Itp For Piping QP
Itp For Piping QP
Itp For Piping QP
PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP
Site survey and Contractual Documents Relevent Contractual Documents Drawing Calculations Design Engg:
1.0 Engineering Approved Drawings Standards & Relevent Standards &Requirements. Project Manager H H
Preliminary activities
Drawing approval , Approved Drawings & Approved Drawings & Approved letter of
2.0 ITP approval & Technical - signature on Project Manager H H
documents to start of Specifications Specifications documents
fabrication and installation .
4.0
Shop Fabrication prior to Dimensions, Heat Number Project specification & approved Project specification & Inspection Report QA/QC , H R
cutting of pipe ,Grade, Size&Specs drawings approved drawings Fab:SUPVR
5.2 Visual Inspection 100% Visual inspection on Approved Drawings & Project specification & Inspection Report QA/QC H R
completed weld Weld map approved drawings
ASME.SEC V,NDT
6.0 NDT Radiogrphy Testing 20 % Weld map/ Records / Asper Scope Procedure &Project Test Reports QA/QC H R
for butt weld of Work and Approved Drawings Specification
1 of 4
DANEM ENGINEERING WORKS WLL. INSPECTION TEST PLAN
PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP
7.0 Blasting&Painting
9.0 Shipping
9.1 Shipping to Site Final Review Delivery Note Relevant Document Delivery Note FAB.SUPVR. H R
( Document &Reports ) ,
Accordance with
10.2 Fit-Up Approved WPS,Check weld Fit Approved Drawings approved WPS and Inspection Report QA/QC , H R
up asper WPS project spec Fab:SUPVR
10.5 Alignment Alignment Check of all As per approved drawings As per approved drawings Inspection Report QA/QC H R
Flanges and Project Spec.
2 of 4
DANEM ENGINEERING WORKS WLL. INSPECTION TEST PLAN
PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP
10.7 Alignment Alignment Check of all valves As per approved drawings As per approved drawings Inspection Report QA/QC H R
and Project Spec.
10.9 Overall dimension Overall dimension check As per approved drawings As per approved drawings Inspection Report QA/QC H R
and Project Spec.
10.11 Visual Inspection 100% Visual inspection on Approved Drawings Weld map As per approved drawings Inspection Report QA/QC H R
completed weld and Project Spec.
Hydro Test Hydro Test of Piping Weld map /Records / Asper Scope App. Drawing &Project Test Report QA/QC H H
10
of Work and Approved Drawings Specification
Mechanical Completion Activities have to be Weld Map and Records App. Drawing Project QC Documents QA/QC H H
12
completed Specification FAB. SUPVR.
3 of 4
DANEM ENGINEERING WORKS WLL. INSPECTION TEST PLAN
PROJECT : FABRICATION AND INSTALATION OF PIPING for the Project "EPIC OF PRECAST CONCRETE WALL,SHELTERS AND OTHER FACILITIES AT VARIOUS STATIONS IN DUKHAN
FIELDS"
QCP NO: DEW Rev:0 Project/Contract No: GC09113800
Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Verifying Responsible Person Remarks
Documents/Reports DANEM QP
4 of 4