Professional Documents
Culture Documents
An Investigation Into The Impact of Comm
An Investigation Into The Impact of Comm
JULY 2019
DECLARATION
This research thesis is my original work and has not been presented for a degree award in any
other university.
Signature……………………………. Date……………………………….
Frank Antony Maina Mwangi
This project thesis has been submitted to the Jomo Kenyatta University of Agriculture and
Technology (JKUAT) for examination by the above student as his original work with my
approval as a University Supervisor
Signature……………………………. Date……………………………….
Ms. Melody Njuguna
JKUAT, Kenya.
ii
DEDICATION
I dedicate this research to God the almighty, my parents and family, who have always had my
iii
INSPIRATION
Learning is an endless process that needeth a brave heart and a humble mind; willing to see
iv
ACKNOWLEDGMENTS
Agriculture and Technology by and large for facilitating my execution of this research and the
This work would not have been without the guidance of my supervisor, Ms. Melody Njuguna.
I sincerely appreciate her support in this course, commitment towards ensuring my success and
I extend the appreciation to Mr. Robert Kang’ethe, my cousin, who the whole thesis through
Last but not least are my classmates and friends who provided ideas, positive input, motivation
and criticism towards accomplishment of standard work, as well as my own errors of omission
v
ABSTRACT
By virtue of the magnitude, complexity, and nature of the works it executes, the construction
industry is a major consumer of capital goods. Improving the communication structure and
information/data management systems however still remains a chronic challenge facing the
industry in many countries worldwide. Apart from advances made by some contractors and
firms to devise mechanisms for communication and to manage information, studies across the
world reveal that construction projects are hardly completed within time and budget. The
Kenyan construction industry has not been spared either. This background can be considered
unhealthy for an industry whose capital consumption is as heavy and the concurrent cost and
The construction industry is estimated to be contributing up to over 60% of the gross formation
in Kenya. According to the Kenya National Bureau of Statistics (2018), construction sector in
Kenya recorded a growth of 9.5% coming fourth after tax revenue, real estate, and transport &
storage. The contribution to Gross Domestic Product (GDP) was estimated at 5.8% in 2017 up
from 5 % in 2016. The increased investment in the housing and infrastructure development
needs to be met with efficiency in the communication and the management of information
meant for it as well as ensuring the value for money to the client in terms of reduced delays,
There is, therefore, a need for effective and efficient communication and information
means employed by construction firms in building projects and also investigated the challenges
encountered in managing data as well as the causes of miscommunication. The rate for adoption
of new technology and MIS as well as the influence on the same by the choice of procurement
method were also sought for and correlated in this study Finally, the researcher established the
impact of, and influence communication and information management in construction has on
vi
the performance of a project. The descriptive research design was employed, making use of
questionnaires to collect data from Quantity Surveying and Architectural firms within Nairobi,
Data collected was analyzed based on a conceptual framework to establish the relationship and
on the dependent variable which, for the case of this research, was project performance.
Comparative and correlational surveys were thus utilized, analysis was done on statistical
Conclusions and recommendations were made based on the findings for the objectives of this
are attributed, with regard to the findings herein, to variations due to communication and
information management.
The study invites investigations on such areas as the influence of language barriers to
communication and information management with the increased interracial interactions in the
industry.
vii
Table of Contents
DECLARATION................................................................................................................................... ii
DEDICATION...................................................................................................................................... iii
INSPIRATION ..................................................................................................................................... iv
ACKNOWLEDGMENTS .................................................................................................................... v
ABSTRACT .......................................................................................................................................... vi
Table of Contents ............................................................................................................................... viii
ABBREVIATIONS ............................................................................................................................ xiii
CHAPTER 1. INTRODUCTION..................................................................................................... 1
1.1. Background of the problem ............................................................................................. 1
1.2. Statement of the problem ................................................................................................. 2
1.3. Purpose of the study.......................................................................................................... 2
1.4. Research objectives ........................................................................................................... 3
1.4.1. General objective........................................................................................................... 3
1.4.2. Specific objectives ......................................................................................................... 3
1.5. Research questions ............................................................................................................ 3
1.6. Justification ....................................................................................................................... 4
1.7. Significance of the study ................................................................................................... 6
1.8. Scope of the study.............................................................................................................. 7
1.8.1. Content scope ................................................................................................................ 7
1.8.2. Geographical scope ....................................................................................................... 7
1.8.3. Time scope ..................................................................................................................... 7
1.9. Limitations and assumptions ........................................................................................... 8
CHAPTER 2. LITERATURE REVIEW......................................................................................... 9
2.1. Introduction ....................................................................................................................... 9
2.2. Previous works on related topics ..................................................................................... 9
2.2.1. Communication in the construction industry ............................................................. 9
2.2.2. Information and data management in the construction industry........................... 12
2.2.3. Procurement methods and standard regulations on communication and
information management ...................................................................................................... 15
2.2.4. The trends in the performance of construction projects ......................................... 17
2.2.5. Miscommunication and Informational conflicts in the construction industry ...... 19
2.3. Theoretical framework ................................................................................................... 21
viii
2.4. Conceptual framework ................................................................................................... 23
2.5. Research gap.................................................................................................................... 24
2.6. Summary .......................................................................................................................... 24
CHAPTER 3. RESEARCH METHODOLOGY .......................................................................... 26
3.1. Introduction ..................................................................................................................... 26
3.2. Research design and strategy ......................................................................................... 26
3.3. Nature and sources of data ............................................................................................. 27
3.4. Target population and sampling frame......................................................................... 27
3.5. Sampling methods ........................................................................................................... 27
3.6. Methods of data collection and instruments ................................................................. 28
3.6.1. Questionnaires ............................................................................................................. 29
3.6.2. Reliability and validity................................................................................................ 29
3.7. Pilot study and sample group ......................................................................................... 30
3.8. Methods of data analysis and presentation ................................................................... 31
CHAPTER 4. DATA ANALYSIS .................................................................................................. 32
4.1. Preliminary Information ................................................................................................ 32
4.1.1. Questionnaire response rate ....................................................................................... 32
4.1.2. Duration of Professional Service................................................................................ 32
4.2. Communication and Information Management by Firms in the Construction
Industry 33
4.2.1. Means of communication............................................................................................ 33
4.2.2. Management Information Systems............................................................................ 35
4.2.3. Reasons for the use of Management Information Systems ..................................... 36
4.2.4. Management of official and professional information ............................................. 37
4.2.5. The rate of adoption of New Technology in the construction industry .................. 40
4.2.6. Influence of procurement methods and contract ..................................................... 42
4.3. Performance of construction projects ........................................................................... 44
4.3.1. Time and cost performance ........................................................................................ 44
4.3.2. . The occurrence of time and cost overruns .............................................................. 44
4.4. Miscommunication in the construction industry ......................................................... 45
4.4.1. The occurrence of informational conflicts as a result of miscommunication ........ 46
4.4.2. Causes of informational conflicts............................................................................... 47
4.5. Influence of communication and information management on project performance
..........................................................................................................................................48
ix
4.5.1. Correlation between the occurrence of time-cost overruns and occurrence of
informational conflict in projects ......................................................................................... 49
4.5.2. Correlation between procurement methods and standard forms adopted versus
slow adoption of new technology .......................................................................................... 50
4.5.3. Correlation between the influence of communication and information
management and slow adoption of new technology ............................................................ 51
4.5.4. Correlation between procurement methods and standard forms versus
communication and information management ................................................................... 52
CHAPTER 5. SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS ........................ 53
5.1. Introduction ..................................................................................................................... 53
5.2. Summary of findings, discussions and inferences ........................................................ 53
5.2.1. Communication and Information Management by Firms in the Construction
Industry................................................................................................................................... 53
5.2.2. Performance of construction projects ....................................................................... 54
5.2.3. Miscommunication in the construction industry ..................................................... 55
5.2.4. Influence of communication and information management on project
performance ........................................................................................................................... 55
5.3. Conclusion ....................................................................................................................... 57
5.4. Recommendations and additional information ............................................................ 58
5.5. Summary of conclusions and recommendations .......................................................... 60
5.6. Areas of further studies .................................................................................................. 61
REFERENCES .................................................................................................................................... 62
APPENDICES ..................................................................................................................................... 68
Appendix I. QUESTIONNAIRE................................................................................................. 68
Appendix II. RAW DATA ............................................................................................................ 77
x
Table of figures
xi
List of tables
Table 4. 8. Storage............................................................................................................................... 39
Table 4. 15. Occurrence of time-cost overruns vs. occurrence of informational conflicts ........... 49
Table 4. 16. Procurement methods and standard forms vs. slow adoption of new technology .... 50
Table 4. 17. Influence of communication and information management vs. slow adoption of new
technology ............................................................................................................................................ 51
Table 4. 18. Procurement methods and standard forms vs. communication and information
management......................................................................................................................................... 52
xii
ABBREVIATIONS
IT Information Technology
xiii
CHAPTER 1. INTRODUCTION
2016). With a clearly defined and traceable structure, parties are able to understand each other
and accountability for all information passed easily achieved. Communication can, therefore,
The construction industry is one of the most information dependent industries (Tam, 1999) but
still heavily based on traditional means of communicating including face to face meetings,
phone calls and physical exchange of drawings and associated paperwork or documents
S. Kajawski & A. Weippert (2004) argue that the construction industry has for long been
in the Kenyan economy and the nature of its works continues to grow in complexity and
magnitude marking unknown levels of competition in the global economy (Nyaseda, 2016).
The history of modern information management parallels to the evolution of relevant computer
hardware and software as well as the devolution of management control from centralization to
decentralization. George B. (2017) argues that the history of Management Information Systems
is divided into eras dating from as early as 1939 when Dr. John V. Atanasoff & his assistant
Proper communication and data management are critical in the construction industry. This is
an industry that from conception to execution of a single project, registers a lot of exchanges
among parties and production of loads of data. If not properly documented and recorded,
there could be cause for so many frictions where some of the information may not get to
1
parties as targeted and some leave no clear ways of backtracking for liability/accountability
development does not involve the services of the top and most skilled personnel only but also
Harris(2018) recently pointed out that lack of defined communication systems that allow
collaborative systems to produce, share, store and retrieve construction data is a major cause
of project delays in Africa. The traditional channels of issuance and follow up of instructions
for instance use of triplicates is inherently slow. In terms of the production of project documents
like drawings, bills, schedule etc., various project team players work in their own cocoons and
come up with information/data with minimal consultation from the rest of the parties and could
thus lead to undetected clashes that when found out, often too late, result in claims and design
The purpose of this study was to investigate the communication and information management
systems used by firms in the Kenyan construction industry and their influence on project
performance.
2
1.4. Research objectives
The main objective of this research was to investigate and analyze the various communication
means and information management systems adopted in the construction industry to study their
iii. To find out the major causes of miscommunication and informational conflicts
ii. How has been the performance of construction projects in the past?
iii. What are the major causes of miscommunication and informational conflicts in the
construction industry?
iv. How much influence do the means of communication and information management
3
1.6. Justification
The Real Estate and construction markets in Kenya have been progressively growing over the
past few years as per statistics by various institutions including Knight Frank, Hass Consult,
Over the past five years, real estate has seen the entry of Institutional investors such as saccos,
private equity funds such as Actis and Taaleri and foreign investors such as Avic, who are
eager to get a share of the cake. Construction of a Sh40 billion mixed-use property, which
includes the 184m tall Avic Tower, is well underway in Nairobi, as Chinese multinational Avic
Tuner and Townsend in February 2018 announced that their business in Kenya was to merge
with Nairobi based Project Management firm Mentor Management Limited (MML) after
acquiring a majority stake in MML from leading growth market investor – Actis.
The infrastructural and housing demand continues to rise by the day. The government in Kenya
considers both as amongst key agenda their development plan for the ongoing term.
According to a report by Cytonn investments (2018), the government of the day aims at
working towards achieving 4 pillars duped the big 4 agenda namely: affordable housing,
agenda of major interest by the government greatly influences the construction industry. The
government of the day plans to deliver 1 million units over the next 5 years out of which, 20%
will be social housing while 80% will be affordable housing. If this is to be achieved
successfully putting into consideration the continued growth in competition, demand and time
limitation, then there calls for parties in the industry to adopt systems/means that facilitate
The government is also dedicated to improving infrastructure in the country by allocating Sh.
273.8 Billion to key infrastructure projects such as Phase 2A of the SGR Project, Mombasa
4
Port Development Project, expansion of several airports and airstrips, exploration of
geothermal, wind and solar resources, rural electrification and The Eastern Electricity Highway
Project connecting Ethiopia and Kenya. The improved infrastructure creates an enabling
environment for investors since accessibility is a major factor that influences the value of the
property. After the completion of the Outering Road, major developments have been set along
the road, for instance, go-downs set around Baba Ndogo area, office and residential buildings
around Donholm area. Construction of mixed-use developments along the expanded Outering
According to the World Bank, Rehabilitation of 400 km of road under the Northern Corridor
Transport Improvement Project reduced transit time from Mombasa to Nairobi by 30%.
Independent road entities have been created while aviation sub-sector institutions now have
financial power. These efforts have helped ease the cost of doing business, improved business
climate, and strengthened regional integration in East Africa Community. Similarly, according
to the report over 200,000 citizens got access to the drainage system, paved roads, improved
water reticulation, and sanitation services. These trends are indications of increasing economic
empowerment amongst the people and increased interest among investors in Kenya as a target
market for business in the line of construction. Prospectively it justifies the argument that,
under the same conditions, the construction industry will continue growing exponentially over
a significant amount of time in the country with the nature of works getting more and more
Communication and information/data management are inseparable with the entire construction
tendering, delivery of the project and maintenance. There was, therefore, need for such an
investigation on proper means of communication and data management to ease processes and
organize the fast-growing and vibrant construction industry. It will also be necessary for the
5
firms in the industry in terms of keeping up with the competition and changes in the nature of
projects.
Technological advancements are fast being made every day across all sectors of the economy.
The construction industry, not only locally, has for a while been too slow per se in following
suit. However, with an increase in the competition, complexity, and magnitude of projects, fast
strides are being taken in the sector; traditional styles of communication being dumped and
people going for collaborative project execution with the adoption of enhanced means of
This research intended to establish the essence of communication coupled with modern
information management systems to efficiency in terms of project delivery within scope and
schedule, achieving quality, profitability and client satisfaction. The research was aimed at
bringing to light that the advantages of properly organizing both from as early as on the short
run outweigh any incurred expenses of reorganization and/or training. Such costs cannot
compare to what is incurred in the case delays due to undefined traditional forms of operation
It is expected that the recommendations at the end of this thesis contribute usefully to the
6
1.8. Scope of the study
This study focused on proper communication and information management as the independent
variable and project performance as the dependent variable. The dependent variable was based
on four major indicators: economical delivery i.e. time and cost wise, quality of work and
customer satisfaction while the independent variable was based on the quality of
profitability. These indicators were considered since they were used to examine the relationship
between proper communication and information management and their influence on the
This study was carried out within the Metropolitan Kiambu and Nairobi counties. Both are
among the fastest growing counties in Kenya with a high level of residential, commercial and
infrastructure developments including road networks that connect to so many parts of the
country. They also proved convenient based on the researcher’s residential location; being
within the immediate region. This research targeted, Architectural, and Quantity Surveying
The literature content included is from the late 20th century to the date of research. During this
period, Kiambu and Nairobi counties experienced major developments in the building
construction and infrastructure sectors where some projects were completed in good time,
others delayed while some were unsuccessful causing great losses to the private clients, the
This research was executed, presented and submitted for examination within a maximum span
of 4 months.
7
1.9. Limitations and assumptions
inseparable factors, critically necessary for effective project execution. However, other than
the technical and financial aspects the study may consider influenced, variations in market
It was assumed that the statistics and findings made for the area specified under the scope are
8
CHAPTER 2. LITERATURE REVIEW
2.1. Introduction
Over the years, communication has evolved with various channels being adopted by numerous
entities in the entire world and so have the means of communication and information/data
management. This chapter looks at previously done work and papers that talk about the
According to Omulo (2008), communication in the construction industry provides the means
for improved management, coordination of individuals’ efforts, time and cost reduction.
Traditional means of communication through hard copies and face to face meetings to discuss
progress is gradually and progressively being replaced by advanced and remote methods of
communication as more growth is registered in the Internet of Things (IoT) and the Worldwide
Web.
interpreting it and effectively disseminating the information to persons that might need it thus
of messages and information among multiple agents (Talbert,1997), the process of interaction
between individuals in which meaningful information is created and shared (Cherry,1978). The
9
Oxford English Dictionary (2008) simply defines communication as the action of conveying
Gartside (1985) regards effective communication as that which reflects in the mind of the
receiver, a true image of the thoughts conveyed by the sender within the shortest timespan
possible for a reaction. Communication between project participants is critical for success. Poor
lifecycle of any project since construction projects are executed by teams. The construction
access to project information on a regular basis owing to the repetition of activities and
Going by the most common situation on the ground, meetings are carried out face to face and
ordination and should be primarily in writing. Change, for instance, should be accompanied by
oral communication over the telephone or at meetings involving as many people party to it as
10
Odiembo (2012) cites telephone, sign language, verbal interaction, physical meetings, letters,
memos, site records, reports, handbooks, regulations, site records and diaries, electronic mail,
schedules and photographs as the methods used for communication in the construction industry
among the stakeholders and during project execution. Omulo (2008) however refers to the same
as tools for communication in construction adding notice boards, drawings/sketches, and radio.
These also serve as the avenues through which the earlier outlined construction documents are
can either be in large or small scale. Large scale communication forming between the parties
occurring between individuals in the same firm. The effects are more severe in large scale
communication where if negative, conflicts and failure of the project may occur. Small scale
communication affects work progress and where acting negatively could result in accidents
and mistakes.
Three models of communication can be adopted in any organization as argued by Levitt and
• a direct contact system that allows flexibility and direct communication among workers
They argue that more effective management of communication can be achieved by the second
model than the first as it allows for input from each and every individual concerned with the
project regardless of their roles and allows direct (thus faster) issuance of information on
11
Hoezen (2014) argues that the quality of communication strongly influences the efficiency and
effectively in order for any given project to be successful. The literature outlines four reasons
for the need for improvement in communication within construction stakeholders. The first
reason is that it could reduce failure (Somogyi, 1999). Second, more open communication at
all levels could lead to innovations (Lenard and Eckersley, 1997) and better technical solutions
(Sorensen, in Atkin et al, 2003). Third, improvement of communication in early project phases
would positively influence the quality as perceived by all involved stakeholders (Emmitt and
Gorse 2003) and finally, improved communication during briefings could enhance decision
making for instance in better ways of looking at requirements first thus less haste in moving to
Communication is influenced by several factors. The first type of factors related to the
organization of the construction process and the second to the stakeholders themselves. The
main aspects relative to the organization of the process are the difference between formal and
informal communication routes during the design phase as well as during the phases of
development and the divorce of design and production while opposing interests on the part of
the stakeholders could lead to hidden agendas, thus often restricted communication (Hoezen &
Reymen, 2006).
Computing and information technology (IT) has radically been transforming the way we live,
learn, work and play (Capron, 2000). Many companies in the construction industry worldwide
do not however generally seem to have appreciated the positive changes and advantages this
Matheu (2005) points out the construction industry as being highly fragmented due to the many
stakeholders across phases in projects. A fact that has led to well identified and documented
12
problems with conveyance and processing of information contributing to the proliferation of
adversarial relationships between parties to projects. Howard et.al (1989) seconds this broadly
referring to the industry as that of AEC (Architecture, Engineering and Construction). As cited
by Nyaseda (2016), Ngowi (2000) argues that unlike other industries, individuals in the
professionals with the roles of each ending as soon as the project ends. Use of technology is,
therefore, being advocated for and increasingly deeming to be a necessity by the day as the
computers, the internet and the internet of things (IoT) allows for collaborative working
necessary in construction project execution. There is however still the debate among firms in
2000). Most companies that have used these systems were either. compelled by influence from
their competition in certain projects or forced by their clients (Matheu, 2005). Klynveld Peat
Marwick Goerdeler, (KPMG), an accounting firm, in a survey done in 2016 indeed found that
most construction firms are waiting for competitors to step towards the adoption of
out that the construction industry has for significantly long been singled out as an industry with
In the article “Construction Productivity in Decline” (2014), the author, a professional engineer
with the National Society of Engineers states that innovation and cutting edge are not words
associated with the U.S construction industry, at least not in comparison to industries like
robotics and aerospace, but even more unfortunate is that the industry’s poor image may be
deserved. Data from federal agencies show U.S construction industry productivity has a long
13
Like all industries, the construction industry is as well experiencing advancements in
technology. However, it has relied on age-old techniques for a very long time. Nobody likes
change, but it is arguable that the construction industry, in particular, is pretty resistant. The
industry is well positioned on the verge of something big technologically; the kind of shake-up
that has the potential to revolutionize the way that people perform their jobs on a daily basis
but isn’t taking full advantage. There calls for a total mindset shift among practitioners which
remains to be a huge challenge (Busta, 2016). A successful project demands that experts
involved are not only experienced but also should be appropriate team players with a similar
mindset and complementary skill sets managed to bring out the best work realizing the vision
A large number of packages are available at every stage of construction to all disciplines
concerned. They provide support for activities like Computer Aided Design (CAD)and
drafting, building visualization, design appraisal, information storage, and retrieval, cost
estimation, project onsite and facilities management, etc. As a project continues with execution
as per design, the information in form of drawings and specifications, as well as construction
methods, has to be communicated amongst the experts involved (Foley, 2005). Using a system
enhancement in the resolution of construction and design problems (Luka.et.al, 2014). Lee et.
al (2010) emphasizes the importance of information for enhancing communication and efficient
This research sought to expose the specific applications serving different firm purposes in the
construction cycle of a project and the consequent necessity to manage/organize and effectively
convey the information originating from these tools. Evidently, IT in the construction industry
14
among firms and organizations party to projects and thus poses as a great foundation, if
information management
Studies done by various researchers show that the procurement methods adopted in
construction have a very great influence on the communication characteristics and the general
method represents the framework that brings together and establishes boundaries of roles and
relationships between parties to projects as well as the allocation of risks setting the contractual
With regard to procurement, as the construction industry evolved over the years, there has been
a continuous quest among practitioners to continuously device methods that save on time and
allow for collaboration amongst the participants. For a very long time, the traditional
procurement method remained in use (and still does) across the world. Seely (1997) and as
cited by Muriithi (2006) points out that the unique characteristic of traditional procurement is
the separation of the responsibilities for design of a project from those of its construction.
Construction under this category of procurement is done in a strictly sequential manner from
identification of a need for a project by a client to selection and consultation with a design
team, production of plans, specifications as well as contract documents and finally the bidding.
This sequential delivery of projects with minimal allowance for practitioners at design and
construction to influence each other even positively amongst factors like high advancements
in technology, rising interest rates, and increased client awareness created a need for evolution
of the method into variants to cater for the acceleration of project life and adoption of
15
collaboration amongst especially the client’s consultancy/design team and the construction
team while the contemporary methods allowed for this so that input from the views of all parties
would be considered right from the design stage. It is also noted that the separation imposed
by the traditional procurement method was of a detrimental effect to the relationship amongst
teams in construction and the method thus obliged the contractor to carry out works as set in
the plans within a specific schedule and budget. The construction team in this method is often
not in a position to value engineer a project or suggest cheaper or faster alternatives from a
construction perspective.
Muriithi (2006) further cites that McDermott (2005) reported an increase in interest towards
alternative procurement methods in the UK industry since the late 1960s considered under 2
main categories i.e. integrated and management-oriented procurement systems. Among the
advantages that came along with the adoption of specifically the integrated systems of
provisions of the contract, of the standards of communication and in different situations and
stages of the project. Where the contract is not of an ad hoc nature, parties may agree to be
governed by standard forms. FIDIC conditions, under clause 1.3, give provisions for
notices, and requests. It stipulates that they should be in writing and delivered by hand, sent
by mail or courier or transmitted using any agreed systems of electronic transmission stated
in the appendix (FIDIC, 1999). The Public Procurement Regulatory Authority standard bid
document for building and associated civil engineering works in its provisions states that
communication between parties shall be effective only when in writing and notice shall be
effective only when it delivered. It is key to note that despite standardization being a positive
16
thing, the construction industry has, though relatively very slowly, continued to develop
standards based on traditional ways of doing things. There is thus lack of efforts to
project level is the procurement method and standard forms of contract adopted. Preference has
evidently been steadily shifting towards systems that allow for collaboration of parties through
the project life cycle in response to changes in clients’ demands and their increased awareness
in construction processes.
Time, cost and quality achieved at the completion of construction projects are the most
evaluation of performance relative to a defined goal (Ali & Rahmat, 2010). They further point
out as noted by Atkinson (1999), the three components of project performance as the “iron
triangle’.
Time overrun is more often referred to as delay defined as time beyond completion date set for
a contract at inception stage (Gamil & Rahman, 2017). It is classified among the most occurrent
problems in the construction industry causing adverse effects on positive project performance.
The concept of cost overrun on the other hand in the construction industry means that a project
failed to achieve its financial objectives by exceeding the contract sum and causing disputes
and litigation which might cause failure and suspension if not an abandonment of a project
Mbatha (1986) in research on government project performance found that 73 percent and 39
percent had time and cost overruns respectively showing that time performance was poorer. A
more recent study reveals that only seven of Africa’s top 20 projects under construction are
17
cost on average 14 percent more than the initial cost estimates taking approximately 188
percent longer to complete. Only 25 percent of projects in Ghana were completed on time and
within budget. In Kenya, approximately 48 percent of projects report a cost overrun and 87
percent have a time overrun (Okowa, 2018). He further proceeds to quote the reasons why time
and cost overruns are still a major challenge identifying reasons among them being poor front-
definition of contracting strategy, structuring of the project team and management of the
professional team. All problems whose occurrence and recurrence in a similar pattern in
The construction industry of Malaysia has had a number of problems delivering quality projects
on time due to the multitude of occupations, professions, and organizations (Ali, 2009). Njenga
(2014) seconds that the construction industry generally has complexities in its nature
stakeholders, etc.
With these statistics on project performance from various zones worldwide, it can be identified
that delivery of projects with specific regard to the achievement of the basic implementation
objectives of time cost and quality is still greatly wanting. A significant percentage of projects
in different countries within Africa have and still experience time and cost overruns and the
trend unfortunately continues. It is in fact so rampant, especially with government projects, that
even some of the local developers and professionals, if not majority, in the construction
industry are per se already borderline complacent with that fact which should not be the case
(Okowa, 2018).
18
2.2.5. Miscommunication and Informational conflicts in the construction industry
The construction industry is a competitive and complex environment with participants different
of talent, specialization, and skills working together from various professions; each with their
own goals and expectation to make the most to their benefit. Since these differences, conflicts
are inevitable and if not properly managed turn into disputes, which are among the main factors
preventing successful project completion in the industry (Cakmak & Cakmak, 2013). Yiu and
Cheung (2006) and as cited by Mitkus & Mitkus (2013) stated that conflicts are sometimes
inevitable in the construction industry due to the high differences in interests among
participants.
Today the products of the construction industry have become more complex in nature and with
that more competitive. Furthermore, the multidisciplinary nature of the industry also leading
to more avenues for conflicts among parties. This makes delivery thus a process in which
disputes virtually ensue. In a single project, there are the following participants as identified by
Muriithi (2006):
The client/employer/promoter
The client is the potential owner of the facility. They develop/identify the need for a facility
and therefore initiate the project process. Clients sponsor, through financing, the construction
The consultants
Since most especially private or institutional clients of the construction industry lack skills
necessary to run construction and specialized departments in their organization, they have to
hire services of professionals to help interpret their requirements. These professionals mainly
19
The contractors
These are the construction companies in charge of the execution of works. From a functional
angle classified into building contractors, civil engineering contractors, specialist service
minor construction works of all kind. Depending on their past performances, financial position
and capabilities to handle works, they are categorized by various government bodies into
workload capacity divisions e.g. category 1 to 7 of the NCA for the purposes of contract
awards.
With regard to projects, Taleb.et.al, (2017) cite that Fox (2001) listed lack of face-to-face
meetings, depending on the formal methods not performing enough informal communication
and unclear structures of communication that do not determine how communication takes place
as some of the obstructions to communication. They further cite that Flicker (2002) claimed
that sometimes in projects, goals, and outcomes lack proper setting through unrealistic work
completion durations being scheduled, variations that inconvenience planning and demand
communication, public interruption, payments, etc. This could give rise to problems including
cost overruns, delay, damage in business relationships, reduced productivity and loss of profit
(Khahro & Ali, 2014). They further point out that conflicts and dispute in construction projects
Chini and Valdez (2003) argue that many claims, disputes, delays, cost and time overruns,
reworks and variations; generally, conflicts can be traced back to errors and clashes in design,
poor administration of contracts, and lax supervision. Ali (2009) further reveals that there are
many reasons including closures and design changes affecting project performance. Others
20
include inappropriate participants, poor management and leadership, poor relations and
and each department in the organization mandated with disseminating their related information
to formulate completeness in the systems. The complex nature of the industry, however, causes
several concurrent communication problems since no proper channeling is adopted to run the
communication processes (Gamil & Rahman, 2017). They go ahead to cite Lee and Bernold
(2008) who reported a lack of proper data channels and inaccurate data transfers as serious
diverse in nature as the construction industry. They manifest in various forms resulting in
unnecessary but apparently unavoidable delays especially where meetings have to be carried
out physically to solve occurrences that would otherwise have simply be solved without the
need for a physical convention in a project scenario. These delays often lead to disruption in
the schedule and eventually consequent cost implications. There is thus need for an
investigation into and the establishment of systems that allow faster resolution of such
conflicts. This study sought to assess the influence management of communication and
construction project delivery, as shown below, the framework has 4 independent variables for
21
Figure 2. 1. Theoretical framework
objectives is also linked greatly with organizational procedures and policies as well as the
attitudes towards a shift from the ‘custom’ to aid decision making, management, and efficiency
of processes.
22
2.4. Conceptual framework
The conceptual framework of this research was founded on the relationship and
insight into how effectiveness, efficiency, quality and the conveyance in information and
completion within schedule and budget, quality and client satisfaction. The chart below relates
the independent variables to the dependent variables and was structured to help the research
design aiming to establish from firms in construction, how the independent variable,
The relationship between the variables was conceptualized as in the figure below with the
Source: Author
This study was based on the concept of successful or rather efficient conveyance for the
industry.
23
2.5. Research gap
The literature available identified numerous potential factors that could affect the performance
worldwide.
Although these significant bodies of knowledge exist especially in the project context, extant
review of the literature suggested that there was a lack of examination theoretically and
factors identified with regard to quality communication, information management and attention
on their means of conveyance for delivery by firms and other participants in construction. This
2.6. Summary
Communication and information management form the heart of implemented projects in the
industry of construction where managers consume up to 90% (Taleb H. , et al., 2017) time
communicating with participants in projects. There are however barriers occurrent during these
important processes and they need resolution. They are so important to project success that
they have been referred to as the lifeblood of projects by a significant number of practitioners.
Firms in the industry need to collaborate and integrate information as well as knowledge to
Literature available revealed that poor communication and poor information management as
major factors contributing to delays in the construction industry manifest in the form of slow
information flow, rework, wrong interpretations thus wrong designs, improper communication
24
approach a key connection between parties involved and the relevant information for achieving
25
CHAPTER 3. RESEARCH METHODOLOGY
3.1. Introduction
This chapter provides a systematic description of the research methodology that was used in
acquiring analyzing and synthesizing the study data. The main elements discussed are the
research design, target population, sample and sampling techniques, sampling frame, research
This study adopted a descriptive research design. It involved surveys and fact-finding inquiries
of different kinds; the major purpose being description of the state of affairs as existent at
present. This design was deemed suitable for this study as the researcher in this method has no
control over the variables and can only report what has happened or is happening, it also allows
the researcher to establish causes of given phenomena and situations as in the nature of the
third objective herein, and finally descriptive research design also allows for utilization of
comparative and correlational surveys thus factors such analytics as were introduced in the
study (Kothari, 2004). The design was therefore not solely descriptive but also analytical in
nature.
The research strategy majorly involved the analysis of quantitative data but allowed, though
relatively minimally, for some qualitative analyses as well. A mixed approach was adopted for
this study. Closed-ended questions were used to gather quantitative data while open-ended
26
3.3. Nature and sources of data
The information gathered plays a crucial role in the study. Primary data was the main type of
data considered for use in this study. Secondary data was considered in the analysis where
The target population for this study involved firms in construction dealing with building
construction including Quantity Surveying and Architectural firms within Upper hill, Kilimani,
The following formula, as popularly used in social sciences research was applied, for such a
case of small (referred to as finite) population to calculate the appropriate sample size (Israel,
1992).
𝑧 2 𝑝𝑞𝑁
𝑛=
𝑒 2 (𝑁 − 1) + 𝑧 2 𝑝𝑞
Where:
p is the sample of the population estimated to have the characteristics under consideration
27
q=1-p, the part of the population that lacks the characteristics under consideration
1.962 𝑥0.95𝑋0.05𝑋325
𝑛=
0.052 (325 − 1) + 1.962 𝑥0.95𝑋0.05
𝑛 ≅ 𝟔𝟎
After determination of the sample size, stratified random sampling method was also adopted
in this research. The process of selecting a sample in such a way that the identified subgroups
in the population are represented in the sample in the same proportion they exist in the
population. It allowed for the selection of equal size samples from each of a number of
Strategic random sampling was then used to select the respondents by dividing the study group
population by the sample size to establish a figure ‘k’. From a list of all the members in the
In the study, questionnaires was the main instrument used for data collection and document
review.
28
3.6.1. Questionnaires
A questionnaire was employed in this research as the tool for data collection. The questions
therein were majorly closed-ended; developed to aid respondents make quick decisions and the
researcher easily code the information obtained for ease and accuracy in subsequent analyses.
This was borrowed from argument as by Sekaran (2003). It was drafted with the queries
soliciting the perspectives of the informants regarding the impact of communication and
A reliable instrument is argued to be one that consistently gives similar results when repeatedly
used to collect data from the same sample of a population. Reliability directly relates to the
validity of the measure (Mukiibi, 2017). He further notes that it can be less precise to establish
&Lincoln (2005) that participant checks, peer evaluation (where another party checks the
researcher’s inferences based on the instrument) and multiple methods are however
In this study, this was confirmed in a mock exercise. The degree to which results from the
analysis of data actually represent the phenomena under study is validity (Mugenda &
Mugenda, 2003). Validity refers to the level to which an instrument measures what it is
supposed to measure and performs as it is designed to, to the point the truth reflects in the
results and is often measured in degrees since it is not often for an instrument to be 100 percent
valid. Validity in this study was established by the inclusion of a variety of objective questions
in the questionnaire and consultation from experts to ensure the instrument meets the standard.
Pre-testing for reliability was carried out- as earlier outlined- simultaneous with that to ensure
29
The following procedure was used for data collection:
c) Telephone contact explaining the research and intention to involve the respondents
d) Delivery of the questionnaire by the most appropriate means deemed i.e. physical
delivery or email
e) Respondents were allowed about 5 office days to complete filling the instrument
To ensure the questionnaire employed for this study effectively functioned to capture the data
as intended, a pilot study mocking the data collection process was conducted where a dummy
sample of 20 prequalified respondents without the target sample was used to pretest the
questionnaires before distributing them to the actual respondents. This aimed at checking the
questions for bias and ambiguity so that all were understood equally by all respondents. A
content validity index (CVI) computed by the formula: number of items declared valid divided
by the number of items in the questionnaire was used to test validity as pre-tests progressed.
This was run by administering the instruments to three (3) experts for judgment on the
relevance of each question in providing answers for the study. The questionnaire is declared
acceptable on the achievement of a CVI above 70% (Amin, 2005). This research employed
30
3.8. Methods of data analysis and presentation
Statistical Package for Social Sciences (SPSS) and/or MS Excel package were used in the
analysis of quantitative data. Descriptive statistics of frequency and percentages were used to
analyze respondents’ opinions on the study area. Correlational and comparative surveys were
Quantitative data encountered was analyzed through document review and content analysis,
checked for recurrent issues emergent and relevant in relation to study the questions as well as
Presentation involved the visual display of various findings of the study. For this study, it was
31
CHAPTER 4. DATA ANALYSIS
Quantity Surveying firms. Questionnaires were sent out to equivalent numbers of each out of
which, 17 and 16 responded respectively giving a response rate of 47.22% from the
Architectural firms and 66.67% from Quantity Surveying firms. Thirty-three questionnaires
out of 60 distributed were returned adequately filled, registering a 55% response rate.
According to Mugenda and Mugenda (2003), a response rate of 50% to 60% is adequate for
analysis and reporting. This analysis was based on the questionnaires returned on time.
(%)
Architectural 17 36 47.22
Total 33 60 55.00
Source: Author
From the findings, 30% of the respondents of the research had been in professional service
for at most 5 years, 24% for 6 to 10 years, 18.18% for 11 to 15 years 21 % for 16 to 20 years
and the rest 7% were in professional service for more than 20 years.
32
4.2. Communication and Information Management by Firms in the Construction
Industry
This section sought information on the means of communication used in the construction
industry as well as their levels of usage, management information systems used and the
reasons for their adoption where applicable, management of official and professional
information with focus on production, conveyance and storage, reasons for slow adoption of
technology in the construction industry and finally the influence the construction
Email 33 4.55 5 5 2 3 5
Meetings 33 4.21 4 4 3 2 5
Memo 33 2.88 3 3 3 1 4
Teleconferencing 33 2.33 2 3 4 1 5
Post 33 2.24 2 3 3 1 4
Radio 33 1.61 1 1 3 1 4
Fax 33 1.48 1 1 2 1 3
Source: Author
33
Figure 4. 1. Means of communication, usage levels
Source: Author
From the analysis, it can be deduced that phone calls are the most common means of
communication with the highest mean of 4.79 and modal score of 5 followed closely by E-
mails and meetings with means of 4.55 and 4.21 and modal scores of 5 and 4 respectively; all
falling above frequent use on a scale of 1 to 5 (1- Very rarely, 2- Rarely, 3- Occasionally, 4-
Frequently, 5- Very Frequently). On the other end, fax is the least frequently used with the
lowest mean of 1.48 and a modal score of 1. It is narrowly preceded by radio; both falling
below rare use. There is a significant level of usage of drive linking and social media
applications both tying at a mean of 3.42 while the use of common data environments and
It is worth noting that, phone calls and emails at the top and fax at the bottom-most
respectively, have notably narrow ranges, all within the range of 2 on both and respective
directions of the scale implying strong relationship in the opinions of respondents on their
level of usage.
34
4.2.2. Management Information Systems
system for organization, evaluation and management of departments and/or parties in a firm.
This study sought to establish their level of adoption as well as the general awareness levels
of their existence within firms’ working environments and allowed respondents to indicate in
Yes 12 36.36
No 21 63.64
Source: Author
36% of the respondents concurred with reliance on MIS systems in their organizations.
36%
64%
Yes No
35
The software, as indicated, used by the respondents included:
Primavera 1 33 3.03
Source: Author
Ms. Project is relatively used, with 12% of the respondents indicating to use it followed
closely by Microsoft Office packages at 9 percent. Computer Aided Design tied with
Microsoft SQL servers both with 2 entries at 6% while the rest got one entry each and thus a
score of 3% of the total population. 64% of the respondents indicated that MIS systems were
From the selection of reasons as to why the respondents use Management Information
Systems provided, each scored as follows out of the total number of 33 responses. No extra
36
Table 4. 5. Reasons for use of MIS
Percentage
Source: Author
33% of the respondents cited that the reason their firms employ MIS systems in their projects
is mainly due to requirements by the clients and/or Project Sponsors. 27% indicated
voluntary use, 21% use the systems on a trial basis while 15% were not certain of the reason
why or conditions under which such a system is used. This indicates therefore that it is more
as a result of demand from the clients and project sponsors that firms in the industry will
employ an MIS system for information management and communication than of it being
voluntary.
The research sought the means firms used in the management of their official professional
37
4.2.4.1. Production
Table 4. 6. Production
Percentage
3D printing 0 33 0.00
Source: Author
The study established that the production of information by means of office computer
packages is the most popular with 94% of the respondents relying on it.
Notably, the use of professional software and Architectural Models are also moderately relied
40% still relies on manual drafting with zero adoption of 3D printing which is an example of
38
4.2.4.2. Conveyance
Table 4. 7. Conveyance
Email 31 33 93.94
Poster/Courier 8 33 24.24
Source: Author
Use of emails to convey firms’ professional information and for official communication
scored relatively high at 94%. Following it was conveyance by means of hand delivery at
67% implying a considerable level of popularity slightly over Internet-based link sharing
which scored 58%. Use of common data environments was the least popular at 12%
4.2.4.3. Storage
Table 4. 8. Storage
Source: Author
Based on the findings, the most popular means for storage of data amongst firms in the
industry is the use of computer hard drives at 82%. Filling and shelving follow at 70% and
39
4.2.5. The rate of adoption of New Technology in the construction industry
On a scale of 1 to 5, respondents agreed that there is apathy in the construction industry in the
adoption of new technology despite the availability of better means for communication and
information management to a mean level of 3.45. This shows a slight skew from neutral (3)
in the general opinion towards agreement. The responses ranged from strong disagreement
(1) to strong agreement (5) with a modal score of 4 showing wide variations in the opinions
of the respondents on the subject matter but with the majority in agreement.
33 3.45 4 4 4 1 5
Source: Author
45
40
35
30
25
20
15
10
5
0
Strongly
Disagree Neutral Agree Strongly Agree
Disagree
Percent 12 6 24 39 18
Percent
40
On aggregate 57% of the respondents were in agreement, 24% neutral while 18% disagreed
with the argument in question. This implies a higher level of agreement among the
Some of the reasons for the slow uptake of technology in the construction industry as
• Rigidity in nature of the industry. This makes professionals reluctant to adopt new
means of working.
the importance of adopting new means and the efficiency they present.
technological tools.
• This also includes training of staff and administrative costs also commonly
considered high
• Ignorance
• Some technological advances are too sophisticated thus not much end-user friendly
• The high cost of training and loss of time resources during training
management
41
• Lack of technical know-how and the skills to handle or manipulate upcoming
On a scale of 1 to 5, respondents agreed that the procurement method and standard contract
(if any) adopted is of critical influence to the communication and information management
and project execution to a mean level of 3.88. This shows a significant skew from neutral (3)
in the general opinion towards agreement (4). The responses ranged from disagreement (2) to
strong agreement (5) with a modal score of 4 (Agree). No strong disagreement (1) was
registered.
33 3.88 4 4 3 2 5
Source: Author
35
30
25
20
15
10
5
0
Strongly
disagree Disagree Neutral Agree Strongly Agree
Percent 0 6 30 33 30
Scale
Percent
42
On aggregate 63% of the respondents were in agreement, 30% neutral while 6% disagreed
with the argument in question. This implies a higher level of agreement among the
Total 33 100.00
Source: Author
15%
21%
64%
procurement method is still heavily relied upon, with 64% of the respondents having checked
it as the most common in their projects, in contrast with other methods available; including the
43
methods proved to facilitate the better collaboration of project stakeholders. Integrated
This section sought to investigate on the time and cost performance of construction projects,
94% of the respondents agreed to have encountered overruns in terms of time and cost in at
least one project they were involved in as illustrated in the chart below.
6%
94%
Yes No
The occurrence of time and cost overruns, on a scale of 1 to 5, scored a mean of 3.73
showing an inclination in the general respondents’ opinion to exceed it being occasional (3)
and more closely towards it being frequent (4). The responses ranged from rarely (2) to very
frequently (5) with a modal score of 3 (Occasionally). No score of it is very rare (1) was
registered.
44
It can, therefore, be concluded from these findings that time and cost overruns are a common
33 3.73 4 3 3 2 5
Source: Author
40
35
30
25
20
15
10
5
0
Very
Very rarely Rarely Occasionally Frequently
Frequently
Percent 0 6 36 36 21
Scale
Percent
informational conflicts in at least one project they were involved in as illustrated in the chart
below.
45
9%
91 %
Yes No
exceed it being occasional (3) towards it being frequent (4). The responses ranged from very
It can, therefore, be concluded from these findings that miscommunication and informational
33 3.45 3 3 4 1 5
Source: Author
46
45
40
35
30
25
20
15
10
5
0
Very
Very Rarely Rarely Occassionally Frequently
Frequently
Percent 3 9 39 36 12
Scale
Percent
the most common they had experienced in projects. Each scored as follows out of the total
Distortion 10 33 30.30
Source: Author
Poor definition and representation is the most common cause of informational conflicts in the
construction industry with a percentage score of 79% amongst the total respondents.
47
Significantly higher than the second cause, use of wrong conveyance media at 45%. Human
relational barriers and distortion scored 36% and 30%. Organizational barriers came last at
18%.
performance, quantitative results from data collected were subjected to bivariate correlation
analyses. This was tested on a scale of 0 to ±1 thereby using the Pearson’s Correlation
Coefficient. Correlation of less than 0.3 was considered insignificant, 0.3 to 0.5 correlation
was considered weak while correlation above 0.5 was considered strong (Gogway & Thatte,
2017). The extreme values of r i.e. when r =±1 indicate perfect positive or negative
correlation is borne in the symbol of the value. Positive correlation signifying proportional
to correlation testing, the significance level of the results was also assessed. Correlation was
48
4.5.1. Correlation between the occurrence of time-cost overruns and occurrence of
Two indicators for project performance i.e. cost and time were tested for, while communication
The table 4.15 below shows the results for the test as deduced from SPSS.
Correlations
due to miscommunication
Pearson
N 33
Source: Author
The results show a strong positive and significant relationship between the occurrence of time-
49
4.5.2. Correlation between procurement methods and standard forms adopted versus
The researcher tested for correlation between the influence procurement methods have on
communication and information management and apathy in the adoption of new technology
Table 4. 16. Procurement methods and standard forms vs. slow adoption of new technology
Correlations
management
communication and
N 33
Source: Author
The results show a strong positive and significant relationship (r=0.66, p=0.004).
50
4.5.3. Correlation between the influence of communication and information
The research sought to establish the correlation between agreement with the argument that
Table 4. 17. Influence of communication and information management vs. slow adoption
of new technology
Correlations
performance
N 33
Source: Author
The results show a moderate positive and significant relationship (r=0.46, p=0.022).
51
4.5.4. Correlation between procurement methods and standard forms versus
The research sought to investigate for correlation between the influence various procurement
methods have on communication and information management against the protracted influence
Table 4. 18. Procurement methods and standard forms vs. communication and information
management
Correlations
information management on
project performance
Influence of procurement
contract on communication
N 33
Source: Author
52
CHAPTER 5. SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS
5.1. Introduction
This chapter contains a summary of the findings, the conclusions, and recommendations of the
study based on the objectives. The chapter also presents suggestions for further study on the
study topic.
The main objective of this research was to investigate and analyze the various communication
means and information management systems adopted in the construction industry to study their
level of influence on the performance of projects and the specific objectives were:
iii. to find out the major causes of miscommunication and informational conflicts
From the analyses of this research, the findings established are discussed below:
Industry
There are blurred lines on what Management Information Systems imply thus proving lack of
amongst professional practitioners. For instance, 54% and 94% respectively checked the use
of professional software and Office computer Packages for production of professional and
53
official information whereas only 36% concurred with reliance on MIS systems in their
players on MIS.
In most cases where the modern means of communication and information management are
used, it is more as a result of demand from clients and/or project sponsors than voluntary
adoption thus implying that an increase in awareness on the means available amongst the
with respondents citing reasons of complacency, lack of top-level management initiative, low
technology literacy levels, high installation costs, lack of skills and expertise to optimize
implementation of the new means available, fear of disruption that introduction of new ways
of working would cause, general rigidity of the industry and resistance to change.
There is a distinct break between the production, conveyance, and storage of official and
Whereas the use of Professional software ranked high in the production of information
coming second to the use of office computer packages, its complements under conveyance
(use of CDE) and Storage (cloud-based drives) ranked relatively low being amongst those of
least popularity in their categories thus implying a partial appreciation of modern means of
Informational conflicts due to miscommunication as well as time and cost overruns were seen
The traditional, and highly structured, procurement method is most popular in the industry. A
contributing factor towards slow adoption of the modern and highly integrated means of
54
communication and information management; as the previous is easily compatible with and is
clearly established with the conventional procedures and means of execution. For the sake of
this research, choice of the procurement system and standard forms of contract adopted, if any,
were associated with the final client satisfaction with the project on execution bearing in mind
that the various methods available perform differently when used in various project situations
Quality of professional information produced and conveyed, for the purpose of this study was
pegged on its representation and definition, with regard to clarity of the communication process
to recipient parties. Its poverty was cited as the leading cause of informational conflicts thus
miscommunication.
Other factors however, proved to contribute in significant extents to the occurrence of the
informational conflicts including use of wrong conveyance media, human relation barriers,
indicating general concurrence with that those provided for test in this research as the main
performance
There is a high level of acknowledgment amongst firms in the construction industry that
This can be proven from the tests of correlation done under section 4.5.
It is evident from table 4.15, occurrence of time-cost overruns vs. occurrence of informational
conflicts, that the correlation between the dependent and independent variable for this research
is significantly strong and positive in nature. This implies that, was the independent variable
55
dependent variable (construction project performance within the Kenyan industry) would be
From table 4.16, procurement methods and standard forms vs. slow adoption of new
technology, it can be established that the procurement method and standard forms of contract
adopted for a project significantly influence the means adopted for communication and
information management. The results indicated the conventional procurement method as being
the most preferred for use in the industry. A high level of agreement in the argument that there
is apathy in the adoption of new technology for communication and information management
reinforces the finding and justifies the conclusion that prolonged use of traditional procurement
methods has been a major contributor towards slowed adoption of technology in the industry.
Table 4.17, influence of communication and information management vs. slow adoption of
new technology, establishes that agreement with the argument that information and
slow adoption of technology for the previous. Keen to be noted here, despite there being 91%
influence to project performance, only 57% of the same respondents felt that there is an
apathy in the adoption of new technology for the same in the industry. Taking the difference
in these results, it can, therefore, be concluded that about 34% of the respondents are in
contentment with the status quo due to reasons ranging from ignorance, lack of access to
information and training to fear of change among others as outlined under section 4.2.5.
significantly strong and positive nature as can be deducted from table 4.18, procurement
methods and standard forms vs. communication and information management. 26% (r² %) of
56
5.3. Conclusions
project performance in a significantly strong and positive nature. 32.5% (r² % - table
management.
be influenced by several other factors such as the competence of the project team, the
planning process, stakeholder management etc. In light of the same, the choice of
procurement method has been found to influence the communication and information
of projects.
industry is wanting in terms of execution within time and budget but the professional
efficiency in the face of continuously growing scales, scopes of works, demand for
compromised.
➢ There are blurred lines on what Management Information Systems imply thus proving
57
5.4.Recommendations and additional information
Based on these findings and discussions, the researcher recommends the following:
management techniques used in the Kenyan construction industry. The best method to
communication media suited for various project needs. It is evident there is need for
education amongst stakeholders on new and better means available for information and
need for the initiative to be implemented from the policy and top-level management
aware stakeholders.
Furthermore, the industry should focus on R&D to come up with effective and user/cost
availed where firms can access information on the developments in the construction
➢ Third, the line of communication must be clearly set out from the onset of any project,
interrogated occasionally and critical adjustments made to avoid information loss and
58
care of as the industry is a capital intensive and a major contributor of national
economic growth.
The data storage and recording system adopted is also of much importance for every
communication received and must be friendly in terms of organization for easy access
to past files. It should also guarantee security of information from loss and undue
leakage.
59
5.5.Summary of conclusions and recommendations
Table 5. 1. Summary of conclusions and recommendations
d. To establish the -32.5% of variations in the performance of projects -Research on other factors
influence of in the Kenyan construction industry can be and documentation on their
communication and attributed to variations due to communication and levels of influence on project
information information management performance.
management on -26% variations in performance of projects with -Comparison of findings to
project regard to communication and information aid formulate an ideal project
performance in management attributed to choice of procurement guide.
construction. method
Source: Author
60
5.6.Areas of further studies
Due to the dynamic nature of the construction industry and limitations in research, the
researcher could not comprehensively exhaust on the matters associated with the influence of
across areas he thought were and remain to be of great interest to the industry:
With the entry of different races especially Chinese contractors and professionals into the local
industry, there is a need for investigation on the effect this has on the efficiency of
communication, the extent and influences of language barriers as well as the competition.
There is also need for investigation on other factors influencing performance of projects,
establishment of the extents to which they do as well as comparison and means to remedy
61
REFERENCES
Ali, A. S. (1999). Cost Decision Making in Building Maintenance Practices in Malysia. UK:
Emerald.
Ali, A. S., & Rahmat, I. (2010). The Performace Measurement of Construction projects
Press.
Atkin, B., Borgbrant, B., & Joseph, B. (2003). Construction Process Improvement. Blackwell
Science.
Atkinson, R. (1999). Project Control Factors at Front End: Indian Perspective. Surat.
Cakmak, E., & Cakmak, P. I. (2013). An Analysis of causes of disputes in construction industry
Capron, H. L. (2000). Computer: Tools fpr an information age. Upper Saddle River: Addison-
Wesley.
Cherry, C. (1978). A Review, Survey and Criticism on Human Communication. London: MIT
Press.
Chini, A. R., & Valdez, H. E. (2003). ISO 9000 and the U.S Construction Industry. Alexander
Emmitt, S., & Gorse, C. (2003). Construction Communication. Blackwell Publishing Ltd.
62
FIDIC. (1999). Conditions of Contract for Construction for Building and Engineering Works
Gamil, Y., & Rahman, I. A. (2017). Identification of Causes and Effects of Poor
Hall.
Gogway, N. J., & Thatte, U. M. (2017). Principles of correlation analysis. Journal of The
Gwaya, A. O. (2016). Course Notes for Research Methodology. Juja, Kenya: Jomo Kenyatta
Harris, V. (2018). Think of BIM as a value creator not a cost factor. East African Digital
of Twente.
Hoezen, M., & Reymen, I. (2006, January). The Problem of Communication in construction.
Howard, H. C., Levit , R. E., Paulson , B. E., Pohl, J. G., & Tatum, C. B. (1989). Computer
63
Kajewski, S., & Weippert, A. (2004). E-Tendering benefits, Challenges and Recommendations
Khahro, S. H., & Ali, T. H. (2014). Causes leading to conflicts in the construction projects.
KNBS. (2018). Economic Survey 2018. Nairobi, Kenya: Kenya National Bureau of
Statistics(KNBS).
Kothari, C. R. (2004). Research Methodology Methods & Techniques. Daryaganj, New Delhi:
Lenard, D., & Eckersley, Y. (1997). Driving Innovation; The role of client and the contractor.
Luka, G. T., Patricia , O. )., & Muhammad, S. I. (2014). Evaluating the effects of
Maritz, W. (2018). Navigating the future of projects. Leveraging digital technology to improve
the delivery success of your capital and infrastructure projects. East African Digital
Matheu, N. F. (2005). Life Cycle Document Management System for Construction. Univesitat
Politecnica de Catalunya.
64
Mitkus, S., & Mitkus, T. (2013). Causes of Conflict in a Construction Industry; A
Mugenda, O., & Mugenda, A. (2003). Research Methods; Qualitative and Qualitative
University.
of Nairobi.
University of Nairobi.
Okowa, N. (2018). How to Manage a mega project in East Africa. The Big 5 Construct East
65
Omulo, E. (2008). Investigation on effective communication management systems on
Samelton, & Levitt, M. (1993). Construction Safety Management. New York: John Wiley and
Sons Inc.
Sekaran, U. (2003). Research Methods for Business. Carbondale, Illinois: John Wiley & Sons.
Industry. Mumbai.
Sunday, D. O., & Afolarin, A. O. (2013). Causes, effects and remedies of errors in Nigerian
676-686.
Technological university.
Taleb, H., Ismail, S., Wahab, M. H., Mardiah, W. N., Rani, W. M., & Amat, R. C. (2017). An
Taleb, H., Ismail, S., Wahab, M. H., Rani, W. N., & Amat, R. C. (2017). An Overview of
Technologi Malysia.
UNRWA. (2000). United Nations Relief and Works Agency for Palestine Refugees in the Near
66
Victor, O. (2017). Primary Sources of Data and Secondary Sources of Data. Advance Statistical
Yiu, T. W., & Cheung, S. O. (2006). Are Construction Disputes Inevitable? City University of
Hong Kong.
67
APPENDICES
Appendix I. QUESTIONNAIRE
Research Title: “An Investigation into the Impact of Communication and Information
Dear Respondent,
between the various means applied and performance of construction projects in Kenya. The
purpose of this study is purely academic and the information given will be treated with the
highest degree of confidence. You have been selected as a respondent for this study. Kindly,
Thank you,
68
69
SECTION A: Preliminary Information
1. Title
surveyor
70
From sections B to D, tick or circle the answers that best indicates your opinion on the
question.
industry
3. On the scale provided, describe how much you rely on the following means for
(5) (1)
a) Emails
b) Radio
c) Fax
d) Post
e) Memorandums
f) Phone calls
g) Teleconferencing
h) Common Data
Environments
sharing
j) Social
applications
k) Meetings
71
4. Do you rely on any management information systems (computer-based systems for
organization or projects?
Yes No
a. Required by client
c. Used voluntarily
72
7. Which means do you use for production and management of official professional
information?
Tick all appropriate under each column. Any other may be stated in spaces thereunder
8. There’s apathy in the construction industry with regard to the adoption of new technology
(5) (1)
73
10. Which is the most common method of construction project procurement you have
a) Traditional (D.B.B)
c) Management-oriented methods
11. “Of critical influence to the communication and information management at the project
level is the procurement method and standard forms of contract (if any) adopted.”
(5) (1)
12. Have you encountered cost and/or time overruns in any project you were involved in?
Yes No
13. How would you rate the occurrence of time and/or cost overruns in projects within the
construction industry?
(5) (1)
74
14. How much do you agree with that communication and information management has an
(5) (1)
15. Have you experienced miscommunication that led to informational conflict in a project(s)?
Yes No
16. How would you rate the occurrence of informational conflicts due to miscommunication in
(5) (1)
17. What are the most common causes of miscommunication you have experienced in your
projects?
b) Distortion
d) Organizational barriers
75
e) Human relation barriers
f) Other
18. Any additional information to aid the research may be given hereunder.
76
Appendix II. RAW DATA
No. Q1. Q2. Q3. Q4.
Email Radio Fax Post Memorandums
Phone calls
Teleconferencing
CDE Drive Social
and link
media
Meetings
sharing
applications
1 QS 16-20 years 5 1 1 3 3 5 3 1 1 3 5 No
2 Arch. <5 5 2 1 1 4 5 2 3 5 4 5 No
4 QS 5-10 years 5 1 3 3 4 5 3 4 3 3 4 No
5 Arch. 16-20 years 4 2 1 3 2 5 3 3 3 3 4 No
6 Arch. <5 4 2 2 2 2 5 1 1 3 3 4 No
9 QS <5 5 1 3 3 4 5 3 4 3 3 4 No
13 Arch. <5 4 2 2 3 3 5 2 2 4 4 4 No
15 QS <5 5 1 1 2 3 5 3 4 4 2 5 No
16 Arch. 11-15 years 4 2 3 3 4 5 2 3 3 5 3 Yes
77
No. Q1. Q2. Q3. Q4.
24 QS <5 5 1 1 4 3 5 3 5 5 5 4 Yes
26 QS <5 5 1 1 1 1 5 2 5 5 5 5 Yes
27 QS 11-15 years 5 1 1 3 3 4 3 3 3 3 5 No
28 QS 5-10 years 5 1 1 1 3 5 1 1 5 5 5 No
29 QS >20 4 3 1 1 3 5 3 3 1 4 3 Yes
30 Arch. <5 5 1 1 2 4 5 3 1 5 2 4 No
31 QS 5-10 years 5 1 1 1 1 5 5 4 5 5 5 No
32 QS >20 5 1 1 2 2 4 3 3 1 3 2 No
78
No. Q5. Q6.
.
12 NA Used voluntarily
79
No. Q5. Q6.
80
No. Q7.
. Production Conveyance Storage
Email;Hand Filing and shelfing;Computer hard
1 Office computer packages delivery;Poster/courier services drives
Office computer
packages;Professional Email;Internet based link Filing and shelfing;Computer hard
2 software;Manual drafting sharing;Hand delivery drives;Cloud-based drives
Office computer
packages;Professional Computer hard drives;Cloud-based
3 software;Manual drafting Email;Internet based link sharing drives
Office computer
packages;Professional Filing and shelfing;Computer hard
4 software;Manual drafting Email;Hand delivery drives;Cloud-based drives
5 Office computer packages Email Computer hard drives
6 Professional software Email Cloud-based drives
Office computer
packages;Professional Filing and shelfing;Computer hard
8 software;Manual drafting Email;Hand delivery drives;Cloud-based drives
Office computer Email;Internet based link
packages;Professional sharing;Hand Filing and shelfing;Computer hard
9 software;Manual drafting delivery;Poster/courier services drives;Cloud-based drives
81
No. Q7.
Office computer packages;Manual Internet based link sharing;Hand Filing and shelfing;Computer hard
33 drafting;Architectural modelling delivery drives
82
No. Q8. Q9.
. If in in
There's apathy agreement above, what
the construction do you
industry think
with are to
regard theadoption
reasons?of new technology in communication and inform
The construction industry is very rigid in nature making industry professionals reluctant to
1 4 adopting new methods.
2 3 N/A
9 3 Most construction firms are adopting emerging technology needs while others are conservative
Poor top management
10 4 Lack of a support team in the industry
11 4 Cost of acquisition
12 4 Majority don't understand the major merits over the normal systems
13 2 N/A
15 4 Slow adaptation
16 4 Insufficient awareness in proper methods of technology and information management
People are resistant to change, some are not user friendly hence sophisticated to be understood by
17 4 the client
18 3 N/A
83
No. Q8. Q9.
Lack of technical knowhow on the best technology to use, required skill set and also software
23 5 pricing
24 1 N/A
26 2 N/A
27 3 No education on technology
28 1 N/A
31 1 N/A
33 1 Fear of change
84
No. Q10. Q11. Q12. Q13. Q14. Q15. Q16.
.
85
No. Q10. Q11. Q12. Q13. Q14. Q15. Q16.
86
No. Q17.
.
1 Organizational barriers
87
No. Q17.
30 Organizational barriers
88
No. Q18.
.
1 N/A
2 N/A
3 N/A
4 N/A
5 N/A
6 N/A
7 N/A
The best method to improve communication in the industry is to create awareness on the importance of
proper communication medium suited for project needs. Furthermore, the industry should focus on R&D to
8 come up on the effective and cost friendly softwares to solve the issues of unaffordability of the softwares.
9 N/A
10 N/A
11 N/A
12 N/A
13 N/A
14 N/A
15 N/A
16 N/A
17 Compare working with different races, language barrier becomes a huge challenge. Exemplify on this....
18 N/A
19 N/A
20 N/A
21 N/A
22 N/A
89
No. Q18.
The line of communication must be clearly set out at the onset of any project.
It must be interrogated occasionally and critical adjustments made to avoid information loss and conflicts.
Data storage system is of most important for every communication recieved and must be friendly in terms
23 of easy access to past instructions filings.
24 N/A
25 N/A
26 N/A
There is need for education to all parties in the construction industry on the use of technologies to ease
27 communication and project planning
28 N/A
29 N/A
30 N/A
31 N/A
32 N/A
33 N/A
90