Professional Documents
Culture Documents
ITER CAD Manual Section 4.5 - Plant Design Processes: ITER - D - 33PE8P v. 1.1
ITER CAD Manual Section 4.5 - Plant Design Processes: ITER - D - 33PE8P v. 1.1
ITER CAD Manual Section 4.5 - Plant Design Processes: ITER - D - 33PE8P v. 1.1
Abstract
Major Changes
Table of Contents
List of Figures
Figure 4.5-1 SOP, South and West plane in the SITE_LAYOUT_PRC ______________ 8
Figure 4.5-2 AXIS_SOP in the SITE_LAYOUT_PRC ___________________________ 8
Figure 4.5-3 Reference part ________________________________________________ 9
Figure 4.5-4 Instance of the SITE_MASTER_ISKE ____________________________ 10
Figure 4.5-5 Plant system reference part _____________________________________ 11
Figure 4.5-6 Example of structure __________________________________________ 12
Figure 4.5-7 Example of Segmentation at Level B2 ____________________________ 13
Figure 4.5-8 Floor interface – Elevation _____________________________________ 14
Figure 4.5-9 Floor interface – Plan__________________________________________ 15
Figure 4.5-10 Building interface ____________________________________________ 15
Figure 4.5-11 Interface skeleton work package _________________________________ 16
Figure 4.5-12 Typed interface part ___________________________________________ 16
Figure 4.5-13 Example of plant design showing the systems inside a building
level _______________________________________________________ 17
Figure 4.5-14 Disciplines and CATIA modules_________________________________ 19
Figure 4.5-15 Overall plant design process ____________________________________ 20
Figure 4.5-16 Mapping of design phases and level of detail in the design ____________ 21
Figure 4.5-17 Functional reference to identify components _______________________ 22
Figure 4.5-18 Functional reference of an object in a diagram ______________________ 22
Figure 4.5-19 Functional reference in ITER properties panel ______________________ 23
Figure 4.5-20 2D-3D checker principle _______________________________________ 24
Figure 4.5-21 2D-3D checker process ________________________________________ 24
Figure 4.5-22 Explicit path to launch workbenches used in ITER___________________ 25
Figure 4.5-23 SITE_MASTER_SKELETON __________________________________ 26
Figure 4.5-24 Example for Building 61 PRC___________________________________ 27
Figure 4.5-25 TGCS origin and surrounding building ____________________________ 27
Figure 4.5-26 Building PRC________________________________________________ 27
Figure 4.5-27 Example of trenches between buildings ___________________________ 27
Figure 4.5-28 ITER properties panel _________________________________________ 27
Figure 4.5-29 Functional reference in SSD ____________________________________ 27
Figure 4.5-30 Functional reference in CATIA V5 _______________________________ 27
Figure 4.5-31 Do not use CNEXT PRM ______________________________________ 27
Figure 4.5-32 Use ITER PRM ______________________________________________ 27
Figure 4.5-33 Systematic PBS 1 number (76) for standard catalogue part ____________ 27
Figure 4.5-34 Example of the PBS 1 number for a parametric part. _________________ 27
Figure 4.5-35 No star connection allowed. ____________________________________ 27
Figure 4.5-36 Analyzing Cross document connection on some trenches _____________ 27
Figure 4.5-37 CATDUA tool _______________________________________________ 27
Figure 4.5-38 Use the resize function to change the nominal diameter. ______________ 27
Figure 4.5-39 Product tree position of mechanical interface skeleton ________________ 27
Figure 4.5-40 Mechanical interface geometry __________________________________ 27
Figure 4.5-41 Interface part plant design ______________________________________ 27
Figure 4.5-42 Skeleton grid ________________________________________________ 27
Figure 4.5-43 Planes to be defined in skeleton grid ______________________________ 27
Figure 4.5-44 Level skeleton _______________________________________________ 27
Figure 4.5-45 Building product structure ______________________________________ 27
Figure 4.5-46 Building interface assembly ____________________________________ 27
Figure 4.5-47 Interface walls _______________________________________________ 27
Figure 4.5-48 Structure design elements ______________________________________ 27
List of Tables
Table 4.5-1 The PRC and their origins _______________________________________ 7
Table 4.5-2 Summary origin of plant data ____________________________________ 9
Table 4.5-3 Plant design classification ______________________________________ 18
iv. Allow use of Equipment and system functionality of CATIA like reporting.
We use several PRC to design the plant:
The SITE_MASTER_ISKE contains the TGCS, the Setting-Out Point SOPXX and the axis
systems of the building or area AXIS_SOPXX, a sketch for the outlines of a building or area
and the south and west plane of the building or area, which are published. The south west
corner of the footprint of the building or area is identical with the local origin of the building
or area and their specific PRC and is coincident with the SOP.
The South West corner of the building is designated as the main building, without taking into
account any annex of the same building.
Data Origin
Concrete Building Absolute position=PRC origin=SOP
Steel structure Relative position=column axis
Plant systems Absolute position=PRC origin=SOP
Table 4.5-2 Summary origin of plant data
The instance of the SITE_MASTER_ISKE is positioned with offset constraints with offset 0
in relation to the reference part.
The interface skeleton work packages for plant systems will follow the modification in the
SITE_MASTER_ISKE only in the SITE_LAYOUT PRC to reflect the change.
In TOKAMAK_COMPLEX inside the bio shield the modelling of plant systems is often done
using CATIA V5 Part design instead of the Equipment & System workbench.
The interface location is the bio shield.
The interface geometry is composed of a mechanical CATPart containing a coordinate point
with a mechanical connector to be able to link to the Part design side and the typed interface
part, which position is driven by the coordinate point.
Figure 4.5-13 Example of plant design showing the systems inside a building level
Type Methodology
Plant systems (inside cryostat) Mechanical part design methodology
Plant systems (outside cryostat) Plant design Methodology
Concrete building Mechanical design
Primary Steel structure CATIA SDD (Steel detailed design)
methodology
Secondary Steel structure Stairs and ladders catalogue
Trenches HVAC + interface part
Bridges Space reservation + interface part
Standard equipment (E&S typed parts) CATIA E&S (Equipment & Systems)
catalogue components
Pipes E&S piping
Cables Not modelled in 3D
Cable trays tbd
Bus bar tbd
Opening (hole) E&S parametric part
Penetration (inside opening) tbd
Support tbd
Embedded/anchor plates E&S parametric part
Maintenance volume component specific CAT Shape on E&S catalogue part
Maintenance volume (corridor etc.) Volume created with part design
methodology or space reservation
Table 4.5-3 Plant design classification
E&S functionality of CATIA is used to:
a) Support the plant design process in the different levels of maturity and detail
b) Respect engineering specification definition
c) Allow easy and quick routing of geometry and changes of the rooting
d) Cover different representation like maintenance volume
Frequently
used
disciplines at
ITER
The design phases require different level of detail. In CATIA the level of detail is associated
to 3 kind of geometrical description:
a) Space reservation
b) Equipment and runs
c) Physical parts for details like elbows, gasket ….
Figure 4.5-16 Mapping of design phases and level of detail in the design
The functional references of an object (pump, valve etc.) which will be represented in the 3D
layout have to be transferred manually to the instance description attribute in CATIA. Only if
the correct identification is available in all datasets a complete and congruent definition of the
plant systems can be achieved. The functional reference can be taken directly from the
diagram or from lists.
SSD:
Predefined
Titleblock of
diagram)
• It is very important to name components in the diagram and in the mock up to be able
to identify and manage the components and enable downstream processes.
Rules file
2D 3D Work
2D XML 3D XML
2D – 3D checker
Result
Environment settings
a) Set up your CATIA system environment compliant to ITER standard before you start
any productive work
b) Install ITER CAD supplier package
c) Use the ITER launcher to Launch CATIAV5 with VPM navigator
d) Use an E&S profile when you are designing for plant
e) Use ITER specific PRM
f) Use the appropriate workbench
Frequently
used
disciplines at
ITER
• Each PRC has its own reference part, positioning the PRC on the site through the
SITE_MASTER_ISKE
• TOKAMAK COMPLEX, BLDG 13, 15 and 17 are exceptions and has all the same
origin: TGCS. Building 13, 15 and 17 PRC shall have the origin and SOP coincident
with the TGCS (TOKAMAK origin). Because there is a strong relation between
building 13 and TOKAMAK, the Building 13 origin will not move because it has to
be aligned with TOKAMAK, there are also strong relation between building 15, 13
and 17. All plant systems for these buildings shall have the origin and SOP coincident
in the TGCS (TOKAMAK origin).
• For equipment and systems inside a Building, design it in the corresponding building
PRC and position all E&S relatively to the building PRC origin (south west corner of
the upper slab floor). ALL Plant equipment and systems even those relatives to the
building structure (like HVAC) will use the south/west corner as local origin.
Attributes
• Exclusively use the ITER properties panel to fill attributes.
• Respect the numbering system (functional reference) see plant design process chapter
for more information.
• Nominal size of runs are pre defined size and compliant with IO standards, use IO
Line ID not Dassault system default catalogues CNEXT
ENOVIA/Structure
• All subsystem should be design in only one WP, if not possible split it using the room
definition and the cross doc connection methodology.
Figure 4.5-33 Systematic PBS 1 number (76) for standard catalogue part
• The (part version) PBS for parametric parts is the system PBS (unique reference).
https://user.iter.org/?uid=2ENP3R
CEx13 Plant Interface Methodology between BLDG (2ENP3R)
• Use the Trenches methodology to route and ensure the position of trenches openings
on buildings.
https://user.iter.org/?uid=2N56BJ
HOW TO route a trench network (2N56BJ)
2D CATIA drawings
• Use plant standard in CATIA to generate 2D drawings
• Rules to avoid ghost links
o Never lock a view - it WILL retain links to older, possibly obsolete models
• Use the Resize function instead of the section in the definition dialog box for a run to
modify the nominal diameter. The section button can be exceptionally used to
simulate the insulation on a run.
Figure 4.5-38 Use the resize function to change the nominal diameter.
methodology like ribs. The first part of the routing belongs to the specific system. To handle
the interface a specific methodology is defined.
C14_Interface_Mechanical_Plant (2F6MSU)
4.5.3.3.2 Granularity
The granularity is defined by the FLOOR LEVEL. For each level a corresponding Structure
Exposed Assembly will be defined.
This CATProduct defines the whole design for a particular Building Level (example
BLDG_11_B2).
• Only 1 CATProduct per Building Level
• It shall contain only 1 CONCRETE WP
• Level definition is:
o Bi for Basement Levels (below Floor Level 0, B1 is the first Basement Level)
o Li for Floor Levels (L1 for Floor Level 0)
o Ri for Roof Level (only one Roof Level per building, so R1)
Some Building Complexes are made of several adjacent Buildings sharing common walls;
these walls are called Interface Walls.
• It shall be saved in Structure Exposed mode in ENOVIA LCA.
• Interface Walls are included into the Master Building (In the Tokamak building for
example), and will be only instantiated into secondary buildings (Diagnostic and
Tritium for example).
• It shall contain only 1 CONCRETE INTERFACE WP.
Columns Interface
Ceiling Plane (Level N) Floor (Level N+1) (Level N+1)
Column (Level N)
Beam primary
(Level N+1)
Wall (Level N)
Beam
secondary
(Level N+1)
Floor Plane (Level N) Floor (Level N)
Beam (Level N)
a Column CATPart:
i First elements to be created.
ii Designed on a sketch and extruded from (Li) Level Floor Plane up to the (Li)
Ceiling Plane.
iii Width and Length of column sections are valued with sketch constraints
(offsets).
b Floor CATPart
i Designed on a sketch and extruded from the (Li-1) Ceiling Plane and (Li) Floor
Plane.
ii Positioned by:
• surrounding elements, mainly beams
• column profiles of the LEVEL_SKELETON_GRID sketches
e Walls CATPart
i Designed on a sketch and extruded between (Li) Floor Plane and:
• (Li) Beam Primary Plane for a wall matching up with a Primary beam
• (Li) Beam Secondary Plane for a wall matching up with a Secondary beam
ii Linked to the LEVEL_SKELETON_GRID for the x, y positioning.
iii Thickness is valued with sketch constraints.
iv Length is obtained by constraining Wall extremities to Column profiles of the
LEVEL_SKELETON_GRID
WP BLDGXX_STEEL-
s
STRUCTURE
BLDGXX_PRIMARY-STRUCTURE
WP BLDGXX_SECONDARY-
s
STRUCTURE
BLDGXX_SKL-SECONDARY-
STAIRS_DECK-PLATFORM-
STAIRS_DECK-PLATFORM-
CATProduct
CATPart
From the catalogue generated elements contain context/import links because of CATIA
behaviour. Contextual links are not allowed.
To correct this:
• Isolate the link or
• Replace the context/import link by a CCP link
In this workbench the designer will have to organise his routing in a set called reservation
network, see image below:
No detail design using part design or any other mechanical workbench is allowed to design
EnS part or create space reservation/allocation.
Through this link is all available information needed about catalogues part:
https://user.iter.org/?uid=2NBUCZ
User Guide for Plant Design 3D Catalogs (2NBUCZ)
Designers must pay careful attention to the workbench they are using.
Only ITER PRM are allowed
Only ITER Line ID coming from ENOVIA are allowed
The placement of equipment comes first, then the designer routes the run, after he can place
the elbows, tees, reducers, then comes on line components. Gaskets, flanges, welds are
considered as piping part and will be automatically placed when the real physical part will be
placed.
Designers have to understand the difference between a run and the real physical part.
During the preliminary design phase only runs and catalogues part must be in the plant scene;
Real physical parts, gaskets, flanges and welds will come during the detail design.
Figure 4.5-60 Different systems in liquid and gas distribution in the building 61
Regarding the piping run alignment between buildings, a methodology has been put in place
to manage the position of run created in the buildings and the runs created on the site layout.
Interface
Interface Building 2
Building 1
The interface piping part methodology relies on catalogue part, inserted through the place
piping part dialog box.
a First this interface piping part is place to the extremity of a run getting outside a
building.
c Finally the new created work package shall be instantiated in the site layout, and of
course the designer has to take care of the position of this work package in the site
Layout using the “BLDGXX_REF_PART” as it has been created in the Building
PRC
https://user.iter.org/?uid=2ENP3R
CEx13 Plant Interface Methodology between BLDG (2ENP3R)
4.5.3.9 Trenches
The trenches have to be designed with HVAC run, this allows to have a rectangular and use
the same principle as for the interface piping part; the methodology is exactly the same.
Except that the trenches are made in the HVAC design workbench and that a dedicated Line
ID has been created for trenches.
Then trench interface part are inserted using the “place HVAC part” function
4.5.3.10 Bridges
For the bridges no specific standards part or methodology has been defined giving the fact the
bridges can be modified often enough. But to ensure the interface positioning a bridge
interface part can be inserted at each end of the space reservation of any kind of bridge. The
interface can be edited and modified.
The items are placed within the cad data of the plant systems in DO which are the basis and
input information for the development of the Configuration Management Models (CMM)
largely used for the space allocation of the systems and the interfaces with other systems and
the buildings as well as for the Procurement Arrangements with the Domestic Agencies (see
Configuration Management Model (CMM) (2EGQKE). Any modifications on the items e.g.
location and size, must be traceable in ENOVIA.
The manage graphics representation allow the designer to show one or all types of
representation needed (main representation, usage, maintenance)
or
and
To be developed