Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

Event A

 Summary:
- The contractor didn’t find the 6 road crossing (only he finds 5).
- She informed George and gives him 2 options: cut pavement/ or do a jack &bore process in
order to install the remaining crossings.
- George refused to cut the pavement.
- Dawn decided to rent the jack&bore equipment that takes: 6 days to arrive on site, and 2
extra days of work.
 Responsibility of delay:

- In this case, the contractor visited the site, checked the location and reported the damages
found to the owner. This work was supposed to be done (personal observations) before
signing the contract.
- According to section 3.2(AIA):

3.2.1  The contractor before working should check the site conditions.
3.2.2  Contractor should check any given condition, and have a personal observation.
No time and money compensation
In reality if the contractor did not sent any claim to ask for time and money compensation. According to:
Event B
 Summary:
- This event took place at step 8 when installing the PVC to guardhouse.
- Shocksmith borrowed a Ditch Witch to perform trench ditching. The contractor started
playing with the machine as a child.
- The owner George and Sam saw him and was not amused by that.
- The first 2 days installation was good until sparks begins to fly out.
- the contractor hit the underground electric service field.
- The contactor promised to repair the damages caused by him. However while repairing he
found that the project was illegitimately powered by electricity (electricity power not
meeting the code).
- The owner accepted to do repairs according to the code.
- Repair + the upgrade of the service feed to legal electricity took 3 days. In addition 1 extra
day was wasted waiting to the inspectors approval on changes
- This delayed the process of installing the underground PVC.

 Delay Responsibility:
- While playing with the machine this leads to smoke and noice
According to special condition:

- According to AIA, the contactor is the one responsible for all damages occurring during
performance of the work, especially that the location of utilities is one of his reponsabilities
that should have been fulfilled previously:
- The contractor should not start work before written instruction from the owner.
No money compensation only time extension because the owner did not respond
quickly.
3.3.1
Also in special conditions

- If they said that the quality of wires that owner put are not good not related…They both
agreed at the end to change the wires.
- Contractor should not rely on the information the owner gives to him
Event C
 Summary
- Hurricane Annie was expected to hit the country.
- On October 26 it hits Virginia and affected the project that was stopped for 2 days.
- The contractor forgot the Ditch Witch outside forgetting to put it in a protected place.
- After the storm calmed out, the contractor found that the machine now is lying underwater and the whole road
too.
- The Owner urged the contractor to remove all dirt and damages.
- The contractor asked a favor of dozen operator which will cover the PVC installation and compact the road
- Overall delay= 5 days (3 days due to hurricane and 2 days for cleaning).
 Responsibility of delay:

- It is right that in the supplementary conditions it is written that an Act of God is at the
charge of the owner. But, the contractor should have expected if not the hurricane at least
the rain(in October rain is usually expected in Virginia), and the contractor should have at
least protected the equipment since he is responsible for the safety of equipment on site:
In the supplementary conditions paragraph 10.12:

Also, if the owner made a proper drainage system you will not be forced to stop the indoor
activity.
- Also, according to AIA, the contractor is responsible of keeping the site clean and free from
waste materials: AIA clause 3.15.1:

No time and money extension


Event D:
 Summary:
- This event affected activity 5 and 16 of the list of required activities.
- The installation of all wires in the clubhouse was nearly complete.
- When Dawn arrived to the site, she learned that vandals had ripped all the copper wire and
plumbing during the night.
- But, none of the conduit or outlet had been seriously damaged and some of the cables
remained.
- It took 4 days to repair the damage. This caused a delay.

 Responsibility of Delay:
- Referring to the special conditions of the contract paragraph10.1.3:
It is written that any act of vandalism is an expected risk to the contractor:

So, it is not the responsibility of the owner since this action is not due to owner’s
negligence.
- Moreover the contractor should have expected vandalism on site, since it was very
common during that period of construction, and the contractor has already heard of
it(handout).
- Remark: If asked that the owner should get an all risk insurance that covers
vandalism(AIA): generally if the owner did not get this insurance then definitely the
contractor should get it.

No time and money compensation


Event E:
 Summary:
- Tyrone decided to check the work in the clubhouses knowing that the preliminary
inspection have been approved last night.
- He noticed that a new wall was built without any prior notice given to Dawn because
George thought that it will not affect the electric work. But the code required that there
should be at least 1 electrical outlet placed on each immovable partition.
- Tyrone wasted 2 days working on this.
- Total delay 5 days. This delayed activities 8 and 17.

 Responsibility of Delay:
- Contractor is right 100%  time and money compensation.
- This activity is not considered critical, and did not involve and time or money
compensation since the repair was done by Tyrone itself and didn’t require any
additional labor.
-

- According to the special condition 12.1.6:


The owner has the right to order any change, and the contractor is entitled to additional
compensation:

- Owner does not know a lot in construction it is not his fault.

Time and money compensation


Event F
 Summary:
- During testing, the alarm system was showing good results. But, when someone turned
on a ceiling fan, the alarm went crazy.
- The ceiling fans used by Laly were unshielded wires, and were of substandard quality.
- George was so angry. He shouts on Dawn to choose the new wires.
- Delay to remove and install new fans tooked 5 days.
 Responsibility of Delay:
- The contactor knew from the beginning that the fans were of inferior properties:
According to the sequence of activities: the installation of ceiling fans is required to take
place before the installation of alarms. The contractor knew that the fans were of
inferior properties, and should have estimated that the alarm it will not work correctly.
So the problem should have been discussed with the owner before installing the
whole alarm system even though the owner is responsible of selecting the ceiling fans.
Failure of the contractor to do so, shows an acceptance of the owner work.

According to AIA 6.2.2: If a part of the work depends on the owner, the contractor
should report any defect or problem in it. If no report was given, this assumes that the
contractor has approved the owner work:

- The contractor should use good quality material:

No time and money compensation

You might also like