Distance From The Axis: Contract No. H359304 Earthworks - Valley Beneficiation Plant and Railway Station Storage

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

MESURES DE DENSITE EN PLACE au DENSITOMETRE A MEMBRANE GA-LABO-R4-F27-V0

In situ density measurements with a membrane densitometer

#N/A NF P 94-061-2 5/14/2019

Contract No. H359304 Earthworks - Valley Beneficiation Plant and Railway Station Storage

Works Compaction 1st Layer Pk176 - 178 Material Pisolite


Part of Works South Road Zone PK173- PK178 Proctor OPM

Date of set up 8/13/2020 Reception Date 8/13/2020 Dry Density (t/m3): 1.76
Implementation workshop Hydro-Compacting Reception Hour 14h00 Moisture Content (%): 20.00
Compactor: CA512 Number of pass 6 Speed Specific Weight (t/m3): 2.74

MEASUREMENT POINT 1 2

Zone No PK173 PK178


Distance from the axis

MEASUREMENT

1st Reading (V0) 145.0 146

2nd Reading (V1) 2620.0 2610

Volume of the hole V = (V1-V0) 2475.0 2464

Hole depth 15.0 15.0

Weight of wet material WW 4890.0 4900.0

Wet density WD = WW/V 1.975 1.988


###
MOISTURE CONTENT

Tare Number A1 A2

Wet material weight + tare WeWt g 635 638

Dry material weight + tare DWt g 588 592

Tare weight g 370 370

Dry material weight DW 218 222

Weight of water WWa = WeWt - DWt 47 46

Moisture Content W = (WWa x 100)/DW 21.50 20.7

Means Moisture Content % 21.50 20.7


Dry density DD (WD x 100) / (100 +
w)
t/m3 1,626 1.647
Compactness C1 = (DD*100) / DDOPM % 95.0 96.3
Layer Thickness after survey cm

Laboratory Technician Laboratory Manager Engineer HATCH COMILOG