12.0 Measurement and Valuation
12.1 Works to be Measured
(New provision)

When Engineer and the Contractor unable to agree the


measurement, the Contractor shall give a Notice to the
Engineer setting out the reasons and the Engineer shall:

• agree or determine the measurement the same under


Sub-Clause 3.7 [Agreement or Determination].

• Until such time as the measurement is agreed or


determined, the Engineer shall assess a provisional
measurement for the purposes of Interim Payment
Certificates.
67
12.0 Measurement and Valuation

12.3 Valuation of Works


(New provision)

When Engineer and the Contractor are unable to agree the


measurement/are unable to agree the appropriate rate or price,
then the Contractor shall give a Notice to the Engineer setting out the
reasons and the Engineer shall:

• agree or determine the measurement the same under Sub-


Clause 3.7 [Agreement or Determination].

• Until such time as the measurement/appropriate rate or


price, is agreed or determined, the Engineer shall assess a
provisional measurement for the purposes of Interim Payment
Certificates.