ELECTRICAL WORKS

DB Load
DESIGN CALCULATIONS - PHASE III - ELEVATED STATION - LINE 8

Project DMRC LINE 8 STATIONS - HAUZ KHAS

Title Load Sheet - Final Distribution Board

Date 19.11.2012
Revision - 1 : As per revised Architectural drawings
Revison 2 - 26.09.2012

Undercroft
S. No. Description LOAD Intermediate 1 & Platform Area Intermediate 2 & 3 Concourse Area Ancillary Building
Area

per unit (W)

SPDB-13

SPDB-14

SPDB-10

SPDB-15

SPDB-16

SPDB-17

UDB-AB
LDB-AB
ADDB-2

ADDB-4

ADDB-3
UDB-10

UDB-15

UDB-16

UDB-17
SPDB-1

SPDB-6

SPDB-7

SPDB-2

SPDB-3

SPDB-4

SPDB-5

SPDB-8

SPDB-9

LDB-10

LDB-15

LDB-16

LDB-17
UDB-1

UDB-6

UDB-7

UDB-2

UDB-3

UDB-4

UDB-5

UDB-8

UDB-9
LDB-1

LDB-6

LDB-7

LDB-2

LDB-3

LDB-4

LDB-5

LDB-8

LDB-9
A SOCKETS & SWITCHES
1 32A Industrial Socket Outlet 2,500 3 1 1 1 1 1 1 1
2 16A Industrial Socket Outlet 1,000 1 2 2 2 1 2
3 20A Industrial Socket Outlet 1,500
4 6/16A universal socket with Moduler Switch 500 1 1 9 1 1 9 2 3 1 1 4 4 43 21 3
5 Advertisement Point 1,500 10 10 27

Power Load/DB 9.00 5.00 0.00 0.00 6.50 0.00 0.00 0.50 15.00 0.00 0.00 0.50 15.00 0.00 0.00 6.50 0.00 0.00 3.50 0.00 0.00 4.00 0.00 0.00 0.50 0.00 0.00 0.50 0.00 0.00 4.50 0.00 0.00 4.50 0.00 0.00 25.00 0.00 0.00 15.00 0.00 0.00 1.50 40.50 0.00 0.00

B LIGHTING FIXTURES

1 1x36W FTL Fixture 40 40 20 160 56 168 52 40 19 24 10 23 9 13 7 14 5 13 7 13 7 87 31 22 11 94 31 3 3


2 2x36W FTL Fixture 80 9 11 6 2 6 2 9 10 29 10 29 9 8 3 7 2 26 7 24 8 88 32 40 14 158 47 15 6
3 4x18W FTL Fixture 80
4 2x18W FTL Fixture 40 2 6 3 3
5 9W CFL Fixture 15 1 1 1 1 1 1 1 1
6 250W Fixture 275 19 6 19 6 2 1
7 1x70W CDM-ET Fixture 85
8 1x150W SON-T on 1.6M GI Pipe at Piers 165
9 1x150W SON-T on 9.0M Pole single arm 165
10 1x150W SON-T on 9.0M Pole Double arm 165

Lighting Load/DB 0.00 0.00 2.32 1.68 0.00 6.88 2.42 0.00 0.00 7.20 2.26 0.00 0.00 2.32 1.56 0.00 3.28 1.20 0.00 3.24 1.10 0.00 1.16 0.54 0.00 1.12 0.38 0.00 7.83 2.51 0.00 7.67 2.59 0.00 10.60 3.82 0.00 4.32 1.68 0.00 16.52 5.00 0.00 0.00 1.87 0.88

Confidential Page...1 October 2012


ELECTRICAL WORKS
DB Load
DESIGN CALCULATIONS - PHASE III - ELEVATED STATION - LINE 8

Ancillary Building

SPDB-AB
1
2

6.50

0.00

Confidential Page...2 October 2012