Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


MAJOR INFRASTRUCTURE PROJECTS
Status as of August 31, 2020

Name of project : Construction of 4 -Storey Regional Prosecutor's Office Building, Regional Office, Region 2, Regional Government Center,
Carig Sur, Tuguegarao City, Cagayan
PROJECT DESCRIPTION:
Construction of Office Building

PROJECT IMPACT :
Intends to provide better facility for the conduct of meetings and other judiciary activities in the region.

CONTRACTUAL DATA : FINANCIAL STATUS :

Project Component : Building Construction Amount


Province : Cagayan Allocation Releases Obligation Disbursement
Region : II FY 2019 PHP 41,970,000.00 PHP 40,190,719.51 PHP 40,190,719.51 PHP 14,066,751.83
Tuguegarao City,
Location : Cagayan
Source of Funds : DOJ FUND FY 2018 Total PHP 41,970,000.00 PHP 40,190,719.51 PHP 40,190,719.51 PHP 14,066,751.83
Mode of Contract : Competitive Bidding
Implementing Office : DPWH-CTDEO

Contractor : DCMS TRADING &


CONSTRUCTION
Total Project Cost (LP) : PHP 40,190,719.51
Cost of Non-Civil Works : PHP 4,019,071.95
Cost of Civil Works : PHP 36,171,647.56
Start Date : October 31, 2019
Contract Duration : 230 C.D.
Time extension due to WSO 01 : 30 C.D.
Time extension due to CWSO 01 : 30 C.D.
Revised Contract Duration : 290 C.D.
Original Completion Date : June 16, 2020
Completion Date : August 15, 2020
Actual Completion Date : -

PHYSICAL ACCOMPLISHMENT : REMARKS:

To-Date
Planned Accomplishment : 100.00%
Actual Accomplishment : 69.00%
Slippage : -31.00%

PROJECT ACTIVITIES EQUIPMENT ON SITE:

Pouring of Concrete in 2nd Floor Columns, Beams and Slab; Backhoe


Plastering of 1st Floor Exterior Wall Minor Tools
One Bagger Mixer

MANPOWER ON SITE:
1 - Project Engineer
1-Foreman
8-Skilled Laborers
10- Laborers

PROBLEMS / ISSUES: ACTION UNDERTAKEN:


Required Contractor to extend Working Hours
PROJECT DELAYED DUE TO 50% LIMITATION ON MANPOWER UNDER Work Shifting Schedule of Work
MODIFIED GENERAL COMMUNITY QUARANTINE AREAS AS
ORDERED BY THE PROVINCIAL GOVERNOR TO COMPLY WITH Provided sufficient materials to cope with uninterrupted work schedule
IMPLEMENTATION OF MINIMUM HEALTH STANDARDS.

Prepared by: Submitted by: Approved by:

JAYLORD A. DE ASIS RAYNALDO T. ARUGAY DANILO U. TABILAS


Project Engineer II Chief, Construction Section District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of August 31, 2020

Construction of 4 -Storey Regional Prosecutor's Office Building, Regional Office, Region 2, Regional
Name of project : Government Center,
Carig Sur, Tuguegarao City, Cagayan
BENEFITS :
SOCIAL ECONOMIC ENVIRONMENTAL
1. establish a bridge between 1. Increase in income 1. Structurally sound modern
public safety and law generation in the local economy type of office building
enforcement responding to due to the increased sales of 2. Provision of septic
crime and social problems; goods and created jobs during systems to manage wastemater
2. Create an aesthetically construction from office building which can
conducive working environment reduce the risk of disease
for employees transmission and human
exposure to pathogens

PROGRESS PHOTOGRAPHS :
BEFORE DURING

LOCATION MAP: