66 12.0 Measurement and Valuation 12.1 Works to be Measured (New provision)
When Engineer and the Contractor unable to agree the
measurement, the Contractor shall give a Notice to the Engineer setting out the reasons and the Engineer shall:
• agree or determine the measurement the same under
Sub-Clause 3.7 [Agreement or Determination].
• Until such time as the measurement is agreed or
determined, the Engineer shall assess a provisional measurement for the purposes of Interim Payment Certificates. 67 12.0 Measurement and Valuation
12.3 Valuation of Works
(New provision)
When Engineer and the Contractor are unable to agree the
measurement/are unable to agree the appropriate rate or price, then the Contractor shall give a Notice to the Engineer setting out the reasons and the Engineer shall:
• agree or determine the measurement the same under Sub-
Clause 3.7 [Agreement or Determination].
• Until such time as the measurement/appropriate rate or
price, is agreed or determined, the Engineer shall assess a provisional measurement for the purposes of Interim Payment Certificates.