Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


MAJOR INFRASTRUCTURE PROJECTS
Status as of October 31, 2020

Name of project : Construction of 4 -Storey Regional Prosecutor's Office Building, Regional Office, Region 2, Regional Government Center,
Carig Sur, Tuguegarao City, Cagayan
PROJECT DESCRIPTION:
Construction of Office Building

PROJECT IMPACT :
Intends to provide better facility for the conduct of meetings and other judiciary activities in the region.

CONTRACTUAL DATA : FINANCIAL STATUS :

Project Component : Building Construction Amount


Province : Cagayan Allocation Releases Obligation Disbursement
Region : II FY 2019 PHP 41,790,000.00 PHP 40,190,719.51 PHP 40,190,719.51 PHP 24,114,431.71

Location : Tuguegarao City, Cagayan


Source of Funds : DOJ FUND FY 2018 Total PHP 41,790,000.00 PHP 40,190,719.51 PHP 40,190,719.51 PHP 24,114,431.71
Mode of Contract : Competitive Bidding
Implementing Office : DPWH-CTDEO

Contractor : DCMS TRADING &


CONSTRUCTION
Total Project Cost (LP) : PHP 40,190,719.51
Cost of Non-Civil Works : PHP 4,019,071.95
Cost of Civil Works : PHP 36,171,647.56
Start Date : October 31, 2019
Contract Duration : 230 C.D.
Time extension due to WSO 01 : 30 C.D.
Time extension due to CWSO 01 : 30 C.D.
Revised Contract Duration : 290 C.D.
Original Completion Date : June 16, 2020
Completion Date : August 15, 2020
Actual Completion Date : -

PHYSICAL ACCOMPLISHMENT : REMARKS:

To-Date
Planned Accomplishment : 100.00% Time extension ,due to 50% limitation on manpower under modified general community
quarantine in strict compliance with local health protocols and standards, is awaiting for
Actual Accomplishment : 87.00% approval.
Slippage : -13.00%

PROJECT ACTIVITIES EQUIPMENT ON SITE:


Minor Tools
Plastering of Interior Wall One Bagger Mixer
Laying of CHB for Parapet Wall

MANPOWER ON SITE:
1 - Project Engineer
1-Foreman
8-Skilled Laborers
10- Laborers

PROBLEMS / ISSUES: ACTION UNDERTAKEN:


Required Contractor to extend Working Hours
PROJECT DELAYED DUE TO THE FOLLOWING : 50% LIMITATION ON
MANPOWER UNDER MODIFIED GENERAL COMMUNITY QUARANTINE Work Shifting Schedule of Work
AREAS AS ORDERED BY THE PROVINCIAL GOVERNOR TO COMPLY WITH Provided sufficient materials to cope with uninterrupted work schedule
IMPLEMENTATION OF MINIMUM HEALTH STANDARDS; AND DUE TO
ADVERSE WEATHER CONDITION.

Prepared by: Submitted by: Approved by:

JAYLORD A. DE ASIS RAYNALDO T. ARUGAY DANILO U. TABILAS


Project Engineer II Chief, Construction Section District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS
Status as of October 31, 2020

Name of project : Construction of 4 -Storey Regional Prosecutor's Office Building, Regional Office, Region 2, Regional Government Center,
Carig Sur, Tuguegarao City, Cagayan
BENEFITS :
SOCIAL ECONOMIC ENVIRONMENTAL
1. establish a bridge between public 1. Increase in income generation in the 1. Structurally sound modern type of
safety and law enforcement local economy due to the increased office building 2.
responding to crime and social sales of goods and created jobs during Provision of septic systems to manage
problems; 2. Create an construction wastemater from office building which
aesthetically conducive working can reduce the risk of disease
environment for employees transmission and human exposure to
pathogens

PROGRESS PHOTOGRAPHS :
BEFORE DURING

LOCATION MAP: