Professional Documents
Culture Documents
Construction Supervision Manual
Construction Supervision Manual
SUPERVISION
UAL
UNITED ARAB EMIRATES
ABU DHABI MUNICIPALITY
ROAD SECTION
1999 Edition
CONSTRUCTION SUPERVISION MANUAL
Page -1-
CONSTRUCTION SUPERVISION MANUAL
Page -2-
CONSTRUCTION SUPERVISION MANUAL
Page -3-
CONSTRUCTION SUPERVISION MANUAL
Page -4-
CONSTRUCTION SUPERVISION MANUAL
Page -5-
CONSTRUCTION SUPERVISION MANUAL
Page -6-
CONSTRUCTION SUPERVISION MANUAL
Page -7-
CONSTRUCTION SUPERVISION MANUAL
APPENDIX
Page -8-
CONSTRUCTION SUPERVISION MANUAL Section 100
100-1
CONSTRUCTION SUPERVISION MANUAL Section 100
have all the authority and powers vested in the (C) Substructure: All that part of a structure
Engineer under the terms of the Contract. The below the bearings of simple and
Resident Engineer’s duty will be primarily to continuous spans, skewbacks of arches,
ensure that the Works are carried out in strict and top of footings of rigid frames;
accordance with the Drawings, Specifications, including backwalls, wingwalls, and wing
and intent of the Contract. The Resident protection railings.
Engineer will have assistants as required by the
progress and nature of the Works underway and (D) Superstructure: All that part of a structure
he will have the authority to delegate in writing above the bearings of simple and
such powers as he may see fit to such assistants continuous spans, skewbacks of arches,
and will furnish to the Contractor a copy of all and top of footings of rigid frames;
such written delegations. excluding backwalls, wingwalls, and wing
protection railings.
Award: The acceptance by the Executive
Council of a proposal to perform the work. Calendar Day: Any day shown on the calendar,
beginning at midnight, extending for a twenty-
Backfill: Material placed in an excavated space four hour period, and ending at midnight.
to fill such space.
Change Order: Contract amendment to effect
Bank Guarantee (Performance Bond): The minor contract modifications including new BOQ
approved form of security, furnished by the Items, addition or reduction of BOQ quantities,
Contractor and issued unconditionally by an Abu additional works, or other such changes that do
Dhabi bank, guaranteeing the full and complete not require an extension of time or an increase in
performance of the Contract. the total contract value.
100-2
CONSTRUCTION SUPERVISION MANUAL Section 100
tenders, proposal, bill of quantities, contract Delay: Any event, action, force, or factor that
agreement and contract bonds, certificate of causes the length of time needed to perform the
insurance, Standard Specifications, Particular work to increase.
Specifications, Project Plans, Standard
Drawings, documents incorporated by reference, Delay Penalty: The delay penalty per day is
and any supplemental agreements that are equivalent to ten percent (10%) of the value of
required to complete the construction of the work the Contract divided by twenty five percent
in an acceptable manner, including authorized (25%) of the period of execution. The delay
time extensions, all of which constitute one penalty is imposed on the Contractor if he fails to
instrument. handover the completed work in the specified
period.
Contract Amendment: An increase or decrease
in the contract price or time made by variation Department: The Municipality of Abu Dhabi.
order or change order.
Department Representative: The duly
Contract Price: The sum named in the Contract appointed representative of the Department
subject to such amendments or additions thereto charged with oversight of the Contract.
or deductions therefrom as may be made under
the provisions contained in the Contract Engineer: The use of the word Engineer in this
Documents. document relates to the Resident Engineer or his
authorized representative within the limits of
Contract Time: The number of working days or their authority.
calendar days allowed for completion of the
Contract, including authorized time extensions. Equipment (Plant): All machinery, equipment,
If a completion date is specified in the Contract, tools, and apparatus, together with the necessary
the contract time expires on that date. supplies for upkeep and maintenance necessary
for the proper construction and acceptable
Contractor: The individual, partnership, firm, completion of the work.
corporation, joint venture, or any acceptable
combination thereof, contracting with the Executive Council: The Government’s chief
Department for performance of the work. executive committee comprised of the various
department heads acting under authority of the
Controlling Item: A work activity in which any laws of Abu Dhabi.
delay that limits completion will result in a delay
in the completion of the Contract, e.g., a critical Extra Work: Work to be performed by the
construction activity. Contractor not provided for in the Contract, but
found essential for the satisfactory completion of
Culvert: Any structure not classified as a the project.
bridge, which provides an opening under the
roadway. Highway, Street, or Road: General terms
denoting a public way for purposes of vehicular
Daily Works Schedule: Prices or rates of travel, including the entire area within the
payment for work executed based on the cost of defined corridor.
labor, materials, and plant used in performing the
work plus the percentages for overheads, profit, Holidays: The legal holidays as defined by the
etc., as approved by the Engineer. Government of Abu Dhabi.
Day: Day as used in the Contract means a Independent Approved Laboratory: A testing
calendar day. laboratory which has been approved by the
Engineer to perform testing and which has been
100-3
CONSTRUCTION SUPERVISION MANUAL Section 100
determined by the Engineer to be free from any placed on a subbase course or a subgrade
conflict of interest. to support a surface course.
Inspector: The Engineer’s authorized (C) Wearing Course: One or more layers of
representative assigned to make detailed specified materials designed to
inspections of contract performance. accommodate the traffic load, the top layer
of which resists skidding, traffic abrasion,
Item (BOQ Item): A detail of work for which and the disintegrating effects of climate.
payment is made under the Contract.
Permanent Works: The Permanent Works to
Laboratory: The testing laboratory of the be executed and maintained in accordance with
Department or any other testing laboratory which the Contract.
is certified or approved by the Department.
Period of Execution of the Contract: (Time for
Lump Sum: The amount bid by a Contractor as Completion) The number of calendar days
a single amount for a complete contract item as allowed by Contract or written agreement for the
defined by the specifications, or a price proposed Contractor to complete the Works in accordance
by a Contractor as a single amount for the with the Contract Documents. The Period of the
performance of extra work. Contract starts on the commencement date when
the Site is handed over to the Contractor as
Materials: Substances used in the construction described in the General Conditions of Contract
of the project and its appurtenances. in the Field of Civil Works, Chapter Two,
Article (2). The Period of Execution of the
Median: The untraveled portion of the highway, Contract ends at the time of the Initial Take Over
street, or road which separates the two traveled described in the General Conditions of Contract
roadways with traffic flowing in opposite in the Field of Civil Works, Chapter Six, Article
directions. (36) and the Special Conditions of the Contract,
Chapter Six, Article (36).
Notice of Award: A written notice by the
Department to the successful Tenderer stating Plans: The project plans, Standard Drawings, or
that his Tender has been accepted and that he is reproductions thereof, approved by the Engineer,
required to execute the Contract and furnish a which show the location, character, dimensions,
Final Guarantee and satisfactory evidence of and details of the work to be performed. All
insurance. such documents are to be considered as a part of
the plans whether or not they are reproduced in
Notice to Proceed: A written notice by the the tender documents.
Department to the Contractor stating the date he
is to commence the Works. (A) Standard Drawings: Drawings approved
for repetitive use, showing details to be
Pavement Structure: The combination of used where appropriate. All Standard
subbase, base course, and/or wearing course Drawings approved by the Department
placed to support the traffic load. plus subsequent revisions and additions are
listed in the tender documents along with
(A) Subbase Course: One or more layers of the latest (current) revision dates.
specified or selected materials, of designed
thickness, placed on the subgrade to (B) Project Plans: Specific details and
support a base course. dimensions peculiar to the work which are
supplemented by the Standard Drawings
(B) Base Course: One or more layers of insofar as they may apply.
specified materials, of designed thickness,
100-4
CONSTRUCTION SUPERVISION MANUAL Section 100
(C) Shop Drawings and Supplemental Revision: Any change made to the Contract
Drawings: Supplemental design sheets, Drawings by the Engineer.
shop drawings, working drawings, or
similar data which the Contractor is Right-of-Way: A general term denoting land,
required to submit to the Engineer for property, or an interest therein, acquired for or
approval or any other supplementary data devoted to transportation purposes.
required of the Contractor.
Roadbed: The graded portion of a highway
Profile Grade: The trace of a vertical plane within top and side slopes, prepared as a
intersecting the top surface of the proposed foundation for the pavement structure and
wearing surface, usually along the longitudinal shoulders.
center line of the roadbed. Profile grade means
either elevation or gradient of such trace Roadside: A general term denoting the area
according to the context. adjoining the outer edge of the roadway.
Extensive areas between the roadways of a
Project: The specific section of the roadway or divided highway may also be considered
bridge on which construction is to be performed roadside.
as described in the Contract.
Roadside Development: Those items necessary
Project Manager: The Contractor’s authorized to the completed highway which provide for the
representative in responsible charge of the work. preservation of landscape materials and features;
the rehabilitation and protection against erosion
Provisional Item: An Item set out in the Bills of of all areas disturbed by construction through
Quantities to cover work that the Department has seeding, sodding, mulching, and the placing of
the option, after award of the Contract and at other ground covers; and such suitable planting
any time during the life of the Contract and prior and other improvements as may increase the
to commencing work on or for the identified effectiveness and enhance the appearance of the
item, to delete such item as the Department may highway.
specify in writing to the Contractor. Provisional
items of work shall not be executed by the Roadway: That portion of the right-of-way
Contractor until authorized in writing by the required for construction, limited by the outside
Department. edges of slopes, including ditches, channels, and
all structures pertaining to the work.
Provisional Sum: An allowance set out in the
Bills of Quantities to cover work which has not Section (When referring to the Specifications):
been specified in detail in the Contract. A numbered article or group of related articles
forming a part of the specifications and applying
Reasonably Close Conformity: Compliance to or controlling the procedure of an operation or
within reasonable and customary manufacturing regulation.
and construction tolerances where working
tolerances are not specified. Where working Shop Drawings: Those drawings, details, or
tolerances are specified, reasonably close supplemental documentation prepared by the
conformity means compliance within such Contractor and submitted to the Engineer for
working tolerances. review and approval.
Responsible Contractor: A Contractor that has Shoulder: The portion of the roadway
the requisite skill, resources, desire, and integrity contiguous with the traveled way for
to complete the work in conformance with the accommodation of stopped vehicles, for
provisions of the Contract. emergency use, and for lateral support of base
and surface courses.
100-5
CONSTRUCTION SUPERVISION MANUAL Section 100
Sidewalk: That portion of the roadway prices quoted in accordance with the Contract
constructed primarily for the use of pedestrians. Documents.
Specifications: The compilation of provisions Tender Form: The prescribed form on which
and requirements for the performance of the tenderer’s offer is submitted.
prescribed work including the Standard
Specifications and Particular Specifications. Tenderer: An individual, partnership, firm,
corporation, or any acceptable combination
(A) Standard Specifications: A book of thereof, or joint venture, submitting a tender.
specifications, which is approved for
general application and repetitive use. Tender Documentation: All writings, working
papers, computer printouts, charts, and data
(B) Particular Specifications: Additions and compilations that contain or reflect information,
revisions to the Standard Specifications data, or calculations used by the Tenderer to
covering conditions and requirements determine the Tender Proposal submitted,
peculiar to an individual project. including material relating to the determination
and application of:
Structures: Bridges, culverts, catch basins,
drop inlets, retaining walls, manholes, endwalls, • Equipment rates
buildings, sewers, service pipes, under drains, • Overhead rates
foundation drains, and other features which may • Time schedules
be encountered in the work and not otherwise • Labor rates
classified. • Efficiency or Productivity rates
• Arithmetic extensions
Subcontractor: An individual, partnership, • Subcontractor and Material Supplier
firm, corporation, or any acceptable combination Quotations
thereof, or joint venture, to which the Contractor
sublets a part of the Contract with the approval Any manuals standard to the industry used by
of the Department. the Tender in determining the Tender Proposal
are also considered bid documentation. These
Subgrade: The roadbed materials beneath the manuals may be included in the bid
pavement structure. The top prepared surface of documentation by reference and shall show the
the subgrade is called finished subgrade name and date of the publication and the
elevation. publisher.
Supplier: One who fabricates, or processes an The term “Tender Documentation” does not
item off the project site, and who may or may not include documents provided by the Department
deliver this item to the project. For purposes of for the Tenderers’ use in the preparation of the
this definition, a supplier shall not include one Tender Proposal.
who establishes a fabricating process or facility
expressly for use of the project, whether on or Tender Guaranty (Surety Bid Bond): The
off the project site; or one who performs work on security furnished with a bid to guarantee that
the project site that is incorporated into the the tenderer will enter into the Contract if its
project. proposal is accepted.
Surety: The corporate body bound with and for Traveled Way: The portion of the roadway for
the Contractor, for the full and complete the movement of vehicles, exclusive of shoulders.
performance of the Contract and for payment of
all debts pertaining to the work. Unbalanced Bid, Mathematically: A bid
containing lump sum or unit bid prices that do
Tender: The offer of a tenderer, on the not reflect reasonably anticipated actual costs
prescribed forms, to perform the work at the
100-6
CONSTRUCTION SUPERVISION MANUAL Section 100
plus a reasonable proportionate share of the Working Time: Daytime hours of operation for
bidder’s anticipated profit, overhead costs, and execution of the works consisting of a single
other indirect costs. eight (8) hour shift, limited to six (6) hours
during the month of Ramadan, exclusive of night
Unit Price: The price offered by the Contractor work, work on officially declared holidays, and
for one unit of work, as defined by the Fridays.
specifications.
101.04 CONSTRUCTION SUPERVISION
Variation Order: Contract amendments STAFF AND RESPONSIBILITIES
resulting in an increase of the Total Contract
Value or an extension of time and requiring
Figure 100.01 shows the typical organizational
approval by the Executive Council.
structure for the construction supervision staff
assigned to a roadway or bridge project. The
Work: Work shall mean the furnishing of all
actual staff requirements for a specific project
labor, materials, equipment, and other incidentals may include additional assignments or certain
necessary or convenient to the successful positions may be excluded depending on the size
completion of the project and the carrying out of and complexity of the project.
all the duties and obligations imposed by the
Contract.
Figure 100.01
CONSTRUCTION SUPERVISION STAFF
Department
Representative
Resident
Engineer
Support
Secretary
Staff
• Chief Utility Coordinator
• Soils & Materials Engineer
Asst Resident
• Office Engineer (Design Specialists)
Engineer • Structural Engineer
• Chief Quantity Surveyor
• Chief of Surveys
100-7
CONSTRUCTION SUPERVISION MANUAL Section 100
• Make layout checks on lines and grades. • Inspect safety conditions and inform the
Contractor of construction safety violations
• Coordination with other Contractors. and follow up action to be taken.
• Maintain all file records on designated • Attend all meetings, and prepare written
forms. These records include all reports on minutes for distribution.
work force, equipment, progress, safety, etc.
• Review correspondence and prepare
• Review and approve the Contractor’s shop responses for signature.
drawings.
• Review, update, monitor, and report on the
• Locate, execute, and interpret all soils and Contractor’s work schedules, CPM-chart,
materials testing according to the and Cash Flow Status.
provisions in the Contract Documents and
Standard Specifications. • Monitor and report on progress of
scheduled utility relocation work.
• The Resident Engineer is responsible for
Contract enforcement and is not to relieve • Provide all photographs before, during, and
the Contractor of his responsibilities after construction necessary to provide
without Municipality authorization. adequate documentation of changes in site
and adjacent structures.
• The Resident Engineer is responsible for the
final materials submittals and review, which • Review and approve the Contractor’s plans
shall be forwarded to the Department with for protection of existing buildings and
recommendations for final approval. structures.
100-8
CONSTRUCTION SUPERVISION MANUAL Section 100
• Approve all restoration or final clean-up • Review and approval of the Contractor’s
work. Shop Drawings as delegated by the Resident
Engineer.
• Review and make recommendations on the
Contractor’s claims. • Monitoring the performance of the survey
party.
• Coordination with other Contractors,
Departments, and Agencies. • Review and approval of the Contractor’s
proposed materials and methods as
• Provide a “punch list” and final inspection. delegated by the Resident Engineer.
• Check and approve the final quantities • Coordination with the Contractor’s
submitted by the Contractor. supervisory personnel regarding schedule,
sequence, and method of work.
• Check and approve the final payment
certificate submitted by the Contractor. • Monitoring conformance with the
Contractor’s schedule.
The Resident Engineer should select competent
personnel and delegate authority to them. He • Continuous Field Inspections of the work in
should also promote training programs in each progress and consultation with both the
phase of the work to increase the knowledge of Engineer’s and Contractor’s supervisory
the other project personnel. staff.
100-9
CONSTRUCTION SUPERVISION MANUAL Section 100
100-10
CONSTRUCTION SUPERVISION MANUAL Section 100
Principal responsibilities of the Survey Party the efficiency and quality of work performed by
Chief include the following: the team.
• Perform survey work under the direction Accuracy and efficiency are imperative in
and guidance of the Chief of Surveys. construction surveying operations. Each
surveyor, regardless of assigned duty, should
• Establish primary horizontal and vertical independently check and double-check all rod
control points including reference ties for readings, instrument readings, calculations, and
re-establishing the points in the field. measurements as the work progresses.
• Rotate staff assignments to develop the The field laboratory technician is assigned to
skills and qualifications of the surveyors. coordinate the work and record keeping of the
materials testing laboratory on the project and is
• Record all measurements, rod readings, responsible to the Resident Engineer. He may
and calculations neatly and accurately in receive additional technical counsel from the
field books as the work progresses. Chief of Soils and Materials where such is
assigned to the project.
• Coordinate with the Contractor’s surveyor
on work priorities and schedules.
Principal responsibilities of the Materials
• Check all work by completing traverse Technician are as follows:
closures and bench circuits.
• Field laboratory set-up, organization,
• Report discrepancies or technical problems maintenance, and operation.
to the Resident Engineer.
• Supervision of staff assistants performing
• With the Contractor, perform joint sampling and testing of materials.
measurements of the completed work for
payment. • Perform sampling, testing, record keeping,
and reporting in accordance with
• Check completed work for conformance to
the line and grade required by the project ⇒ Project Plans and Specifications
plans in coordination with the Inspector
⇒ Municipality Policy and Procedures
assigned to the item of work.
Directives.
• Perform regular checks of the Contractor’s
⇒ Materials Testing Manual
setting out to verify proper execution and
accuracy.
⇒ AASHTO Standard Methods of
Sampling and Testing
• Maintain equipment in proper condition
and perform frequent calibration checks.
⇒ Construction Supervision Manual
101.04.07 Surveyor ⇒ Construction Supervision Directives
The project Surveyors work directly under the ⇒ Sampling Guide and Certifications
supervision of the Survey Party Chief. Surveyors Manual
are assigned duties according to their technical
abilities such as Instrumentman, Rodman, etc. • Copy all test results to the Resident
Ideally, all surveyors should be trained on the job Engineer and Contractor.
to gain experience at each position and improve
100-11
CONSTRUCTION SUPERVISION MANUAL Section 100
• Perform regular checks of material • Coordinate with the Survey Party Chief to
delivered to the project for conformance check the line and grade of completed work
with the approved source or supplier. for conformance with the plans and
specifications.
• Maintain neat accurate records.
• Report questionable methods of operation
• Monitor the frequency and number of tests by the Contractor to the Resident Engineer.
required for every operation.
• Report to the Resident Engineer any failure
101.04.09 Inspectors of the Contractor to conform to plans and
specifications and to provide good
All Inspectors on construction projects are to workmanship.
report to the Resident Engineer unless other lines
of reporting have been indicated by the Resident • Process the joint measurement forms and
Engineer. Inspectors assigned to various phases maintain records of their status.
of the work have an important part in assuring
the quality of work in the finished project. They • Maintain records of completed works for
must be completely familiar with the plans, interim and final payment and as-built
specifications, particular specifications, and plans.
construction methods for the phases of the work
to which they have been assigned. If the • Maintain detailed records of work
Inspector finds that he does not fully understand performed by the contractor on a Day
any of the items that he has been charged with, Works basis.
he should seek a clarification of these items from
the Resident Engineer. • Make special notes and document the
Contractor’s activities that may lead to
Principal responsibilities of the Inspector are as claims.
follows:
• Be fair and firm in dealings with the
Contractor. Consider alternatives and
• Ensure performance of the work in strict
consequences carefully before making
accordance with the plans and
decisions.
specifications.
• Issue instructions to the Foreman in charge
• Maintain a detailed diary of the day’s work
of the work and do not argue with the
activities, issues, work approved or
Contractor or his representatives.
rejected, hours of operation, labor and
equipment used, etc., and sign at the end of
each day.
100-12
CONSTRUCTION SUPERVISION MANUAL Section 100
• Notify the Resident Engineer of conditions Prior to the actual start of construction the
that render it impractical or unreasonable Consultant and/or the Resident Engineer
to enforce the specifications. assigned to the Contract will be required to
monitor the execution of the Pre-commencement
• Report and document any accident that of Construction Activities. These activities are
occurs on site and notify the Resident described in the following table indicating the
Engineer immediately. interaction between the Department, Engineer,
and the Contractor. It should be emphasized that
• Enforce performance of the work in strict the pre-commencement activities are a
accordance with the approved Safety Plan. cooperative effort between the Department, the
Engineer, and Contractor.
• Check detours and traffic control zones for
proper placement of signs, barricades, and
lights. PRE-COMMENCEMENT ACTIVITIES
INSPECTOR’S AUTHORITY
Municipality Engineer Contractor
• Assigned by the Resident Engineer based on the
Inspector’s knowledge, experience, and ability. Notice of • Conformed • Final
• Limited authority for the rejection of materials Award Contract Guarantee
or portions for the work.
Documents • Execute
• May prohibit methods of work that do not
• Propose Site Contract &
conform to the specifications.
Staff Insurance
• Advise Contractor of methods that are likely to Policies
impair the quality and conformance of the work
Notice to
to specification requirements. Notify the
Proceed • Preconstruc- • Site Office
Resident Engineer immediately.
tion Meeting Facilities
• No authority over the Contractor’s management,
• Site • Service
direction, or scheduling of work.
Handover Reservation/
• No authority to alter or relax any plan or
Existing
specification requirement.
Utility
• No authority to issue instructions contrary to the Records
plans or specifications.
• Preliminary
• May direct stoppage of work where the safety of Program
workmen or the public is threatened. Notify the
• Notice of
Resident Engineer immediately.
Intent
• Direct correction of conditions that are
• Mobilization
hazardous or unsafe.
Start • Review • Manual
Construction Program Excavation
101.05 PRE-COMMENCEMENT OF
CONSTRUCTION
101.06 SCOPE OF WORK
101.06.01 General
Following the consideration of Tenders, the
Department will issue a written notice to the
The Scope of Work is defined by the Contract
successful Tenderer stating that the Tender has
Documents including the Tender Documents,
been accepted and that he is required to execute
Specifications, Bills of Quantities, and Plans.
the Contract and furnish a satisfactory Final
Guarantee. This action advances the project
from the Design and Tender phases to the
Construction Supervision phase.
100-13
CONSTRUCTION SUPERVISION MANUAL Section 100
The Contract Documents establish the conditions In directing the Contractor, the Resident
under which alterations to the work may be Engineer will determine the applicability of the
made, quantities increased or decreased, and set existing BOQ Items to the additional (or deleted)
forth limitations that are extremely important in work and advise the Contractor of his
the administration of the Contract. The Resident determination. If the existing BOQ Items are not
Engineer should read these sections carefully. applicable to the amendment, the Contractor will
be requested to propose new unit rates for the
The Municipality may make amendments to the items. The Resident Engineer may determine that
form, quality, quantity, or schedule of the works the work cannot be properly measured and
and issue written orders to the Engineer directing valued and order the work be performed on a
such amendments. The Resident Engineer will in Daily Works basis.
turn direct the Contractor in writing to make the
amendments. The nature of the amendment may The Contractor is required to submit, in writing,
result in one or more of the following: any intention to claim extra payment or an
amended rate and state whether an extension of
• Increase or decrease in quantities for which time will be part of his claim. The nature of the
established BOQ Items are applicable. amended work must be properly considered in
determining the most appropriate procedure for
• New items or different character of work for implementing the change and amending the
which the existing BOQ Items are not Contract. Generally, three courses of action are
applicable. available as follows:
Figure 100.02
FORMALIZATION OF CONTRACT AMENDMENTS
Resident
Resident Resident Engineer Submits
Municipality Contractor’s Change Order
Engineer’s Engineer ‘s to Municipality
Order Evaluation Representative
Evaluation Evaluation
Will Exceed
Use Existing
Total Contract
BOQ
Value
Variation
Order
Need Time
Extension
Day Work
Day Works
Summary
100-14
CONSTRUCTION SUPERVISION MANUAL Section 100
1. Daily Works. Work of a minor nature, that Contractor results in faulty work, the Contractor
in the opinion of the Engineer cannot be is to be clearly advised in writing that the
properly measured or valued, will be paid on Resident Engineer is not dictating the means.
a Daily Works basis in accordance with the
BOQ Daily Works Schedule and procedures. When the Engineer or his representative have the
authority to select or prohibit a method of
2. Change Order. A Change Order may be construction, the Resident Engineer shall issue
issued to effect the amendment if: written instructions to the Contractor when this
action is desirable.
• A Time Extension is not required, and
The Resident Engineer shall ensure that the
• The Total Contract Value will not be
project is constructed within construction and
exceeded.
geometric limits shown on the drawings.
The Change Order mechanism may be used Structures are to be built to the neat lines shown
to implement new BOQ Items with unit rates on the drawings. Should changes be required,
developed in accordance with the procedure the Resident Engineer shall ensure that these
described in the Contract Documents. changes are executed within the existing limits of
Change Orders are executed by written construction or that approval for new limits has
approval of the designated Municipality been obtained before the Notice to Proceed is
official. issued to the Contractor. Utilities shall be
constructed in the Service Reservations shown on
3. Variation Order. Amendments resulting in an the drawings or in reservations provided before
increase of the Total Contract Value or an construction.
extension of time will require formal
execution of a Variation Order by higher It is the duty of the Resident Engineer to see that
authorities. the project is constructed according to the plans
and specifications, and in strict compliance with
Figure 100.02 shows the potential steps required the terms of the Contract. He shall not direct that
for formalization of a Contract amendment. the work be stopped, except for reasons relating
to safety. He has the authority to reject both
101.07 CONTROL OF WORK unsatisfactory workmanship and materials.
These rejections must be made in writing to the
101.07.01 General
Contractor immediately upon discovery. The
written rejections are to refer to the appropriate
The Contractor is responsible for the means
plan or specification requirement.
employed to construct the works. When the
Contract specifies the means or methods by
101.07.02 Site Instructions
which the work is to be done, the Resident
Engineer must refuse to accept work done by any
The issuance of a Site Instruction involves a
other means or method not specifically
matter that cannot wait for a formal letter and an
authorized. This is to be done even though the
instruction in writing is imperative. Site
Contractor may contend he can secure the same
Instructions must be given in writing and copied
results by some other method.
to the Department Representative. The Resident
Engineer will issue a formal letter confirming the
When the plans and/or specifications do not
directions stated in the Site Instruction as soon as
specify the means, it is the Contractor’s
possible.
responsibility to select a means by which to
accomplish this work. Should the Resident
Engineer believe that the method selected by the
100-15
CONSTRUCTION SUPERVISION MANUAL Section 100
101.07.03 Schedule
In order to be effective in these matters, the
The Contractor is required to submit a Program Resident Engineer must be able to measure the
of Works for approval of the Resident Engineer progress of the Contract works.
and the Municipality. The program must be
carefully scrutinized considering: The Resident Engineer shall be fully aware of all
aspects of the progress of his project including:
PROGRAM OF WORKS
CONSIDERATIONS • Status of Work Items With Regard to the
Contractor’s Approved Schedule,
• Conformance to Contract Time for Completion. • Current Overall Status of Completion, and
• Approval for Greenery (trees and grass)
Removal. • the Probable Project Completion Date.
• Availability and Time Required for Approval
and Procurement of Materials. There are numerous methods available to
• Construction Staging Plan. evaluate progress. Figure 100.03 provides an
• Detours and Police Approval. explanation of some of the most common
• Utility Works and Accommodations of Work by methods. The Resident Engineer should examine
Others. the results of each measurement indicator
• Available Labor, Plant, and Equipment
carefully.
Resources.
• Critical Path Time Scheduling.
• Weather and Religious Considerations.
These methods of progress evaluation depend
• Mobilization and Pre-Construction Activities. heavily upon information to be furnished by the
• Clean-up and Final Inspection/Punch List. Contractor. It is extremely important to impress
upon the Contractor that the Resident Engineer
will be using these methods to measure his
Progress will be measured against the progress and that such measurement is going to
Contractor’s program and the schedule should be be based upon the Contractor’s own input. The
realistic and achievable. Monthly Reports input data must be acceptable and, if not, should
showing progress consistent with the program be rejected and resubmittal of the needed data
schedule are in the best interest of the requested.
Contractor, Engineer, and the Municipality. The
Contractor should update the schedule and re- The indicators developed from each of these
submit for approval when the old schedule methods of progress evaluation should be
becomes invalid due to actual progress being explored and any needed remedies discussed and
delayed. The revised schedules can support (or agreed. The Resident Engineer shall be
invalidate) Contractor’s claims and show the new thoroughly aware of the findings indicated by
revised completion date or what resources and each of these methods before meeting with the
action must be provided to meet the original Contractor. The Resident Engineer’s role in this
completion dates. situation is to provide responsible directions to
the Contractor on behalf of the Municipality for
101.07.04 Progress Evaluation and Reports controlling and expediting the work. The
Resident Engineer must formally inform the
The Resident Engineer shall evaluate of the Contractor in writing when falling behind
Contractor’s progress. An important function of schedule, documenting the apparent reasons and
the Resident Engineer is to assure the time delays. Letters should be sent on a bi-
Contractor’s timely performance of the work. weekly basis until the Contractor has regained
Verification of the work done for progress control of his schedule.
payments, anticipation of the Contractor’s
problems, and early corrective actions are all
significant responsibilities of the Resident
Engineer.
100-16
CONSTRUCTION SUPERVISION MANUAL Section 100
Figure 100.03
Work Units Accomplished The Contractor’s progress toward partial or substantial completion
of key work items, areas, or phases in comparison to schedule
milestones is monitored.
100-17
CONSTRUCTION SUPERVISION MANUAL Section 100
The Contractor’s proposed work program determined from the approved Program of
(schedule) will be reviewed and approved by the Works. This letter will be drafted by the Resident
Engineer in coordination with the Municipality. Engineer for transmittal to the Contractor.
During the course of the work, events may
transpire modifying activities shown on or The proper assessment of delay penalties will be
affecting the schedule. In this event, the Resident made by the Municipality based on progress
Engineer will take action to immediately have the reports initiated by the Resident Engineer. Such
Contractor revise and resubmit the schedule for assessment will not be made before the
approval. It is emphasized that maintaining a authorized Contract period expires.
current, valid schedule is vital to the control of
the work and progress. 101.07.06 BOQ Recapitulation
Monthly Progress Reports shall be submitted to The Resident Engineer must also be aware of the
the Municipality using the following format: quantities that are expected to be used in
construction of the project in accordance with the
MONTHLY PROGRESS REPORT plans and specifications. Frequently the BOQ
FORMAT quantities include a contingency allowance
beyond what is actually required. Conversely,
certain BOQ quantities may be less than actually
• Letter of Transmittal with brief summary, required.
highlights, time expended, and percentage
completed. In order to determine these variances, the
• Table of Statistics including Contract Resident Engineer’s staff should perform a BOQ
number, date of Contract award, date of recapitulation by taking off the required
notice to proceed, original Contract period, quantities directly from the construction plans or
approved time extensions, revised Contract approved shop drawings. This data should be
period, days elapsed, percentage of time compared to the BOQ quantities to establish the
elapsed, percentage of anticipated completion projected underruns and overruns. Recapitulation
(from progress schedule), percentage of actual quantities should be updated at least quarterly
completion (measured on the same basis as (four times a year) during the course of the
percentage of anticipated completion), Contract to reflect additional works and revised
Contract completion date, original Contract quantities. This information is vital to the
amount, approved Variation Orders, revised Resident Engineer in assessing progress,
Contract amount, and value of completed schedules, estimated final cost, and potential
work. quantity changes due to extra work, variation
• Narrative description of Construction orders, or field modifications. A Statement of
Activities. Overrun Quantities and a Statement of Underrun
• Narrative of the Engineer’s Activities. Quantities are included with the Interim Payment
• Pertinent Progress Photos. Certificates.
• General Location Map.
• Narrative report of Progress Problems, their 101.08 CONTROL OF MATERIAL
cause, and proposed solutions. An adequate and effective system for control of
• Safety Issues. materials used in the project is essential to ensure
• Progress Chart showing scheduled progress that the materials furnished and the final product
and actual progress. conform to the Contract requirements. Regular
inspections of field work by the Resident
101.07.05 Progress Letters and Delay Engineer are performed to:
Penalties
• Ensure compliance with Contract require-
The Contractor should be notified by letter when ments.
actual progress falls behind projected progress as
100-18
CONSTRUCTION SUPERVISION MANUAL Section 100
• Permit prompt appropriate corrective action, • SM-29 form duly completed with all
should unacceptable material or workmanship relevant details.
be detected.
• Material Approval forms duly completed
• Provide regular documentation of for use of the Department and the
construction progress or lack of progress. Consultant.
The following procedure should be followed for 2. A sample tag shall be attached to each
approval of materials to be incorporated in the sample.
Permanent Works.
3. All samples shall be entered into the Sample
1. The Contractor shall submit, for the Receipt and Testing Book with all relevant
approval of all concerned parties, a complete details.
description and details of the materials
together with the names of manufacturers/ 4. Concrete cubes shall be numbered
suppliers from whom he proposes to obtain consecutively and entered at the back of the
such items. In addition to the above, the Sample Receipt and Testing Book. The
Contractor’s submittal shall include the columns shall be revised to show 7-day and
following: 28-day testing dates and other appropriate
information.
100-19
CONSTRUCTION SUPERVISION MANUAL Section 100
5. The applicable standard should be referred workmanship, level, and any other requirements
to for the testing procedure. Copies of these of the Resident Engineer are fulfilled. Results are
standards and the actual testing procedure given on the individual test forms and on the
shall be supplied to each field laboratory and Daily Summary (SM-26) to enable work to
to the central laboratory. proceed. These forms are completed and signed
by the Soils and Materials Engineer on a weekly
6. The tests shall be carried out promptly based basis.
on priorities established by the Soils and
Materials Engineer. SM.24: (A) (C) & (G) - Asphalt, Concrete,
and Soils, Aggregates Testing Books
7. The test results shall be issued and signed by These books give in a condensed form the
the Soils and Materials Engineer. relevant results of tests carried out on the various
samples tested in the site laboratory.
8. Municipality Materials Engineer will review
test results. SM.25: Asphalt Core Testing
This form gives all the data related to the taking,
9. Finally the test results are forwarded to the
the thickness, and the relative density of asphalt
Resident Engineer with comments.
cores.
101.08.03 Quality Control Procedures
SM.26: Daily Summary of Laboratory Test
Results
Sampling and testing to ensure compliance with
The field laboratory technician completes this
the specifications is often a joint cooperative
form when all the results of the previous day’s
effort between the Department, Resident
testing are known and presents it to the Resident
Engineer, Contractor, Manufacturer or Supplier,
Engineer on a daily basis. The form contains
and the Materials Engineer. The Department or
condensed results of all tests carried out, with the
Resident Engineer can order additional testing as
type and location of such tests, and comments
felt necessary, at any time. General quality
where necessary.
control procedures are described for the basic
components used in local highway and bridge
SM.27: Materials Approval Book
construction.
Use of this book and completion of the relevant
entries ensures close control of the processing
101.08.04 Testing Records
and status of materials approvals.
Testing forms are used in the laboratory to
SM.28: Materials Record Book
calculate the results of the tests indicated on the
Use of this book ensures that site checks of
individual forms. Results, where specific, are
deliveries and storage of approved items are
normally given at the bottom of or on the
carried out and that cross reference is made to
extreme right hand side of the forms. A sample
the Materials Approval Book.
of the various testing forms in current use may
be obtained from the Municipality’s Central
SM.29: Materials Approval Submittal
Laboratory.
All materials to be incorporated into the
permanent works should be supported by
Relevant forms of specific use to the Resident
acceptable documentation and a recommendation
Engineer are as follows:
for approval from the Soils and Materials
Engineer. Final materials approval is the
SM.23: Request for Testing of Construction
responsibility of the Resident Engineer. Also,
The first part of this form is filled out by the
copies of all correspondence related to materials
Contractor on completion of a section of work
and materials approvals shall be sent to the Soils
considered ready for testing. Approval to carry
and Materials Engineer. To assist in ensuring
out such testing, as requested, is given by the
that materials submittals are supported by all the
Resident Engineer after checks for acceptable
pertinent correspondence, etc., Form SM-29,
100-20
CONSTRUCTION SUPERVISION MANUAL Section 100
• Emission Controls
100-21
CONSTRUCTION SUPERVISION MANUAL Section 100
100-22
CONSTRUCTION SUPERVISION MANUAL Section 100
• Conduct periodic safety briefings for all field satisfied with the cleanup and restoration of his
personnel under his direction. The briefing property. Unless the owner specifically requests
will include discussions of accidents that otherwise, private property will be cleaned and
have occurred, safety considerations on restored in the same manner as government
proposed work for the immediate work property.
month, and the type of construction or the
use of special equipment. 101.10 MEETINGS
101.10.01 Regular Job Meetings
• Record, in his daily diary, the time of each
safety inspection, safety briefing, or other
For meetings arranged and conducted by the
safety-related activity and include a brief
construction supervision staff, an agenda will be
description of the event.
proposed and distributed before the date of the
• If agreeable with the Contractor, the meeting, when possible, to the named attendees.
Resident Engineer and Inspectors should In particular, prior notice for all meetings is to be
attend the Contractor’s safety meetings. given to the Department to enable the
Attendance is to observe the coverage of the Representative to attend.
meetings and communicate expectations
regarding future safety problems. A complete summary of conference notes of the
meeting must be recorded to avoid any
• The Resident Engineer will be authorized to misunderstanding regarding agreements and
suspend the work due to failure of the conclusions reached during the meeting. The
Contractor to correct conditions that are Resident Engineer in charge of the meeting will
unsafe for the workers or to the general appoint another staff member or record the notes
public. As a procedure, any work having himself and prepare the official meeting minutes
conditions that the Engineer finds unsafe for even though others may also be taking such
the workers or to the general public will be notes.
suspended immediately and continuously
until the unsafe conditions have been After the meeting minutes are prepared in final
corrected. form, copies will be transmitted to each person
attending the meeting. All meeting minutes are
In the event unsafe conditions are observed, these to be copied to the Department for information.
conditions should immediately be brought to the When necessary and appropriate, the recipient
attention of the responsible party. During the will be asked to acknowledge receipt of the
construction progress, the entire field staff must minutes.
be alert to ensure that the Contractor complies
with the Municipality safety requirements and all 101.10.02 Preconstruction Meeting
other applicable laws, codes, and ordinances.
Immediately after the Notice to Proceed is
101.09.08 Protection and Restoration of issued, the Consultant in cooperation with the
Property and Landscape Department Representative will arrange a
preconstruction meeting with the Contractor
Work outside the roadway limits of construction (including a responsible Officer and the Project
whether on public or private land that is related Manager) and the Resident Engineer. This
to the project must have the approval of the meeting is to discuss items of mutual interest
Engineer. concerning the start, operation, and completion
of Contract work.
The Contractor must furnish evidence at the
completion of the project that the owner is
100-23
CONSTRUCTION SUPERVISION MANUAL Section 100
100-24
CONSTRUCTION SUPERVISION MANUAL Section 100
101.11 SURVEYS
PROGRESS REVIEW MEETINGS
The primary project horizontal and vertical
AGENDA
survey controls should be in place as shown on
the Contract drawings. All necessary auxiliary
A written agenda will be prepared for each
staking and field surveys and measurements to
meeting and sent to the Contractor in advance.
build the project will be performed by the
Its general format should allow for discussions
Contractor. The Resident Engineer will carry
on the following:
out a re-check on the primary controls and a
• Review of the Contractor’s progress
check of the supplementary surveys established
• Review of current problems by the Contractor.
• Review of past problems still unresolved
• Anticipated problems The job site control must be located to remain
undisturbed by construction. The Contractor is
The Resident Engineer will summarize the to be informed that the cost of replacing basic
discussions at the meeting, identifying controls that his forces may disturb will be at his
responsibility for follow-up action, and expense. The Contractor is also responsible for
undertake the following: maintenance of all basic and supplementary
control lines.
• Prepare handwritten Minutes of Meeting
indicating clearly who is responsible for The Resident Engineer will use survey personnel
appropriate action to be taken. for the following:
• Establish such additional documentation, • Spot check the Contractor’s control points
including correspondence, as may be for detection of movement.
necessary to confirm appropriate or
significant information for the record. • Provide measurements as the basis for
payment of completed work. Partial
101.10.05 Safety Meeting payment for incomplete work does not justify
a survey for each payment, provided
The Resident Engineer or his representative will reasonable checks of quantities can be
meet the Contractor to discuss safety aspects on obtained by other means.
an as-needed basis, with regular formal meetings
held at least on a monthly basis to discuss all • Assist in quantity measurements as required.
instructions, actions, and general items. The
regular meeting is to be documented with copies It is the Contractor’s responsibility to build the
of the minutes distributed to attendees and the project as staked from basic controls. The
Department. Resident Engineer is not responsible for the
Contractor’s auxiliary staking or measurements.
However, if any error in such auxiliary surveying
is observed, detected, or suspected, the possible
error should promptly be brought to the
Contractor’s attention in writing.
100-25
CONSTRUCTION SUPERVISION MANUAL Section 100
100-26
CONSTRUCTION SUPERVISION MANUAL Section 100
As to general detail and arangement only. This approval does not relieve
the Contractor of responsibility for conformity to specifications and
correct details and fit of parts after assembly.
(CONSULTANT)
Date: By:
100-27
CONSTRUCTION SUPERVISION MANUAL Section 100
(CONSULTANT)
Date: By:
100-28
CONSTRUCTION SUPERVISION MANUAL Section 100
100-29
CONSTRUCTION SUPERVISION MANUAL Section 200
SECTION 200
EARTHWORK PRELIMINARY FIELD INSPECTION
CHECKLIST
201 GENERAL
The Resident Engineer and his assistants should 9 Identifying individual trees, bushes, shrubs, and
be thoroughly familiar with the plans and plantings for green area removal.
specifications, the site conditions, obstructions, 9 Clearing indicated by plans and clearing
and maintenance of traffic requirements before actually needed
9 Typical sections shown by plans
the Contractor begins the grading operations.
Upon issuance of the Notice-To-Proceed to the
9 Existing soils, major excavations, and
embankments
Contractor, the Resident Engineer and
Department Representative will make a plans-in-
9 Utilities, fences, or other obstructions to be
moved or protected
hand inspection of the project. The Resident 9 Plot lines
Engineer should prepare meeting minutes of the 9 Building construction activities
walk through noting observations and indicating 9 Survey monuments, evidence of archaeological
appropriate action items (See Preliminary Field sites, or other physical features to be protected,
Inspection Checklist). The inspection should preserved, relocated, etc.
note in particular any site obstructions, including 9 Borrow sources and haul roads
greenery, buildings, or other contractors working 9 Unusual soil or moisture conditions such as high
ground water
in the area.
9 Handling of traffic through or around the work
Before the start of any grading operations, the
9 Changed conditions differing from the Contract
Drawings
Resident Engineer should inspect the drainage of 9 Structures to be demolished.
lands next to the roadway. This inspection is to
ensure that all drainage structures, inlets, outlets,
cross culverts, and curbs are properly located. disposed of, be allowed on the site. The materials
In addition, the Resident Engineer should are to be immediately removed as part of the
investigate the need for any additional drainage demolition process and hauled to an approved
or protective facilities. disposal site.
During the course of grading and draining, he Removal limits should be clearly marked prior to
should make certain that the sequence of commencing work. Sawcuts shall be made where
operations is such that damage to any work will the existing pavement or sidewalk is to be joined
be kept to a minimum in the event of heavy rains. with the new work. The Contractor is responsible
for the preservation of areas to remain at the
202 CLEARING AND GRUBBING limits of work and no payment will be made for
restoration or repair of damaged areas beyond
202.01 EXISTING PAVEMENT, CURBS, the established limits. Removal operations should
AND SIDEWALK REMOVAL be conducted in a neat, workman like manner.
Traffic control provisions including pedestrians
This operation is normally the first phase of should be in place prior to commencing work.
construction. The removal of existing pavement
and curbs often requires the use of special 202.02 PRESERVATION OF TREES AND
equipment, such as hydraulic hammers, to break GREENERY
up the materials to facilitate loading and
disposal. This material is generally unsuitable for Trees, shrubs, and planted areas within the
use and the requirements for such disposal are project limits that do not interfere with the
included in the Standard Specifications. In no planned improvements must be left in place
case will the stockpiling of the material, to be undamaged. Precautions must be taken to protect
200-1
CONSTRUCTION SUPERVISION MANUAL Section 200
200-2
CONSTRUCTION SUPERVISION MANUAL Section 200
before, during, and after the walk through with have a thorough knowledge of the Contractor’s
the contractor. Development of specific operations. He must be aware of problem areas
procedures for the Contractor to handle which may arise during the excavation operation
unexpected conditions should be given and should have discussed contingency plans for
consideration prior to beginning demolition of resolving the problem.
any structure.
204.01 UNCLASSIFIED EXCAVATION
Foundations will normally be removed to a
designated depth and basement floors will be
The Standard Specifications define the
removed to clear critical project elements. The
excavation requirements within the roadway
remaining portions shall be broken to provide for
prism. It includes all materials encountered
the drainage of water. When backfilled, all voids
regardless of their nature or the manner in which
are to be filled and compacted to provide a firm
they must be removed. The materials may be
base for construction of the project works.
soft, hard, silt, sand, wet or dry and are all
measured and paid for in the same way.
When indicated in the plans or identified by the
Unclassified excavation even includes curbs,
Municipality to be salvaged, material or
sidewalk, asphalt, and rock excavation unless
salvageable items should be removed, stored, and
there is a special item for rock in the Contract.
transported to a previously identified location
without unnecessary damage. The agency that
The Contractor is responsible for removing the
wants the salvaged material must identify the
material using equipment that suits the type of
location where the material is to be transported
soil, distance to be hauled, and the volume
and when that location is available to accept the
involved. The excavation will be marked with
salvaged material. This information is needed
slope stakes in the same manner as for
prior to beginning the demolition process so the
embankments. The Inspector must check the
Contractor can arrange his work around those
levels and slopes periodically as the work
constraints.
progresses. The slopes should be dressed as the
cut area comes down.
Documentation of items removed is sometimes
overlooked. All items listed in the plans and
The Contractor may choose to add water to the
special provisions or encountered during the life
soil in the cut area before hauling. This is an
of the Contract should be documented to show
acceptable practice and is usually left to the
what was removed and when the removal was
Contractor’s option.
accomplished. Obstructions that have specific
pay items for removal shall be carefully
If unstable soils or pockets of rubbish or other
measured prior to the removal. In any case, a
unsuitable materials are met with at subgrade
record of the number of men in the crew, the
level, the Resident Engineer will instruct the
equipment used, and the time required to remove
Contractor to remove this from the project. This
each obstruction should be recorded by the
material will be paid for separately, so it is
inspector.
important that accurate measurements are taken.
204 EXCAVATION Material excavated from the roadway that is
Excavation involves the loosening, digging, identified as unclassified material may be used
loading, hauling, and disposal of the earth for embankment construction provided that it
materials in roadway cut sections. This process meets the specification for borrow material - load
is done as specifically described in the bearing. It must have the required California
specifications and job provisions. Before Bearing Ratio (CBR) value, or better. If the
beginning this operation, the Resident Engineer material does not achieve the required CBR, it is
and the Project Manager shall have discussed the to be hauled away from the project and disposed
removal and disposition of material excavated of.
from specific areas. The Resident Engineer must
200-3
CONSTRUCTION SUPERVISION MANUAL Section 200
Unclassified excavation is paid for by the cubic Undercutting below subgrade elevation may be
meter measured by cross-sections taken before ordered by the Resident Engineer to correct an
and after in the excavation area. This work is unstable condition, divert water, or to provide a
performed by the Surveyors and the Inspector more gradual change from cut to fill at grade
should be alert to see that no excavation is points. Any undercutting that has been
performed until the cross-sections are taken. authorized by the Resident Engineer should be
measured for payment as roadway excavation.
204.02 EXCESSIVE UNDERCUTTING An exception would be for extenuating
conditions that would warrant performance of
the work as extra or day works. The extenuating
If at anytime, the Contractor excavates outside
purposes should be based on conditions that have
the construction limits or below subgrade
changed or could not have been reasonably
elevation, except as required by the plans, or if
expected by the Contractor. This extra work
he gouges or undercuts the slopes, the Resident
needs prior approval by the Department.
Engineer shall immediately notify the Contractor,
in writing, that the specifications do not permit
Before the work is accepted, the roadway section
payment for such material. When the Contractor
affected by such undercutting shall be true to the
excavates below subgrade, except as required by
grade and section shown on the plans.
the plans or as directed by the Resident Engineer,
he will replace the over-excavated materials with
a material of equal or better quality and compact
it to the required density at his expense.
UNDERCUTTING
200-4
CONSTRUCTION SUPERVISION MANUAL Section 200
204.04 CUT SLOPES The contractor shall not place any material to be
wasted without the permission and approval of
the Resident Engineer. Useable surplus material
The Contractor’s selection of equipment for
shall not be wasted when borrow material is
finishing slopes is based upon steepness, access,
being used on the site.
and type of material.
200-5
CONSTRUCTION SUPERVISION MANUAL Section 200
200-6
CONSTRUCTION SUPERVISION MANUAL Section 200
The amount of inspection needed to secure approximately parallel to the finished grade. As
proper construction will depend primarily on the the earth materials are being dumped and spread,
size of the project, the nature of the soils, the rate large roots and other perishable materials must
at which material is being placed, and the be removed and disposed of outside the limits of
governing specifications. However, compaction the work. Good drainage and/or dewatering
tests in each layer should be taken at a frequency must be maintained throughout the construction
to ensure proper compaction density is being operation. Frequent checks should be made to
achieved. see that the work conforms to the proper cross
section, all drainage or dewatering facilities are
205.02.01 Uniformity of Material operating, and that the embankment site is in the
best condition possible to protect against erosion
The proper blending of materials is very essential from runoff or working in a wet condition.
in obtaining proper embankment consolidation.
The use of graders, or similar equipment, The selection of the equipment used to haul the
ordinarily will accomplish the desired result in embankment materials is usually the
most soils. When it is necessary to place unlike Contractor’s option. The Contractor should not
materials in the same embankment layer, care be allowed to operate the equipment in such a
should be taken to use equipment and methods manner that it will be harmful to any section of
that will provide a satisfactory blend of these the completed roadway. The soil may be spread
materials. The result of the blending should be a with the hauling equipment or with blade
mixture that can be uniformly compacted after graders, bulldozers, or other acceptable
moisture has been applied using a uniform rate equipment.
of application. When feasible, poorer materials
should be used in the lower portion of the 205.02.03 Layer Thickness
embankment. Standard proctor compaction
molds should be made of each material type Good compaction is ordinarily obtained when
blend, for comparison of ideal moisture content earth embankment layers are relatively thin.
vs. compaction density to actual soil density tests Unless otherwise specified, experience indicates
taken during the installation of the compacted that the required density can easily be obtained
layers. by constructing layers 15 to 20 centimeters or
less in loose depth.
205.02.02 Hauling, Spreading, and Shaping
205.02.04 Moisture Content
Before beginning the construction of an
embankment, the location of the construction The success of compaction operations is
should be clearly outlined by construction stakes. dependent to a large extent on proper moisture
Any staking that is done by the Contractor control. If the proper amount of moisture is
should be checked by the Resident Engineer. uniformly distributed throughout the
Stakes that are disturbed or destroyed should be embankment layer, rarely will there be any
reset immediately. The use of this system of difficulty in obtaining satisfactory compaction,
checks will avoid errors discovered in provided the thickness of the layer does not
embankment slopes or widths after construction exceed the capabilities of the equipment being
of the embankment has advanced to the point used. The common tendency to construct earth
where corrective measures are difficult and embankments at moisture contents on the dry
costly. side of optimum makes the task of securing
uniform moisture distribution and satisfactory
Washes, holes, and other low areas in the compaction more difficult. Usually it is better to
embankment foundation should be filled and begin compaction with the moisture content
compacted before beginning the construction of slightly high. In humid areas it may be better to
the first lift of embankment. The first lift should begin with the moisture content at optimum.
begin in the low areas with the intent of
eventually providing an embankment layer
200-7
CONSTRUCTION SUPERVISION MANUAL Section 200
The mixing and blending of soils and water obtained. This moisture range is indicated by the
should be thorough. Lumps must be broken moisture-density curve.
down to ensure a uniformly moist condition.
When adding water to a layer of material, care Good compaction depends on the moisture
must be taken to avoid overlapping or gapping content of the materials being compacted. Too
between successive passes of the water wet or too dry a material will not compact as
distribution equipment. Wet or dry streaks are required no matter how many passes are made
undesirable and should be avoided. The with the roller. In this event, the Inspector
equipment operator should be instructed to begin should advise the Contractor so that he might
applying water on one side of the embankment take the appropriate action. Succeeding lifts
and work progressively across the fill to the other should not be placed until the moisture-density
side to avoid having wet or dry streaks in the requirement is met. If the embankment is wet,
center of the embankment. The importance of discing and/or drying is necessary before
making several light applications rather than one compacting. The Contractor is required to aerate
heavy application of water should be the material or distribute and incorporate water
emphasized. It is desirable to have the moisture uniformly as necessary to control the moisture
pre-mixed prior to placing and compacting the content. Where the moisture is within limits, but
material in the final course or layer density is not, additional compaction is required.
• Water should not pond in the ditches. Once the material has been moisture-conditioned,
Ditches and channels must be constructed the fill layer is graded and leveled uniformly
and maintained in such a manner as to avoid using a motor grader. The grader operator is
damage to the roadway. assisted by a grade checker who communicates
the overfill or deficit areas from the survey grade
• Eroded areas due to storm water runoff stakes to the operator as the work progresses.
should be recompacted to match adjacent Once the layer has been placed satisfactorily the
levels prior to resumption of compacting the rolling operation proceeds.
next layer.
A steel-wheeled vibratory roller will provide the
205.02.06 Compaction required compactive effort in most low plasticity
soils with a minimum number of passes. In
As required by the specifications, each layer higher plasticity soils, a sheeps foot roller may
must be compacted to a density not less than 95 also be used to compact the material. The
percent of the relative maximum density. When selection of equipment is the Contractor’s
95 percent maximum density is required, the prerogative and he will normally use equipment
moisture content of the material must be within that achieves the required compaction
the range of values at which this density can be consistently and with the fewest number of
200-8
CONSTRUCTION SUPERVISION MANUAL Section 200
200-9
CONSTRUCTION SUPERVISION MANUAL Section 200
When finished, the subgrade will be smooth and • A complete record of all the density tests
level in all directions and properly compacted. made to determine the acceptability of
The Resident Engineer will inspect the subgrade embankment, with remarks which explain the
and give the final approval for placing the corrective action taken at locations where
pavement materials on it. The Contractor is failing test results were obtained and reasons
responsible for ensuring that the subgrade will be for not making the required tests at other
protected from traffic damage and moisture loss locations.
until the paving operation starts.
• Complete records of manpower and
207 RECORDS equipment usage needed for analysis of any
time or cost claims. This is important in
The Resident Engineer will ensure that a daily determining the amount of delay should the
record of events on the project is maintained. The Contractor be delayed for any reason.
Inspector’s diary should include the following:
208 MEASUREMENT AND
• The limits of the work accomplished for the
PAYMENT
day.
Project records must be kept by the Resident
• A complete record of equipment, labor, and Engineer in such a manner that all partial
materials used in any operation that is, or progress and final payments can be easily and
may later be determined to be, extra work. clearly supported by recorded data. This data
should include when the work was completed,
• The number and classifications of labor measurements and calculations to support the
used. quantities, and should be initialed or signed as
required by the persons who made the
• Discussions of project prosecution with the calculations and measurements. A continuous
Contractor’s representative that are of an record should be kept via immediately recording
unusual nature. If a discussion of a problem the completion of the work by the appropriate
leads to specific recommendations or BOQ unit such as each, square meter, etc.
instructions being given the Contractor,
record it. The quantities involved in the earthwork shall be
measured and paid for according to the Standard
• Weather conditions and their effect on
Specifications.
quality and workability of earthwork
materials.
Figure 200.01 identifies what documentation is
• Damage to private property or utilities required to support the earthworks operations for
caused by the Contractor’s equipment during measurement and payment and the individuals
the operation should be noted and the action with primary and secondary responsibility to
taken recorded. record it.
• The final disposition of salvageable Interim payments for lump sum items should be
materials should be noted. based on rational methods, such as for building
demolition, where payment could be based on
• Measurements and notes made to actual volume of buildings demolished (floor
substantiate the classification and quantity of area x height) prorated to the total volume to be
the various materials encountered in the demolished.
excavation.
200-10
CONSTRUCTION SUPERVISION MANUAL Section 200
Figure 200.01
RESPONSIBILITY MATRIX
Responsibility
Materials Technician
Resident Engineer
Quantity Surveyor
Municipality
Contractor
BOQ Unit
Inspector
Surveyor
Item Description Required Documentation
Existing Pavement/ NSP * Site Measurements z
Sidewalk Removal * Quantity Calculations z
Green Area Removal NSP * Municipality Approval z
* Field Notes/Diary z
* Flagging/Staking z
Clearing & Grubbing NSP * Field Notes/Diary z
* Flagging/Staking z
Buildings & Demolition LS * Field Notes/Diary z
* Flagging/Staking z
Removal of Obstructions CM * Field Notes/Diary z z
* Existing Condition Measurements z
* Quantity Calculations z z
Unclassified Excavation CM * Existing Condition X-Sections z
* Finished Grade X-Sections z
* Quantity Calculations z
Borrow Material CM * Source Approval z z
* Existing Condition X-Sections z
* Finished Grade X-Sections z
* Quantity Calculations z
Unsuitable Material CM * Diary z
* Removal Measurements z z
* Borrow Material Calculations z
Borrow Placement NSP * Moisture Content z
* Compaction z
* Grading/Placing; Layers, z
Drainage, Uniformity
Subgrade Preparation NSP * Finish Grade Levels z
* CBR Tests- Existing z
* Scarifying z
* Moisture Content z
* Compaction z
* Grading/Placing z
z - Primary Responsibility
- Secondary Responsibility
NSP - No Separate Payment
200-11
CONSTRUCTION SUPERVISION MANUAL Section 300
Asphaltic base courses are discussed in Section • Los Angeles abrasion tests
400.
• Sulfate and chloride content
302 AGGREGATE SUBBASE
• Sand equivalent test
COURSES
302.01 DESCRIPTION The Inspector must be assured that all
preliminary tests have been made and that the
proposed material is acceptable when placed.
The aggregate subbase course is placed
Frequent discussions with the Resident Engineer
immediately above a prepared subgrade. This
will no doubt be necessary, particularly when
course usually consists of granular materials
base operations are first started. This is a
such as crushed stone, crushed or uncrushed
crucial period since many trials are sometimes
gravel, and sand that has been obtained from a
necessary before the Contractor can produce
source that has been approved by the Engineer.
consistently acceptable aggregate. Regardless of
the difficulties encountered, no base should be
Aggregate subbase is usually specified where a
accepted which does not meet the requirements.
free-draining material is desirable.
If substandard material is inadvertently placed it
300-1
CONSTRUCTION SUPERVISION MANUAL Section 300
should be removed and replaced. The Contractor An Inspector shall be present at all times when
should not be allowed to haul substandard material is being deposited on the road to see that
material onto the work site. proper spacing of loads is maintained.
Contractor’s personnel shall see that loads are
302.03 TESTING dumped uniformly and in the proper location and
amount to conform to the required cross-section
after compaction. The loose material should be
Sampling and testing of the proposed aggregates
placed a little more than the specified maximum
should be done according with the Standard
thickness to allow for compaction. The aggregate
Specifications, Section III, Subsection 300.06.
material should not be dumped in piles but
As the basing operations proceed, testing should
should be spread either by traveling truck or by
be done on a continuing basis. Maximum
use of mechanical spreaders.
density and optimum moisture should be
determined according to AASHTO T180. The
Spreading is usually done with loaders and motor
Resident Engineer has the responsibility to have
graders. Hauling over the subgrade should be
materials that do not comply with the
avoided as much as possible. The aggregate
requirements of the Standard Specifications
should be transported to the dumping point over
rejected and removed from the project. Rejected
the aggregate that was previously placed, and
materials that have been corrected and re-tested
then dumped on the end of the preceding
are not to be used until written approval is given
aggregate. Precautions should be taken when
by the Resident Engineer.
spreading the aggregate to avoid segregation;
that is, the large stone separating from the fine
302.04 PLACING
portions. If segregation does occur, the
Contractor should be required to re-mix the
Subbase and base materials are usually more aggregate by blading, rototilling, or by other
expensive than the subgrade material. Each layer acceptable methods.
of material must be finished to the specified
tolerance so that the next, more expensive layer This is especially important when placing
will not be used needlessly. The subgrade surface material over geotextile fabric. In areas of high
upon which the material is to be placed should be ground water, aggregate materials need to be
carefully examined. The subgrade should be clean and free draining which requires geotextile
moist to prevent the loss of moisture from the material to resist the movement of fine material
aggregate during compaction operations. Soft into the base course and compromising the
spots, ruts, and grade deficiencies should have strength of the foundational materials.
been corrected by removing, replacing material,
or regrading where necessary. The top of the The Inspector should be constantly alert during
subbase should be shaped to the required grade placement to detect changes in the appearance of
and cross section and smoothed to provide the aggregates, particularly on pit run material,
drainage. Subbase or base materials shall not be so that tests may be made immediately on the
placed until the subgrade preparation has been changed material. Often, excessive silt, clay, or
completed and approved by the Resident organic matter inadvertently becomes mixed with
Engineer. It is important that subbase installation the base material and should be removed. An
proceeds quickly after completion and approval excess of these materials is very detrimental to
of the subgrade preparation. However, a the base since they reduce the strength of the
sufficient amount of subgrade shall be prepared base when it is saturated with water. Constant
and approved for placement of base materials so vigilance accompanied by testing will help assure
that the construction procedures for either that detrimental materials are not used.
operation are not compromised.
300-2
CONSTRUCTION SUPERVISION MANUAL Section 300
When the plan thickness of the base is greater moisture content, as it may easily be for
than 15 centimeters, the base must be granular-type material, water should be added as
constructed in multiple courses. Each course indicated by the specifications.
should be such that its thickness after
compaction does not exceed 15 centimeters. The The water may be introduced by one of the
surface of the first course may require the light following methods:
application of water before the spreading of the
aggregate for the next course. The spreading, • Passing of the materials through a stationary
balancing, and reshaping of the second and plant, mixing in the water thoroughly.
successive courses should be done in the same
manner as they were for the preceding course. • The water may be added to windrows on the
Care should be taken to ensure that the density of road and mixed by blading back and forth or
a given course is not disturbed by the operations rototilling.
of the subsequent course.
• Prewetting of stockpiles.
The moisture content at which compaction can
be most easily obtained, with a stated amount of In any case, thorough and uniform distribution
compaction effort, is referred to as the optimum of the water must be obtained throughout the
moisture content. Laboratory tests will reveal material. Moisture added to the surface aids
the moisture content that constitutes optimum only the material near the surface. The material
moisture content. The in-place density should be at the bottom of the layer does not receive the
determined according to AASHTO T205, or needed moisture and therefore ultimate
other specified density test. If the natural compaction will be less at that level. Water must
moisture content of the available material is be added to the surface to replace that lost by
found to be low, compared to the optimum evaporation during processing.
300-3
CONSTRUCTION SUPERVISION MANUAL Section 300
• Steel-wheeled rollers
Aggregate base and subbase materials are
moisture tolerant and the moisture density curve • Pan-type vibrating compactors
exhibits a relatively wide range of moisture
values where the specified density can be In most cases, pneumatic rollers and vibratory
achieved. However, watering of aggregate base rollers will be used to compact aggregate base
and subbase courses must be done with care. and subbase courses. Most of the compaction is
Excess watering is wasteful, but more important, achieved by the vibratory or steel-wheeled
it may result in the saturation of the subgrade rollers.
with serious damage resulting. The Engineer and
Inspector should be on the lookout for any soft Typically, compaction starts with rollers from
spots which might develop in the roadway the extreme sides and gradually proceeding
following excessive watering. Most of the water toward the axis of the road. Rolling continues
that falls on granular material penetrates to the until a relative density of not less that 95 percent
subgrade almost immediately. Any “sponginess” of the maximum dry density has been obtained.
or “pumping” and resultant movement under Each layer of the aggregate base and subbase
wheel loads is usually first noticed as excessive courses applied to the roadway must be watered
looseness of base materials. If this condition and compacted to the required density before the
should occur, a thorough investigation shall be placing of successive layers.
made and corrective measures taken before the
prime coat is applied. The most positive means of determining the
adequacy of water and compaction effort is by
302.06 COMPACTION density tests. The amount of compaction that will
be required, is normally expressed as a
Compacting means rolling the aggregate with percentage of the maximum density achieved
equipment in order to obtain the required density with the “Modified Proctor” (AASHTO T180)
in the base course. Strength and durability of the tests. The in-place density should be determined
base course are directly related to the density. according to AASHTO T205.
The first course should be compacted to the
required density. Then, the spreading of the More frequent testing at the beginning of the
second course may take place. The second course work will usually pay off by preventing over-
should then be shaped and compacted to the watering and over-rolling and by providing the
required grade, cross section, and density. The Inspector with a “feel” for the material. It is
same process should be repeated for each stressed again that the Inspector needs to be alert
successive course. to over-watering which can damage the
subgrade.
302.07 COMPACTION EQUIPMENT
Once the required moisture content and
compaction are achieved it must be maintained.
The Contractor is free to determine the types and
This can be accomplished by the continuous
numbers of compaction equipment he will use
addition of small amounts of water to replace
and the patterns they will follow. The main
moisture lost by drying of the surface.
concern of an Inspector is that adequate density
is obtained throughout the base course.
302.08 FINISHING
Machinery most commonly used to apply the
compaction effort may be any one or a Finishing operations include the shaping,
combination of the following: trimming, and rolling necessary to leave the
aggregate base at the proper grade, cross section,
• Pneumatic-tired rollers and surface condition. It should be noted that it
is the Contractor’s responsibility to correct the
300-4
CONSTRUCTION SUPERVISION MANUAL Section 300
¾
rollers. The rubber tires seal the base, prior to
ultimate sealing by the prime coat, leaving a Additional aggregate placed without
smooth hard surface. scarifying the underlying surface.
Finishing equipment used to shape the compacted ¾ Foreign objects in the base.
base course to the proper grade and cross section
In such places, the surface must be first
typically consists of a motor grader. The
scarified, so that the added aggregate will
scarifying attachment on the grader is used to
mix in and bond with the material.
loosen the base surface so that shaping can be
accomplished and a smooth base surface can be • Cracks and Checks: Cracks and checks
provided. appearing in the compacted base course may
be caused by the underlying aggregate being
Some of the most common difficulties found for
too wet or defects in the subgrade such as
proper finishing, their possible cause, and
the material not being properly mixed with
correction are as follows:
an area of segregated fine material on the
• Areas of Failing Density: Insufficient surface. In these areas, the defective
density within certain areas may be due to underlying base needs removal and
the moisture content not being correct or a correction as necessary.
lack of rolling done in those areas.
• Contamination: Contamination of aggregate
Considering the cause, different correction
bases occurs when the subgrade materials
procedures may be needed: wetting and
become mixed with the base material. To
remixing, or drying by scarifying and
correct the situation, the Contractor should
remixing, then the required reshaping and
dig out and remove the mixed materials. He
recompacting.
should then reshape, compact the subgrade,
• Areas not to Eveness and Grade: Areas of and replace the material removed with clean
the base that are too high are generally aggregate.
caused by insufficient spreading and
compacting. Such areas can be trimmed to
CHECKING GRADE
acceptable evenness. Areas that are too low
will need the application of additional
aggregate material. These areas must be
Checking the grade and shape of the finished
scarified, the new material added, then
aggregate surface is done using the following
reshaped and compacted.
methods:
• Wet, Spongy Areas: Wet spongy areas • Hand Levels
• String Lines
usually occur due to over-watering. These
• Cross Sections
areas can be repaired by scarifying, aerating,
• Straightedge
reshaping, and recompacting. In some
instances, more aggregate may have to be
added.
300-5
CONSTRUCTION SUPERVISION MANUAL Section 300
300-6
CONSTRUCTION SUPERVISION MANUAL Section 300
300-7
CONSTRUCTION SUPERVISION MANUAL Section 400
Equipment and procedures common to both types The aggregate used in the mix is removed from
of plants are as follows: the stockpiles and placed in individual cold-feed
bins. Each different size aggregate is
• Aggregate stockpiling proportioned out of its bin by the size of the
• Cold-feed systems opening of the gate at the bottom of each bin or
• Asphalt cement supply system by use of a variable-speed belt feeder.
• Surge silos Generally, belt feeders beneath the bins deposit
each aggregate on a gathering conveyor located
• Emission control equipment
under all the cold-feed bins. The gathering
conveyor transports the combined aggregate to
When the plant is set up and ready to operate,
the charging conveyor, which carries it up to the
the Resident Engineer should make a thorough
aggregate dryer.
examination of the equipment. Checking is done
for compliance with the Standard Specifications,
The dryer operates on a counter flow basis. The
Section IV-1, Subsection 401.02. The Resident
aggregate is introduced into the dryer at the
Engineer should become familiar with plant
upper end and moves down the drum both by the
features determining the mechanical condition of
drum rotating (gravity flow) and by the flight
each component part and examine each
400-1
CONSTRUCTION SUPERVISION MANUAL Section 400
configuration inside the rotating dryer. The slope the weigh bucket is discharged into the pug mill
of the dryer, its speed of rotation, diameter, and the wet-mix time begins. The mixing time
length, and number and design of flights control for the blending of the asphalt cement with the
the time required for the aggregate to pass aggregate should be no more than that needed to
through the dryer. Aggregate passes from the completely coat the aggregate particles with a
dryer to the hot elevator through a discharge thin film of the asphalt cement material. The
chute that is located near the burner end of the total time in the pug mill, made up of dry-mix
dryer. The burner is located at the lower end of time and wet-mix time, can be as short as 28
the dryer, and the exhaust gases from the seconds in most cases.
combustion and drying process move toward the
upper end of the dryer, against the flow (counter When mixing is complete, the gates on the
to the flow) of the aggregate. As the aggregate is bottom of the pug mill are opened and the mix is
tumbled through the exhaust gases, the material discharged into the haul vehicle or into the
is heated and dried. Moisture is removed and conveying device that carries the mix to a silo
carried out of the dryer as part of the exhaust gas and eventually into the truck. For most batch
stream. The hot, dry aggregate is discharged plants, the time needed to open the pug mill gates
from the dryer at the lower end. and discharge the mix is approximately 7
seconds, thus the total mixing time for a batch
The hot aggregate is transported to the top of the would be about 35 seconds (Dry-mix time + wet-
plant mixing tower by a bucket elevator. Upon mix time + mix discharge) in most cases.
discharge from the elevator, the aggregate
normally passes through a set of vibrating The plant is equipped with emission-control
screens. The finest aggregate material goes devices, both primary and secondary systems.
directly through all the screens into the number 1 Either a wet-scrubber system or a dry-fabric
hot bin. The coarser aggregate particles are filter system (bag house) can be used as the
caught by the different size screens and deposited secondary collection system to remove
into one of the other hot bins. The separation of particulate matter from the exhaust gases that
aggregate in each of the hot bins depends on the flow out of the dryer and send clean air to the
size of the openings in the screen that is used in atmosphere through the stack.
the screen deck and the gradation of the
aggregate in the cold feed bins. If recycled asphalt pavement is incorporated into
the mix, the material is placed in a separate cold-
The aggregate is held in the hot bins until it is feed bin from which it is delivered to the plant.
discharged from a gate at the bottom of each bin It can be added to the new aggregate in one of
into a weigh hopper. The correct proportion of three locations: bottom of the elevator, the hot
each aggregate is determined by weight. If bins, or the weigh hopper, with the last location
reclaimed material is used in the mix, it typically being the one most commonly used. Heat
is entered into the weigh hopper as an additional transfer between the superheated new aggregate
aggregate. and the reclaimed material begins when the two
materials come in contact and continues during
At the same time that the aggregate is being the mixing process.
proportioned and weighed, the asphalt cement is
pumped from its storage tank to a separate weigh 401.01.03 Continuous Mix Plants
bucket located on the tower just above the pug
mill. The proper amount of material is weighed The components of this type of plant include the
into the heated bucket and held until it is needed cold-feed system, asphalt cement supply system,
in the pug mill. aggregate dryer, hot bucket elevator, screen unit,
hot bins, mixing unit and holding hopper, and
The aggregate in the weigh hopper is emptied emission control system.
into a twin shaft pug mill, and the different
aggregate fractions are mixed together. After The cold-feed bins are similar to those used on a
this brief dry-mix time, the asphalt cement from batch plant, and typically a constant-speed feeder
400-2
CONSTRUCTION SUPERVISION MANUAL Section 400
belt is located under each bin. Material is gates, and a tunnel and conveyor system.
proportioned from each bin by the size of the The plant Inspector is responsible to ensure
discharge gate opening and deposited on the that the gates are adjusted so that the
gathering conveyor. The aggregate is transferred aggregates, in the proper quantity and size,
to a charging conveyor for delivery to the dryer. are delivered through the plant to maintain
Inside the dryer, the moisture in the combined uniform production according to the job-mix
aggregate is removed as the material is heated formula without overflowing.
from ambient temperature to the desired mixing
temperature. The dried and heated aggregate is 2. Dryer The component parts of the dryer
then carried up an inclined bucket elevator to the consist of the following:
screen deck, where it is divided into various sizes
and temporarily held in small hot bins. • A rotating cylinder (dryer) usually from
1 to 3 meters in diameter and from 6 to
The aggregate is continuously removed from the +12 meters long.
bins, proportioned according to the desired
• A burner that is either gas or oil fired.
gradation in the mix, and transported to the pug
mill. The asphalt cement is kept in a storage
• A fan that may be considered part of the
tank and then pumped to the mixing tower, where
dust collector system, but its primary
it is sprayed on the aggregate. The asphalt
function is to provide the draft air for
cement, measured by volume instead of weight,
combustion in the drum.
is mixed continuously with the aggregate as the
two materials are moved toward the discharge The sensing element of a thermometric
end of the pug mill by the mixing paddles. instrument should be located in the discharge
Mixing time can be increased or decreased by chute to record or show the temperature of
changing the retention or dwell time of the the aggregate as it passes from the dryer. A
aggregates in the pug mill, usually by altering the pyrometer or other type of instrument is
setting of the pug mill discharge end gate or by used. The aggregates should be heated to a
reversing one or more sets of paddles. temperature between 135º C and 163º C at
the time of mixing. The temperature will
Because the mixing is a continuous process, a vary depending on the characteristics of the
small capacity, temporary holding hopper is asphalt plant. The sensing element also
provided at the discharge end of the mixer to starts the automatic burner controls.
store the material until it can be delivered into a
haul truck. For emission-control purposes, the 3. Dust Collector The fan exhausts the draft air
plant is equipped with a primary dry collector from the upper end of the dryer and other
and a secondary wet collector or a bag house. components of the plant into the dust
collector system. The system may be
If a recycled mix is being produced, the recycled composed of either a bag house, cyclone
asphalt pavement material is placed in a separate collector, wet washer or “scrubber”, or some
cold-feed bin and transported to the pug mill by a combination. This draft air contains dust
charging conveyor. This material is added particles, vapor, and gases that must be
proportionately, by volume, to the new aggregate reduced or controlled before emission into
that has been superheated in the dryer. The heat the atmosphere. As stated in the Standard
transfer and mixing of the two materials is Specifications, collected dust may be
accomplished as they move through the pug mill. reintroduced into the flow of aggregate.
401.01.04 Plant Component Descriptions 4. Screening Unit On most plants the screening
(Batch and Continuous) unit is of the flat table vibrating type, usually
equipped with four decks. The size of the
1. Cold Aggregate Feeder The cold aggregate screens on the decks varies with the type of
feeder in a commercial plant may be bituminous concrete to be produced. The
equipped with separate bins, adjustable top deck is covered with a scalping screen
400-3
CONSTRUCTION SUPERVISION MANUAL Section 400
that removes all the oversize material and Asphalt cement is usually weighed into an
discharges this material into a reject chute. overflow-type bucket suspended on a
The screening unit should be cleaned daily weighing mechanism with a springless dial
and checked for loose or torn screens. scale.
5. Graded Aggregate Bins The bituminous When the plant is ready to operate, the scales
plant should be equipped with the number of should be cleaned, each part carefully
aggregate bins required by the specifications. checked, and load tested by a commercial
These bins hold the heated and screened scale mechanic for the accuracy specified.
aggregates in various size fractions required Each scale should be equipped with a quick
for the type of bituminous mixture to be adjustment to zero to compensate for
produced. The bin partitions must be tight, accumulations of dust and asphalt cement
free from holes, and of sufficient height to during production operations. Mixing plants
prevent the intermingling of aggregates. should have the required number of test
Each bin should be equipped with an weights nearby for frequent testing of all
overflow pipe that will discharge any excess scales.
aggregate from the bin. Bin shortages or
excesses should be corrected by adjusting The Contractor may provide an approved
any or all of the following as required: automatic printer system that will print the
weight of each material delivered, provided
• The cold feeder gates. the system is used with an approved
• The screen sizes. automatic batching and mixing control
• The hot bin pull weights. system.
On batch plants the bottom of each bin is 7. Graded Aggregate Bin Control Gates Up to
fitted with a discharge gate that may be the point of discharge from the graded
operated manually or automatically. The aggregate bins, the functions of the
gate’s closure should be positive enough to continuous-mix plant and the batch-mix
ensure that no leakage into the weight box plant are essentially the same. In
will occur. On continuous-mix plants the continuous-mix plants, the proportioning of
gates must be adjusted and locked in place to the separate sizes of aggregate is
provide a continuous and uniform flow of accomplished through the adjustable gates on
material from each bin to the pug mill mixer. the feeder of the gradation unit. These gates
Samples of aggregates from these bins may deposit the aggregates onto the elevator to be
be secured from “gates” or “windows” in the delivered directly to the pug mill. The
sides of the bins, or by diverting the flow of asphalt cement is delivered to the pug mill
aggregates from the bins into the sampling through a calibrated metering pump. The
containers. aggregate feeder and the asphalt cement
pump are geared to a common power source
6. Scales On the batch-mix plant, a weigh so that proportions of aggregate and asphalt
hopper for the aggregate is found directly cement remain constant, regardless of
under the graded aggregate bins. The weigh variations in power supply.
hopper is suspended on a weighing
mechanism that is generally equipped with a Before production begins, a careful
springless dial scale. Aggregate weight from calibration of the flow of aggregates from
each bin is marked accumulatively so that each feeder gate must be made. The rate of
the last mark will read the total amount of flow of aggregate from each bin is
aggregate in each batch. The sequence of determined by weighing the amount
weighing from each bin must be strictly discharged at various openings and
observed. The recommended practice is to computing the quantity delivered per
weigh the coarse aggregate fraction first. revolution of the feeder drive shaft. A curve
is then plotted for each gate, showing pounds
400-4
CONSTRUCTION SUPERVISION MANUAL Section 400
of aggregate per revolution against the gate • The temperature of the combined
opening in centimeters. materials.
• The quantity of materials in the mixer.
The Contractor must furnish a copy of the • The clearance between the paddle tips
manufacturer’s operating instructions, that and liner plates.
will show the operating speed of the feeder
and the asphalt cement pump delivery rate The paddle tips and liner plates should be
for the various sprocket sizes. The sprocket checked for excessive wear and when the
size for the asphalt cement pump must be clearance exceeds the dimensions specified,
checked for the delivery rate required, by the paddle tips and liner plates should be
weighing the quantity of material pumped replaced.
into a container over a carefully timed
interval. A thermometer must be installed in The mixers of batch-mix plants and
the circulating line just ahead of the pump. continuous-mix plants are essentially of the
This is done as the temperature of the same design, except for the variations in
asphalt cement must be controlled within a arrangement of the paddle tips. In the batch-
very narrow range to control fluctuations in mix mixer, the materials are dumped into the
percentages of asphalt cement in the mixture. center of the mixer and the paddle tips are
arranged to give an end-to-center mixing or a
8. Asphalt Cement Control Unit Satisfactory run-around (figure eight) mixing pattern.
means should be provided, either by The material is held in the mixer for the
weighing or metering, to obtain the proper required mixing time and then discharged
quantity of asphalt cement in the mix within through the discharge gate into the
the tolerance specified. Means should also transporting vehicles. The mixer should be
be provided for checking the quantity or rate equipped with an automatic timing device to
of flow of asphalt cement as it passes into regulate the dry-mixing and wet-mixing
the mixer. periods automatically and a batch counter to
accurately record the number of batches
9. Pug Mill Mixer After proportioning, the produced. In a continuous-mill pug mill, the
aggregate and asphalt cement are introduced materials are introduced in one end of the
into the pummel for mixing. The pug mill mixer and the paddle tips are set to transport
mixer should consist of twin shafts equipped the materials to the discharge end as the
with paddles for mixing the ingredients into a mixing is accomplished.
homogeneous mass. The main parts of the
pug mill mixer are: The degree of mixing varies with the depth
or volume of material in the pug mill, which
• The paddle tips can be controlled by the following:
• The paddle shanks
• The spray bar • Raising the dam on the discharge end of
• The liners the mixer to hold the material in the
• The shafts mixing unit for a longer period and at a
• The discharge gates depth that will intensify the mixing
• The heated jacket action.
400-5
CONSTRUCTION SUPERVISION MANUAL Section 400
based upon the ability of the holding bin to gates must be adjusted to deliver the proper
hold and discharge mixtures within the proportion of aggregates to the gradation unit. A
quality criteria specified in the job-mix sieve analysis of the aggregates from each bin of
formula without segregation. Discharge into the gradation unit should be made to calculate
the surge/storage bins should not be a direct the bin weights (or gate openings and pump
stream but through a batching device (job- sprockets for a continuous-mix plant) required to
hopper). produce a mixture that will conform with the job-
mix formula. It is important to draw several dry
11. Haul Trucks and Scales Haul trucks used to batches through the plant. This will give the
transport the mixture to the roadbed should screening unit a chance to operate at normal
be in good operating condition, capable of operating speed before securing the samples used
hauling the mixture without spillage, and in making the sieve analysis. The hot bin
capable of dumping into the asphalt paver or weights determined from these screen analyses
windrow sizer. Before beginning hauling will be used to start production of the plant. The
operations, each truck will be assigned a procedures for establishing bin weights, sample
number. The inside of each truck bed may forms, and possible causes of fluctuations in
be lightly coated with a soap detergent gradation, density, and stability results are
solution, lime water solution, or an approved generally explained in publications governing the
commercial oil emulsion (soluble oils) in the design and production of concrete mixtures.
proportions recommended by the
manufacturer. If such coatings are applied, 401.01.06 Inspection During Mixing
truck bodies should be rinsed immediately Operations
before loading to remove excess coating
material. The use of diesel fuel, kerosene, or Before the beginning of each day’s production,
other like products as a truck bed cleaning the Plant Inspector should check to see that the
agent is not to be allowed. When required various gates, scales, timers, etc., are accurately
by the specifications, the truck beds must be set before mixing begins. In addition, the
properly insulated and equipped with screening unit, bins, and overflow vents should
suitable covers. be checked and cleaned. The recording
thermometer charts for the previous 24-hour
Truck scales or hanging weight hoppers period should be collected, dated, and filed in the
under holding bins of the size and type project records.
specified for the project should be furnished
and installed by the Contractor. A After mixing begins, and throughout the day, the
commercial scale mechanic should supervise Inspector must make the required job control
the installation and provide the initial check tests or submit samples to the central laboratory
on the accuracy of the scales. Periodic for testing. If possible, an assistant should do
checks for accuracy, during construction, the routine tests leaving the Plant Inspector free
should be made by the Resident Engineer to observe all the plant operations at frequent
according to specification requirements. intervals. The Plant Inspector should also
Accuracy checks should be recorded in a schedule periodic visits by personnel from the
field book as part of the permanent project central laboratory to check raw materials and the
records. final product at the plant. The experienced Plant
Inspector’s presence around the plant will
401.01.05 Establishing Mix Proportions contribute much to the production of a uniform
mixture.
The Resident Engineer should furnish the Plant
Inspector a copy of the job-mix formula after it During the day, the Inspector should make
has been approved by the central laboratory. periodic checks of the following:
During the preliminary operating period and
before securing any samples, the cold feeder
400-6
CONSTRUCTION SUPERVISION MANUAL Section 400
• The aggregate stockpiles, cold feeder gates, • The weighing and mixing operations.
and overflow vents for any overflow of the
graded aggregate bins. • Observing the mixture in the trucks for
uniformity in appearance.
• The temperature of aggregates, asphalt
cement, and mixture in trucks. The Inspector should observe the work of the
scale person on the truck scales at the plant, and
• The allowable tolerance in gradation for each should see that the required tests of the scales are
hot bin to ensure that it is not exceeded and done. The Inspector should see that the daily
that the gradation of the finished mixture totals are promptly obtained, checked, entered on
does not vary from the specification limits. the daily report, and made a part of the
permanent job records.
• The proper dryer operation.
400-7
CONSTRUCTION SUPERVISION MANUAL Section 400
400-8
CONSTRUCTION SUPERVISION MANUAL Section 400
however, provisions should be made to sample 401.03.04 Duties before Paving Begins
the asphalt from the sample valve located in a
circulatory feed line to obtain verification The Road Inspector should be thoroughly
samples. familiar with the plans and specifications for the
project and have the equipment necessary to
401.03 ROAD OPERATIONS check all phases of the paving operation. The
Inspector should check with the Contractor’s
Superintendent regarding the previously agreed
401.03.01 General
to paving sequence. The lift thickness shall not
exceed 5cm unless otherwise shown on the
The construction of an asphalt concrete
drawings or approved by the Resident Engineer.
pavement begins with the delivery to the roadbed
In addition, the Inspector should see that the
of a workable mixture proportioned and mixed
construction equipment required by the
according to the specifications. The pavement
specifications is on the project, and that the
should be constructed of the type of mixture,
barricades, warning signs, and other traffic
number of courses, and at the depth specified.
control equipment are in place.
Before delivery of the mixture, the surface to be
1. Layering The lift or layering sequence
paved should be shaped to the correct grade and
should be discussed and agreed with the
cross section, and compacted to the density
Contractor prior to the start of operations.
specified.
Subsequent layers should be placed as soon
as possible, but not before the preceding
If the paving operation sequence is not set forth
layer has been finished and cooled.
in the specifications, the Contractor should
Placement of subsequent courses (types)
submit a proposed sequence of paving operations
may not proceed until the previous course
to the Resident Engineer for approval. Once this
has been tested and approved for
sequence has been agreed upon, it will not be
conformance of the mix and density to the
changed without prior written approval.
specification requirements.
401.03.02 Traffic Control 2. Surface Preparation Before paving
operations, the Road Inspector should
Traffic control should be thoroughly discussed at thoroughly check the surface on which the
the preconstruction conference. At this time, pavement is to be placed. If the surface is a
definite traffic control procedures should be soil or aggregate, a prime coat, when
established that provide maximum safety for the required, should be applied and thoroughly
workers and the traveling public, with the least cured. On some soil bases a light
interruption of the work. All traffic control application of water should be applied for
devices and procedures used to direct traffic dust and/or moisture control. The surface
through the construction area should be should be checked for correct grade and
according to the Manual on Uniform Traffic cross section, and all work areas,
Control Devices (MUTCD) and of the type depressions, or potholes should be repaired
shown on the plans. to give a firm and unyielding paving base.
401.03.03 Weather When an existing surface is to be resurfaced,
the surface should be cleaned of dirt and
Weather and temperature limitations for this type other extraneous matter, all pavement defects
of construction should be according to the repaired, and cracks filled with approved
specifications. Plant production operations bituminous filler material. If a leveling
should be suspended at the imminent approach of course is to be applied, the existing surface
and during wet weather. should be checked and the roughest areas
marked to receive a pre-leveling course
400-9
CONSTRUCTION SUPERVISION MANUAL Section 400
before the leveling course. A tack coat, deficiencies in the condition of the equipment
when required, should be applied to all may be discussed and corrected. This will avoid
surfaces. The tack coat should be applied to delays once the work is under way and ensure
the width and length to be paved with that the best possible surface finish can be
consideration given to the operation of traffic obtained. Listed below are some of the more
and other factors. Tack coat application important details the Inspector should check
should be limited to the maximum area that during inspection of the paving equipment:
will be covered within the same day’s paving
operation. 1. Paving Machines The Inspector should
become familiar with the mechanical features
3. Grade and Alignment Controls The on the type of paver to be used on the
pavement edges should be marked by a project. In doing so, an intelligent appraisal
string line or paver guide line sufficiently in of the condition and adjustment of the
advance to ensure paving continuity. These machine may be made. Handbooks of
should be set and nailed to the surface at operating instructions are available from
intervals that will permit the line to be held each manufacturer, in which the various
taut and should be checked to be sure that adjustments and operating details are shown.
the proposed pavement width is obtained.
The profile grade controller on the paving 2. Rollers Steel-wheeled rollers should be
machine shall be activated by a traveling checked to determine that the wheels can roll
articulated averaging beam not less than in a true plane and that they do not have flat
9.14m in length or taut string line (wire) set spots or ridges. The steering and driving
to grade. mechanism must be free of excessive play, or
backlash, and the motor and driving
401.03.05 Inspection of Paving Equipment transmission free from oil leaks. Each roller
will be fitted with a water tank connected to
The Road Inspector should make a personal spray bars and mats on each wheel. The
inspection of the Contractor’s paving equipment, wetting mats should be checked for excessive
checking the condition and adjustment of the wear and the spray bars checked for proper
component parts of the paving machine and operation.
rollers. By making this inspection before the
beginning of the paving operations, obvious
9 On all paving machines the operating motor should be checked for proper governor operation, and to
ensure the motor operates smoothly, without missing.
9 On track-laying machines, the track linkage must be correctly adjusted and the tracks and pins checked
for excessive wear.
9 On pneumatic-tired machines, all tires should be inflated to the correct pressure, and the chain drives
checked for correct adjustment and/or excessive wear.
9 Tamper bars should be checked for correct R.P.M., proper clearance from screed, length of stroke,
and excessive wear on the tips.
9 Vibrators on the screed should be checked for proper height above the vibrating screed.
9 Screed plates should be checked for excessive wear, proper crown and tilt adjustment, and check that
the screed heating burner operates efficiently. Screed extensions should be in the same true plane and
flush with the screed bottom. Vibrators on a vibrating screed should be checked for proper operation.
9 Electronic grade and thickness controls should be checked for proper operation.
400-10
CONSTRUCTION SUPERVISION MANUAL Section 400
Pneumatic-tired rollers should be equipped Vehicles that impair the functioning of the
with smooth tires in good condition, of equal paver should be rejected.
size, ply, and equally inflated. Tire
pressures and loading of the roller may be 4. Miscellaneous Tools A check should be
varied to give the desirable ground contact made to see that the Contractor has available
pressures. All wheels should roll true, on the project an adequate supply of rakes,
without wobble or creep. shovels, brooms, and other small tools. The
Contractor should be properly equipped with
Vibratory rollers should be acceptable for portable barricades, cones, or other means of
bituminous mixture compaction and should protecting the freshly laid mixture from
be able to exert the compaction effort damage by traffic.
equivalent to steel-wheeled and pneumatic-
tired rollers with separate controls for energy 401.03.06 Mix Delivery
and propulsion. Vibratory rollers should be
capable of providing a smooth pavement Placing and finishing operations must be
surface, free of ridges, indentations, or other performed in daylight unless nighttime operations
objectionable features. The use of equipment are specifically approved by the Resident
that results in excessive crushing of the Engineer.
aggregate will not be permitted.
ROLLING OPERATION
400-11
CONSTRUCTION SUPERVISION MANUAL Section 400
Asphalt concrete mix delivered to the paving 401.03.07 Spreading and Finishing
location should be checked for the following:
The asphalt mixture is spread and finished by a
1. Uniform Rate The number of trucks, haul self-propelled paver. In small, irregular areas,
distance, plant capacity, capacity of paving the mixture may be spread and finished by hand.
and compactive equipment, and job site lay
down rate are all factors to be weighed by The principal duty of the Road Inspector is to
the Contractor in the efficient delivery of mix ensure that a pavement or base course is
to the site. Ideally, the paving machine constructed to the correct grade and cross section
should never have to stop and wait for a set forth in the plans, and with the surface
delivery, nor should more than 3 trucks be texture, density, and riding surface of good
queued at any time at the paver. The quality.
Inspector should continually monitor the
situation and ensure the Contractor is To begin paving operations with a paver, the
making proper adjustments in the delivery screed should be heated to the proper
schedule. temperature and grade controls set to construct
the longitudinal joint. This must be carefully
2. Temperature The Standard Specifications checked to ensure good riding qualities and that
require the mix to be delivered to the paver it conforms to the tolerance requirements before
at a temperature between 120°C and 160°C. the paver is allowed to continue. Particular care
The Contractor should be instructed to make should be exercised in setting the thickness
adjustments at the plant if the measured control device to ensure the spread and crown
temperature approaches or exceeds these required. When matching the edge of a
limits. In cold weather, the trucks should be previously laid section of pavement, the paver
covered to retain the heat rather than screed should overlap the existing edge 2.5 to 5
overheat the mix at the plant. centimeters. The thickness control should be
adjusted to leave the material slightly higher than
3. Appearance Each truckload should be
the previously laid section of pavement.
checked for uniformity and proper mixing at
Overlapping this edge will force enough material
the plant. Any experienced Inspector can
into this area to be sure that the joint is
detect potential problems, such as improper
completely filled and moisture proof. The height
temperature, asphalt content, or non-uniform
of the material above the previously laid edge of
mixing, through visual observation of the
pavement should be adjusted so that when the
mix in the truck and the flow characteristics.
longitudinal joint is properly compacted, the
pavement should be uniform in cross section
PAVING CHECKLIST within the tolerances specified.
400-12
CONSTRUCTION SUPERVISION MANUAL Section 400
detected. The Inspector must insist on prompt 4. Varying surface texture Insufficient mixing;
action to locate and correct any trouble that over mixing; overheating the mixture;
occurs. Some of the most common difficulties varying the dry mixing period; segregation of
met with and their possible causes are as follows: the mix in the trucks; worn or damaged
screed plate.
1. Wavy surface (short choppy waves) Worn or
poorly adjusted tracks or drive chains; the 5. Bleeding patches on the surface Asphalt not
truck driver setting the brakes too tightly; uniformly mixed; excessive moisture in the
excessive paving machine speed. mix; excess asphalt cement; too much tack
or prime coat.
2. Wavy surface (long waves) Excessive
variation in the amount of the mix carried in 6. Irregular rough spots in the pavement The
the auger box ahead of the tampers or roller is standing on the fresh surface; abrupt
screed; rolling too early; roller operating too reversing of the roller; trucks backing into
fast; over-controlling the screed. the paver; poor workmanship at the
transverse joints.
3. Excessively open surface texture Improper
adjustment of the tamper bar; improper When the paving machine is equipped with an
speed of the tamper bar; the screed plate is automatic grade control unit, it is essential that
rough or galled; excessive paving machine the paving crew and Inspector be thoroughly
speed. familiar with its operation and adjustments.
When this unit malfunctions, it tends to
compound its errors; therefore, the paver must be
stopped immediately, the pavement corrected,
400-13
CONSTRUCTION SUPERVISION MANUAL Section 400
Immediately after the asphalt mix has been The line of rolling shall not be changed suddenly
spread and struck off, the surface shall be or the direction of rolling reversed suddenly. If
checked and any irregularities adjusted and then rolling causes displacement of the material, the
compacted thoroughly and uniformly by rolling. affected areas shall be loosened at once with
hand tools and restored to the original grade of
To prevent adhesion of the mix to steel-wheeled the loose material before being re-rolled. Heavy
rollers, the wheels shall be kept properly equipment or rollers shall not be permitted to
moistened, but excess water will not be permitted stand on the finished surface before it has been
by the Engineer. compacted and has thoroughly cooled.
After the longitudinal joints and edges have been 1. Transverse Joints Transverse joints shall be
compacted, rolling shall start longitudinally at carefully constructed and thoroughly
the sides of the road and shall gradually progress compacted to provide a smooth riding
towards the center. On a super-elevated section, surface. Joints shall be checked with a
rolling shall begin on the low side and progress straight-edge to assure smoothness and true
to the high side, overlapping on successive trips alignment. Joints shall be formed with a
by at least one-half the width of tandem rollers bulkhead, such as a board, to provide a
and uniformly lapping each preceding track. The straight line and vertical face. If the joint has
rollers shall move at a slow but uniform speed been distorted by traffic or by other means, it
with the drive wheels nearest the paver. The shall be trimmed to line and the face shall be
speed shall not exceed 4.8 km/hr. for steel- painted with a thin coating of emulsified
wheeled rollers or 8.0 km/hr. for pneumatic-tired asphalt before the fresh material is placed
rollers. The operating speed shall be approved by against it. To obtain thorough compaction of
the Engineer. these joints, the material placed against the
400-14
CONSTRUCTION SUPERVISION MANUAL Section 400
joint shall be tightly pushed against the Care shall be exercised in consolidating the
vertical face with a steel-wheeled roller. The course along the entire length of the edges.
roller shall be placed on the previously Before it is compacted, the material along
compacted material transversely so that not the unsupported edges shall be slightly
more than 15 cm of the rear rolling wheel elevated with hand tools. This will permit the
rides on the edge of the joint. The roller shall full weight of the roller wheel to bear on the
be operated to pinch and press the mix into material to the extreme edges of the mat.
place at the transverse joint. The roller shall
continue to roll along this line, shifting its 4. Breakdown Rolling Breakdown rolling shall
position gradually across the joint, in 15 to immediately follow the rolling of the
20 cm increments, until the joint has been longitudinal joints and edges. Rollers shall be
rolled with the entire width of the roller operated as close to the paver as possible to
wheel. Rolling shall be continued until a obtain adequate density without causing
thoroughly compacted, neat joint is obtained. undue displacement. In no case shall the mix
temperature be allowed to drop below 107°C
2. Longitudinal Joints Longitudinal joints shall prior to breakdown rolling. If the breakdown
be rolled directly behind the paving roller is steel-wheeled, it shall be operated
operations. The first lane placed shall be true with the drive wheel nearest the finishing
to line and grade and have a vertical face. machine. Pneumatic-tired rollers may be
The material being placed in the abutting used as breakdown rollers.
lane shall then be tightly pushed against the
face of the previously placed lane. Before 5. Intermediate Rolling Pneumatic-tired rollers
rolling, the coarse aggregate in the material or steel-wheeled rollers, described in Clause
overlapping the joint shall be carefully 401.05, Rollers, of the Standard Specific-
removed with a rake and discarded. Rolling ations, shall be used for the intermediate
shall be performed with a steel-wheeled rolling. The intermediate rolling shall follow
roller. the breakdown rolling as closely as possible
and while the paving mix is still of a
The roller shall be shifted over onto the temperature that will result in maximum
previously placed lane so that not more than density from this operation. Rollers shall be
15 cm of the roller wheel rides on the edge of used continuously after the initial rolling
the newly laid lane. The rollers shall then be until all of the mix placed has been
operated to pinch and press the fine material thoroughly compacted. Turning of rollers on
gradually across the joint. Rolling shall be the hot paving mix which causes undue
continued until a thoroughly compacted, neat displacement will not be permitted by the
joint is obtained. Engineer.
When the abutting lane is not placed in the 6. Finish Rolling The finish rolling shall be
same day, or the joint is distorted during the performed with three-axle tandem rollers
day’s work by traffic or by other means, the unless otherwise permitted by the Engineer.
edge of the lane shall be carefully trimmed to Finished rolling shall be accomplished while
line, cleaned, and painted with a thin coating the material is still warm enough for the
of emulsified asphalt before the abutting lane removal of roller marks.
is placed.
All rolling operations shall be conducted in close
3. Edges The edges of the asphalt course shall sequence. In places inaccessible for the operation
be rolled concurrently with or immediately of standard rollers as specified, compaction shall
after rolling the longitudinal joint. be performed by manual or mechanical tampers
of such design as to give the desired density.
400-15
CONSTRUCTION SUPERVISION MANUAL Section 400
9 Check the condition and adjustment of the 401.04 RECORDS AND REPORTS
paving machines and the rollers.
9 See that traffic control is organized and
functioning properly. Make sure that all The Joint Measurement Sheet and the Inspector’s
required signs are in place. Daily Report should thoroughly document the
9 Check the application of the tack coat. Do not completed and approved asphalt concrete
allow tacking of more surface than will be operations. This phase of the work includes
paved each day. Be sure that adjoining materials that are costly to place and compact
surfaces such as kerbs, manholes, etc., are and represent a significant portion of the value of
properly tacked. the overall construction Contract. Records for
9 Examine the pavement base to ensure that the
this work must reflect the importance of this
required patching and/or preleveling is done.
Make checks on paving depths or spread before
operation in every detail. The Inspector and
the beginning of the paving operations. Surveyor should check each stage of the
9 Make sure that cold transverse joints are cut operation as the work proceeds. Correction of
back to the vertical before continuing a lane. defects after placement may result in:
9 Check the transverse joint for smoothness and
appearance. • Loss of product integrity
9 Watch the trucks dumping into the paver hopper • Lower rideability of the wearing surface
for adverse effect on paver operation.
•
9 Check the temperature of the mixture at the
•
Poor appearance
Shorter service life
time of delivery to the paver and during the
compaction of the course.
9 Maintain a constant inspection of the mat The inspection staff must continually check the
behind the paver for signs of roughness or a work for conformance with the plans and
non-uniformity of mixture. specification requirements to ensure the outcome.
9 See that the longitudinal and transverse joints Never assuming that the work is proceeding
are raked and compacted properly. satisfactorily, but rather constantly proving that
9 Make frequent checks of the spread yield and it is. Progress of the work including inspections
depth.
9 Watch rolling operations. See that the best
made, instructions to the Contractor, noted
deficiencies with follow-up corrective actions,
rolling sequence is used to fit the conditions.
Watch for excessive speed of the rollers. Check and approvals given should be reported in detail
and adjust the amplitude and frequency of the by the Inspector. In addition, the Plant Inspector
vibrating rollers. should complete the Daily Bituminous Concrete
9 Keep records of truck loads used each day. Batch Plant Report and the Road Inspector
Check with the Plant Inspector concerning daily should complete the Asphalt Concrete Daily
totals. Field Inspection Report.
9 Make sure the job is in good shape at the end of
each day. See that all lights, barricades, etc., The Plant Inspector usually files the reports,
are properly placed. See that all signs not when required, with the Municipality. However
required during non-working hours are
the Road Inspector must measure the area paved
removed or covered.
each day and furnish this information to the Plant
Inspector, along with the number of loads or
After final rolling, the smoothness, levels, cross partial loads rejected or wasted. The records of
falls, density, and thickness shall be checked and the quantity of material produced and material
any irregularity of the surface exceeding the placed must agree and be properly documented
specified limits and any areas defective in to form an unquestionable basis for pay
texture, density, or composition shall be quantities.
corrected as directed by the Engineer, including
400-16
CONSTRUCTION SUPERVISION MANUAL Section 400
400-17
CONSTRUCTION SUPERVISION MANUAL Section 400
the depth of the material will be necessary. the data that it is designed to measure. The
The calibration is based upon the number of wheel should be maintained in a clean
liters contained in the tank as determined by condition because if material is allowed to
the measuring stick. build up and remain on the wheel, incorrect
results will be obtained.
2. Heating System The heating system consists
of one or two burners and an equal number 5. Spray Bar To ensure proper working
of heating flues. Each burner emits a flame condition of the spray bar, the following
directly into a flue that transfers heat to the inspections and adjustments must be made:
asphalt cement material. The heating system
should be checked to make certain that it can • Nozzles: The nozzles should be
maintain the asphalt cement material at the removed from the spray bar, cleaned,
required application temperature. When and examined for size, wear, and
being heated, the asphalt cement material damage to the edges of the nozzle or the
must be circulated. Care should be taken nozzle opening. Uniform distribution of
that the safe maximum heat of the material the asphalt material depends on the
in the tank is not exceeded. nozzles being in good condition and
being the proper size. Usually, the
3. Circulating System The circulating system smallest size nozzle available for a
consists of a pump and a line passing distributor will provide the most uniform
through the distributor tank to the spray bar distribution. The nozzles should be set
and to the hand spray. The pump should be so that the slots are at the angle with the
checked to make certain that it can circulate spray bar recommended by the
the asphalt material through the tank and the manufacturer of the distributor.
spray bar. The pump should also be capable
of developing and maintaining a constant, • Spray Bar Height: The height of the
uniform pressure along the entire length of spray bar should be set so that the exact
the spray bar. This uniform pressure is number of laps of bituminous material
important so that an equal quantity of required will be obtained. The height for
material will be sprayed from each nozzle a double lap can be determined by
without atomizing the asphalt material or closing every other nozzle, operating the
emitting a distorted fan. distributor at the proper pump speed or
pressure, and raising or lowering the
The control for the valve system, by which spray bar by not more than 1.5
the discharge of asphalt material from the centimeters at a time. This procedure is
nozzles is controlled, should be inspected continued until it is determined by visual
and adjusted, if necessary. There should be observation that exactly one single lap of
no slack in the linkage from the control to the material is being applied. For a triple
valve system so that all the nozzles will be lap, close the second and third, fifth and
completely opened or completely closed sixth, etc., nozzles and follow the above
immediately when the control is operated. procedure. The distribution vehicle
The pump tachometer or pressure gauge, should also be equipped with a hand held
which registers the pump discharge, should hose and nozzle for spraying areas that
be checked for accuracy. are inaccessible to the vehicle.
400-18
CONSTRUCTION SUPERVISION MANUAL Section 400
A power broom should be used for cleaning the Close control should be exercised over the
existing surface in preparation for construction. operation of the distributor so that the material
All loose material, dust, dirt, caked clay, and will be applied uniformly. If the distributor has
other foreign material should be removed to the been properly inspected and adjusted, the
full width of application. Particular care must be material will be applied uniformly in the
taken in cleaning the outer edges of the width to transverse direction unless one or more of the
be primed. nozzles become clogged. To obtain the required
uniform rate of distribution in the longitudinal
402.03.03 Water Truck direction, the circulating pump and distributor
must be operated at the proper constant speed.
If the base surface is quite dry, water may be The length of spread for each distributor load of
sprinkled on it lightly from a water truck. If material should be determined and marked on the
water is applied, the base is to be rolled prior to road as an aid to obtaining the required rate of
the priming operation. application.
402.04 ROAD OPERATIONS As the amount of prime coat required varies with
the surface texture and density of the underlying
layer, site trials will be carried out to determine
402.04.01 Repair of Defects
the application rate desirable to achieve
maximum penetration with a minimal amount of
On new subbase courses, repairing the surface
‘puddling’ occurring after spraying, and within
will seldom be necessary. In this instance, the
the 0.25 to 0.50 kg/m² specified limit.
subbase course should have been constructed to
the specified tolerance when finished. Any
Prior to spraying, the correct positioning of the
defects found in the newly constructed subbase
spray bar nozzles will be checked to ensure
course must be repaired before any application
uniform coverage with no streaky application
of prime coat is made.
pattern. A light spray of water shall be applied
just prior to prime spraying.
402.04.02 Traffic Control
NO PRIME COAT MAY BE APPLIED
Traffic control should be thoroughly discussed at
WITHOUT THE PRESENCE OF A
the preconstruction conference. At this time,
TECHNICIAN AND INSPECTOR.
definite traffic control procedures should be
established that provide maximum safety for the
A standing start spray will not normally be
workers and the traveling public, with the least
allowed. If a standing start is necessary,
interruption of the work. All traffic control
cardboard or other absorbent material must be
devices and procedures used to direct traffic
placed under the spray bar area in order that the
through the construction area should be
prime spray is commenced with the applicator
according to the Manual on Uniform Traffic
moving at the pre-calculated speed.
Control Devices (MUTCD) and of the type
shown on the plans and approved by the
The temperature of the prime will be checked to
Municipality.
ensure that it is between 60 and 85 degrees C
and noted on the appropriate form. Prime coat
402.04.03 Weather Limitations
should not be applied more than 48 hours
preceding placement of asphaltic concrete
The prime coat should not be applied when the
paving.
existing surface is wet, when it is foggy, raining,
or threatening rain. Temperature limitations
The transverse joints on prime coats should be
should be according to the specifications.
made carefully. This can be done most
successfully by starting and stopping each
400-19
CONSTRUCTION SUPERVISION MANUAL Section 400
application of asphalt cement material on square meter, upon the existing pavement surface
building paper. Each successive application to ensure a thorough bond between the old and
should overlap the end of the preceding one by 1 new courses. Tack coats are used primarily
centimeter to avoid a gap in the surface. By between layers of asphaltic concrete.
using the building paper, there will be less
chance of creating puddled areas needing to be 403.02 MATERIALS
rectified.
Before use, all materials must be inspected,
The longitudinal joints for prime coats that are
tested for compliance with the requirements of
not placed to the full width of the roadway in a
the specifications, and approved by the
single pass should also be carefully controlled.
Municipality.
Since using building paper on these joints is not
practical, slight overlapping the adjacent passes
403.03 EQUIPMENT
is better than to have a gap in the surface.
402.05 RECORDS AND REPORTS Refer to Section 402.03 of this manual for the
applicable equipment.
Data concerning the construction operations for
403.04 ROAD OPERATIONS
prime coats should be recorded in detail on the
Prime/Tack Coat Application form (SM-34). In
doing so, the necessary data is recorded so that 403.04.01 Surface Cleaning
the final pay quantities can be determined. Both
the Inspector and Laboratory Technician have The existing surface must be cleaned just before
responsibility for the proper application of prime the applying of the asphalt material. All foreign
coat. materials such as paper and mud should be
removed and the entire surface should be
402.06 MEASUREMENT AND PAYMENT thoroughly broomed to remove dirt and dust.
400-20
CONSTRUCTION SUPERVISION MANUAL Section 400
limitations should be according to the road as an aid to obtaining the required rate of
specifications. application.
Close control should be exercised over the Cold milling is the process of removing all
operation of the distributor so that the material and/or portions of an existing asphalt pavement
will be applied uniformly. If the distributor has to accomplish the following:
been properly inspected and adjusted, the
material will be applied uniformly in the • Remove a distressed pavement
transverse direction unless one or more of the • Improve the roadway profile
nozzles become clogged. To obtain the required • Restore the roadway cross section
uniform rate of distribution in the longitudinal • Improve drainage
direction, the circulating pump and distributor
must be operated at the proper constant speed. The pavement is removed at locations, depths,
The length of spread for each distributor load of and widths according to the typical sections
material should be determined and marked on the indicated in the Contract Documents or as
directed by the Resident Engineer. This work
400-21
CONSTRUCTION SUPERVISION MANUAL Section 400
usually includes removal of the milled material and transported to designated locations according
from the highway right-of-way and cleaning the to the project specifications.
remaining pavement surface so it may be suitable
for maintaining traffic, if necessary, before The milled pavement surface should be
paving. Unless specified otherwise by the thoroughly cleaned of all loose aggregate
Contract Documents, the reclaimed pavement particles, dust, and other objectionable material
becomes the property of the Contractor. by using power brooms, power blowers, power
vacuums, or other means. Oversize pieces of
404.02 EQUIPMENT pavement or loose aggregate material should be
removed and disposed of at the approved waste
disposal site.
Equipment for cold milling includes a self-
propelled milling machine capable of removing
The pavement removal operations should be
the existing pavement to the required depth of cut
conducted to minimize the amount of dust being
and slope. The milling machine should be
emitted. The operation should be planned and
equipped with a grade control system that will
conducted so that it is safe for persons and
automatically control the longitudinal profile and
property next to the work as well as the traveling
cross slope of the milled surface. This is
public.
achieved by referencing from one or more skid
sensors moving along the pavement surface or
At the end of any day’s production, a smooth
from a preset fixed reference line. The machine
transition to the existing pavement should be
should be capable of leaving a uniform surface
achieved.
suitable for maintaining traffic, if necessary,
without excessive damage to the underlying
404.04 RECORDS AND REPORTS
pavement structure. The milling machine may be
equipped with an integral loading means to
remove the material being cut from the roadway Project records should reflect a complete
and discharge the cuttings into a truck in one summary of the construction operations done on
operation. the project and, with proper documentation, form
an unquestionable basis for pay quantities.
Additional equipment may be necessary to These records should include project diaries,
remove the pavement near manholes, water measurements of area and depths for volume
valves, curbs, and other obstructions. calculations of work completed.
400-22
CONSTRUCTION SUPERVISION MANUAL Section 400
Two approaches have been used to size the 405.02.01 Recycled Material
material before recycling in a central hot mix
plant: The recycled material should consist of the
existing asphalt pavement (aggregates and
• The pavement can be reduced in size in-place asphalt). Normally a maximum of 50 percent
and then hauled to the central plant. can be recycled through a batch plant and 70
percent through a drum mixer.
• The pavement can be removed from the site
and sizing can be done with equipment 405.02.02 New Aggregate
normally associated with aggregate
processing. The virgin aggregate should be added as required
to meet job-mix specifications.
Plant sizing can be done with conventional,
fixed, and portable crushing and screening 405.02.03 Asphalt Modifier
equipment. The pavement is normally ripped
and broken to a size suitable to be received by The asphalt modifier or recycling agent should
the primary crusher before loading onto the haul be capable of giving the required mix properties.
units. Using grid rollers or other types of
equipment to produce a properly sized material 405.02.04 New Asphalt
on the roadway before hauling to the central
plant may prove to be economical. Additional new asphalt, as required, should be
added to meet the job-mix design.
Equipment to centrally process recycled material
can be separated into at least three general 405.02.05 Recycled Mixture
categories:
The recycled mixture should be a uniform
1. Direct flame heating mixture of recycled material, new aggregate, and
2. Superheated aggregate asphalt (as required), and asphalt modifier (as
3. Without heat required). The mixture is then combined to have
the properties of a new asphalt pavement
Central-plant recycling techniques are different composition complying with the job
from the other methods of recycling in that the specifications.
material is removed from the roadway and mixed
either cold or hot at a central location. 405.03 EQUIPMENT
Additional asphalt, recycling agents, cement,
lime, aggregate, or other materials may be added
1. Asphalt heating and mixing plants designed
at the plant.
to produce a uniform mixture within the job-
mix tolerances. Many existing hot mix plants
405.02 MATERIALS AND MIX DESIGN
can be modified to produce the recycled
mixture. These modifications generally
The mixture design process for central plant involve new cold feed bins with continuous
recycling requires the determination of both the weighing devices.
type and amount of asphalt material to be used.
If asphalt is to be the binder, the central 2. An asphalt paver that can spread the mixture
laboratory should determine the need for a to the thickness and width specified, true to
modifier recycling agent and/or the quantity of the line, grade, and crown shown on the
asphalt material. This can be determined only by plans.
detailed laboratory testing. Samples of the
existing asphalt surface should be obtained and 3. Haul trucks.
subjected to the standard series of tests.
4. An asphalt distributor.
400-23
CONSTRUCTION SUPERVISION MANUAL Section 400
Plant operations to centrally hot process the Asphalt concrete operations shall be reported
recycled material can be separated into at least daily by the Inspectors assigned to the work.
two general categories: direct flame heating and The Plant Inspector should complete the Daily
superheated aggregate. Bituminous Concrete Batch Plant Report. The
Road Inspector should complete the Asphalt
405.04.01 Direct Flame Heating Concrete Daily Field Inspection Report.
400-24
CONSTRUCTION SUPERVISION MANUAL Section 400
400-25
CONSTRUCTION SUPERVISION MANUAL Section 400
Project records should reflect a complete The materials required for the replacement of
summary of materials incorporated in the asphaltic pavement courses shall match existing
construction operations done on the project and, materials and shall be as specified in Section II-
with proper documentation, form an 7, Subgrade Preparation, Section III, Subbase
unquestionable basis for pay quantities. These and Base Courses, and Section IV, Asphalt
records should include the following: Works, of the Standard Specifications.
400-26
CONSTRUCTION SUPERVISION MANUAL Section 400
requirements of Section III, Subbase and Base raise the asphalt wearing surface back to match
Courses, of the Standard Specifications. The the proper grade, as follows:
replaced aggregate base course layer shall be
primed with an bitumen emulsion, prime coat, at 1. Cut and remove the upper 3 centimeters of
the application rate approved by the Engineer. the pavement starting just in back of the
depression. Haul away and dispose of all
Replacement of any damaged or removed removed pavement.
subbase drainage system piping, aggregate
bedding, and geotextile fabric shall match 2. Wire broom clean the surface and lightly
existing and be placed in accordance with tack coat the surface and paint the edges of
Section 604.04, Other Related Works, of the the cut with bituminous emulsion at the rate
Standard Specifications. of 0.25 to 0.50 kilograms of tack coat per
square meter of surface area.
After approval of the compacted aggregate
subbase layers by the Engineer, the individual 3. Fill the cut with Type II wearing course hot
asphaltic pavement layers shall be saw cut back mix asphaltic concrete and compact with a
to produce steps a minimum of 60 centimeters steel-wheeled roller by first compacting the
wide between layers of the existing pavement. hot asphalt concrete 15 centimeters from the
two traffic edges and then by rolling in the
The faces of the layers shall be saw cut straight direction of traffic. The drive wheel of the
and vertical and shall be wire-broomed and roller shall be in the forward position,
painted with bituminous emulsion, tack coat, without vibratory action.
immediately prior to laying the replacement
4. Check the level of the patch with a straight
asphaltic courses.
edge and make corrections as required.
Asphaltic courses shall be installed in
408 SAND-ASPHALT COURSES
thicknesses and compositions to match the
existing pavement layers as far as is practical or
as otherwise directed by the Engineer. Layers 408.01 SAND-ASPHALT SUBBASE
shall be laid and compacted in accordance with
the requirements of Section IV, Asphalt Works,
The sand-asphalt subbase course is located
of the Standard Specifications with prime and
immediately above the subgrade and consists of
tack coats as directed by the Engineer. In no
material of a superior quality to that which is
case shall a single layer of asphalt paving be laid
generally used for subgrade construction. This
greater than 8 centimeters in thickness, unless
course is composed of a mixture of mineral
otherwise approved by the Engineer.
aggregate, mineral filler, and asphalt binder
heated and mixed in a stationary central mix
The top asphaltic layer shall be finished level and
plant. This course is placed on a prepared
smooth with the existing pavement, and under no
surface in various depth and width combinations.
circumstances shall the road be opened to traffic
The depths of the sand-asphalt subbase course is
before all replacement of asphaltic courses and
designated on the plans and cross sections. It is
markings have been completed and approved in
the Contractor’s responsibility to ensure that the
writing by the Engineer.
placement of this subbase course is according to
the plans, cross sections, and the Standard
If in the opinion of the Engineer, the replaced
Specifications. It is the duty of the Inspector to
asphaltic pavement and/or underlying trench
call to the attention of the Resident Engineer all
backfill settle to unacceptable levels over time
conditions that appear to require changes in the
(where the surface grade has settled more than
subbase course depth due to unforeseen
10mm below the design elevation, when checked
conditions found after construction has started.
with a straight edge), the Contractor shall make
repairs by applying an asphalt “skin patch” to
400-27
CONSTRUCTION SUPERVISION MANUAL Section 400
Materials used to construct the sand-asphalt As with all asphaltic base course construction,
subbase shall meet the requirements of Section the Road Inspector should ensure that succeeding
III of the Standard Specifications. courses are not placed until the previously placed
course has cooled to the extent that it will not be
Further instructions to Plant and Road Inspectors distorted by equipment.
regarding testing, plant operations, and road
operations are the same as for the other asphalt
SAND-ASPHALT COURSES
courses discussed above.
400-28
CONSTRUCTION SUPERVISION MANUAL Section 500
500-1
CONSTRUCTION SUPERVISION MANUAL Section 500
Table 500.01
Minimum Concrete Strength
Class of Concrete
Requirements K140 K250 K335 K415 K455 K500
Minimum crushing strength
Kg/cm² 140 250 335 415 455 500
Preliminary Test Cubes at 7 Days
Minimum crushing strength
Kg/cm² 100 185 250 310 345 375
Work Test Cubes at 7 Days
Minimum crushing strength
Kg/cm² 185 335 445 555 605 665
Preliminary Test Cubes at 28 Days
Minimum crushing strength
Kg/cm² 140 250 335 415 455 500
Work Test Cubes at 28 Days
Slump range (mm) 60-120 60-120 60-120 60-120 60-120 60-120
Water cement ratio (max) 0.50 0.45 0.42 0.42 0.40 0.38
Minimum cement content 220 300 400 425 435 445
Kg/m³
The concrete class for each individual structure 502.02.04 Concrete Class K415
or component is specified in the Standard
Specifications. General usage is indicated as High strength structural concrete used for all
follows: post-tensioned structures.
502.02.01 Concrete Class K140 502.02.05 Concrete Class K455 and K500
Utility concrete is used for mud slabs, blindings, Special types of structural concrete are used on
and non-reinforced sections. structures and at locations as indicated on the
Drawings and in the Particular Specifications.
502.02.02 Concrete Class K250
502.03 MIX DESIGN APPROVAL
Basic structural concrete used for all bridge
substructures including footings, piers,
Before any concrete is allowed for use on the
abutments, wingwalls, and approach slabs. Uses
project, samples of all material that is to be used
on other reinforced sections include: barriers,
in the mix are to be submitted to the Resident
parapet walls, retaining walls, light pole
Engineer for testing. The samples will be tested
foundations, and traffic signal foundations.
in the site laboratory under the direction of the
Resident Engineer and according to the Standard
502.02.03 Concrete Class K335
Specifications. The Contractor is not to have
any materials delivered to the site until he has
Higher strength structural concrete used for non-
received written approval from the Resident
post-tensioned superstructure deck slabs,
Engineer.
diaphragms, and sidewalks where bridge decks
are cast on prestressed girders.
Once the Contractor has received the Resident
Engineer’s written approval of the individual
material components, he is required to submit a
500-2
CONSTRUCTION SUPERVISION MANUAL Section 500
proposed mix design for the Resident Engineer’s aggregate should be carefully washed before the
approval. The mix design is to be proportioned batching operation to remove any airborne
by weight and based upon trial mixes that were chlorides.
conducted with the approved materials for the
specified class of concrete for the project. The Regardless of whether aggregates are tested at
Resident Engineer’s approval of the mix design the point of production or at the job site, a test
is based upon tests performed according to the report showing numerical results must be
Standard Specifications. If approved, the available. This report is to show that the
Resident Engineer will inform the Contractor in aggregates are acceptable before being
writing. If the Contractor’s mix is not approved, incorporated in the work.
the Resident Engineer should advise the
Contractor of areas of non-compliance and Cement must be handled and stored in a manner
suggested modifications for achieving to prevent loss, wetting, or contamination. It is
compliance. usually furnished from calibrated bins at the
cement plant. If there is no documentation
The Contractor is required to arrange submittal accompanying the shipment of cement indicating
of the samples and mix design as early as that it has been tested, a preliminary test sample
possible. No concrete work is to be allowed until must be submitted according to the requirements
written approval from the Resident Engineer is of Section V of the Standard Specifications.
received by the Contractor. Should any changes Different types of cement must not be
in the attributes or source of materials used for intermingled or used in place of the type
the approved mix occur, the Contractor is specified.
responsible for submitting new samples and a
new mix design to the Resident Engineer for Potable water is acceptable for use in concrete
approval. unless it contains sugar. Water of unknown
quality should be tested and found acceptable
The Resident Engineer or his Inspectors should before incorporating it into the mix. All water is
take samples of the work mix frequently to to be checked for pH levels, chlorides, and
monitor compliance with the approved mix temperature.
design.
The hauling of mixing water should be done in
502.04 HANDLING MATERIALS clean, covered containers. Assurance of using
acceptable water is the responsibility of the
Inspector for on-the-job mixing.
In order for the necessary aggregate stockpiles to
be built without the overlapping of different
Admixtures, except those used for air-entraining,
materials, adequate storage facilities need to be
should not be used without obtaining prior
provided. Stockpiles should be formed on bases
approval of the Resident Engineer. Samples of
approved by the Resident Engineer and should be
the proposed retarders or admixtures, unless
built in layers not exceeding 1.5 meters in
previously approved, must be submitted before
thickness, with each layer being completed
use.
before the next one is started. Conical stockpiles
built by discharging the coarse aggregate at one
502.05 CONCRETE BATCH PLANT
point or end-dumping over the sides of stockpiles
INSPECTION
should not be permitted. Use of equipment on
the stockpile should be held to a minimum to
avoid contamination, breakage, and segregation. The Inspector of materials and batching
operations is responsible for enforcing
Aggregates removed from the stockpiles and compliance with the specifications. The duties of
placed in bins should be handled in a manner to the Inspector will start at the time materials are
prevent segregation, degradation, contamination, being accumulated and continue until final
and to ensure relatively uniform moisture. All records for the project are complete. The
Inspector must be familiar with the source and
500-3
CONSTRUCTION SUPERVISION MANUAL Section 500
type of aggregate intended for use, mix method of determining batch quantities, scale
proportions, moisture content, method of weights, yield, effective water, cement
determining scale weights, batching equipment, factor, and the procedures for adjusting
tests, and reports. The Inspector should be proportions and yield when using air
familiar with the manufacturer’s brochures on entrainment. The design mix as established
the batching equipment to understand its and approved should be included in the
operation. The Contractor will be required to permanent records of the project.
provide this information.
• Calibration of weighing and measuring
The importance of proper plant inspection cannot devices, balancing scales and checking
be overemphasized since proper proportioning of calibrations, and systematic and regular
materials is one of the major steps in obtaining a checking of scale settings for batches to
satisfactory concrete mix. The Inspector should assure proper quantities are being dispensed.
be guided by the idea that the quality of the end Scale settings are not to be made by the
product is dependent on each step along the line, Inspector since this is the responsibility of
and no amount of extra effort at one step can the Contractor’s representative. Check to
compensate for errors, omissions, or ensure that all scales have been certified.
inefficiencies at some other step of the process.
• Make free moisture tests. These tests are
Before the start of batching operations, the required so that batch weights may be
Resident Engineer and the Inspector should be adjusted and to ensure that the maximum
assured that all equipment is of an approved allowable water-cement ratio is not being
design and complies with the requirements of the exceeded. The batcher should be advised
specifications. Hoppers or bins should be set immediately of any change in moisture
level and loaded for at least 24 hours before content of the aggregates and of the
calibration. The Contractor should have maximum liters of water that may be added
available at the proportioning plant, at all times, at the mixer without exceeding the
not less than ten 23-kilogram weights for specifications and design limits.
calibration and verification of scales. A cradle
or test platform should be provided for each • Require that central-mix concrete be hauled
scale for testing purposes. in vehicles meeting specification require-
ments and in a manner to avoid segregation
The specific duties of the Plant Inspector should and be delivered at the site with proper
include the following: consistency and workability before the
concrete starts to take its initial set. Require
agitating-type trucks if this condition cannot
• Observation of the stockpiling and handling
be met.
of materials to assure compliance with the
specifications.
• Check truck mixers to ensure that they
contain a water-metering device of
• Maintain laboratory inspection report
prescribed accuracy, approved revolution
records to verify that all materials are
counters, mixing blades inside the drum that
acceptable prior to incorporating into the
are not caked with mortar, loose, broken,
Works.
bent, scalloped, worn more than 20% of any
• Make a periodic check, at least daily, of the dimension, or otherwise damaged. Truck
quantity of cement actually used by mixers should not be permitted to mix
comparing the total quantity received to the batches having volumes greater than the
theoretical quantity used, taking into account maximum capacity indicated on the
the cement remaining on hand. manufacturer’s rating plate.
500-4
CONSTRUCTION SUPERVISION MANUAL Section 500
• Proper handling, curing, and breaking of storm water to inlets, catch basins, storm sewers,
cubes to determine the compressive strength and ditches; and are an effective means in the
of the concrete. control of driveway entrances, both as to location
and width.
• All required records and reports should be
kept current and prepared in conformance It is good practice to consult with the property
with the instructions of the Resident owner before finally placing the depressed curbs
Engineer. All test reports should be dated for driveways. Shifting the locations to suit the
and signed by the person making the test. property owner is acceptable if safety standards
An orderly record should be kept of all and local ordinances are not violated.
specific checks or tests made to determine
compliance with the specifications, such as: In relatively level areas where storm water runs
off very slowly, there is a tendency for water to
1. All calibrations, verifications, and stand if curbs are not designed and built to
checks proper grades. Studying the drainage conditions
2. Scale certifications on any project where curbs will control or have
3. Cumulative total of all acceptable an affect on the drainage is very important for
materials received the Resident Engineer. This study should be
4. Moisture tests made before the start of any grading work. It
5. Scale weight settings may be found necessary to make minor
6. Cumulative total of material used alterations in grades or minor changes in
7. Compressive test results elevations of inlets to catch basins, culverts,
8. Inspector’s Daily Reports pipe, etc., to assure efficient drainage.
502.05.01 Inspector’s Diary Concrete work for curbs will consist of the
following:
A diary must be maintained by the Inspector and
should be a concise record of daily events and • Construction of cast-in-situ foundations for
observations. This record should include: all use with precast concrete curbs and cast-in
special instructions to the Contractor, unusual situ curbs, noses, and curb cuts.
actions taken by the Inspector, daily time of
starting and ending operations, the extent of • Construction of cast-in-situ concrete
progress by stations or structure sections, lost haunches for use with precast concrete
time due to breakdowns or other reasons, a curbs, cast-in-situ curbs, noses, and curb
counting of the Contractor’s forces, the cuts.
temperature, and weather conditions.
• Construction of cast-in-situ curbs, noses,
503 CONCRETE ELEMENTS and curb cuts.
503.01 CONCRETE CURBS • Construction of precast curbs.
500-5
CONSTRUCTION SUPERVISION MANUAL Section 500
Casting will be carried out in lengths not to unsuitable material shall be removed and
exceed 5 linear meters separated by expansion replaced with approved borrow material
joints of pieces of bituminous preformed joint which shall be thoroughly compacted
filler. according to the Standard Specifications.
500-6
CONSTRUCTION SUPERVISION MANUAL Section 500
3. Concrete Placement: The concrete shall be than the depth of the curb. The templates
proportioned, mixed, and placed according to are to be set carefully and held firmly during
the requirements of class K250 concrete. the placing of the concrete. The templates
Consolidation of the concrete placed in the can remain in place until the concrete has set
forms will be by vibration or some other sufficiently to hold its shape but will be
acceptable compaction method. The removed while the forms are still in place.
concrete must be allowed to set sufficiently The resultant 3 mm wide contraction or open
so that the forms can be removed without joints in the curb will match the contraction
injury to the curbing or the nose. The top of joints in the concrete median sidewalk.
the concrete is to be struck off to the cross
section specified, after which, it will be 6. Expansion Joints: Expansion joints will be
finished smooth and even by means of a formed at 5 meter intervals using preformed
wood float. The required radius at the top expansion joint filler having a thickness of 2
front edge is provided by means of the centimeters. Curbs constructed next to the
proper radius edging tool. Where no radius is concrete median sidewalk will have
specified, the top edges shall be separated expansion joints that match and are located
from the form using a slightly rounded at the same point as the expansion joints in
edging tool. This prevents spalling of the the sidewalk.
corner and produces a neatly finished curb.
7. Curing: Immediately upon completion of the
4. Finishing: After the concrete has taken its finishing, the curbing shall be moistened and
initial set, the front or face form must be kept moist for three days, or the curbing and
carefully removed, with the back form nose shall be cured with a membrane curing
remaining undisturbed. The exposed top and material. The method and details of curing
front faces are finished with steel or will be subject to the approval of the
aluminum trowels using a minimal amount Resident Engineer and are described further
of water to produce a cement paste. When in this section.
the timing is right, minimal trowelling is
necessary to fill the voids and form induced 8. Backfilling: After the concrete has set
irregularities, producing a relatively smooth, sufficiently, the spaces in front and back of
even surface. It is extremely important that the curb will be backfilled to the required
this finishing procedure is accomplished elevation. Backfill will be with suitable
within 2-3 hours of the concrete pour to material, which shall be thoroughly tamped
achieve the desired result. Proper finishing in layers of not more than 15 centimeters.
cannot be attained otherwise. No
plastering of hardened concrete surfaces 503.01.04 Precast Curbs
will be allowed.
Precast curbs shall be constructed of class K250
5. Contraction Joints: Curbing will be concrete using Type V cement and precast by the
constructed in sections having a uniform hydraulic press method. The curb element will
length of 2.5 meters unless shorter sections be 60 centimeters long, where required to be laid
are necessary for closures. No section will in straight lines, but may be reduced to 20
be less than 1.2 meters. These sections will centimeters for laying on curves. The edges are
be separated by sheet steel templates set to be perfectly sharp without flanges and
perpendicular to the face and top of the curb lippings. All joints are to have a constant width
or nose. The templates are to be 3 not to exceed 0.5 centimeters.
millimeters in thickness over the width of the
curb and not less than 5 centimeters longer
500-7
CONSTRUCTION SUPERVISION MANUAL Section 500
On main roads, curbs are generally not placed of constructing barriers are described in the
until after the subbase and base courses have Standard Specifications.
been placed, compacted, and approved by the
Resident Engineer. For secondary roads and • Cast-in-place by slip form or extrusion
parking areas, curbs are normally placed on a • Cast-in-place by fixed form
100mm thick concrete foundation. • Precast
Precast curbs are to be placed on a setting bed of Whichever method is used, the final appearance
mortar not exceeding 3 centimeters thick. The will be influenced by the foundation. Vertical
mortar is to be one part Type V Portland cement cracking of slip formed barriers is a common
and two parts sand. No mortar shall be used problem. In some cases, the problem can never
after it has partially set and no material from any be completely eliminated. The condition can be
previous mortar batch will be used to mix a new eased by attention to the rate of travel,
batch of mortar. maintenance of the proper concrete level when
feeding the machine, properly operating
The grade and elevation at the top face of the vibrators, and fine tuning the concrete mix.
curb shall be controlled by a stringline to
produce a straight alignment true to grade. Once 503.02.01 Constructing Barriers
set, the curb serves as the control for the
construction of pavement and drainage If possible, the Resident Engineer should inspect
structures. The Contractor’s setting-out should previous work done by the equipment to be used.
be continuously checked by the Surveyor and By inspecting previous work, any shortcomings
Inspector to ensure the curb is constructed within can be discussed with the Contractor and
the allowable tolerance. corrective measures agreed upon. When
constructing barriers, the following general
Precast curb that is cracked, chipped, or requirements must be met:
otherwise damaged shall be marked by the
Inspector and rejected. Any type of on-site • Methods of casting, handling, and placing
repair to precast concrete elements is the barriers must be approved by the
unacceptable and will not be allowed. Resident Engineer.
Haunching is poured as a backing to the curb as • The required steel reinforcement and anchor
soon as possible to provide stability. The final bolts for bridge railings must be set in place.
operation is filling of the joints between the curb The Contractor is responsible to set these
elements with cement grout and striking the accurately and firmly secure them in place.
joints with a tool capable of producing a slightly They must be secured to prevent the weight
concave joint. of the fresh concrete from moving them out
of place. Slip-forming of bridge barriers or
503.02 CONCRETE BARRIERS parapets is not allowed.
500-8
CONSTRUCTION SUPERVISION MANUAL Section 500
• Precast barrier sections will probably be Before construction begins, the Resident
inspected at the suppliers plant but the units Engineer is responsible for the review of all the
should also be inspected before installation. phases of the work. He must see that all
The fact that precast barriers were inspected members of the Contractor’s crew are familiar
and accepted at the plant does not mean they with the duties to which they are to be assigned.
must be accepted on the job if they are Advance planning and organization of the
defective. As with any precast item, it is engineering and inspection teams will do much to
good practice for the Resident Engineer to eliminate the confusion and improper
inspect finished work at the plant early in the construction inspection sometimes found during
production run. If there are any differences the first day’s work. All inspection equipment
in inspection criteria between the project and and testing tools should be on hand before the
the plant Inspectors, they can be resolved beginning of paving, and demonstrations should
with the least disruption and expense to all be conducted to acquaint the Inspectors with
parties. their proper use.
• A joint sealant is used in all three types of The Resident Engineer should make certain that
barriers, but the application and sealing all Inspectors are instructed in the proper
procedures vary so it is important that the methods of keeping notes, records, and diaries.
Inspector is aware of the provisions for the Accurate records of construction progress and
particular type of barrier and the particular test results are essential in evaluating pavement
project. The Resident Engineer will provide performance through the years.
the project specific instructions for the
approved sealant to the Inspectors. The Inspector is assigned the responsibility for
obtaining the construction of structurally sound
503.02.02 Aligning Barriers pavement with the desired riding qualities and of
performing the necessary checks and tests on this
The barrier lines should be profiled so that the portion of the operation to determine that it meets
form heights can be established to produce a the Contract requirements. To do this, the
smooth line at the top of the barrier. A smooth Inspector must be able to recognize good
profile is important because errors and poor construction practices, have a working
construction on barriers are highly visible. The knowledge of the equipment used, be able to
top profile of the barrier should be adjusted to issue clear-cut decisions to the Contractor’s
smooth out any irregularities or departures in the representative, and be fully aware of all required
finished deck grade from the design grade. tests and reports. It is recommended that the
Contractor provided brochures, from
503.03 CEMENT CONCRETE manufacturers of the equipment to be used, be
PAVEMENT made available to the Inspector.
Modern concrete paving is a highly complex, All records and reports should be kept current
mechanized operation. Proper organization and and prepared in conformance with instructions
planning of the work are essential by both the from the Resident Engineer. All test reports
Contractor and the Resident Engineer. A cement should be dated and signed by the person making
concrete pavement has a high initial cost and the tests. An orderly record should be kept of all
many years of satisfactory service are expected specific checks or tests made to determine
from this type of pavement. It is imperative that compliance with the specifications.
the Resident Engineer and Inspectors are
thoroughly familiar with the specifications and
techniques applying to the work if this objective
is to be attained.
500-9
CONSTRUCTION SUPERVISION MANUAL Section 500
500-10
CONSTRUCTION SUPERVISION MANUAL Section 500
Ready mixed concrete may be used for this work Pre-stressed concrete bridge members (typically
provided it meets the requirements of the beams, girders, and members of girder systems)
specifications, complies with ASTM C94, and are cast at a concrete fabrication yard. Section
meets with the approval of the Resident VIII-2 through VIII-5 of the Standard
Engineer. Concrete transported by truck mixer, Specifications along with Section 700 of this
agitator, or other transportation device shall be manual contain the requirements for quality
discharged in the forms within one (1) hour after assurance including the following:
the cement has been added to the water or the
aggregates. • System manufacturer’s qualifications
• Sampling and testing
All concrete is to be air-entrained concrete. The • Certification
air entrainment shall be produced by the addition • Submittals
of an approved air-entraining agent at the mixer. • Technical assistance
Air-entraining cement is not to be used. The
volume of the entrained air in freshly mixed The Resident Engineer and his Inspectors should
concrete shall not be less than 4 percent and not be familiar with these requirements as well as
more than 7 percent, unless otherwise ordered by those of the plans and job specifications.
the Resident Engineer. The air-entraining
admixture is to comply with ASTM C260. 503.05 PRECAST STRUCTURES
500-11
CONSTRUCTION SUPERVISION MANUAL Section 500
500-12
CONSTRUCTION SUPERVISION MANUAL Section 500
4. Mortar Joints: Joint material should be Alternatively, when directed by the Engineer,
identical to the mortar bed composition and the existing tiles, mortar bed, and concrete
consistency. Jointing should not commence base course shall be saw cut along straight
sooner than 24 hours from tile placement. lines with the tiles, mortar, and concrete
Tile grout is placed with hard rubber trowels closest to the trench removed and disposed
working at a 45° angle to the joints to firmly of. For the alternative case, an expansion
squeeze the material in place. After the joint shall be installed between the existing
mortar has set, the joints are cleaned and and replacement quarry tiles.
tooled to achieve the finished surface.
Again, the installation is covered with damp Expansion joints shall be installed at not to
hessian and plastic sheeting for a minimum exceed 4-meter intervals in any direction
of 3 days. through both new and existing quarry tile
pedestrian pavement.
5. Joint Sealing: All expansion joints should be
clean and free of debris prior to placing After removal of the quarry tiles and
approved joint sealer. The instructions of concrete base course, the exposed subgrade
the manufacturer of the approved sealer shall be excavated 20 centimetres and the
should be strictly followed. surface compacted using mechanical
compactors to a minimum of 95% of
6. Repairs: This section includes the procedure Modified Proctor Density. The excavation
for the removal and reinstatement of quarry shall be backfilled in not less than two lifts,
tiles for repairs or utility installations or with aggregate subbase material, gradation
maintenance. ‘B’. Each lift shall be compacted to a
minimum of 95% of Modified Proctor
7. Removal: The quarry tiles, underlying Density at optimum moisture content.
mortar bed, and concrete base course shall
be broken out with a power concrete saw and Installation of the concrete base, mortar bed,
cutting tools to the extent required, along and quarry tiles over the newly prepared
lines that leave the remaining tiles whole and subgrade shall meet the requirements of
unbroken, and removed and disposed of at an Section V-6, Quarry Tiles, Precast Tile
approved disposal site. Blocks, Interlocking Pedestrian Pavers, and
Interlocking Vehicular Pavers, of the
8. Materials: The Contractor shall provide new Standard Specifications. Particular care
quarry tiles for replacement, matching shall be taken with placement and timing of
existing sizes, type, thickness, colors, and latex mortar prior to tile installation, and
pattern, and meeting the Standard follow-up curing procedures for the proper
Specification requirements. tile bonding.
9. Restoration: After the Engineer’s approval Figure 500.01 shows the details of sidewalk
of trench backfill to subgrade level, any restoration over a utility trench.
disturbed tiles, mortar bed, and concrete
base course areas shall be removed to Quarry tiles shall be laid symmetrically,
undisturbed existing tiles, along lines that starting at centers of areas and finishing with
leave the remaining quarry tiles whole and equally cut rows on the sides, matching
unbroken, with the mortar and concrete base existing patterns and colors, or to a new
course cut on a vertical face. pattern as directed by the Engineer.
500-13
CONSTRUCTION SUPERVISION MANUAL Section 500
Figure 500.01
QUARRY TILE SIDEWALK DETAILS
503.07 INTERLOCKING PAVING The plant inspection will assess all aspects
BLOCKS of the manufacturing methods, quality
control procedures, component materials, the
curing and storage facilities, and labeling/
Interlocking paving blocks are used in both
identification procedures for the pre-cast
pedestrian and vehicular areas. The locations
pedestrian and vehicular pavers.
where the blocks are to be placed are indicated
on the plans. The Contractor is required to
Based on this inspection, the Engineer will
prepare and submit shop drawings for the
notify the Contractor of any improvements
pedestrian pavers indicating colors, patterns, and
that are necessary before provisional
locations for the Resident Engineer’s review and
approval of the plant will be issued. In the
approval. No pavers are to be fabricated until
event improvements are outstanding, a
the colors and patterns have been approved in
follow-up inspection will be made by the
writing.
Engineer before the plant is considered for
approval to produce pavers.
503.07.01 Materials
During the actual production of pavers, the
The quality of paver materials is extremely
Engineer will periodically inspect the plant to
important to ensure the integrity, durability, and
ensure continued compliance with the
performance of the pavers in the harsh
provisional approval.
environment. A strict quality assurance program
will be implemented in accordance with the
2. Manufacturer’s Plant, Production, and
following:
Testing Quality Assurance Procedures: All
1. Plant Inspection and Approval: Prior to pavers shall be produced strictly in
approval of a supplier to produce precast accordance with the requirements of the
pavers, the manufacturing facilities will be specifications. The plant, materials,
inspected by the Engineer. equipment, and method of manufacture shall
500-14
CONSTRUCTION SUPERVISION MANUAL Section 500
500-15
CONSTRUCTION SUPERVISION MANUAL Section 500
Abu Dhabi shall inspect the production Manufacturer to obtain the certifications
facility and report on the following: from the materials suppliers and
distribute as indicated herein.
• Sand/aggregate mix proportions.
• Cement content of mix. 6. Requirements of On-Site Delivery: The
• Water cement ratio. receipts for pavers delivered for use on all
• Color weight per mix. Government Contracts must state the name
• Curing facilities & procedures. of the Contractor, Contract Number, and the
identification number of each batch/bundle
A minimum of 25 random samples shall be delivered to the site.
taken by the independent testing company.
The samples shall be tested by the Each delivery shall also be accompanied by
independent testing company for dimensional copies of the In-house Certification and
accuracy, compressive strength, and reports on the testing for dimensional
specified flexural strength as follows: accuracy, compressive strength, and water
absorption relevant to the batches delivered.
• Dimensional check - 15 blocks On delivery of pavers to the site, copies of
• Water absorption - 15 blocks these documents must be transmitted to the
• Compressive strength - 5 blocks Engineer responsible for supervision of
• Flexural strength - 5 blocks construction for the Government.
A report shall be issued to the Manufacturer, No pavers shall be laid on site until the
Municipality, Consultant, and Contractor Engineer receives and approves the aforesaid
covering each inspection. documentation.
500-16
CONSTRUCTION SUPERVISION MANUAL Section 500
from the exposed faces. All sound pavers 95% of Modified Proctor Density. Replace
designated by the Engineer for re-use shall the protected existing geotextile fabric over
be carefully handled, stacked, and protected the newly prepared subgrade and install new
until needed. The Engineer shall be the sole geotextile fabric such that a minimum 30
judge of which, if any, of the pavers are centimeter overlap is made between the
acceptable for re-use. All unusable pavers, existing and replacement geotextile fabric.
broken pieces, and other debris (mortar,
concrete base, etc.) shall be removed and Replacement of aggregate subbase and base
disposed of at approved disposal sites. The courses shall be made to match existing by
Contractor shall be responsible for ensuring carefully compacting against undisturbed
that all re-usable pavers are kept protected existing courses to match the existing levels
until required for re-use. Any pavers which, and densities. Installation of replacement
in the opinion of the Engineer, are unsuitable aggregate base and subbase courses shall
at the time of re-use shall be removed from meet the requirements of Section III,
the site and dispose of. Subbase and Base Courses, of the Standard
Specifications.
It is expected that unless the pavers are new
and recently installed, they will in general be Replacement of any damaged or removed
rejected, to be replaced by new pavers subbase drainage system piping, aggregate
matching the existing in type, size, and color, bedding, and geotextile fabric shall match
to be supplied by the Contractor. existing and be placed in accordance with
Section 604.04, Other Related Works, of the
2. Materials: All materials shall be in Standard Specifications.
accordance with Section II-7, Subgrade
Preparation, Section III, Subbase and Base After approval of the installed subgrade or
Courses, and Section V, Concrete Works, of base course by the Engineer, the pavers shall
the Standard Specifications. be installed in accordance with Section V-6,
Quarry Tiles, Precast Tile Blocks,
New interlocking vehicular and pedestrian Interlocking Pedestrian Pavers, and
pavers shall be subject to Municipality Interlocking Vehicular Pavers, of the
quality assurance procedures as previously Standard Specifications.
described.
New pavers shall be provided as necessary
3. Restoration: After the Engineer’s approval to match the size, thickness, and style of the
of trench backfill to subgrade level, the existing pavers as closely as possible.
existing pavers, base and subbase courses Where pavers matching the existing are
shall be removed to a minimum of 60 unavailable, the Engineer shall direct the
centimeters from the edge of the backfilled style of pavers to be used.
trench, or to non-disturbed paver areas,
whichever is further, or to areas as directed In placing the pavers, the Contractor shall
by the Engineer. Underlying geotextile ensure that no spaces are left between the
fabric shall be protected and laid back over individual paver blocks, the sides of pavers
the remaining pavers while the replacement shall be touching each other. The pavers
subgrade is prepared. The existing subgrade shall be secured in place using plate
and top of backfilled trench shall be compactors in order to achieve the proposed
excavated 30 centimeters and the surface levels and grades. Sand shall be used as
compacted to a minimum of 95% of filler between the pavers. The concrete
Modified Proctor Density using mechanical pavers shall be placed in a proper pattern to
compactors. Fill the excavation to the match the existing pavers unless otherwise
original subgrade level with aggregate directed or agreed by the Engineer. Re-use of
subbase material, gradation ‘B’, compacted pavers having paint striping will not be
in not to exceed 15-centimeter thick layers at permitted.
optimum moisture content to a minimum of
500-17
CONSTRUCTION SUPERVISION MANUAL Section 500
• Materials delivery - Pavers delivered to the site After the falsework, forms, and reinforcement
must be tagged as indicated above or rejected. have been erected and set in place, the contractor
The Inspector should note the batch will be ready to begin placing concrete. This
identification numbers keyed to the installation phase is the most critical operation in building a
location in his diary. structure. Previous operations can be corrected
without too much trouble, however, placing
• Utility chambers - All utility chambers,
concrete is probably the most costly and time
drainage structures, etc., within the paver area
shall be adjusted to the required finish grade consuming rework. For this reason all possible
and sloped to conform with the required cross- efforts should be made to make the first concrete
section. In most cases, this can be checked by placement the only placement.
the Inspector with a stringline or straightedge.
Circular frames/covers should be surrounded Before concrete is ordered for any portion of the
by a square or rectangular concrete frame in project, the Resident Engineer should make
accordance with the approved shop drawings. certain that the necessary skilled and unskilled
No pavers will be installed until this work is workers, equipment, and tools are on the site or
complete and approved by the Inspector. readily available to properly handle, place,
vibrate, finish, and cure the concrete.
• Curbs - Precast and cast-in-situ curbs will be
complete, cured, and formwork removed prior
to commencing work. The Contractor is responsible for informing the
Resident Engineer when he intends to start
• Patterns - The Inspector should review the work placing concrete. Before placement, the
on site with the Contractor’s supervisor to Inspector should ensure that the forms have been
confirm the laying requirements and make checked for alignment and that the reinforcement
adjustments in the location or spacing due to is the proper size and placed at the proper
site conditions such as utility and drainage spacing and cover. Also the forms and the rebar
structures or area geometry. should be given a final check for cleanliness. All
sawdust, chips, and any other debris from the
• Compaction - Tamping and leveling should be
interior of the forms must be removed. Final
performed with a plate compactor as soon as
possible following completion of a defined area. approval of the work for placement of concrete is
The finished grade after compaction should be the responsibility of the Inspector.
checked against the required elevation and
adjustments made in the pre-compacted height The following guidelines are useful to the
as necessary. Inspector assigned to the concrete pour:
• Cutting - Cutting of pavers will only be done 1. Equipment Approved equipment must be on
with a block splitter or concrete saw. The work hand for placing concrete in every part of
should be laid out to minimize the number of the structure. Tools for spreading the
cuts and small pieces. Manufactured special
concrete must have handles long enough to
pieces for corners, half blocks, etc., are
desirable and should be incorporated wherever
reach all parts of the forms. The vibrators
possible. must be checked to see that they are in good
condition and an extra vibrator and power
• Spacing - The blocks should be placed together source should be on hand in case of a
tightly (maximum joint 3 mm). Loose laying to breakdown.
reduce cuts or increase coverage area will not
be permitted. 2. Embedded Items All embedded items must
be in their correct positions and solidly
fastened. If wood inserts are to be used, they
must be soaked in water for at least 24 hours
500-18
CONSTRUCTION SUPERVISION MANUAL Section 500
prior to being placed in the forms. After all is prepared to meet the time intervals before
reinforcement has been placed, a special the concrete is placed. Placing should start
check should be made to be sure that bolts, in the corners and ends and progress in
fixings, or inserts for any required uniformly placed layers within the forms.
appurtenances have been installed and have When concrete is being placed in walls or
not been displaced. other long, narrow sections, a uniform depth
should be maintained. The layers should be
3. Placement Rate The planned rate of placing between 15 centimeters and 30 centimeters
the concrete should be limited to such rate for reinforced concrete and no greater that
that the concrete can be finished before the 45 centimeters for unreinforced concrete.
beginning of the initial set.
9. Segregation: Care should be taken to fill
4. Water Never permit extra water beyond that each part of the form by depositing the
specified in the design mix to be added to concrete as near the final position as
increase workability. possible. Shovels should be used to move
concrete. When moved, the concrete tends to
5. Consistency Observe the consistency of the segregate. Usually the rock will stay where
concrete and watch for obvious differences it was dumped, and all that moves is the
between the first, middle, and latter portions mortar and fine materials. The Resident
of the mix as it is discharged from the mixer. Engineer should observe this work closely.
Variations of this type are usually caused by Once the concrete is placed, it should be
worn mixer blades or hardened concrete in moved as little as possible.
the mixer drum. The cause of segregation
should be corrected before reusing the 504.02 PUMPING CONCRETE
equipment or the equipment should be taken
out of service.
Equipment to pump concrete into position is
6. Freefall The placement of concrete should often used, particularly on bridge projects, with
be continuous for each pour sequence to concurrence of the Resident Engineer.
avoid a cold joint and the concrete shall not
freefall more than 1.5 meters. Avoid Pumping of concrete involves the following
segregation of the mix by using chutes, special considerations, equipment, and
hoppers, or pipes. procedures:
500-19
CONSTRUCTION SUPERVISION MANUAL Section 500
3. Pump Priming Initial pumping of grout (one 6. Delivery Placement should progress from
part cement to one or two parts water) will the furthest point away from the pump, back
lubricate the pump and pipeline. One half of towards the pump. This will serve to
a cubic meter of grout will lubricate 300 eliminate pipelines on fresh concrete and to
meters of a 15-20 centimeter diameter eliminate the problem of lubricating sections
pipeline. This grout is then wasted. With of pipe added on. The pump hopper should
these preparations, it should be possible to always be full. Begin dumping from the next
pump a normal mix with slumps ranging truck before the last truck is finished to
from 5 centimeters to 15 centimeters. prevent combining first and last parts of the
loads. Pump continuously. Slow down
4. Uniformity Excessively wet, as well as dry, when needed to prevent running out of
mixes can cause pumping problems. If concrete in the hopper, pump, and pipeline.
mixes are uniform, a pump will operate at a Vacuum or pressure build-up can cause
constant engine speed and constant pressure. pumping problems. The pipeline is
Variations in the mix can be detected by sometimes vented through a valve to guard
observing the pump pressure and listening against vacuum or pressure build-up.
for uneven engine operation.
504.03 VIBRATING CONCRETE
5. Sampling Concrete samples are taken from
the discharge points of the hoses. Concrete
is accepted at the chutes of the trucks, but As concrete is placed, it will contain areas with
acceptance should be verified at the hose undesirable voids. If it were left this way, the
discharge points by separate slump tests. A concrete would have a rough surface and
dry run should be made to be sure all questionable strength. To eliminate the
equipment is in proper working condition undesirable voids and settling, the concrete must
before placement begins. be consolidated to a uniform density while it is
being placed. Vibrators are used to consolidate
500-20
CONSTRUCTION SUPERVISION MANUAL Section 500
the concrete. The portable spud-type vibrator is • In multilayered pours, the concrete must be
most commonly used. placed in shallow layers and each layer of
concrete vibrated after it is poured. The
Vibrators should be capable of transmitting vibrators are to penetrate the previous layers
vibration to the concrete at frequencies of not a few centimeters to permit a good mixing of
less than 4,500 impulses per minute (75 Hz.) and the layers.
visibly affecting a typical mix (25.4 mm slump)
for at least a distance of 46 centimeters from the • The vibrators should not rest against the
vibrator. reinforcing steel bars that extend from the
concrete that has taken an initial set. The
The Resident Engineer must be sure that the vibrations will break the bonds between the
Contractor’s workers use the vibrators concrete and the bars.
effectively. Improper vibration will result in
segregated concrete and ultimately a weak • Vibrators should not touch the inside
structure. surfaces of the form walls. This will cause a
double vibration that can loosen the forms
Below are some important points for the and weaken the supports. This will also
Inspector to watch for: cause segregation against the form walls.
• Vibrators should enter and leave the surface • The vibrators must have sufficient line to
vertically. This prevents possible reach the bottom of the form.
segregation at the surface.
• The vibrator should not be operated like a
• Inspection of vibration techniques involves fishing rod. When an operator throws the
experience and judgment. Experienced vibrator out on the surface of the concrete
personnel will usually remove the vibrator and drags it back, the concrete does not
when the surface just begins to glisten and consolidate properly and tends to segregate.
the air bubbles cease to appear. Immersion
• Avoid over-vibration. When over-vibration
should not last more than 30 seconds
occurs, the surface of the concrete appears
• Care should be taken to ensure that the wet and consists of a layer of mortar
vibrators are not used to move the concrete containing very few coarse aggregates. This
in the forms. This will cause segregation. top layer will be weak and deteriorate
Concrete should be placed with chutes, quickly.
tremie tubes, and when necessary, hand
• Use of a dirty vibrator will introduce
shovels.
material into the concrete that will weaken
• Consolidation should be done concurrently the structure and increase the possibility of
with placement. future failures.
500-21
CONSTRUCTION SUPERVISION MANUAL Section 500
occurs, it can cause serious problems. It is combined with wind, the results can be
may even create conditions so unsatisfactory disastrous for the concrete. If the concrete
that the Contractor is forced to remove the temperature at the completion of mixing
concrete and start over. exceeds 32ºC, it may be rejected.
500-22
CONSTRUCTION SUPERVISION MANUAL Section 500
The Contractor is responsible for having a 1. Wrought formwork On this type of forms,
plan of action to reduce the temperature of the surface is tooled or wrought. The
the concrete delivered to the site of the work. formwork is constructed of steel or plywood
When the temperature of the concrete or planed dressed or undressed timber. The
reaches 24ºC, generally a water reducing insides of the forms are lined with an
retarder must be added to the concrete. The approved fiberboard.
use of additives is subject to the approval of
the Resident Engineer. Other heat reducing 2. Lined formwork This formwork is made of
measures include shading and/or spraying sawn tongue and grooved timber. Each
water on the aggregate stockpiles or cooling piece is of the same width and thickness
the mixing water with ice. When ice is unless it is otherwise specified.
used, it is to be considered a part of the
water in the design mix. Under no 3. Sawn formwork Sawn formwork consists of
circumstances should the mixing operations timber sawn at the mill. All boards of sawn
be considered complete until all the ice in the form work are of the same width.
mixing drum has melted.
4. Special formwork Special formwork consists
Wind, low humidity, and high temperatures of the formwork required to produce an
can cause rapid loss of moisture from the ornamental pattern on the concrete surface.
surface of concrete. The moisture loss will
Forms can be made of either wood or metal and
cause shrinkage cracks to appear on the
in some cases, such as for barriers, fiberglass
surface. When there are unfavorable wind,
can be used. Details of the forming are subject to
humidity, and temperature conditions, it may
inspection by the Resident Engineer. Such an
be necessary to erect shade and/or wind
inspection does not relieve the Contractor of his
breaks. In extreme conditions, it may even
responsibility for the forms and the resulting
be necessary to postpone placing the bridge
lines, grades, and dimensions of the completed
deck or paving concrete until more suitable
structure. If the forms will result in irregular
environmental conditions prevail. This
lines, patches, rough surfaces and joints, uneven
should be done to avoid too rapid drying of
chamfers, offset joints, broken or wrinkled
the surface and severe shrinkage cracking.
plywood marks, non-uniform texture and color,
When concrete is placed under these
they should be rejected.
conditions, it is extremely important that the
curing medium is applied immediately after
504.05.01 Wood Forms
finishing.
Wood is the most commonly used form material.
504.05 FORMS
Generally, form faces are constructed of
plywood that is braced by lumber studs. Wood
Forms hold the concrete in place until it gains forms for all exposed concrete surfaces should be
enough strength to hold its shape. The forms made of lumber that is dressed and free of
must be strong enough to support the pressure defects. When constructed, the forms should
and the weight of the fresh concrete and any provide mortar tight joints that produce smooth
other loads such as finishing equipment and wind and even concrete surfaces.
loading. In addition, the forms are to be able to
withstand the effects of vibration caused by The Resident Engineer should be sure to check
vibrators used for the consolidation of the the condition of the wood that is used as forming
concrete. material. Lumber that is too dry will warp from
rain or the moisture in the concrete. Lumber that
Unless otherwise directed, all formwork is to be is too green will shrink causing joints to open in
fabricated according to Standard Specifications the surface.
and is to be one of the following types:
500-23
CONSTRUCTION SUPERVISION MANUAL Section 500
500-24
CONSTRUCTION SUPERVISION MANUAL Section 500
500-25
CONSTRUCTION SUPERVISION MANUAL Section 500
Table 500.02
Form Removal
Description Period Percentage of
Design Strength
Falsework supporting 14 days 80%
ramps, slabs, or beams
Walls 1 day 70%
Columns 2 days 70%
Sides of beams and all other 1 day 70%
vertical surfaces
500-26
CONSTRUCTION SUPERVISION MANUAL Section 500
504.08 REINFORCEMENT After the bars have been checked for certification
and markings, they can be stored until ready for
504.08.01 Materials use. The bars must be stored above ground on
platforms, skids, or other supports and should be
The epoxy-coated reinforcement manufacturer/ protected from damage, corrosion, dirt, scaling,
supplier must be approved by the Resident paint, oil, or other foreign substances. The bars
Engineer/Chief of Soils and Materials. Approval should be stored under cover.
will be based on test results on representative
samples and manufacturer’s certifications. The handling of epoxy-coated bars is important.
Materials delivered to the site should be checked All bundling bands are to be padded and all
as follows: bundles are to be lifted with a strongback,
multiple supports, or a platform bridge to
• Check the supplier’s delivery tickets, heat prevent bar to bar abrasion from the sags in the
number tags, and certificates of compliance bar bundle. The bars or bundles are not to be
for epoxy-coated bars. These tickets should dropped or dragged. Extra care in handling of
be compared to the documentation approved these bars is beneficial to the Contractor in
by the Resident Engineer. reducing or eliminating in-place coating repairs.
• Check the bars against the plan requirements Additional requirements for epoxy-coated bars
for proper grades, lengths, sizes, numbers, are as follows:
and bends. An identification tag should be
attached to each bundle or group of bars. • The Contractor is to supply a representative
0.28 kg sample of the coating material from
• Check all the bars for visible damage to the each batch of material. The sample is to be
epoxy coating. packaged in an airtight container and
identified by the batch number.
REINFORCEMENT
500-27
CONSTRUCTION SUPERVISION MANUAL Section 500
• In general, fabrication is to be performed • Tack welding instead of tying the rebar is not
before coating for bent bars and straight bars allowed.
less than 7.6 meters in length with the
following exceptions: • Check splices for the correct bar laps at the
splices.
1. For coating and then bending, the
fabricator must clearly demonstrate the • Splicing by welding will be permitted only if
satisfactory condition of the coating after indicated on the plans or if authorized by the
bending. Resident Engineer in writing. Where a weld
is made, the following is to be observed:
2. Bars less than 7.6 meters in length may be
sheared or sawn to length after coating, 1. Each weld must be of the specified size
provided end damage to the coating does and length.
not extend more than 12 mm from the cut
end and it is coated before any visible 2. The bars must not be burned.
oxidation appears. Flame cutting will not
3. The bars must not be made smaller at the
be permitted.
weld. The welds must not be cooled by
• The epoxy coating is to be checked visually wetting them with water.
for continuity of the coating. It must be free
4. Welding must be done by certified
from holes, contamination, cracks, and
welders.
damaged areas. There must not be more
than two holidays (pinholes not visually • Reinforcement steel temporarily left
discernible) in any 30 cm of the epoxy- projecting from the concrete at the joints is
coated bar. A holiday detector is to be used not to be bent without prior approval of the
according to the manufacturer’s instructions Resident Engineer.
to check the epoxy coating for holidays.
Bars having three or more holidays in 30 cm • The bars are to be properly spaced and
are to be cleaned and re-coated or replaced located.
as directed by the Resident Engineer.
• Watch for bent bars. If a bar with a bad
504.08.02 Placement kink or bend that is not required by the plans
is encountered, the bar should be rejected. If
All reinforcing steel is to be accurately placed the bend or kink is minor, it may be
and securely held in position. The Contractor straightened with a hammer. However, if a
has the option of placing the reinforcing steel bar is repeatedly bent it will be weakened.
either by the piece or in sections. Heating reinforcing bars for bending is not
allowed.
The following are items that should be observed
and checked during the placement of reinforcing • Check the condition of the bars. The surfaces
steel: should be free of dirt, oil, grease, mortar, or
any other foreign material that may prevent
• Count the number of bars used. The count the steel from bonding with the concrete.
should equal the number required by the Before concrete placement, the forms and
plans. rebar are to be flushed with clean neutral pH
water to wash away any atmospheric
• The correct size bars must be used in the conveyed chlorides. Excess wash water is to
specified locations. be allowed to drain away.
• All bars are to be securely tied in the proper
manner according to the specifications.
500-28
CONSTRUCTION SUPERVISION MANUAL Section 500
500-29
CONSTRUCTION SUPERVISION MANUAL Section 500
The Resident Engineer should not approve a on site. Only mixes using full packs are to be
delay in removal of forms or a delay in the used. Part pack mixes will not be permitted.
finishing unless there are valid and sufficient Repair mortars should not be applied when the
reasons for such delay. ambient temperature is below 5°C. Mixing shall
be carried out strictly in accordance with the
It is difficult and more costly to obtain a finish manufacturer’s recommendations using only
on hardened concrete equal to that obtained by suitable mechanical mixers. The Contractor is to
finishing the concrete while it is still green. The ensure the correct equipment is on site. The
Resident Engineer should not accept inferior liquid components shall always be thoroughly
finishing, regardless of the method used. mixed together first and the powder/filler added
to the mixed liquids. Under no circumstances
Excessive use of water to facilitate the finishing shall any other components be used in the mix
operation should not be allowed due to other than those supplied or recommended by the
weakening of the outer portion of the concrete, manufacturer.
which can lead to premature spalling or scaling.
Use of a sand/cement paste to “plaster” the 506.02 CONCRETE PREPARATION
concrete surface to achieve the required finish
will also not be permitted.
The damaged concrete shall be broken out.
Where the removal depth corresponds to the
506 CONCRETE REPAIRS depth of concrete cover and thereby exposes
Certain minor defects such as cracks, honeycomb reinforcement, breaking out shall continue to
pockets, and chipped edges or corners of expose the full circumference of the steel and to
concrete structures that are not detrimental to the a further depth of 20-30mm or as directed by the
structural integrity may be tolerated by the Engineer. The depth of breakout for any repair
Resident Engineer if proper repairs are made. area shall be a minimum of 10mm and feathered
Damaged areas to be repaired or replaced will be edges will not be accepted. To achieve this, the
determined by the Engineer on a case by case rim of the area to be repaired shall first be cut to
basis. Where repairs are allowed, an epoxy a depth of about 10mm using a suitable tool.
mortar material will be used. The following The areas shall be cleaned as necessary with any
describes the materials and procedures to be combination of suitable grit, steel brush, water-
followed in performing epoxy mortar repairs: blasting technique, compressed air, or any other
suitable means in order to remove any remaining
506.01 MATERIALS loose material. The preparation shall be such as
to leave a sound exposed concrete substrate free
from dust, loose particles, and any deleterious
In vertical or overhead locations, the repair
matter. Reinforcement damaged during the
material shall be a lightweight, high-build epoxy
removal of concrete or the preparation process
resin, non-shrink repair mortar. In horizontal
shall be repaired or replaced to the satisfaction of
locations, or vertical locations where the repaired
the Engineer.
areas will be subjected to physical abrasion, the
repair material shall be an abrasion resistant,
506.03 CONCRETE BONDING AGENT
epoxy resin, non-shrink repair mortar. In
locations where an impermeable lining or render
is required, the repair material shall be an Depending on the final selection of the type of
abrasion resistant, epoxy resin, lining mortar. epoxy mortar, an appropriate concrete bonding
The Contractor will submit product agent shall be used in strict compliance with the
specifications and performance data to the manufacturer’s requirements. The bonding agent
Resident Engineer for approval of epoxy mortar shall be prepared in accordance with the
compounds prior to use. manufacturer’s instructions. It shall be worked
into the irregularities of the substrate according
The resin mortars are to be of the pre-measured, to the manufacturer’s recommendations before
pre-packed type so that no batching is required commencing to apply the repair mortar. The
500-30
CONSTRUCTION SUPERVISION MANUAL Section 500
timing of the repair mortar application must be In practice, two methods of curing have proven
in accordance with the instructions of the effective for most concrete work:
bonding agent manufacturer. The repair area
may be approached in stages to allow for proper
timing of the bonding agent. If the application CONCRETE CURING METHODS
becomes dry, it shall be removed before applying
another coat. • Supplying Additional Moisture by water curing.
500-31
CONSTRUCTION SUPERVISION MANUAL Section 500
performing the finishing for a Class 2 finish. specified in the Particular Specifications or
Since this is usually the critical period for proper directed by the Resident Engineer, all structures
curing, the Inspector shall make certain that are to receive a Type A waterproof membrane.
whatever method of protection is used, it will be
effective. 508.01 WATERPROOFING MEMBRANE,
TYPE A
If the Contractor has elected to perform the Before any application of the waterproof
curing by means of the liquid membrane method, membrane is made, the Contractor is responsible
the temporary covering should be removed and for submitting the proposed materials to the
the compound applied before the surface has lost Resident Engineer for approval. The individual
its moisture. If too dry, it should be thoroughly components; primer, membrane, and protection
moistened before applying the compound. board must be compatible and endorsed by the
Curing compounds are applied by low pressure membrane manufacturer.
spraying devices, as a mist, which is easily
windborne, therefore, coverage may not be Upon receipt of the written approval of the
uniform. Holidays or small openings in the Resident Engineer, the Contractor is responsible
resulting membrane often appear on the leeward for delivering the products to the job site in
side of surface texture irregularities. Proper unopened containers that are clearly labeled with
shielding should be provided to minimize this the manufacturer’s name, brand designation,
potential problem or another type of curing, type, and class. The products are to be stored in
which would provide a minimum of at least one an approved dry area with all roll goods placed
gallon of compound per nine square meters of one pallet high and laid flat. The Contractor is
bridge deck surface, should be used. The responsible for ensuring that the products are
Inspector should be sure to monitor the site kept dry at all times and that they are protected
conditions for possible variation in the rate. The from contact with soil and exposure to the
materials in many curing compounds separate elements.
and may need agitation before use. The
specifications do not specifically require The Contractor is to coordinate the application
agitation but the Resident Engineer may require of the self-adhering waterproofing membrane
it to maintain the integrity of the curing work so that the placement of the protection
compound. Unapproved curing compounds are board follows the waterproofing membrane
not to be used. Thorough mixing should be done application within a reasonable time. The
at least once daily while curing compound is application of the primer materials can be made
being used. using a brush or roller. The membrane sheet is to
be applied with 12 cm overlaps at the edges and
The rate of application of the compound should ends, and rolled down firmly and completely. If
be checked occasionally and a record made in the the work must be left partially complete, the
Inspector’s diary as to the area covered and exposed edges on the outside strips are to be
quantity used. finished with a trowelled bead of mastic. The
following procedure for fixing the membrane to
508 WATERPROOFING CONCRETE the concrete surfaces should be complied with:
SURFACES
• Primer Over a cleaned concrete surface, the
Generally, all concrete below grade is to be primer is applied following the membrane
protected with a complete waterproofing manufacturer’s printed instructions and
membrane system. There are two types of allowed to dry. If the concrete is not covered
waterproof membrane, Type A and Type B. All within 36 hours, re-priming is required. The
materials used for waterproofing are to comply membrane should be installed after
with the Standard Specifications, Section V-8, structures are completed to avoid a
Subsection 508.03 for Type A waterproofing piecemeal application with an excessive
membrane and Subsection 508.04 for Type B number of seams.
waterproofing membrane. Unless otherwise
500-32
CONSTRUCTION SUPERVISION MANUAL Section 500
WATERPROOFING
• Membrane After the primer has dried, the to the outer edge of the slab and is to be
Contractor is to apply the self-adhering protected until the following overhead work
membrane to the concrete surface without is completed. Membrane that is placed on
stretching and with the polyethylene face out. sidewalls is to extend down and out to the
The membrane is to be smoothed down with edge of the previously applied horizontal
heavy hand pressure or with a small roller. slab membrane.
The edges and ends are to be lapped as
specified. • Reglet Where the top of the membrane ends
at a reglet, the membrane is to extend therein
• Corners and Edges The inside and outside and the reglet is to be filled with rubberized
corners of the membrane are to be doubled mastic.
using an initial strip of 30 cm width
membrane centered along the axis of the • Protrusions Areas around piping and
corner. The strip is then to be covered by a protrusions are to be double covered with an
regular application of the self-adhering additional layer of self-adhering membrane
membrane. All exposed edges of the for a minimum of 300 mm in all directions.
membrane are to receive a trowelled bead of The membrane edges are to be coated and
mastic. the gaps between the protrusions are to be
filled with a rubberized mastic.
• Horizontal Slabs and Sidewalls Membrane
that is placed on horizontal slabs is to extend
500-33
CONSTRUCTION SUPERVISION MANUAL Section 500
500-34
CONSTRUCTION SUPERVISION MANUAL Section 600
600-1
CONSTRUCTION SUPERVISION MANUAL Section 600
600-2
CONSTRUCTION SUPERVISION MANUAL Section 600
600-3
CONSTRUCTION SUPERVISION MANUAL Section 600
600-4
CONSTRUCTION SUPERVISION MANUAL Section 600
be placed to allow each joint or section of 3. Joining Pipe The method of joining rigid pipe
pipe to be easily adjusted to the proper line requires careful attention. The ends must be
and grade. fully shoved home and the inner surfaces
should be reasonably flush and even. Joints
2. Pipe Laying Pipe laying should proceed for rigid pipe must be made with rubber
starting at the low end of the section between gaskets recommended by the manufacturer
drainage structures. The first pipe section and approved by the Resident Engineer.
should be a short (3.0 Meters maximum) Rubber gaskets must form a flexible
piece adjacent to the drainage structure and watertight seal. The Inspector should ensure
properly located with respect to the drainage that gasket lubricants are compatible with
structure. The drainage structure is generally the gasket. Petroleum based lubricants could
constructed first simplifying the proper damage rubber gasket materials.
positioning of the pipe but this is optional.
Bell and spigot pipes should always be laid 4. Pipe Bedding Pipe bedding is intended to
with the “bell” end at the higher elevation provide a uniform foundation that will
than the spigot end. The reinforcement minimize the effects of differential settlement
required for the unlimited width trench and assist the pipe in resisting embankment
condition should be in place and fixed to the loads. Two types of pipe bedding are used;
bedding anchors prior to pipe laying. The a concrete cradle and concrete encasement.
mud slab should be thoroughly cleaned prior Concrete pipe is supported by a concrete
to the pipe laying operation as later cleaning cradle unless otherwise specified on the
of soils and debris is difficult. The pipes plans. GRP pipe is always placed in concrete
should be fixed in final position using encasement. The Resident Engineer should
precast concrete wedge blocks. After be familiar with the requirements set forth in
checking by the Surveyor, the pipes are fixed the Standard Drawings, Standard
to the bedding anchors using wire ties. Specifications, Section VI-2, Subsection
Bedding anchors are used to resist floatation 602.07 regarding concrete bedding for
of the pipe during the concrete pour for the pipelines and mud slabs for storm water
concrete cradle or concrete encasement. drainage.
600-5
CONSTRUCTION SUPERVISION MANUAL Section 600
5. Concrete Cradle After the pipe has been documents or, in the opinion of the Engineer,
laid, a concrete cradle is formed by pouring is unsuitable.
concrete up to the “springline” or widest
point on the pipe. In fill sections, the Backfill material must be placed and
embankment must be built up and compacted compacted in 15 cm maximum layers. Each
at least 30 cm above the top of the proposed layer of backfill must be mechanically
pipe before digging of the trench can begin. tamped to 95 percent of the maximum
density. Imported backfill material must
6. Concrete Encasement Concrete encasement consist of borrow material selected from
is used for all GRP pipe. It is also used for approved borrow pits unless otherwise
high embankment conditions where trench indicated on the plans.
loads on the pipe are very high. The
Inspector should make sure that the thickness The load supporting strength of any pipe is
and concrete strength requirements are never directly affected by the condition of the
less than shown on the plans. material around the pipe and of the bedding
material. Usually, the higher the degree of
7. Forming Forming may be required for the compaction of the backfill, the less the pipe
unlimited trench width condition to contain will deform under load. Consolidation of the
the concrete encasement and/or cradle. material alongside the pipe results in an
Forms must be firmly braced against the increased transfer of the embankment load
sides of the trench to avoid deflection and directly onto the pipe.
maintain the proper clearances as indicated
on the Standard Drawings. Backfill and compaction between the
concrete encasement or cradle and trench
8. Concrete Placement The completed walls for the unlimited trench width
installation should be checked and approved condition needs special attention. Hand
by the Inspector and Surveyor prior to tampers and vibratory plate compactors may
pouring concrete. Concrete placement, not achieve the desired compaction rates due
finishing, and curing operations are to working in narrow widths. The
described in Section 500. Contractor’s operation should be carefully
scrutinized to ensure the required
compaction is being achieved. Caution
CONCRETE POUR CHECKLIST
should be used to avoid over-tamping to the
extent that the pipe is lifted out of position.
9 Pipe grade and alignment are proper.
600-6
CONSTRUCTION SUPERVISION MANUAL Section 600
• After flooding, water will be drawn 3. Pervious Backfill Type III A 5 cm layer of
down to a level that is under the base granular backfill material is placed over the
elevation of the lift. geotextile fabric which aids in the filtering of
fines and provides a cushion for the pipe
• Repeated flooding and draw down cycles during placement. The material must be
will continue until the specified carefully placed to avoid damage or
compaction and elevation is reached. displacement of the filter fabric. Hauling and
The use of vibratory compaction spreading equipment should always be on the
equipment may help to achieve the placed material and not on the geotextile.
required compaction.
4. Perforated PVC Pipe The perforated pipe is
• A minimum of two acceptable in-situ placed in the trench fully bedded over its
density test results per layer per section length with pervious backfill type III
will be required. Moisture content by material. The grade and alignment should be
‘Speedy’ moisture methods should be checked and approved by the Surveyor and
used to ensure test results are made Inspector prior to allowing the Contractor to
available in the shortest possible time. completely backfill the pipe. Approval
should include complete and proper
605 DRAINAGE STRUCTURES AND connections to the receiving drainage
APPURTENANCES structure and PVC end caps at the upper
ends.
605.01 PAVEMENT SUBBASE
DRAINAGE SYSTEM 5. Pervious Backfill Type V Pervious backfill
type V is a coarse mixture of aggregates
The purpose of the pavement subbase drainage from 1/2” to 8” graded in accordance with
system is to remove excess water from the the specifications. A 20cm layer is typically
aggregate base courses under the pavement specified and must be compacted to 95% of
resulting from high ground water conditions that the maximum dry density.
are prevalent on Abu Dhabi Island. The subbase
drainage system consists of perforated pipes The completed installation must be inspected
placed parallel to and under all low side curb in place by the Municipality Representative in
lines of main roads, parking areas, service and accordance with the Standard Specifications.
sector roads. The perforated pipes are connected
605.02 MANHOLES, INLETS, AND
to the storm water drainage system. Pervious
CATCH BASINS
backfill material which surrounds the perforated
pipe is separated from the existing soils or 605.02.01 General
subgrade material by a geotextile material. The
procedures for construction of the subbase Before work begins on any drainage structure,
drainage system are described as follows: the Inspector and the Surveyor should examine
the plans and the Contractor’s staking to assure
1. Shop Drawings The Contractor will include that the structure will be properly located and
the perforated pipe system on the storm pipe connections suitably aligned with
water drainage system shop drawings thestructure walls. Adjustments may be needed
identifying pipe locations, invert elevations, to improve the integrity of the structure.
and connections to the drainage structures.
600-7
CONSTRUCTION SUPERVISION MANUAL Section 600
600-8
CONSTRUCTION SUPERVISION MANUAL Section 600
Table 600.01
Drainage Structure
Waterproofing
Structure Exterior Interior
Inlets Waterproofing Membrane Type A Coal Tar Epoxy
Catch Basins Waterproofing Membrane Type A Coal Tar Epoxy
Manholes Waterproofing Membrane Type A GRP Liner
Junction Chambers Waterproofing Membrane Type A GRP Liner
The Standard Specifications allow precasting of ensure the pipe connections will be straight and
various drainage structures or components. The at the proper invert elevations.
Contractor is required to prepare detailed shop
drawings and method statements for the Resident 605.02.05 Wall Construction
Engineer’s approval of both precast and cast-in-
situ components of the drainage system. The Reinforced concrete construction guidelines are
Inspector should be thoroughly familiar with the included in Section 500. Drainage structures
approved shop drawings. typically consist of heavily reinforced concrete
buried structures with numerous corners, angles,
605.02.02 Excavation pipe connections, and benches. They require
careful attention for placement of reinforcement
The excavation for structures shall allow suitable and formwork to obtain necessary clearances and
space between the outside of the structure and permit proper spacing and vibration of the
the suitably supported soil face for construction concrete. The Inspector should assure that the
and inspection of the structure before backfilling. Contractor has carefully conformed to the
Excavations must be suitably braced, sheeted, or approved shop drawings and has anticipated
sloped back in accordance with the specification problems prior to concrete placement.
requirements. The Inspector shall insist on a
safe working environment at all structure 605.02.06 Pipe Connections
locations. Overexcavation should be avoided
and any disturbed materials shall be Pipe connection requirements vary with the type
recompacted, tested, and approved prior to of pipe material and structure detailed as
placement of the concrete mud slab. follows:
600-9
CONSTRUCTION SUPERVISION MANUAL Section 600
• Precast Units - Blockouts are normally pipe materials. Various exfiltration and
provided in precast structures to accept infiltration test procedures and allowable
minor pipe connections. The connection tolerances are detailed in the specifications.
procedures should be detailed in the
Contractor’s approved method statement. 607 RECORDS
Epoxy bonding is required for all such
Drainage system construction involves many
construction joints.
different items which comprise a large portion of
the Bill of Quantities. An efficient and orderly
605.02.07 Frames & Covers
means of recording and documenting the
inspection, testing, and measurement of the work
Installation details will be shown on the
will ensure that all items and operations have
approved shop drawings. Normally the walls of
been checked and approved.
inlet or catch basin structures are constructed to
within 30 cm of finished elevation to allow the
Organization begins at the shop drawing
frame and cover to be set and aligned with the
preparation stage when the Contractor and
curb. The frame should be supported in position
Resident Engineer discuss and agree on a number
using metal chairs or precast K250 concrete
identification system for all structures and
blocks. Manhole frames are anchored with
pipelines that will track the operations from
galvanized rods as shown on the plans.
initial excavation through final testing of the
work. Summary forms that record the progress
606 TESTING of work for pipe runs and structures should be
Testing for watertightness is required for completed and maintained daily for the benefit of
drainage system pipelines and structures in all supervision staff as well as the Contractor.
accordance with the Standard Specifications.
Deflection testing is also required for flexible
600-10
CONSTRUCTION SUPERVISION MANUAL Section 600
Pipe Type Depth Trench Mud Pipe Concrete Backfill & Compaction Testing
Run Size Category Exc Slab Placed Cradle/Enc L-1 L-2 L-3 L-4
600-11
CONSTRUCTION SUPERVISION MANUAL Section 700
700-1
CONSTRUCTION SUPERVISION MANUAL Section 700
700-2
CONSTRUCTION SUPERVISION MANUAL Section 700
704 BRIDGE SUPERSTRUCTURE weeks before placing the concrete in the deck, a
pre-construction conference should be held to go
Erection of false work for cast-in-place
over the procedures to be used and to emphasize
superstructures follows completion of the
the critical areas of construction. As a
substructure supports. The Contractor is
minimum, this should include a discussion of the
required to prepare and submit a method
rate of pour, personnel and equipment and back-
statement to the Resident Engineer for approval
up equipment to be used, type of finish, and
as described in Section 504.06, Falsework.
curing details.
The method statement should be supported by a
Proper positioning of the reinforcing steel is very
detailed set of structural calculations certified by
important. Adequate blocking and ties are
a licensed structural engineer. Allowance is to
necessary to hold the steel in place. If the traffic
be made in the initial falsework levels for any
on the reinforcing steel causes it to deflect, the
settlement of supports and deflection due to the
spacing of the chair supports is not adequate. A
dead weight of the concrete and prestressing
pre-check of the screed setting for proper
forces. Levels and camber should always be
elevations and clearances to the reinforcing steel
checked and any final adjustments made during
is essential before any concrete placement. The
the concrete placement. No further adjustments
finishing machine should be run the full length of
should be attempted after the concrete has started
the pour after the screed is adjusted to check the
to set.
deck thickness and cover of the reinforcing steel.
During the pour, frequent checks should be made
704.01 BRIDGE DECK CONSTRUCTION
of the actual cover obtained directly behind the
finishing machine and recorded in the Inspector's
Construction of maintenance-free bridge decks Daily Report.
requires close attention to details. One or two
700-3
CONSTRUCTION SUPERVISION MANUAL Section 700
Quality concrete is required. Uniform all the project people who will be involved in
consistency of the concrete should be maintained inspection will be well informed.
throughout the pour. Along with the guidelines
set forth in Section 500 of this manual, the It is important that the Resident Engineer is
following should be observed: The water-cement advised as far ahead as possible of the date that
ratio is very important. It should be the the Contractor plans to prestress so that
minimum possible to produce the required arrangements can be made for inspection. There
workability and not exceed the specification are detailed requirements in the specifications
limit. and on the plans covering materials, procedures,
forms, hardware, etc. Even though the actual
Unless otherwise specified, to keep the water- pre-stressing may be inspected by others, the
cement ratio as low as possible, the use of a project personnel are responsible for quality
water reducing additive is recommended. control throughout the operation from forming to
However, no water reducing additives are to be final acceptance.
used until approval has been given in writing by
the Resident Engineer. Frequent checks of the Pre-stressed concrete bridge members (typically
free water contained in the aggregates is beams, girders, and members of girder systems)
necessary to determine the amount of water are cast at a concrete fabrication yard. Section
actually contained within the concrete mix. VIII of the Standard Specifications contains the
requirements for quality assurance including
704.02 PRE-STRESSED CONCRETE system manufacturer qualifications, sampling
and testing, certification, submittals, and
technical assistance. The Resident Engineer and
Pre-stressing can be accomplished by pre-
his Inspector should be familiar with these
tensioning, by post-tensioning, or by a
requirements as well as those of the Contract
combination of these two methods.
Documents.
In the first method, tendons are tensioned before
After the award of a contract involving the use of
the concrete is placed. After the concrete has
prestressed concrete, the Resident Engineer shall
developed a specified strength, the anchorages
see that the Contractor provides the name of the
for the tendons are released and the forces in the
Subcontractor who will produce the prestressed
tendons transferred to the concrete.
concrete members. The Resident Engineer shall
then see that the manufacturer submits complete
In the second method, post-tensioning, tendons
details on his facilities and equipment, shop
are placed in ducts in the concrete and are
drawings, and proposed methods for review and
anchored and stressed after the concrete has
approval by the Structural Engineer.
developed a specified strength. Then the ducts
are pressure grouted. The third method is a
While the inspection of prestressed concrete will,
combination of the first two methods. In
in most cases, be performed by an Inspector who
accordance with the design, some of the tendons
has had experience in this field, he may work in
are pre-tensioned with the remaining tendons
another area and the site of the plant may be a
post-tensioned.
considerable distance from the project. Such
circumstances should not cause the Resident
Pre-stressing is specialized work that is done by
Engineer to shirk his responsibilities regarding
crews trained and experienced in the operation.
the manufacturing of the members that will be
Although the responsibility for pre-stressing lies
used on the project being built under his
with the Contractor, it is important that the
direction. He should know everything about the
Resident Engineer and Inspector are familiar
process that the Inspector is expected to know
with the operation. The Resident Engineer
and he should make certain that the Inspector is
should ask for any necessary training and advice
knowledgeable on the subject and that he is
well ahead of the pre-stressing operation so that
applying this knowledge to the extent necessary
to obtain the desired results. Communication
700-4
CONSTRUCTION SUPERVISION MANUAL Section 700
between the Inspector and the Resident Engineer The stress induced in the pre-stressing steel must
should be sufficiently frequent to keep the be measured both by gauges and by elongation of
Resident Engineer thoroughly informed of the the tendons. Variation in modulus of elasticity in
problems, progress, schedules, etc. the steel or variation in tightness of twist in the
strands will produce variations in elongation for
Transportation and erection are the responsibility the same gauge readings. Conversely, variations
of the Contractor and the manufacturer. Various in friction between the tendons and the supports
kinds of devices are anchored in the concrete for or in the ducts or friction and losses in the jack
the purpose of lifting the members. The members and pumping system will produce different gauge
should not be lifted in any way other than by use readings for the same elongation.
of the devices provided. Members should always
rest in an upright position setting on blocks LOAD MEASURING GUAGE
located near the ends just as they are to be REQUIREMENTS
installed in the structure. The Inspector should
observe the handling of the members; prime
responsibility for proper handling is the • An accuracy within two percent and should be
Contractor's. The Inspector should record and calibrated by an approved laboratory before
report any improper handling or any damage, their use.
known or suspected, to the Resident Engineer. • A certified calibration curve should be
furnished by the laboratory for each gauge or
704.02.01 Forms and Equipment device.
• Gauges should be calibrated for the jacks with
which they are to be used.
Unless otherwise specified, the following lists the
• Gauge dials should be not less that 20 cm in
general guidelines that should be followed
diameter and should be readily legible. Dials
concerning forms and equipment: should read in kilograms or be accompanied by
a chart from which the dial reading can be
Only steel forms, in good condition, may be quickly converted to kilograms.
used. They should be of sufficient thickness, • All gauging devices should be re-calibrated at
braced, stiffened, and anchored so they will least once each year; however, if during the
withstand the forces due to placing and vibrating progress of the work, any gauging system
the concrete without loss of correct alignment. appears to be giving erratic or erroneous
The forms must be thoroughly cleaned and results or if the gauge readings and elongation
coated with a bond breaker before each use. measurements indicate materially different
stresses, the jack and gauges should be re-
Joints must fit tightly to avoid loss of mortar and
calibrated.
to avoid rough blemishes on the concrete.
• Anchorage and gripping devices should be
adequate to hold the tendons secure under the
704.02.02 Construction required loads without appreciable movement
or slippage.
The position of the strands in relation to the form • At least two concrete vibrators, of the proper
soffit and sides should be checked carefully as size and vibration frequency, should be
the strands are being initially tensioned since available.
adjustments of their position is difficult after a • When required, pressure grouting equipment
number of strands are tensioned. Strands should capable of exerting pressures up to 700 kPa
be in correct position as shown on the plans, must be available.
laterally and vertically, with a tolerance of six • If work is to be performed at night, adequate
lighting should be provided.
millimeters being allowed. Post-tensioning ducts
and end bearings should also be checked for
position. The allowable tolerance for positioning
these elements is six millimeters.
700-5
CONSTRUCTION SUPERVISION MANUAL Section 700
If the difference in indicated stress between the Metal chairs or small precast concrete blocks
jack pressure and the pressure computed from may be used to support the strands and stirrups.
the elongation is less than five percent, the lower
of the two should be brought up to the specified 704.02.03 Reinforcement and Details
value, resulting in there being a possible
overstress rather than an understress. If the The center line of bearings, or the beam center
difference is more than five percent, the entire line, should be marked on the form soffit and
operation shall be carefully checked and the used as a reference for spacing of stirrups, drape
source of error determined and eliminated before supports, bearing devices, diaphragm
proceeding. It may even be necessary to have the connections, etc. Ordinary reinforcing may be
jacks and gauges re-calibrated. The Inspectors prefabricated in cages by wiring or tack welding.
should have available pre-stressing information Each weld should be kept to an absolute
required and should be thoroughly familiar with minimum. No wiring shall be permitted in close
it. proximity to the pre-stressing tendons without
adequate protection to the tendons. Positioning
In central plant manufacturing, long pre- of the reinforcing should be performed with care
tensioning beds are generally used, allowing to make certain that the correct distance from the
several members to be made with one strand. forms is maintained. End bulkheads and
The tension must be the same for each member bearings should be set out far enough to
but if strands are draped, friction at hold-down compensate for elastic shortening of the member
and hold-up points during stressing may reduce when tension is released.
the tension in the members toward the non-
jacking end. This should be checked and 704.02.04 Placing Concrete
corrective measures taken if the condition exists.
Checking may be done by computing the The Inspector should not permit the placing of
elongation of some convenient length, say six to concrete in any member until the forms,
seven meters, which may be measured on a reinforcing steel, and pre-stressing tendons have
straight section of strand between supports. This been checked by him for compliance with the
length is marked on the strand in two or three specifications and the approved working
locations before stressing; then after stressing, drawings and he has given his approval for the
the elongation’s are determined and compared. placing of concrete to continue. When the forms
Corrective measures should be taken if results and the steel are hot, due to rays of the sun, they
indicate non-uniformity of tension in the should be sprayed with water ahead of the
members. placement of concrete. The consistency of the
concrete should be closely controlled through
The usual procedure for stressing is to place a frequent moisture tests of the aggregate and
small initial stress, about five percent of the slump tests of the concrete. No more water
total, into the tendons before marking them for should be used in the mix than necessary for
elongation measurements. This is to take the good placing. Concrete should be deposited as
slack out of the tendons, seat the opposite end nearly as possible in its final position without
anchor, and tighten up the bearing surfaces. The resorting to moving the concrete appreciably in a
initial stress produces some elongation. The longitudinal direction by use of vibrators.
manufacturer's recommended modulus of Concrete should be placed in at least two
elasticity should be used in all elongation continuous horizontal layers for I-shaped beams
computations. One set of stressing calculations of depths not exceeding one meter and at least
may be used for more than one member three such layers for beams of greater depth.
providing the members are identical, but the The first layer of concrete should completely fill
Inspector should satisfy himself that the stressing the bottom flange and extend 5 to 10 cm up into
set-up is the same as that for which the the web. Care should be exercised to see that all
calculations are made. parts of the forms are completely filled with
concrete, that the coarse aggregate is worked
away from the form faces by use of the vibrators
700-6
CONSTRUCTION SUPERVISION MANUAL Section 700
and by use of spades, and the concrete is worked the curing is not accomplished unless the
under and around the pre-stressing tendons and temperature of the air surrounding the member is
the reinforcing bars without displacing them. above 70°C. The rate of cooling must not
exceed 4°C per hour. Usually 12 to 18 hours at
Vibrators must comply with the specifications a temperature near 70°C will result in the
and there should be at least one spare vibrator to required minimum concrete strength for release
be used in case there is a breakdown. Vibrators of the tendons.
should be inserted into the fresh concrete slowly
and withdrawn slowly. Coverings or hoods over the members should be
at least 15 cm above the concrete surface and be
704.02.05 Concrete Tests tight enough to prevent heat and moisture loss.
700-7
CONSTRUCTION SUPERVISION MANUAL Section 700
Specifications, Section VIII-2, Subsection stress caused by the weight of the tops of the
802.07.b will be rejected. beams.
Any prestressed girder displaying one of the If the beams tip over or are to be stored upside
following defects shall be rejected and a new down, they will crack. The beams should be
girder is to be cast at the Contractor's expense: stored off the ground and the supports should be
placed where the actual structure support will be
• Any girder represented by samples not located.
meeting the specified strength.
704.02.11 Handling Pre-stressed Concrete
• Any girder that has one tendon exposed for a Beams
length more than 24 diameters, or two or
more exposed tendons. The beams should be picked up and supported
only at the designated pick-up points unless the
• Honeycombing of the girder to such an plans state otherwise. These pick-up points are
extent that chipping away of the loops protruding out of the tops of the beams
honeycombed concrete results in the (one near each end).
conditions above describing exposed pre-
stressing steel. The pick-up cable should maintain a safe slope.
A safe slope would normally be 1½:1. If a
• Any girder that has a stress crack in the area flatter slope is used, the beam may be damaged.
beginning 10 cm from the unit end to the Normally the Contractor will use two cranes,
center line of the unit that is greater than 13 which will not create any problems. If he uses
mm in depth and five thousandths (0.005) of one crane, the Inspector should make sure that
a cm in width. the cables are long enough. In addition, they
must be the same length for proper balance.
704.02.09 Inspecting Beams and Girders
704.02.12 Erection of Pre-stressed Concrete
When the beams or girders arrive, the Inspector Beams
should look for any cracks. Small hairline
cracks are usually due to shrinkage and are not Pre-stressed concrete beams are erected
critical to the strength of the beams. However, according to the framing plans included in the
large cracks indicate that the beams were contract documents and according to the shop
probably dropped, or something dropped on drawings. The framing plans show a plan view
them, or stacked incorrectly. of the beams with their markings. The beams
will have erection marks painted or stamped on
Also check the reinforcing steel that protrudes them to show where each beam is to be placed.
out of the top of the beams. This reinforcing
steel will be used to tie the beams and the deck 704.03 POST-TENSIONED CONCRETE
slab together, so it should not be broken or bent.
Any damage should be reported to the Resident
Engineer. The construction of cast-in-place post-tensioned
concrete bridges requires considerable attention
704.02.10 Storing Pre-stressed Concrete to details of construction by the Contractor and
Beams Inspectors.
The Contractor must store the prestressed Besides the falsework and form plans for the
concrete beams in an upright position. This is structure being approved by the Structural
important because the pre-tensioned cables are Engineer, post-tension detail plans will be
located in the bottom of the beams. This makes submitted for approval. Included in these details
the beams resistant to compression and tensile will be the anchoring details, jacking forces,
tendon profile, elongation of the tendons, and the
700-8
CONSTRUCTION SUPERVISION MANUAL Section 700
tendon stressing sequence. In many structures, should check the reels of strand intended for use
the dead load of the structure is increased at the and reject those that show damage to the strand
jacking ends during the jacking operation. In or visible rust.
these cases, the falsework at the jacking ends
must be designed to carry the additional load. Some projects may be designed for the use of
high strength steel rods instead of strands. These
The installation of the post-tension system begins rods come in various sizes to give the required
with the placing of assemblies consisting of a steel area for the tendon in one bar instead of
bearing plate, transition cone or trumpet, and bundling several strands in the tendon.
grout inlet. Duct sections consisting of a rigid
conduit are assembled with couplers and are tied Jacking operations are not to be started until the
to the stirrups. Anchorages and bearing plates concrete in the structure has cured for the
are securely fastened to the forms to prevent specified time or reached the specified strength.
movement and loss of mortar during concreting. Jacking will be carried out in the sequence shown
Connections between trumpets and ducts, ducts on the approved post-tension details to reduce the
and couplers, and ducts and vent saddles are amount of eccentric loading on the structure.
taped with a durable and waterproof tape to DURING THE JACKING OPERATIONS,
prevent intrusion of mortar. NO PERSON SHOULD BE DIRECTLY
BEHIND EITHER END OF THE
It is necessary that the ducts be located in the TENDONS.
position shown on the approved post-tension
details in order for the structure to function as Each jack used to stress tendons will be equipped
designed. A misaligned duct will cause increased with either a pressure gauge or load cell along
friction and localized stress that can result in a with certified calibration charts for determining
failure of the member during the stressing the jacking force.
operation. The Inspector must check to see that
the ducts are properly located and securely Gauging devices should be re-calibrated at
fastened in place to prevent movement during intervals of not more than 180 days; however, if
concreting. during the progress of the work any gauging
system appears to be giving erratic results, or if
On continuous structures, vents must be placed gauge readings and elongation measurements
at the high and low points of the tendon and show materially different stresses, the jack and
grout inlets at the end of the tendon. the gauges must be re-calibrated. As per the
Standard Specifications, Section 802.09, an
At the completion of the duct installation and agreement of ±5 percent is satisfactory.
before placement of concrete in the top slab, a
device of smaller diameter than the inside A starting load, usually 20 percent of the jacking
diameter of the duct is blown though the ducts to load, as shown in the approved post-tensioning
ensure no undetected damage or blockage has schedule is applied to the tendons. The purpose
occurred. of this starting load is to take up the slack in the
tendon so that an accurate elongation
The pre-stressing reinforcement strand is measurement may be made. This load is applied
delivered to the site in sealed reel-less packs or by the hydraulic jack and measured by the jack
reels containing desiccant to prevent corrosion. gauges. During the stressing operation, the
It is necessary that the pre-stressing tendons will be jacked to the specified load and
reinforcement is free of rust and kept clean while the jacking load and elongation will be recorded.
it is assembled, stressed, and grouted. Normally Also the elongation after seating must be
the grouting will take place within 10 days of the measured and recorded. The Inspector shall
time the strand is removed from the packs to immediately report to the Resident Engineer any
prevent the accumulation of rust. The Inspector unusual situation related to the gauge and
700-9
CONSTRUCTION SUPERVISION MANUAL Section 700
POST-TENSIONING JACK
700-10
CONSTRUCTION SUPERVISION MANUAL Section 700
700-11
CONSTRUCTION SUPERVISION MANUAL Section 700
700-12
CONSTRUCTION SUPERVISION MANUAL Section 700
704.04.03 Shop Inspection The temperature of the heated area will not
exceed 620°C (A dull red) and will be controlled
The Resident Engineer shall ask the Contractor by temperature indicating crayons, liquids, or
to give notice at least two weeks in advance of bimetal thermometers.
the beginning of shop work if an inspection is
required. Such an inspection would normally be Following the straightening of a bend or buckle,
conducted by a structural specialist. If the steel is the surface of the metal will be inspected
fabricated out of the country, the shop inspection carefully for evidence of fracture.
will be performed by a third party inspection
firm. The Resident Engineer must receive 705 BEARINGS
documentation that the inspection has been made
705.01 GENERAL
before approval and installation of the steel
members. The Resident Engineer should also
give the steel a visual inspection as it is received Elastomeric (neoprene) bearing pads are
on the project, before unloading from the truck. commonly used for relatively light reactions and
The requirements for shop inspection are moderate superstructure movements. Pot type
specified in the AASHTO Construction Manual bearings are used for heavy reactions and large
for Highway Bridges and Incidental Structures, superstructure movements.
if not otherwise included in the specifications.
705.02 ALIGNMENT
704.04.04 Storage and Handling
Before erection of the superstructure is started,
Upon delivery of the steel, it should be inspected
the center line of bearings should be laid out on
for signs of damage and any such damage should
all substructure units by precise methods, and the
be recorded and reported to the Contractor.
roadway center line (or reference line) and center
line of bearings scratched or otherwise marked
The unloading of the steel must be accomplished
on the concrete. Bearing areas should be
by means of equipment and methods which will
checked to see that a plane surface is provided at
not damage the members. The steel should be
the correct elevation. If the concrete surface that
moved by use of slings and wood blocks to
will be in contact with the bearing pad is rough
prevent damage to flanges. Steel members
or irregular, it should be ground to provide full
should never be dropped. Steel should be stored
and uniform bearing. If a bearing area is low
in a well-drained area which is in no danger of
with respect to other areas on the unit or in
being flooded. All beams and girders should be
relation to other units of the structure, shims of
placed in an upright position, on wooden blocks.
the same size as the masonry plate, and of the
Blocking shall be provided that will keep all
required thickness, should be ordered with the
members off the ground and clear of grass,
approval of the structural specialist. Avoid
brush, or other material. Long members shall be
using a number of thin shims if a single one of
supported in a manner that will prevent injury
the required thickness can be made from
from deflection. The members should also be
standard thickness plates. The shims should be
handled and transported in an upright position.
made from the same type of steel as that
They should be braced to prevent overturning.
specified for the bearings.
704.04.05 Straightening Bent Material
705.03 BEARING PADS
Methods for straightening of plates, angles, or
other shapes and built-up members that will not Preformed fabric or plastic bearing pads are
produce fracture or other injury to the metal will required to conform to the AASHTO
be approved by the Resident Engineer. Distorted Specifications for Highway Bridges. Such pads
members will be straightened by mechanical may be used without testing providing a
means or by the careful planned and supervised certification has been received by the Structural
application of a limited amount of localized heat. Engineer stating that the material proposed for
700-13
CONSTRUCTION SUPERVISION MANUAL Section 700
700-14
CONSTRUCTION SUPERVISION MANUAL Section 700
grout flowing. After the grout has taken its • Unusual problems encountered and their
initial set, remove the form and cut the edges of solutions.
the grout with a trowel to about a 45-degree
bevel from the bottom of the shoe to the top of • Changes, extra work, and time extensions,
the pier coping. Do not allow the finished grout and their justifications.
to extend above the bottom of the shoe.
• Results of materials test reports and
706 EXPANSION JOINTS dimensioned checks.
• Recurring reports.
700-15
CONSTRUCTION SUPERVISION MANUAL Section 800
SECTION 800
MAINTENANCE AND STAGING TRAFFIC STAGING DRAWING CONTENT
OF TRAFFIC
• Traffic maintained on existing roads
801 GENERAL
• Work areas
For guidance on requirements, the construction • Traffic carried over completed permanent
supervision staff should refer to AASHTO Guide works
Specification, Section 618, the Manual on • Description of work activities for each stage
Uniform Traffic Control Devices, the Standard • Pedestrian accommodations
Specifications, the Particular Specifications, • Maintenance of access to business and
and/or the project maintenance of traffic and residential properties and car parks
• Signs, barricades, and placement details
construction staging drawings.
• Special guide signs
• Maintenance of major utility services and
The control of traffic through construction appurtenances
projects is very important. Construction • Temporary signal control
operations may inconvenience people who live • Typical sections of detours
along the right-of-way as well as those who must • Detour geometrics
travel through a project built under traffic. • Major utilities to be constructed that are
Anything the Inspector can do to minimize this critical to the staging sequence
annoyance will improve public relations. Every
effort should be made to handle traffic through
and around construction with a maximum of The proposed staging plans must be carefully
safety and with as little inconvenience and delay reviewed by the Resident Engineer to satisfy
as possible. The constant watchfulness of the himself that the works can be constructed safely
Resident Engineer and all construction personnel and efficiently. Before the Contractor can receive
is necessary to accomplish this. approval, the proposed staging scheme must be
approved in writing by the Department and the
Often traffic handling is planned prior to the job Traffic Police.
being bid and construction phasing plans are
included in the contract documents. The Resident 802 TRAFFIC CONTROL DEVICES
Engineer must evaluate the traffic planning based (TCDs)
on the conditions found at the site of the work.
Cooperative efforts between the Engineer and the
All traffic control devices (TCDs) and the
Contractor are absolutely necessary and are to be
application of traffic control measures shall
encouraged at all levels of authority. Traffic
conform to the Standard Specifications. The
handling needs will depend on the way the
Resident Engineer’s Inspector should constantly
Contractor chooses to prosecute the job and
evaluate the TCDs in light of the Contractor’s
therefore he is required to prepare and submit
operations. Modifications may be needed to
detailed traffic staging and detour plans for
ensure safety. Knowing when TCDs are not
review and approval by the Resident Engineer.
required is just as important as knowing when
they are required. The effectiveness of all TCDs
The traffic staging plans are directly tied to the
is reduced if one is left in place after the need for
Contractor’s schedule and must be reviewed and
it passes. This leads drivers to believe they can
evaluated together. Drawings prepared for traffic
ignore other TCDs in construction zones. When
staging should clearly indicate the following:
TCDs are no longer required, they should be
removed.
800-1
CONSTRUCTION SUPERVISION MANUAL Section 800
visibility at night. A night inspection of the applied to keep them in good condition and
TCDs is necessary to evaluate them, as this is visible. Damaged barriers should be rejected.
the period when the traveling public must rely
more heavily on the TCDs. End treatments vary from special terminal
sections to merely flaring the ends. The
The various traffic control devices, typical TCD treatment best suited to the situation should be
installations, and construction details are shown used. The criteria for end treatment is to use that
in the Standard Drawings including barricades, which will give the best protection under the
traffic cones, delineators, drums, and concrete given conditions at the least cost. The first
barriers. criteria for use of an end treatment should never
be the convenience or the least cost to the
803 PAVEMENT MARKINGS Contractor.
805 DETOURS
Unnecessary pavement markings should be
eradicated as soon as possible. Traffic
movement is influenced to a great extent by In a construction zone that carries considerable
pavement markings; therefore, misleading traffic, it is usually preferable to provide a route
markings can be a significant contributing cause which will take the traffic around the
of traffic accidents. construction zone. Detour plans are provided in
the Contract Documents. Should the detour
Temporary pavement markings should be placed plans require modification or a design change,
where the travel path has been changed and the Engineer must follow the review process to
where traffic is to operate on new pavement obtain written approval from the Department and
overlays or where final pavement markings the Traffic Police. When this situation arises, he
cannot be placed immediately or where traffic should be familiar with the considerations and
will be placed on intermediate layers. principles by which detours are designed. It is
desirable, whenever possible, that both ends of
804 TEMPORARY CONCRETE the detour are visible to approaching motorists.
BARRIERS Transitions should not be in close proximity to
horizontal or vertical curves, structures, or any
obstruction which would interfere with the
Construction and installation details for motorists view of the transition. Plans for
temporary concrete barriers are to be shown on detours should be prepared in accordance with
shop drawings and submitted for approval prior the Standard Drawings.
to placement.
Detours should be designed to the highest
In order to function as designed, the barrier must geometric standards relative to the approaching
be a reasonably rigid structure. The foundation facility and physical limitations of the area.
has to be solid and uniform. In some cases Transition lengths, curve radii, and super-
where a barrier is placed close to a vertical drop elevations should be consistent with the design
off, it may be desirable to place steel pins at the standards required for the speed of traffic that
backside of the barrier to prevent movement. If will be entering the detour. This could require an
pins are driven through the holes on the front additional stage in the construction, for example,
face, the pins must not protrude above the the placing of asphalt concrete over Portland
surface of the barrier. The barrier sections need cement concrete pavement to build up
to have full bearing on firm material to function superelevation.
properly. Barriers should be periodically
cleaned, painted, and new reflective panels
800-2
CONSTRUCTION SUPERVISION MANUAL Section 800
DETOUR ROADWAY
Any sudden major changes in either geometric Barricades are inherently fixed object hazards.
standards or speed limits should be avoided, if Therefore, they should not be used unless the
possible. The element of surprise can be reduced construction hazard the motorist may encounter
by making gradual, step-down reductions. These is greater than the hazard of striking the
reductions should be made in increments of not barricades. They should not be used as primary
more than 15 kilometers per hour. delineation to guide traffic.
When traffic volumes are high and construction Delineation devices must be maintained and kept
periods lengthy, detours should be built to clean. When delineators become covered with
standards consistent with those required for grime or are damaged, they become ineffective.
paved roadways. When warranted, temporary The condition and positioning of these devices
concrete barriers are recommended. Proper end should be checked daily.
protection must be provided.
806 PROCEDURES FOR SHIFTING
Unnecessary traffic stripes or arrows on asphalt TRAFFIC
pavement should never be merely blacked out
with oil or paint. Rather, the striped and
adjacent areas should be sandblasted or ground It shall primarily be the responsibility of the
down in a pattern different from the original Resident Engineer to see that detours and new
marking until the marking is no longer visible. facilities are in proper condition for handling
This change in pattern minimizes the possibility traffic. Before transferring traffic from an
that the original marking will still be visible to existing roadway to a new facility, the following
drivers, especially at night or in rainy weather steps should be taken:
when covered-over stripes have a tendency to
shine in contrast to the pavement.
800-3
CONSTRUCTION SUPERVISION MANUAL Section 800
1. Complete Detour or New Facility The Good records of traffic control facilities include:
Contractor shall construct detours, in their dates and times of day that inspections were
entirety, before traffic will be permitted to made; statements of conditions found; a complete
use them. New facilities shall be sufficiently listing of type, size, and location of devices;
completed to preclude any hazard to public orders to the Contractor to make changes or
traffic. corrections; time and date that devices are
removed or modified; photographs and comments
2. Inspection by Resident Engineer As soon as explaining any variations from standard
the detour or new facility is completed, the procedures.
Resident Engineer shall conduct an
inspection to determine its adequacy for The Contractor shall designate an individual
accommodating traffic. Special attention acceptable to the Resident Engineer responsible
will be paid to signs, barricades, lighting, for traffic control surveillance so that necessary
and all traffic control devices. Safety action may be taken with the least delay. The
aspects and driver convenience and comfort assigned individual shall complete the Daily
shall have priority. The Resident Engineer Record of Detour Maintenance form on a daily
shall coordinate this inspection the basis and submit one copy to the Resident
Department Representative. If the Engineer. The Inspector is responsible for
Department is not satisfied that the facility is checking the report for accuracy and ensuring
completed, the Contractor shall be instructed that action items identified are promptly followed
accordingly. up.
3. Inspection by Road Section Project Manager
808 MEASUREMENT AND
Unless the Department objects, the Resident
Engineer will submit a formal letter to the
PAYMENT
Department indicating the date a detour or
new facility is to be opened to traffic. The All the items of work are to be measured in
letter will indicate the expected length of accordance with the Standard Specifications or
detour operation and include drawings Particular Specifications. The Resident Engineer
showing the location and the layout of the should examine the payment provisions carefully
detour. because some items of equipment may become
property of the Municipality and, therefore, must
807 RECORDS be accounted for.
800-4
CONSTRUCTION SUPERVISION MANUAL Section 800
• 10% when the detour is removed and the • 75% when barricades, temporary lighting,
site is restored to the complete and temporary signals are delivered to the
satisfaction of the Engineer. site.
• No additional quantities will be paid for • 15% prorated over the period of use and
detour lengths exceeding plans as a maintenance.
result of revisions approved for the
Contractor’s benefit. • 10% when the item is removed to the
satisfaction of the Engineer.
2. Temporary Barricades, Temporary Lighting,
and Temporary Signals and Controls
800-5
CONSTRUCTION SUPERVISION MANUAL Section 900
900-1
CONSTRUCTION SUPERVISION MANUAL Section 900
• The date
904 FIELD NOTES AND
COMPUTATION BOOKS • Weather conditions
Field notes are the written record of pertinent
• Names of all persons in the party
information, measurements, and observations on
the project prepared by the Surveyors and • Signature of the person making entries
Inspectors. They should be kept according to
uniform practices and conform, at a minimum, to The title page must be completed as the book or
the following general requirements. project is started. The book must be adequately
indexed and cross-referenced as to its contents.
904.01 BOUND BOOKS
904.05 PERMANENCE
All field notes and computations should be
recorded in bound books. Notes should never be All entries should be made directly into bound
made on a set of plans or on loose-leaf pads and books. At completion of the project, they should
then discarded. All pages should be numbered be filed as part of the permanent record of the
and each book should be indexed. There should project.
900-2
CONSTRUCTION SUPERVISION MANUAL Section 900
900-3
CONSTRUCTION SUPERVISION MANUAL Section 900
The Joint Measurement Sheet details the measured and the work meets the contract
measurement of work for payment. For example, document requirements, including the
a completed section of aggregate subbase will be acceptability of materials and test results from
jointly measured by the Contractor and the materials lab.
Engineer’s Surveyors producing a sketch
complete with stations, offsets, and dimensioning The Request for Testing of Construction forms
necessary to define the measured item. are submitted for work that is ready for materials
Computations to determine the quantity for testing such as compaction tests. These forms
payment are clearly indicated and arranged for provide documentation of the testing of the
ease of checking by the Quantity Surveyor. The works by supervision staff.
signature of the Inspector indicates that he is in
agreement with the limits of work being
Figure 900.01
Contractor’s Daily Work Program Flow Diagram
900-4
CONSTRUCTION SUPERVISION MANUAL Section 900
Figure 900.02
Joint Measurement Sheet Flow Diagram
Figure 900.03
Request For Testing of Construction Flow Diagram
900-5
CONSTRUCTION SUPERVISION MANUAL Section 900
Payment estimates must be supported by 1. The Contractor shall prepare and submit to
documentary evidence that work items paid have the Resident Engineer a daily program of
actually been performed. The Resident Engineer work. See Figure 900.01.
must be sure that all items paid have been
2. The Resident Engineer will provide a copy of
properly inspected and approved. Whenever
the Contractor’s daily program to the
payment is made based on an estimate, the basis
Municipality Site Representative. See Figure
of the estimate must be well defined to assure
900.01.
that over payment to the Contractor is avoided.
3. The Engineer’s Surveyor will verify
The Interim Payment Estimate form is a quantities by field measurements jointly
tabulation of all contract pay items taken directly taken with the Contractor and recorded in the
from the conformed Bill of Quantities (BOQ) survey field book. The Surveyor will allow
including the unit rate and previous period the Contractor to make a copy of the field
quantities which were paid. The estimate form is book and later certify his measurements by
prepared by the Contractor and thoroughly signing the Joint Measurement Sheets.
checked by the Quantity Surveyor before finally
submitting the estimate to the Resident Engineer 4. The Inspector will record construction
for approval. The quantities are cross-checked progress, manpower, and equipment in the
with the Quantity Book maintained by the Inspector’s daily report and later certify that
Quantity Surveyor that details all items of work the work conforms to the Contract
measured and approved for payment tabulated requirements by signing the Joint
from the Joint Measurement Sheets. The Interim Measurement Sheet.
Estimate Bill Summary is used to consolidate the
payment by BOQ numbers or categories such as 5. The Contractor shall submit Joint
“Bill No. 6 Storm Water Drainage Works.” The Measurement Sheets for each completed item
Interim Payment Summary provides a complete of work or portion completed each month.
synopsis of the monetary valuations pertaining to Joint Measurement Sheets shall be submitted
the Contract relevant to the pay estimate and is with a location sketch or drawing, a copy of
signed by all parties. This form is the basis for the relevant Surveyor’s field book page,
the Contract Progress Payment Certificate calculation sheets if required, and any other
submitted to the Municipality for processing of necessary information attached. See Figure
the payment. 900.02.
Computers are increasingly being used for the 6. The Quantity Surveyor will review the Joint
maintenance of these and other project records Measurement Sheets, check the calculations,
and for estimate preparation. In such cases, sign certifying the calculations are correct,
back-up files and computer security is extremely and forward them to the Resident Engineer
important. for approval.
900-6
CONSTRUCTION SUPERVISION MANUAL Section 900
900-7
CONSTRUCTION SUPERVISION MANUAL Section 900
forward them to the Resident Engineer for • Financial Affairs Report (English and
approval. Arabic).
8. The Quantity Surveyor will record the • Other designated Consultants’ approved
approved quantities in the Quantity Book Final Payment documents.
and file the approved Joint Measurement
Sheets. The Quantity Surveyor will also 906.02 PAYMENT FOR MATERIALS
maintain As-Built Drawings on which all STORED ON SITE
construction works with approved Joint
Measurement Sheets will be recorded by The Resident Engineer must pay particular
highlighting completed portions and listing attention to the Contractor’s request for payment
the quantities approved for payment. of materials stored on site. He must use
discretion as to the percentage of each type of
9. As soon as one work item is completed, all
material he deems appropriate to pay relative to:
the approved Joint Measurement Sheets for
that item will be verified against the As-Built
Drawings. All surface finish work will be • Actual job progress according to the CPM
remeasured if necessary to verify the schedule.
accuracy of the quantities.
• Where the material is stored, the method of
10. When all Joint Measurement Sheets are storage, and any deterioration.
finalized and the quantities are agreed, the
• Length of storage time before the material is
Contractor shall prepare a Final Quantity
scheduled to be incorporated in the final
Book (Summary) sheet which will be signed
product.
by the Quantity Surveyor, Resident
Engineer, and the Contractor’s Project
Proper control of materials on site may be
Manager for final payment purposes.
utilized as an effective tool to control many
11. Based on the agreed quantities, the aspects of the project. In general the Resident
Contractor shall prepare the Final Payment Engineer should be guided by the following:
application and forward it to the Resident
Engineer for checking and onward 1. All quantities shall be physically checked on
transmittal to the Municipality. site and documented in the progress payment
support file.
12. The Engineer will check and certify the final
payment and forward it to the Municipality 2. Where the job site area is too restrictive, the
along with the following documents: Engineer may approve additional storage
areas proposed by the Contractor. In this
• Contract Progress Payment Certificate. case, the Contractor must provide:
900-8
CONSTRUCTION SUPERVISION MANUAL Section 900
c. Letter certifying that all materials stored by the Contractor and supervision staff at the
at the additional storage area are the end of each day’s work. A number of
property of the Municipality and will be supplementary forms are used in the
used solely for that specific project. documentation of day works and samples are
included in the appendix.
3. In no instance shall payment be made for
more materials than those required to 908 SAFETY RELATED
complete the project and furnish any required REPORTING
spares.
4. No payment shall be made for materials Although every effort is made to avoid accidents,
which are not approved. each incident must be reported using the
prepared form. The Resident Engineer’s Report
5. No payments shall be made for materials not of Contractor’s Accident is normally initiated by
yet delivered, even on the basis of letters of the Inspector as being the individual that is likely
credit. a witness to the occurrence. When an accident
occurs the Inspector should assert himself at the
6. Unit rates for materials shall be based on the scene to gather all of the information necessary
materials portion of the tender unit rate to complete the report form. He should then
breakdowns or materials invoices, whichever discuss the matter with the Resident Engineer
amount for the specific item is less. and present the completed form for his review
Materials on Site payments are not to exceed and signature. The Project Utility Engineer is
75% of the actual invoice value of the similarly responsible for preparing the Utility
materials. Incident Report.
900-9
CONSTRUCTION SUPERVISION MANUAL Section 900
900-10
CONSTRUCTION SUPERVISION MANUAL Section 1000
• Safety Issues
1000-1
CONSTRUCTION SUPERVISION MANUAL Section 1000
1003.03 CORRESPONDENCE WITH THE • Subject Matter --- listed in order, with
CONTRACTOR concise information on decisions reached,
issues discussed, and actions required.
1000-2
CONSTRUCTION SUPERVISION MANUAL Section 1000
1004.02 DEFINITIONS
1. Project Termination Report. Not less than 60
days prior to the anticipated PHOI, the
• Preliminary Handing Over Inspection Resident Engineer shall submit the Project
(PHOI) Termination Report. Its function is to
The Government's review, with the Engineer, provide a closing out status report while
of the completed Works and all materials simultaneously furnishing a major item
incorporated therein for compliance with the check list to the Resident Engineer. Updates
Contract Documents. The PHOI is held at of the Project Termination Report are to be
the close of the project's construction submitted as required but not less than every
activities and the starting of its maintenance 30 days.
period by members of the Municipality
Projects Committee along with the Engineer 2. Prefinal Inspection. The Contractor shall
and the Contractor. submit a written Notice of Completion of the
Works which shall include, for the approval
• Final Handing Over Inspection (FHOI) of the Resident Engineer, a proposed
The FHOI is held at the end of the project's schedule for completing the below listed
maintenance period (normally one year) by items.
members of the Municipality Projects
Committee along with the Engineer and the • Unfinished items of Contract work.
Contractor. It signifies the project's final
handing over to the Government. • Agreement of final quantities.
1000-3
CONSTRUCTION SUPERVISION MANUAL Section 1000
held. This letter will be discussed by the • Receipts for office facilities, vehicles, or
MPC who will establish the date and time other Contractor-owned property which
for the inspection. Once that schedule is reverts to the Contractor at the
confirmed, the Resident Engineer shall, in completion of the Contract.
turn, provide the Contractor with written
notification of the schedule for the PHOI. • Receipts for the specified number of
warranties, instruction manuals,
4. Agency Notification. Concurrent with the guarantees of installed equipment,
letter recommending the Government certificates, and service manuals.
schedule the PHOI, the Resident Engineer
shall also notify the following agencies of the • A written description of the
PHOI: arrangements which have been made for
the maintenance and reimbursement of
• Sanitary Drainage Network Section ongoing costs for vehicles supplied by
the Contractor to the Government for its
• Agriculture Section use during the project’s maintenance
period.
• Etisalat
6. Final Payment Certificates. The Final
• W.E.A. The Director, Transmission Payment Certificate will normally be
processed upon completion of all works,
• W.E.A. The Director, Distribution
administrative items, the agreement of final
quantities, and the settlement of all disputes.
• Other agencies as designated by the
Engineer or the Department. 7. The Preliminary Handing Over Inspection.
Members of the MPC, the Engineer, and the
5. Required Documents from the Contractor.
Contractor meet at the designated time to
Concurrent with the letter recommending the
conduct the PHOI. Prior to the inspection,
Government schedule the PHOI, the Resident
the Resident Engineer shall prepare the
Engineer shall also direct the Contractor to
Minutes of Inspection of the Works which
submit, no later than ten days after the
should also include the Attendee List.
PHOI, the below listed documents.
8. Minutes of Inspection. A field inspection of
• A statement that all subcontractor and
the project is made and, if accepted by the
supplier accounts have been settled and
MPC, signatures are obtained from all
no outstanding accounts relative to the
attendees. If the Works have been
Contract exist, including any third party
satisfactorily completed, a date is established
claims.
for the Preliminary Handing Over, which
• An inventory, including storage location, then becomes the project's Completion Date
of all spare items and/or surplus material and is so recorded in the Minutes of
which are the property of the Inspection. The Minutes of Inspection are
Government. then forwarded to the Chief of Road Section
establishing the date of Preliminary Handing
• Certification of the receipt of salvable Over and the start of the Maintenance
material which has been delivered to Period.
other Government agencies, i.e., W.E.A.
9. MPC Minutes of Preliminary Handing Over.
This must also include the W.E.A.
A copy of the MPC's Minutes of Preliminary
Materials Balancing Statement.
Handing Over is obtained from the
• Delivery receipts for equipment supplied Municipality which confirms the Preliminary
to the Government in conformance with Handing Over Date of the project.
the Contract Documents.
1000-4
CONSTRUCTION SUPERVISION MANUAL Section 1000
10. As-Built Drawings. The Engineer is • Has the advance payment recovery been
responsible for preparation of the As-Built correctly calculated and at what point are the
Drawings. These drawing must be completed retained amounts recommended to be
before the preliminary handing over, as the released?
various agencies require the as-built
drawings prior to certifying the completion • Have the As-Built Drawings been reviewed,
of their respective works. approved, and signed by the Resident
Engineer prior to the specified number of
11. Final Accounting. The Resident Engineer print's being produced?
must submit all of the project's final
documents to the Chief of Road Section for • Has the Contractor furnished the name,
use in preparing the Final Accounting. The address, fax, and/or telephone number of the
minimum documents to be submitted are: representative to contact during the project's
Maintenance Period?
• Final Payment Certificate
1004.06 DISPOSITION OF DOCUMENTS
• Final BOQ Item Tabulation UPON PRELIMINARY
• Financial Affairs Report HANDING OVER
The production of the Financial Affairs 1. Project Files. The Site office records shall
Report shall utilize data furnished by the be packed in clearly numbered containers
Resident Engineer. and an index of the files giving file numbers,
12. Certificate of Preliminary Handing Over. A descriptions, and dates shall be prepared. A
copy of the Certificate of Preliminary copy of the index shall be furnished together
Handing Over must be issued to the with the storage location of the files.
Contractor for his records.
When activity on the project has ceased, all
13. Resident Engineer's Inventory. Prior to the files relating to the project will be
PHOI, the Resident Engineer's staff shall consolidated.
inventory, catalog, and box the project
The Document Control files contain copies
records in accordance with the Close-out
of the Agreement between the Government
Checklist and the Disposition of Documents
and the Contractor and all subsequent
in sections that follow.
actions by the Government which alter the
1004.05 CLOSE-OUT CHECKLIST FOR time or financial aspects of the project.
USE PRIOR TO PROCESSING
During the consolidation of the permanent
THE FINAL PAYMENT
records, all duplication shall be eliminated.
CERTIFICATE
The storage of unique documents in personal
files will not be permitted.
• Are the Site office files complete and has
duplication been eliminated? 2. As-Built Drawings. As-Built Drawings shall
be prepared by the Engineer as further
• Have the specified number of copies of described in Section 1005.
guarantees, warranties, certificates, and
service manuals been received and then 3. Final Quantity Computations and Completed
forwarded to and receipted by the correct Field Survey Books. The Final Quantity
individuals? Computations and completed field survey
books are not duplicated and should be
• Has the compilation of “Materials Furnished stored in a fire-proof location.
by Others and Incorporated into the Works"
been completed?
1000-5
CONSTRUCTION SUPERVISION MANUAL Section 1000
1000-6
CONSTRUCTION SUPERVISION MANUAL Section 1000
drawings as required to clearly indicate as-built center lines including their positions within
conditions. The Engineer will also obtain the the service reservation.
necessary computer files from the Cotnractor and
other Consultants, if necessary, for preparation • Details of all newly installed ducts,
of the CADD based record drawings. contingency ducts, and other permanent
Works with sufficient dimensions to locate
During the course of the work, the Contractor these with respect to the building lines, road
shall have the right to call for record drawings, center lines, and their positions within the
mylar and digital, at any time so that he may service reservation.
check and update them for accuracy and
completeness. The Contractor should be • Plan details of all existing and new
provided a minimum of two prints of each record protection works installed by the Contractor
drawing for this purpose. to existing utility lines and all protection
works installed for the new utility lines with
All reproducibles of record drawings so prepared sufficient dimensions to locate these.
shall be dated and signed by the Engineer and
countersigned by the Contractor’s • Type and size of the utility lines, existing
Representative. Each record drawing shall be a and installed.
clear and legible reproducible on 3 mil polyester
• Sufficient cross-sectional details to show the
film or similar material. Each drawing set will
depth of the utility lines and details of the
be bound.
protection work installed to both the existing
and newly laid utility lines.
1005.02 RECORD DRAWINGS FOR
UTILITIES • The locations of existing utilities in unaltered
positions that were determined by manual
The Engineer will produce accurate record excavation in accordance with Clause
drawings of utility Works immediately upon 205.04, Manual Excavation, of the Standard
completion of the work covered by one work area Specifications.
as described below. These record drawings shall
be similar in form to the Contract Drawings. One During the course of the work, the Contractor
work area shall comprise the extent of work shall supply to the Engineer accurate working
described in each Contract Drawing as included drawings in stages for a particular section of the
in the Contract Documents and as directed by the utility line installed. Within five days of
Engineer. receiving the written directives from the
Engineer, the Contractor shall immediately
The record drawings shall generally show the produce such working drawings as required by
following: the Engineer, complying with the above details,
and supply to the Engineer sufficient quantities
• The plot boundaries and the plan details of of reproducibles for the Department and each
existing development within these areas. utility agency. In addition, after approval by the
Engineer and as part of the Contractor’s normal
• All existing utilities and ducts which are notice of intent procedures and/or when directed
permanently left in their locations with by the Engineer, the Contractor shall submit to
sufficient plan dimensions to locate these. Town Planning Department a minimum of one
full size transparency and one full size print of
• Location and details of all temporary all utilities working drawings, on a stage by
construction such as utility supports, etc., stage basis during the course of work. The
which are permanently left in place. transmittal cover letter and record of transmittals
to Town Planning Department shall be in a
• Details of all newly installed utilities with
format approved by the Engineer. These
adequate dimensions to locate these with
transmittals shall be made on a regular basis,
respect to the building lines and/or road
1000-7
CONSTRUCTION SUPERVISION MANUAL Section 1000
with copies of all transmittal letters copied to the crossing out the original design details which
Engineer. have been changed. Other details may be
drawn on the original Contract Drawings as
1005.03 FINAL COMPILATION AND required and shall be labeled, "AS-BUILT
SUBMITTAL OF RECORD DETAILS," in order to differentiate them
DRAWINGS from original design details.
1000-8
CONSTRUCTION SUPERVISION MANUAL Section 1000
same size as described above. Other the plans if not already provided in the
supplementary drawings shall bear the Contract Drawings.
designer’s title block, with the Drawing No.
block left blank. (c) CCTV System. All pull boxes shall be
numbered on the drawings and tabulated
Each Record Drawing shall incorporate the on separate sheets using the following
below listed information in a separate block format:
of 80mm X 160mm size, preferably located
in the lower right hand corner of each sheet: Pull Box Station/ Reference Pull Box
Number Offset Line Type
Record Drawing No.
Contractor ( ) (d) Roadway Lighting. Each sheet shall
Date: include an identification legend which is
identical to that shown on the Contract
Consultant ( ) Drawings for the roadway lighting poles,
Date: their related appurtenances, and circuits.
If not already provided in the Contract
Municipality Drawings, the poles, control cabinets,
Date: and service turrets shall be assigned
numbers. Roadway lights which have
The supplementary tabulation sheets may been installed by others within the
show the information described above, project limits shall also be shown and
within the designer’s title block in lieu of the shall be so described.
Amendment Description block.
(e) Utilities. Using either the standard
The Record Drawings shall be consecutively legend shown on the Contract Drawings
numbered from No. 001 (the new List of or one preferred by the utility
Drawings) to the final sheet in the set. departments and agencies, the utility
record drawings shall be prepared on
All Record Drawings, except those marked
common as-built base plans and must
"REDRAWN", "NOT USED", or
include the information listed below.
"TENDER DRAWING - NO
The legend shall appear on each as-built
CORRECTIONS," shall be stamped "AS-
utility drawing. All utility works
BUILT" in bold letters within the title block.
constructed by others as well as those in
2. Information on Drawings. The project's existence at the time of the project’s
geometry shall be shown as accurately as tendering, which were not removed, shall
possible and as constructed on site with also be shown and described
particular emphasis on the following: accordingly.
(a) General Plans. All bench marks and • Geometry of the roads and other
other survey monuments shall be shown improvements.
along with a clear description of their
locations. • Plot boundaries and plot numbers.
(b) Storm Water Drainage System. All • Service reservation widths and
usable bench marks, pipe sizes, lengths, distribution as well as their
direction of flow, and levels shall be centerline stationing and offsets or
shown. Each sheet shall include an ties to permanent structures.
identification legend which is identical to
that shown on the Contract Drawings as • Stationing at street intersections and
well as a small-scale location plan. A along the roadway centerlines.
Drainage Schedule should supplement
1000-9
CONSTRUCTION SUPERVISION MANUAL Section 1000
• Bench Marks and other survey drawn on a 3-mil thick mylar that is the
monuments with descriptions. same size as the Contract Drawings.
The tabulation shall describe all usable
• Sector numbers and street names. ducts located within the project’s limits,
regardless of their being in existence at
• Utility name, the type, number of the time of tendering or constructed
ducts, size and location within the during the project.
service reservation, the type of
protective works, and all pertinent (f) Service Reservations. Separate service
utility structures. reservation plans, without the utilities,
shall be provided at a scale of 1:1250.
• Small scale key map. The service reservations shall be fully
described as to location, width, and
Separate Record Drawings shall be distribution.
prepared for each utility and, wherever
feasible, shall be correlated with the (g) Profiles and Cross Sections. In addition
Contract Drawings. Record Drawings to showing the as-built elevations, cross
for utilities which have been combined sections included with the Contract
on the Contract Drawings shall be Drawings shall be revised to show the
prepared on separate Record Drawings existing ground elevations as surveyed
to clarify the as-built conditions by the Contractor prior to the start of
construction. Unless needed to clarify a
When the Contract Drawings are used particular as-built condition, cross
for the base plans, the as-built data is to sections which are additional to those in
be superimposed on the plans using the the Contract Documents are not
as-built symbols with no erasure of the required.
original lines. Pertinent unbuilt
structures and/or unverified existing 3. The Review and Approval of Record
utilities shall be neatly crossed out and Drawings. Proof copies of each Record
an explanatory label added. Notes or Drawing shall be transmitted to the
labels on the original Contract Drawings Contractor for review and concurrence.
which are no longer relevant shall also Each waterworks Record Drawing will then
be neatly crossed out but not deleted. be reviewed and approved by the W.E.A.
Consultant or Representative. Electrical
Record Drawings which illustrate the as- works Record Drawings require prior
built water works must include both the approval of W.E.A. Irrigation Record
standard title blocks and a title block for Drawings require prior approval of the
the W.E.A. Consultant. The W.E.A. Agriculture Section. Telephone works
Consultant's title block shall be 56mm x Record Drawings require approval of
150mm in size, preferably located in the Etisalat.
lower left hand corner of each sheet.
Similarly, Record Drawings for other 4. Distribution. After approval of all Record
utilities, where other specialist Drawings by the Utility Agencies and prior
Consultants/Departments are involved, to the Contract completion date, the Engineer
shall also include both standard title will further distribute Record Drawing sets
blocks and the title block of the as described below.
designated Consultant and/or
Department. (a) For the Department. One (1) complete
set of Record Drawings, full size
Record Drawings for each type of utility reproducibles, and/or a compact disk,
shall be supplemented by a sheet (or two (2) complete sets of Record
sheets) entitled, "TABULATION OF Drawings, full size blue or black line
UTILITY DUCTS," which shall be prints, and one 3.5" computer disk in
1000-10
CONSTRUCTION SUPERVISION MANUAL Section 1000
CADD format for record purposes. In (f) For the Utility Agencies. One (1) full
addition to as-built drawing files, a file size reproducible and one (1) full size
containing the entire project shall be blue or black line print of each selected
archived. The CADD files shall be in sheet that is pertinent to the function of
the project true coordinates and the following agencies; and a 3.5"
containing all works related to the computer disk as described above:
project in a complete form. The CADD
files shall include, but not by way of • Sanitary Drainage Network Section.
limitation, roadway layout; all utility
works, including water, electrical, and • Agriculture Section.
telephone; pavement marking; roadway
signs and traffic signals. Each roadway • WEA Electrical.
feature shall be included in one or more
• WEA Water (Note: Waterworks
layers of the file. Each layer shall not be
specifications may require that
used for more than one feature. If
additional copies be provided.)
necessary, this information can be
included in several files with each file • Etisalat.
including the complete works relating to
one or more roadway aspect. All files (g) For Other Requirements. Five (5)
shall have a common coordinate system. complete sets of Record Drawings, of
half size (A3 size), black line, bound
(b) For the Engineer and the Contractor. prints on quality bond paper.
One (1) complete set of Record
Drawings, full size reproducibles, and a Two (2) complete microfilm sets of
3.5" computer disk as described above. Record Drawings mounted on computer
index cards properly identified with
(c) For Town Planning Department. One (1) labels. Each microfilm set shall include
set of full size reproducibles and one (1) suitable storage containers (with
set of full size blue or black line prints of identification labels).
the Geometric Layout, Service
Reservation Plans, and surface finish General plans and overall service
plans; and a 3.5" computer disk as reservation plans and utility plans
described above. including plans for Storm Water
Drainage works, all full size Record
(d) For Town Planning Department. One (1) Drawings which shall be 1:1250 scale or
set of full size reproducibles and one (1) as needed.
set of full size blue or black line prints of
Record Drawings for utilities, and a Geometric layout plans and surface
3.5" computer disk as described above. finish plans, both full size Record
Drawings which shall be 1:500 scale,
(e) For the Department of Planning. One (1) unless otherwise specified or as needed.
complete set of full size blue or black
line prints and a 3.5" computer disk as Cross-sections, structural, and other
described above. specific detail Record Drawings shall be
of the scale as indicated in the
specifications or as needed.
1000-11
CONSTRUCTION SUPERVISION MANUAL Appendix
APPENDIX
CONSTRUCTION REPORT FORMS
A-0
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
__________________
Resident Engineer
A-1
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
Date:
I.R. No.
Weather Temperature
High Low
The above described work was incorporated into this project and was inspected by:
Inspector’s Signature
A-2
ABU DHABI MUNICIPALITY
ROAD SECTION
Consultant:
Contract No. JMS No.
Contractor: Date:
A-3
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
COMPUTATION SHEET
A-4
A-5
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
A-6
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
TOTALS
A-7
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
A-8
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
QUANTITY BOOK
A-9
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
Quantity
Surveyor
(Consultant)
Project Manager
(Contractor)
Resident
Engineer
(Consultant)
A-10
ABU DHABI MUNICIPALITY
ROAD SECTION
B. O. Q. RECAPITULATION
Project: Contractor:
Date:
Page ……….. of ……….. Latest Update:
A-11
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
B.O.Q No.
Description:
Page of
Location:
A-12
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
Mathematics
Previous Payment
Format
A-13
ABU DHABI MUNICIPALITY
ROAD SECTION
A-14
ABU DHABI MUNICIPALITY
ROAD SECTION
SUB - TOTAL
A-15
ABU DHABI MUNICIPALITY
ROAD SECTION
SUB - TOTAL
A-16
ABU DHABI MUNICIPALITY
ROAD SECTION
A-17
ABU DHABI MUNICIPALITY
ROAD SECTION
SM - 23 Consultant: …………………………….
Contract No. ………...
No.
REQUEST FOR TESTING OF CONSTRUCTION
A-18
ABU DHABI MUNICIPALITY
ROAD SECTION
Subject
Location
Works to be Performed
All work shall be performed in accordance with the applicable provisions of the Standard and
Particular Specifications and with the terms of Article (8), Paragraph 12, of the Special
Conditions of Contract
Dist:
Original – Contractor
Yellow – Q.S
Blue – Retained
A-19
ABU DHABI MUNICIPALITY
ROAD SECTION
DAY WORKS
A-20
ABU DHABI MUNICIPALITY
ROAD SECTION
Project: Contractor:
DAYWORK SUMMARY
FOR AUTHORIZED WORK
JMS No.
SUB-TOTAL
PROFIT &
OVERHEAD
TOTAL
GRAND TOTAL
A-21
ABU DHABI MUNICIPALITY
ROAD SECTION
SCHEDULE No. 1
Bill No. 18 Dayworks: ...……………………...
Valuation:
Period Ending:
SUB-TOTAL
Percentage to be added to sub-total
for profit and overhead ………..
Total for Schedule No. 1
Carry to Summary of Dayworks
Resident Engineer
A-22
ABU DHABI MUNICIPALITY
ROAD SECTION
SCHEDULE No. 2
Bill No. 18 Dayworks: …………………….
Valuation:
Period Ending:
Sub-Total
Percentage to be added to sub-total
for profit and overhead ………..
Total for Schedule No. 2
Carry to Summary of Dayworks
Resident Engineer
A-23
ABU DHABI MUNICIPALITY
ROAD SECTION
SCHEDULE No. 3
Bill No. 18 Dayworks: ……………..……………
Valuation
Period Ending
Sub-Total
Percentage to be added to sub-total for
profit and overhead ……….……...
Total for Schedule No. 3
Carry to Summary of Dayworks
Resident Engineer
A-24
ABU DHABI MUNICIPALITY
ROAD SECTION
Contractor Time AM / PM
Description of Accident
Primary Cause
P
Name of Injured Employee Age
E Occupation Nationality
R Nature of Injury
S
O
C N First Aid Doctor Visit Hospital Fatality
N
O E
Type of Equipment
N L
T
R &
/
A o
C r Extent of Damage
T
O E
Q
R U
S I
P
M
E
N
T
A-25
P Name of Injured Party Age
E Sex Nationality
T R Address
H S
O Nature of Injuries
I N
R &
D / Property Description and Location
O Name of Property Owner
R
Address
P
P Nature of & Extent of Damages
A R Estimate of Damaged Property
R O
P
T E
Y R
T
Y
What Corrective Action, if Necessary, has been taken by the Contractor to Prevent Recurrence?
A-26
ABU DHABI MUNICIPALITY
ROAD SECTION
Abandoned in
Service
INTERNAL USE ONLY
Describe Incident in Detail Including any Resulting Physical Injury or Property Damage
……………………………….
Resident Engineer
A-27
ABU DHABI MUNICIPALITY
ROAD SECTION
Date:
Detour Location Description Lighting Barricades/Signs Flashing Lights Overall Cleanliness Action
No.
A-28
ABU DHABI MUNICIPALITY
ROAD SECTION
LETTER OF TRANSMITTAL
Under Separate Cover/the following items for your review & comments
Remarks Signed:
A-29
ABU DHABI MUNICIPALITY
ROAD SECTION
APPROVAL OF SUB-CONTRACTORS
Signature: Signature:
Contractor Date Sub-Contractor Date
TOTAL
Percent of total contract approved on this form
Percent of contract previously approved
Percent of total contract approved
Comments: Reasons for non approval
Approved
Stamp Stamp
A-30
ABU DHABI MUNICIPALITY
ROAD SECTION
SITE INSTRUCTION
No.
Date
Time
Subject:
Location:
Instruction:
Received by
FOR CONTRACTOR
RESIDENT ENGINEER
A-31
ABU DHABI MUNICIPALITY
ROAD SECTION
Sheet No.
Engr.’s Contractor’s DESCRIPTION Sub- Date ASSIGNED Date Disposition FORWARDED Remarks
Dwg. Dwg. No. mittal Received Returned
To/Off Date To Date
No. No.
A-32