Overall Equipment Effectiveness Calculator

Enter Date / Time Period / Equipment


Period/Equipment

Time A Total Time Available 480 minutes

B Scheduled Downtime 0 minutes

C Unscheduled Downtime 70 minutes

D Operating Time (A-B-C) 61 minutes

Availability Rate = D/(A-B) 12.72%

E Total Production 268 pieces

F Ideal Run/Cycle Time 4.39 pieces per minute

Performance Rate = (E/D)/F 100.00%

G Reject/Scrap Produced 0 pieces

Quality Rate = (E-G)/E 100.00%

OEE Availability Rate Performance Rate Quality Rate

12.72% 12.72% 100.00% 100.00%