Professional Documents
Culture Documents
Practice Questions: Project Cost Management 107
Practice Questions: Project Cost Management 107
Practice Questions: Project Cost Management 107
Practice Questions
INSTRUCTIONS: Note the most suitable answer or
each multiple-choice question in the appropriate
space on the answer sheet.
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
12. When you review cost per ormance data on your project,
di erent responses will be required depending on
the degree o variance or control thresholds rom the
baseline. For example, a variance o 10 percent might
not require immediate action, whereas a variance o
100 percent will require investigation. A description
o how you plan to manage cost variances should be
included in the—
a. Cost management plan
b. Change management plan
c. Per ormance measurement plan
d. Variance management plan
Project Cost Management ◾ 111
17. You receive a rantic phone call rom your vice president
who says she is going to meet with a prospective client
in 15 minutes to discuss a large and complex project. She
asks you how much the project will cost. You quickly
think o some similar past projects, actor in a ew
unknowns, and give her a number. What type o estimate
did you just provide?
a. De nitive
b. Budget
c. Order-o -magnitude
d. Detailed
23. Your project manager has requested that you provide him
with a orecast o project costs or the next 12 months.
He needs this in ormation to determine i the budget
should be increased or decreased on this major construc-
tion project. In addition to the usual in ormation sources,
which o the ollowing should you also consider?
a. Cost estimates rom similar projects
b. WBS
c. Project schedule
d. Costs that have been authorized and incurred
114 ◾ PMP® Exam Practice Test and Study Guide
36. Assume that the project cost estimates have been pre-
pared or each activity and the basis o these estimates
has been determined. Now, as the project manager or
your nutrition awareness program in your hospital, you
are preparing your budget. Because you have estimates
or more than 1,200 separate activities, you have decided
to rst—
a. Aggregate these estimates by work packages
b. Aggregate these estimates by control accounts to
acilitate the use o earned value management
c. Use the results o previous projects to predict total costs
d. Set your cost per ormance baseline
118 ◾ PMP® Exam Practice Test and Study Guide
38. The reason that the cost per ormance index (CPI) is
shown as a ratio is to—
a. Enable a detailed analysis o the schedule regardless o
the value o the schedule variance
b. Distinguish between critical path and noncritical path
work packages
c. Provide the ability to show per ormance or a speci ed
time period or trend analysis
d. Measure the actual time to complete the project
39. Assume that your actual costs are $800; your planned
value is $1,200; and your earned value is $1,000. Based
on these data, what can be determined regarding your
schedule variance?
a. At +$200, the situation is avorable as physical progress
is being accomplished ahead o your plan.
b. At –$200, the physical progress is being accomplished
at a slower rate than is planned, indicating an un avor-
able situation.
c. At +$400, the situation is avorable as physical progress is
being accomplished at a lower cost than was orecasted.
d. At –$200, you have a behind-schedule condition, and
your critical path has slipped.
Project Cost Management ◾ 119
40. The CPI on your project is 0.84. This means that you
should—
a. Place emphasis on improving the timeliness o the
physical progress
b. Reassess the li e-cycle costs o your product, including
the length o the li e-cycle phase
c. Recognize that your original estimates were undamen-
tally fawed, and your project is in an atypical situation
d. Place emphasis on improving the productivity by
which work was being per ormed