Professional Documents
Culture Documents
Contractual Arrangement
Contractual Arrangement
Contractual Arrangement
ARRANGEMENT
FOR BQS559
What is Contract?
a contract (or informally known as an
agreement in some jurisdictions) is an
agreement having a lawful object entered into
voluntarily by two or more parties, each of
whom intends to create one or more legal
obligations between them.
Basic Elements of Contract?
Offer Acceptance
(contractor) (client)
Consideration
(contractor & client)
Contractual Arrangement?
Contractual arrangement provide legal
framework set up to formalise relationship
between the client, consultants and the
contractors.
BQ
Lump Sum
(Predetermined
contract sum) Drawings and
Specifications
Fixed Price
(Firm Price)
Re-measurement Schedule of Rates
(Contract sum
ascertained on
completion) Approximate BQ
1. FIXED PRICE CONTRACTS
The contractor contracts is to do the work at a price
estimated in advance.
Contractor takes the risk of calculating approximately
how much work is involved and its cost.
Contract sum is predetermined and stated in the
contract.
Traditional contracts are usually fixed price contracts
Once the contract is in force, the lump sum price is
fixed – unless there is breach by client (eg. v.o)
1.1 Lump Sum
• Contractor is responsible for carrying out all
the works shown in the BQ or Drawings and
specifications, for a fixed price.
• Contract price is fixed in advance.
Lump Sum
(Predetermined
contract sum)
1.1 Lump Sum
• Advantage
• Client is able to define the work and prepare design – known budget
• Contractor has incentive to adhere the schedule and budget.
• Drawbacks
• Design should be completed before construction-extend design &
construction time
• Lack of flexibility – changes are expensive & open to claims attempts.
• Risky to contractor is they prepare imperfect documents
When to use lump sum contract?
1. Project is well-defined, not complex.
2. Client wants certainty of price and has fixed budget.
3. Suitable for routine construction-familiar by contractors and
manage to get accurate estimates.
4. Not favourable for emergency project; insufficient time to
prepare complete plans to obtain bids.
BQ
1.1.1 Bills of Quantities (BQ)
Prepared by QS in accordance with
the rules of SMM.
All contractors tender on the same
measurement data.
Bills sets out in a format the quantity
for each of the work components.
The sum of the price inserted for each
items in BQ collectively makes up the
total tender price.
BQ is considered as the best basis for
estimating, tender comparison and
financial administration.
BQ
1.1.1 Bills of Quantities (BQ)
Characteristics:
1. Both the quantity and unit rates in the BQ form part of the
contract.
2. Virtual completion of the design precedes the signing of the
contract.
Advantages
1. Both parties have a clear picture of the extent of their
respective commitments.
2. The unit rates in the BQ provide a sound basis for the
valuation of variation works.
3. A detailed breakdown of the tender sum is readily available.
Disadvantages
1. The length of time taken in the design & BQ preparation –
time consuming
Drawings and
1.1.2 Drawings and Specifications Specifications
Contractor is responsible for carrying out all the works shown on drawings
and specification.
Contractor must calculate his tender sum based upon the contract
drawings and specification.
Contractor will calculate his own quantities.
Contractor may be required to submit a schedule of his rates used to
arrive at the tender figure in order to value variations.
This approach does not provide easy comparison of tender sums.
Drawings
BQ and
1.1.2 Drawings and Specifications Specifications
Characteristics:
1. Tenderers are supplied only with complete working drawings
& a full specification.
2. Virtual completion of the design precedes the signing of the
contract.
Advantages
1. Time required for preparation of tender document is reduced
as the process of preparing BQ is eliminated.
2. Both parties can have a clear picture of their respective
commitments when signing the contract.
Disadvantages
1. No breakdown of the tender sum is immediately available.
2. The valuation of V.O. presents problems.
1.2 RE-MEASUREMENT
• Contract sum is ascertained on completion by
measuring the work done and valuing on the basis
of an agreed schedule of prices.
• Rates can be adjusted for fluctuations, variation to
the works and other matters.
• The contract is used when the extent of work
(particularly quantities) is unknown.
Re-measurement
(Contract sum
ascertained on
completion)
1.2 RE-MEASUREMENT
• Advantage
• Work may commence earlier – tendering cycle shorter.
• Can avoid delay and expense for detail drawings, specs etc
• Drawbacks
• Client & contractor involves in updating price & time (re-measurements) in
agreeing the work qty.
• Total cost only can be certain upon completion
When to use re-measurement contract?
• Extent of work (particularly qty) is unknown
• Insufficient time to prepare the detailed
drawings necessary for accurate bills.
1.2.1 Schedule of Rates Schedule of Rates
PLUS
Cost Escalation
Inefficient in
(eg. Petrol and
Item Ideally material
material price
management
increase)
P.C. Labour 10,000 10,000 10,000
P.C. Materials 15,000 17,000 18,000
P.C.
8,000 8,000 9,000
Plant/Equipment
TOTAL 33,000 35,000 37,000
Add overhead 10%
4,950 5,250 5,550
+ profit 5% = 15%
Cost to the Client 37,950 40,250 42,550
2.2 Cost plus a fixed fee Prime Cost + Fixed Fee
Cost Escalation
Inefficient in
(eg. Petrol and
Item Ideally material
material price
management
increase)
P.C. Labour 10,000 10,000 10,000
P.C. Materials 15,000 17,000 18,000
P.C.
8,000 8,000 9,000
Plant/Equipment
TOTAL 33,000 35,000 37,000
Add overhead
5,000 5,000 5,000
&profit
Cost to the Client 38,000 40,000 42,000
Prime Cost +
2.3 Cost plus a fluctuating fee Fluctuating Fee
Cost Escalation
Inefficient in
(eg. Petrol and
Item Ideally material
material price
management
increase)
P.C. Labour 10,000 10,000 10,000
P.C. Materials 15,000 17,000 18,000
P.C.
8,000 8,000 9,000
Plant/Equipment
TOTAL 33,000 35,000 37,000
Add overhead 10%
4,950 4,550 4,070
+ profit 5% = 15%
Cost to the Client 37,950 39,550 41,070
2.4 Target Cost Contract Target Cost Contract
Item Price
Actual Prime Cost 55,000
Fixed Fee 10,000
TOTAL 65,000
Item Price
Actual Prime Cost 48,000
Fixed Fee 10,000
TOTAL 58,000
Traditional
/Conventional
Method of
Design & Build
procurement
Management-
based
Traditional
3.1 Traditional /Conventional
The client selects the design consultants to design and
contractor to build the building as designed.
The main contract is between the employer and the
contractor. The design consultant has no contractual
agreement with the contractor; however the consultant
will administer the contract on behalf of the clients.
The award may be by competitive tender or by
negotiations and the contract price may be in the form of
lump sum, unit prices or cost plus arrangement.
3.2 Design & Build Design & Build
Contract 1 Contract 2
• Useful for client who have a number of building program in succession
• Negotiation may apply for the 2nd contract on the basis of successful tender (1st
contract)
• Projects are normally similar in nature, time scale and contract conditions.
• Can consist of a number of projects eg. individual starts to finish dates, flexible
timing to give continuity of work – promotes cost and time saving
• Accumulated knowledge and expertise from project teams available
• Tender price are able to be reduced due to economies of scale.
4.2 Term Contract
- For maintenace, repair, renovation works
Term contract -can vary from 1-3 years or more (period of
contract)