure 2-135: Close Up of 1" Baird Pressure
(shown with wired and tagged adjustment screw Relief Valve
cover in place)
The materials used to tag the 1" Baird pressure relief valves (Figure 2-136) are ordered
Modified
2" Brass Tag Adjustment Screw
3
/32" Cable
with Sleeve Adjustment
Screw Cover
Figure 2-136: 1" Baird Pressure Relief Valve (with tagging materials)
The SPM pressure relief valves are equipped with an adjustment screw cover and only
Figure 2-137: 2" SPM Pressure Relief Valve (with Sanjel 2" Brass
Tag)
wide standard method for labeling is used. Brass tags are labeled on one side with iron
accommodate the adjustment screw cap. This involves drilling a 1/8" hole completely
through the side of the nut part of the adjustment screw (Figure 2-139).
1/8” drilled
hole
Table 2-41: Relationship between Working Pressure Rating, Spring Number & Orientation, and
Bore Seat Internal Diameter
ALUMINUM WORKING VOLUME SPRING SEAT INLET CAP
BRONZE PRESSURE (GPM) AT ARRANGEMENT BORE AND COLOR
31G S.S. OR RANGE 25% OVER AND NUMBER OUTLET CODE
MONEL SET
PRESSURE
762 7601-2-LLP 25 - 400# 3-100 Thin 1x1 19 11/8” 2” NPT White
• Visually check the mounting bolts for rust, weekly. Replace with Grade 8 bolts, if
needed.
• Check the structural frame for cracks, at the 250 hour service.
• Check the tightness of the mounting bolts, at the 250 hour service. Tighten the
bolts, if necessary.
transported to the next job site. When transporting the skid on shore, a winch truck can
be used. When transporting the skid to an offshore drilling rig, via a ship, sometimes the
skid will be disassembled and cranes will be used to lift each piece of the skid onto the
ship.
Warning
Risk of substantial equipment damage or serious personal injury
To avoid damage to the crash guards, never use any part of the crash guards as a lifting point.
NOTE: Before lifting and transporting the main skid, make sure the mix tank, averaging
the end rolls of the cross member, and the cross member itself, at the engine end of the
secondary skid (Figure 2-140 and Figure 2-141). Then, winch the skid with the winching
cable to a proper position where the skid can seat on the deck of the winch truck
Figure 2-140: Tightening Winching Cable around Lifting Lugs and Cross Member
Figure 2-141: Tightening Winching Cable around Lifting Lugs and Cross Member (cont’d)
Figure 2-142: Lifting and Transporting the Skid using a Winch Truck
Warning
Risk of substantial equipment damage or serious personal injury
The surge tank load cell safety pin must be locked, prior to lifting and traveling, and then
removed before the job starts.
The cement heads must be secured with chains, on the storage domes, prior to lifting and
traveling.
All iron must be locked on the racks prior to lifting and traveling.
To transport the iron skid using a winch truck, first, tighten the winching cable around
the end rolls of the cross member and the cross member itself at the surge tank end of
the skid. Then, winch the skid with the winching cable to a proper position where the
2.18.3 Lifting the Main Skid using Cranes (with the Skid
Assembled)
Depending on the number of available cranes, and the lifting capacity of each crane, to
Caution
Risk of moderate equipment damage or minor personal injury
The lifting slings that are attached to the end rolls of the secondary skid must be vertical to
prevent the slings from contacting and damaging the crash guards of the primary skid. Spreader
bars must be installed to keep the slings vertical.
To lift the entire skid using two cranes, two 125 ton cranes are recommended. The four
lifting points, that are connected to the lifting slings, are the four end rolls of the two
Caution
Risk of moderate equipment damage or minor personal injury
The lifting slings that are attached to the secondary skid must be vertical to prevent the slings
from contacting and damaging the crash guards of the primary skid. Spreader bars must be
installed to keep the slings vertical.
To lift the entire skid using one crane, a 200 ton crane is recommended. The four lifting
points that are connected to the lifting slings are the four end rolls of the two cross
2.18.4 Lifting the Main Skid using Cranes (with the Skid
Disassembled)
When carrying or transporting the skid, via a ship, sometimes the skid needs to be
disassembled to allow the ship to accommodate the skid. One situation is that the
secondary skid will be removed from the primary skid. Then, the primary skid will be
lifted as one unit and placed on the ship by one crane or two cranes. The other situation
is that the primary skid will be disassembled into three parts: the engine skid, the pump
skid, and the hydraulic skid (after the secondary skid has been removed). In this case,
each single skid will be lifted and placed on the ship by one crane.
2.18.4.1 Eight Point Lifting using One Crane (with the Secondary
Skid Removed)
Before lifting the primary skid, using one crane, follow the procedure below to remove
the secondary skid from the primary skid, and set up the primary skid for lifting.
1. Unbolt all the Grade 8 bolts, and washers, fastening the secondary skid to the
primary skid. NOTE: Sanjel requires using Grade 8 bolts for fastening the skids
together. Refer to Table 2-44 for the specifications of the Grade 8 bolts.
2. Fold all the ladders and remove any tools and loose equipment.
3. Pull away the screw lock pins of the lifting lugs of the pump skid. Extend the
lifting lugs and insert the screw lock pins back, to secure the lifting lugs.
Caution
Risk of moderate equipment damage or minor personal injury
The lifting slings that are attached to the skid frame must be vertical to prevent the slings from
contacting and damaging the crash guards or any components of the skid. Spreader bars must be
installed to keep the slings vertical.
The eight lifting points, that are connected to the lifting slings, are the end rolls of the
two cross members of the primary skid, and the four lifting lugs of the pump skid (Figure
2-145). Sanjel requires using the G-209 S-209 screw lock pin anchor shackles (Figure
2-146) to fasten the slings to the lifting lugs. Refer to Table 2-45 for the specifications of
Figure 2-145: Eight Point Lifting using One Crane (with Secondary Skid Removed)
Table 2-45: Specifications of G-209 S-209 Screw Lock Pin Anchor Shackles
Nominal Working Stock No. Weight Dimensions (in.) Tolerance
Size Load Each +/-
(in.) Limit (t) G-209 S-209 (lbs.) A B C D E F C A
1-3/8 13-1/2 1018598 1018605 13.53 2.25 1.50 5.25 1.42 3.63 3.31 .025 .13
G H L M P
6.38 9.16 .75 6.84 1.50
2.18.4.2 Eight Point Lifting using One Crane (with the Secondary
Skid Removed)
Before lifting the primary skid using one crane, follow the procedure described in the
previous section, to remove the secondary skid from the primary skid and set up the
Caution
Risk of moderate equipment damage or minor personal injury
The lifting slings that are attached to the skid frame must be vertical to prevent the slings from
contacting and damaging the crash guards and any components of the skid. Spreader bars must
be installed to keep the slings vertical.
The eight lifting points, that are connected to the lifting slings, are the end rolls of the
two cross members of the primary skid, and the four lifting lugs of the pump skid (Figure
2-147). Sanjel requires using the G-209 S-209 screw lock pin anchor shackles (Figure
2-146) to fasten the slings to the lifting lugs. Refer to Table 2-45 for the specifications of
Figure 2-147: Eight Point Lifting using One Crane (with Secondary Skid Removed)
the secondary skid from the primary skid, disassemble the primary skid, and set up
1. Unbolt all the Grade 8 bolts, and washers, fastening the secondary skid to the
primary skid.
2. Fold all the ladders and remove any tools and loose equipment.
3. Disconnect all the associated hydraulic lines, electrical lines, pipes, and drive
lines.
4. Pull away the screw lock pins of each skid. Extend the lifting lugs of the skid and
insert the screw lock pins back to secure the lifting lugs.
Caution
Risk of moderate equipment damage or minor personal injury
The lifting slings that are attached to the skid frame must be vertical to prevent the slings from
contacting and damaging the crash guards and any components of the skid. Spreader bars must
be installed to keep the slings vertical.
For the hydraulic skid, the four lifting points are the two end rolls of the cross member
and the two lifting eyes (Figure 2-148). For the pump skid, the four lifting points are the
four lifting lugs (Figure 2-149). For the engine skid, the four lifting points are the two end
rolls of the cross member and the two lifting lugs (Figure 2-150). Sanjel requires using
the G-209 S-209 screw lock pin anchor shackles (Figure 2-146) to fasten the slings to
the lifting lugs. Refer to Table 2-45 for the specifications of these types of shackles.
Figure 2-148: Four Point Lifting for Hydraulic Skid Figure 2-149: Four Point Lifting for Pump Skid
2.18.5 Four Point Lifting using Two Cranes (for the Iron
Skid)
Warning
Risk of substantial equipment damage or serious personal injury
The surge tank load cell safety pin must be locked prior to lifting and traveling.
The cement heads must be secured with chains, on the storage domes, prior to lifting and
traveling.
All iron must be locked on the racks prior to lifting and traveling.
The surge tank end is heavier than the swivel joint rack end of the iron skid, so in order
to keep a good balance when lifting the skid, two cranes should always be used. To lift
the skid using two cranes, the four points that are connected to the lifting slings are the
Figure 2-151: Four Points Lifting using Two Cranes for Iron Skid
operations. All Sanjel equipment must adhere to a strict maintenance and testing
Warning
Risk of substantial equipment damage or serious personal injury
Always be familiar with the pressure limits of the equipment in use.
The maximum pressure is limited by the weakest equipment component.
Pressure test with a minimal number of personnel in the pressure test area.
Pressure test outside, whenever possible.
During pressure testing, secure and fasten all loose equipment using safety slings.
Place warning signs to alert all personnel to the planned pressure testing.
Cordon off the area surrounding the pressure test.
NOTE 2: A safety meeting must be held prior to the pressure testing to ensure that all
personnel are aware of, and in compliance with, the pressure testing safety procedures.
• All pressure relief valves should be tested, on a weekly basis. The tests results
• Should the relief valve test at a different pressure than what is on the tag (± 5%
tolerance) remove the adjustment cap, adjust and retest the valve. Retag the
1. Attach the fitting to the wing half of the Haskell hydraulic pressure testing pump.
Attach the Haskell pump to the pressure relief valve and connect its water and air
lines.
NOTE 1: Using the Haskell pump to adjust and test the pressure relief valve is
simpler, and safer, than performing the operation using the pump on the SCM
unit.
NOTE 2: When the unit is equipped with Weco iron, adjust the discharge
NOTE 3: When the unit is equipped with Guiberson iron, adjust the discharge
2. Increase the pressure from the Haskell pump until the pressure relief valve
reaches bypass pressure. Record the bypass pressure value and release the
Haskell line pressure, so that the valve reseats. Increase the compression of the
spring stack by turning the adjusting nut on the valve by half turns. Repeat the
test until the valve reaches the desired bypass pressure (refer to Table 2-40).
Danger
Risk of extreme equipment damage, severe personal injury or possible death
Always stay clear of high pressure lines when adjusting and testing pressure relief valves to
protect against fitting failures or line breaks.
3. Once the correct relief valve bypass setting is reached, the pressure relief valve
should be labeled with an aluminium tag and wired between the adjusting screw
and lock nut. This tag lists the current valve bypass pressure setting, and serves
as an indicator to determine if the valve has been altered since the last
accordance with the Engineering Memo (dated January 28, 2003), which
requests a chart documented function test of the pressure relief valve setting,
checks are performed. The Haskell pressure pump will calibrate the system and
measurements and panel gauge readings is detected. The pressure calibration steps
are as follows:
1. Install a pen chart in the chart recorder to capture the results of the pressure
system calibration.
3. Attach the Haskell pump to one of the discharge plug valves. Open the return line
valve to the unit tanks and open the discharge valve opposite the side of the
Haskell pump.
4. Circulate water from the Haskell pump through the discharge fluid end of the
pump and out the discharge valve. Close the discharge valve once water flows
out.
5. When circulation is established, close the return line valve and pressure the line
to 10 MPa (1,450 psi). Shut in the system and visually inspect the pen recorder,
deck gauges, and electronic pressure head on the HMI screen to verify that all
pressure readings are the same (± 5% tolerance). Hold the pressure for at least
three minutes. If the readings are not the same, isolate the inaccurate sensor,
6. When all the pressure sensor readings are in agreement, pressure the line to 32
MPa (4640 psi). Shut in the system and ensure the pressure sensors are still in
agreement. Hold the pressure for three minutes. If the readings are not the same,
isolate the inaccurate sensor, perform the necessary maintenance, and repeat.
7. When all the pressure sensor readings are in agreement, bleed off the system
pressure to the unit tanks by opening the return valve. Remove the Haskell
pressure pump and add the pressure chart, with the date of calibration, to the
8. Update the Component Pressure Maintenance Log. Keep it with the unit records.
9. Ensure all charts with the recorded pressure test measurements are dated and
kept with the unit maintenance record. NOTE: Occupational Health and Safety
Engineering has certified the treatment (or treating) iron for the current year. The
pressure relief valve, and pressure heads, must also be inspected and certified. The
1. Discuss the pressure line test, and pressure limits, with the company
2. Pressure test the lines to 10% over the maximum expected working pressure (job
4. With the discharge valve closed, prime the pumps by circulating fluid through the
return lines to the tanks, using only the pressurizer pump. Once circulation is
confirmed with the engine idle, engage the pump in pump gear to circulate back
5. Perform the treating iron test. Ensure the fluid destination valve (well head, pit,
etc.) is open before opening the discharge valve. Close the unit return valve. If
possible, engage the pressurizer pump and confirm circulation by checking for
the tank volume decrease. If the discharge pressure is higher than the
pressurizer output, roll the pump at idle (and in high gear) while watching the
6. Once circulation is confirmed without pressure, shut the pump down and
pressure up for the pressure test. Shut in the fluid destination valve to “dead end”
7. With the engine idling, and the unit in low gear, apply low pressure to the line
(approximately 25% of final pressure). Observe for any leaks (apparent by falling
pressure on the gauge). The treating iron pressure test is accepted when the
pressure remains at the required test pressure for ten minutes and is 10%
8. The Job Supervisor or a Sanjel employee must inspect the lines and pumps for
leaks.
Danger
Risk of extreme equipment damage, severe personal injury or possible death
NOTE: If there is a leak, ensure that all pumping stops. Release the treating iron
line pressure through the bleed off line (if a check valve is present) or by opening
the return valve on the unit (if no check valve is present). Once all pressure is
bled from the line, the supervisor may instruct Sanjel personnel to repair or
9. Once an acceptable test has been performed, bleed off the treating iron line
• Before connecting any treating iron, visually inspect each component for signs of
NOTE: Do not use the equipment unless the equipment is recertified and
re-serialized.
• Prior to (and during) pressure testing and pumping operations, move all
personnel to a safe area. All personnel involved in the pressure test must be in
Warning
Risk of substantial equipment damage or serious personal injury
Install high pressure warning signs marked "DANGER-HIGH PRESSURE AREA-KEEP CLEAR"
near the iron and in locations that can be seen by individuals approaching the treating iron.
• Lay treating iron beside the catwalk or down the pipe rack to the V-door between
the catwalk and the rig floor. Stay away from the drilling pipe, casing, or tubing on
the rig.
• Ensure oil is used on all thread connections and that the thread connections are
• Secure the line at the top, and bottom of the V-door, to prevent the line from
• Use water for pressure testing. Never pressure test with hydrocarbon based
• Do not exceed the rated working pressure of the treating line connections, or the
fluid ends, during the pressure test. If, for any reason, the pressure ratings must
• Always test the wellhead and customer master valve, which is the final
customer valve does not hold the pressure, obtain approval from the customer
before continuing with the treatment. This approval must be recorded on the
Treatment Report.
• Rented treating iron may be used only if it is rated to 103 MPa (15,000 psi)
working pressure. The vendor must provide proof that iron has been inspected,
o Ensure the treating lines are flexible and can move during the treatment.
o All treating lines must be on a solid surface. If this is not possible, fasten
the line with chains or blocks. The air hoist, chains, and safety slings must
o For jobs with two or more pumps, the units must be connected to a
common treating line with laterals. The treating line from each pump unit
to the main treating line must have swivel joints that allow the line to
move. These swivel joints must be installed next to the lateral. Each of
the pump units must have an operating pressure transducer and the main
o Before installing a valve or treating iron, the supervisor must check the
pressure rating of the wellhead valves and fittings. If the rating is not
from the customer before connecting to the wellhead (see Table 2-46).
NOTE: Advise the customer immediately, if there is a problem with the equipment.
o This equipment must be fastened to the elevator links with a safety cable.
(MPa/psi)
Pressure
Unit Number
MAX
INSPECTION INTERVAL: WEEKLY RECORD PRESSURE READING
28/
1 Manifold
4,000
70/
2 Deck Gauge
10,000
7/
5 Return Pressure Relief
1,000
Date
INSPECTORS
INITIALS
Table 2-47).
Problem Reason/Solution
Engine
Transmission
Triplex Pump
Problem Reason/Solution
Triplex pump has no suction NOTE: It is important to circulate the truck first.
• Switch from the tub suction to the tank suction.
• Jack the short suction valve to remove any debris.
• Turn off the pump, remove the 2" caps, and pop valves
using the “valve popping stick”.
• If the valves will not pop (possibly debris is stuck in the
valve in the pump),
Triplex pump has no discharge • Check to see if the return line is closed.
Lubrication
Lube line not functioning • Cement or debris is trapped in the lube line.
(plugged)
• Worn packing is trapped in the lube line.
• Check to determine if the valves are malfunctioning.
• Check the oil level (relieve pressure first).
• No pressure.
Problem Reason/Solution
Centrifugal Pump
Low pressure on the mixing water • Check the water diffusion plate.
pump
• Check the mixing "Y" screen filter.
• Check the mix head pressure in the “Process
Variables” screen.
Low mix water rates • Check the rpm of the mix water pump.
• Check to determine if the supply valve to the mixing
water pump is fully open.
• Low water pressure in the centrifugal pump (mixing
water pump).
Hydraulics
Problem Reason/Solution
Mixing System
Density too high • Check if the PLC program is on the proper recipe.
• Check the problems with the mix water system.
• The bulk control valve is malfunctioning.
• The “MIX WATER VALVE” is set to “MANUAL”.
• The “CEMENT VALVE” is set to “MANUAL”.
Bulk control valve not opening • Visually inspect the bulk control valve for buildup.
• Disengage the hydraulics and operate manually.
• Turn the main and instrumentation power switches on.
Problem Reason/Solution
Mix water rate decreasing or low • The mix water automated valve is closed.
• The mixing water pump rpm is low.
• The fish trap filter is plugged.
• The mixing water pump is sucking air.
Dry cement out of vacuum • Check the poppet. Replace, if it is not seating.
breaker
Aeration in slurry • Check the blend of the slurry. Add defoamer when
needed.
• There is excessive air in the cement. Check the bulk
operation starting from the bulk unit, the bulk cement
hose, to the bulk control valve.
Problem Reason/Solution
Fluctuating rates of the 2" Coriolis • Set the valves in proper positions.
• Close 3" valve for two seconds to clean out 2"
recirculation line.
• Maintain proper rpm on the recirculation pump.
• Mixing tank volume is getting too low and sucking air.
SCM unit. Performing these items will greatly reduce the frequency of breakdowns.
1. Inspect and clean up the mix head; check and clean the vacuum breakers after
every job.
3. Inspect the hydraulic, air, and coolant lines in areas where rubbing is suspected.
4. Complete a proper wash up and ensure that all components of the unit are clean.
6. During prolonged engine idles, always keep the engine above 1000 rpm.
8. Inspect the plumbing system for potential wear and deterioration daily.
3.0 APPENDIX A
3.1 MARK IV AT system description and
troubleshooting (for electricians)
The Sanjel Cyclonic Mixer (SCM) is a high energy mixing system that combines water
and dry bulk cement to produce uniform slurry. The control system for the SCM is called
the Mark IV with Automated Technology (AT). The operator enters the cement blend
data, which the system uses to calculate set-points for water and bulk cement delivery.
Numerous process variables are monitored and specific valves are adjusted,
continually, to maintain tight control over the process. The water and bulk cement
essentially a computer that runs a custom program, which analyzes process variables,
performs calculations and generates outputs. These outputs are used to control the
process, as well as visually provide the operator with process status and variable
values. The interface to the PLC, and the process, is a Human Machine Interface (HMI).
The HMI is a 15" touch screen display that is also a computer running on Windows CE.
It provides the operator with a visual interface of the process, and the ability to input
The system transmits data to the Field Data Acquisition Program (FDAS) program. This
job data is recorded and enables the operator to produce a graph, on location, for the
customer. Numerous process variables are also recorded to a data card located in the
HMI. This data can be used to analyze the job in the event there are concerns.
for averaging. The water and cement are brought into a high energy mix head, which
sits above the mix tank. As the slurry volume increases, it eventually reaches the weir
that separates the two tanks. At this point, the slurry flows into the averaging tank. The
small fluctuations of density, in the mix tank, are averaged out by the volume of slurry in
the averaging tank. The high pressure pumps transport the cement slurry from the
The control system regulates three valves which control the process (master water
valve, mix water control valve, and bulk cement control valve). The descriptions of these
o The master water valve is a pneumatic butterfly valve that sends an open,
by the PLC or manually via the toggle switches on the upper control
console. When opened, it directs water to the high energy mix head and to
o Additional water for the process is regulated with the mix water control
to the PLC and a BD101 servo valve driver board. It can also be controlled
on the upper control console. This valve directs water into the recirculating
loop of the mixing side of the process. In the event of hydraulic failure, the
o The bulk cement control valve adds dry bulk cement to the high energy
actuated and provides position feedback to the PLC and the BD101 servo
hand.
The slurry on the mixing side is circulated, by a centrifugal pump, back to the bottom of
the high energy mix head. This helps to blend the slurry. Part of the circulated slurry is
directed through the 2" Coriolis mass flow meter. This meter continually measures the
slurry density and this value is used in calculations that control the bulk cement valve.
A surge can is used to aid in constant delivery of cement to the high energy mixing
head. There is still a small risk of fluctuations with the delivery of the bulk cement.
These fluctuations are mitigated by continually monitoring the process and updating the
The mix water control valve is controlled using a calculated set-point from the cement
program. Feedback is provided with a 3" magnetic flow meter. The water that is directed
to the high energy mix head goes through a series of jets. These jets form a water
pattern that wets, and blends, the incoming cement. The mix head combines the water,
and cement, with the recirculated cement to produce the cement slurry.
Cement that travels from the averaging tank to the down hole pump passes through the
4" Coriolis mass flow meter. This meter is used to measure down hole density and rate.
The system can also use the magnetic pickups on the down hole pumps to monitor
The revolutions on all four centrifugal pumps are monitored. The rpm of the pumps are
directly related to the process pressures of the system. There are recommended
operating ranges for the centrifugal pumps, but the process pressures are what
3.4.1 Rates
This subsection discusses the various flow rates.
transmitted to the PLC via ProfiBus. The measuring range of the instrument is 0 – 3
m3/min (0 – 19 bbl/min). There is a display on the transmitter, which can be used to view
the mix water rate, in the event the control system fails. The flow rate to the mix head
jets is about 250 liters/min (66 US gal/min) with the unit operating at a recommended
rpm and pressure. The bypass flow rate to the recirculation line is about 1200 liters/min
(317 US gal/min) with the unit operating at a recommended rpm and pressure.
measuring this rate is to use the 4" Coriolis mass flow meter, which is located in the
piping between the discharge of the down hole boost pump and the suction of the high
pressure down hole pumps. This flow rate is sent to the PLC via ProfiBus. Observe the
range of the 4" Coriolis meter in the density measurement area (Figure 3-1).
A magnetic pickup is located in the housing of each of the high pressure down hole
pumps (above the bull gear). When this gear makes one full revolution, it displaces
each of the pump plungers one time. The PLC uses the frequency signals from the bull
gears to calculate the flow rate of the pumps. The PLC adds these rates and displays a
pickup, located on the high pressure down hole pumps. These rates are displayed,
panel, located under the upper control console, that can be accessed from ground level.
Both these inputs are routed through magnetic pickup amplifiers. The operator can input
a meter factor for each channel and the value is displayed on the “Process Variables”
faceplate.
NOTE: Since the rate is calculated in the PLC, a meter factor of 1 is used in FDAS.
3.4.2 Pressure
This subsection discusses the various pressures.
15000 psi) range. There is a full range calibration mode on this sensor. The PLC
outputs a digital signal to an interposing relay, which activates the transducer’s full scale
output.
NOTE: The treating pressure sensor is located on the discharge piping of the high
15000 psi) range. There is a full range calibration mode on this sensor. The PLC
outputs a digital signal to an interposing relay, which activates the transducer’s full scale
output.
NOTE: The treating pressure sensor is located on the discharge piping of the high
process pressure (annular pressure). There is a signal input panel, located under the
operator’s console, that can be accessed from ground level. This is where the operator
psi range. Use either a sensor that has the full range calibration mode or a standard two
wire 4 – 20 milliamp sensor. The value for this auxiliary transducer is displayed in the
160 psi range. This measurement represents the water pressure at the mix head. The
160 psi range. This measurement represents the recirculation pressure at the mix head.
160 psi range. This measurement represents the back pressure in the 2" mass flow
meter, in the recirculating loop, of the mixing system. The value is displayed in the
160 psi range. This measurement represents the boost pressure at the suction of the
high pressure down hole pumps. The value is displayed in the “Process Variables” area.
3.4.3 Density
This subsection discusses the various densities.
flow rate, total and temperature. These signals are transmitted to the PLC via ProfiBus.
The excitation current value is sent to the PLC via the 4 – 20 milliamp analog output.
The excitation current range is 0 – 100 milliamps. The instrument measures mass flow
and converts this to a liquid flow rate and density. The measuring limit varies with the
density of the slurry. The instrument has a range of 0 – 1150 kg/min (0 – 2500 lb/min).
Since water has a density of 1000 kg/m3 (8.34 lb/gal), then the measuring range would
be 0 – 1.150 m3/min (0 – 7.2 bbl/min). If the slurry being pumped had a density of 2000
kg/m3 (0 – 16.68 lb/gal), then the measuring range would be 0 – .575 m3/min (0 – 3.6
bbl/min).
flow rate, total and temperature. These signals are transmitted to the PLC via ProfiBus.
The excitation current value is sent to the PLC via the 4 – 20 milliamp analog output.
The excitation current range is 0 – 100 milliamps. The instrument measures mass flow
and converts this to a liquid flow rate and density. The measuring limit varies with the
density of the slurry. The instrument has a range of 0 – 5800 kg/min (0 – 12, 787
lb/min). Since water has a density of 1000 kg/m3 (8.34 lb/gal) the measuring range
If the slurry being pumped had a density of 2000 kg/m3 (16.68 lb/gal) then the
actuator. There is a signal for open and a signal for closed. The feedback assembly is a
Namur sensor and is run through a Namur amplifier. The signals are amplified to a 24
volt level, which is sent to the PLC. The Namur amplifier also has an alarm output,
which is sent to the PLC. If one of the Namur sensors is faulty, an error message will be
When in “Man” mode, the “Master Water Open/Close” switch controls the
electric/pneumatic valve. The master water valve “Auto/Man” switch also sends a 24
potentiometer. In “Auto” mode a 0 – 10 volt signal is sent from the PLC to the BD101
hydraulic driver board. In “Manual” mode the 0 – 10 volt control signal is generated by
NOTE: The potentiometers only utilize the middle 50% (5 turns of the 10 turns
available) of travel. This means there is a dead band at the bottom, and top, of the
potentiometers range. A 24 volt status signal is sent to the PLC when “Auto” is selected.
potentiometer. In “Auto” mode a 0 – 10 volt signal is sent from the PLC to the BD101
hydraulic driver board. In “Manual” mode the 0 – 10 volt control signal is generated by
NOTE: The potentiometers only utilize the middle 50% (5 turns of the 10 turns
available) of travel. This means there is a dead band at the bottom, and top, of the
potentiometers range. A 24 volt status signal is sent to the PLC when “Auto” mode is
selected.
that operates the cement valve. The signal is sent to the BD101 servo driver board, as
well as the PLC. The signal represents 0 to 360 degrees of travel. The cement valve
only rotates about 160 degrees, so approximately 45% of the signal is utilized. The 10
that operates the cement valve. The signal is sent to the BD101 servo driver board, as
well as the PLC. The signal represents 0 to 360 degrees of travel. The mix water valve
only travels about 90 degrees, so only 25% of the signal is utilized. The 10 volt
NOTE: This signal causes the 2" Coriolis meter symbol on the “Process Variable”
screen.
NOTE: The excitation current level indicates the amount of entrained air present in the
slurry. The 2" and 4" Coriolis symbols change color depending on the level of the
1000 psi). The pressure transducer signal first goes through a current loop splitter, so
that a signal can also be sent to a LED local display. See Section 3.7 Miscellaneous
The pressure transducer is connected to a hydraulic load cell, located under one of the
three mounting legs of the surge can. This measurement represents 50% of the weight
of the surge can. The hydraulic load cell has an effective measurement range of 8
inches. This means that whatever load is applied to the cell is distributed over the 8
inches.
When used with the 1000 psi pressure transducer, this provides a measuring range of 0
– 8000 lbs on the one leg of the surge can. Since the hydraulic cell only measures half
the weight of the surge can, a factor of two is applied to represent the entire weight of
the load cell. This means we have an effective measuring range of 0 – 16000 lbs.
NOTE: There is a tare function that allows the weight of the surge can to be “zeroed”.
valve, which opens or closes the master water butterfly valve. The electric/pneumatic
valve can be manually actuated for testing, using mechanical overrides on the assembly
(AUTO control) or the potentiometer on the control panel (MAN control). Both of these
signals are sent to the BD101 board via the water valve “AUTO/MAN” switch.
PLC (AUTO control) or the potentiometer on the control panel (MAN control). Both
these signals are sent to the BD101 board via the cement valve “AUTO/MAN” switch.
over pressure trip is activated when the treating pressure is greater than the over
pressure trip point. When the function is activated, it sends a signal to the engine ECM
“throttle inhibit” input, which sets the engine’s rpm to low idle. It also sends a signal to
the transmission TCM “Quick to Neutral” input, which puts the transmission to Neutral.
To reset the over pressure trip, the treating pressure must be lower than the over
pressure trip value. Before resetting the over pressure trip function, return the
NOTE: The transmissions will not shift into gear, when the rpm is 800 rpm or greater.
control valve that opens or closes the high pressure return valve. The speed, at which
the valve actuates, is controlled by an adjustable hydraulic flow limiting valve, in series
engages the “quick to neutral” and “throttle inhibit” functions, as well as cutting power to
the engine ignition power. These actions ensure the engines will be shut down in a
NOTE: The Emergency Shutdown push-button must be pulled out, in order to reset the
rig savers.
purpose of the display is to provide a weight indication of the product in the surge can.
This indication will assist the operator with keeping the level constant during mixing
operations.
loop splitter) from a two wire 24 volt powered pressure transducer. The pressure
transducer is mounted to a hydraulic load cell located under one of the three legs of the
surge mount. This measurement represents 50% of the weight of the surge can.
The display is scaled to produce the actual weight of the surge can. A tare function can
be activated by a remote push button mounted near the display. This allows the
operator to tare the weight of the surge can with no product. After this is done, only the
density of the mixed slurry. The hydraulic actuators were used because of their torque,
reliability and simplicity. The rotary hydraulic actuator rotates a valve by using a rack
and pinion assembly. See Figure 3-2 for the configuration of the hydraulic actuator.
The Parker BD101 board (Figure 3-3 and Figure 3-5) serves as a driver for the Parker
The BD101 uses the difference between the command signal and the feedback to
produce an output to the BD15 valve. The BD15 valve is controlled by a plus/minus 60
milliamp signal. The spool valve in the BD15 valve is normally centered. When the
BD101 board sends an output signal, it causes the spool valve to travel in one of two
directions.
This causes pressurized hydraulic oil to be directed to one side of the hydraulic actuator
while the other side is returned to the reservoir. The result is that the valve being
actuator and the signal is sent back to the BD101 board and the PLC. As the valve
moves, the error signal is reduced. When the command signal equals the feedback
The command signal comes from two points. For automatic control, the 0 – 10 volt
signal comes from the PLC. When the manual control is desired, the signal comes from
the potentiometer located on the control panel. This signal is selected by using the
“AUTO/MAN” switch on the control panel. Because both the water and cement valves
do not turn 360 degrees, the command signal is not the full 0 – 10 volts. The control
range is approximately 3 – 7 volts. The feedback signal increases, as the valves open
The command signal comes into the BD101 board as a positive signal. The feedback
signal comes into the board as a positive signal on the “FDBK” terminal. The amp
inverts the feedback signal and it is measured as a negative signal at TP2. If a reading,
with a meter, shows that the feedback signal is positive on TP2, reverse the wires on
terminals 1 and 2. The feedback signal that goes to the PLC is positive.
NOTE: For detailed instructions on how to setup, and troubleshoot, these components
3100 lb/min).
centrifugal pump.
back pressure to compress any entrained air in the slurry. Excessive entrained air can
cause erroneous readings from the instrument. In extreme cases it can cause the
the boost pressure to the down hole pumps, as well as the back pressure on the 4"
Coriolis meter. Once again this back pressure is important for the correct operation of
the instrument.
Sufficient pressure is also important to ensure smooth pumping of the slurry. This
pressure can be regulated by the valve that restricts the circulating flow back to the
averaging tank.
NOTE: If the pressure drops too low (less then 10 psi), you will “starve” the down hole
Triplex pumps.
• Master water valve switch in “AUTO” or “MAN” but the valve must be open
• Mix water centrifugal pump operating at 2200 rpm (min allowable is 1200)
• If any “simulation” is active (density or rate), the above conditions are overridden
and the system will go into mixing mode. The reason for this action is that
o If the condition lasts more than 3 seconds, the cement valve will close.
o If the system is in “MAN”, the cement valve will not close as it is assumed
• After “Start Mixing” is active, the cement valve will not open until the mix water
3.10.2 Alarms/Notifications
• If the recirculation density is 200 kg/m3 (2 lb/gal) higher than the set-point, the
• During mixing, if the cement valve is 100% open and the density is 30 kg/m3
(0.25 lb/gal) lower than the set-point, the “bulker” symbol on the “Process
• If the down hole Triplex pump’s boost pressure is less than 30 psi, the value
flashes.
• The Coriolis meter symbols on the “Process Variables” page are colour coded
o Green (0 – 18 ma)
• The centrifugal pump symbols are “color coded” dependent on the rpm. See
Table 3-1).
General
Cannot shift transmission into • Engine rpm too high • Reduce engine rpm to less than
gear 800
Cannot reset over pressure • Treating pressure is • Wait till treating pressure declines
greater than over
pressure trip value
Mixing Functions
System does not start after • See “Message” • Ensure conditions are met
“Start Mixing” is pressure area for warnings
No Mix water rate after “Start • Closed valve • Verify that all valves in flow path
No recirculation rate (2" • Plugged inlet of 2" • Partially close the recirculation
Coriolis flow meter) Coriolis flow meter valve going to the mixing head.
This will direct more flow through
the 2" Coriolis. Once flow is
established, open the valve and
pinch it back if the 2" Coriolis
back pressure is low
Maximum mix water rate is • Mix water pump • Increase rpm of pump
less than 250 liter/min (66 rpm is low
gal/min) • Switch hydraulic engine to high
throttle
Process Errors
Excitation current limit • Entrained air • Check the back pressure reading.
Pinch in the recirculation flow to
the mix head to increase the
pressure to the 2" Coriolis flow
meter
Data
Cannot retrieve files from • Incorrect storage • Verify that the computer name is
memory card folder path in data correct
archiving screen in
HMI
3.14 Glossary
ProfiBus The PROFIBUS (Process Field Bus) is a standard for field bus
communication in automation technology.
answering the following questions. The training department uses this information to
6. Are there topics covered in the training not covered in this unit? If Yes
the answer is Yes, please explain. No
9. Please list any topics that should be included in future versions of this unit.
10. Comments:
Thank you for providing feedback on this unit. Please send the completed form to: