Commissioning Check List M

Fan /Compressor
TISHREEN IRN688 QM MAX01AN011 C02
Kraftwerk/Power Plant Block/Unit KW-Nr./Plant Code UA Inhaltskennzeichen/Contents Code Zähl-Nr./Reg. No.

System: Control Fluid System

Component: Fan Control Fluid Cooler 1


Fan Control Fluid Cooler
Control Fluid System Page: 1 of 1 Appendices:

No. Activity Remarks/Confirmation

1 Startup preparations: the following preconditions must be fulfilled prior to


the initial startup.
Copyright © Siemens AG 2004 - All Rights Reserved

1.1 Inspection of the component within scope of system check.


1.2 Check of alignment (erection record), including parallelity and zero-offset of
belt disks, belt tension.**
1.3 Cleaning of air intake duct completed, filters installed.
1.4 Check of all relevant protection and permissive signals
1.5 Commissioning of the oil system** n.a.
oil flushing start , end n.a.
oil filling with oil type n.a.
1.6 Rotate impeller manually, check for freedom of movement
1.7 Check of direction of rotation of the drive
1.8 Install emergency stop button for drives t 6.6 kV n.a.
Uncoupled run of drive only**
1.9 Fan Control
Manually-operated valves /dampers Fluid Cooler
set to correct positions as per the
operation manual (eg.mechanical seals, cooling water and oil systems)**
1.10 Pre-commissioning of auxiliary equipment

2 Initial start up: the following data shall be measaured: ***


Handhabung: RESTRIKTIV / Distribution: RESTRICTED

2.1 Operating current A n.a.


2.2 Speed / speed range 1/s n.a.
2.3 Coastdown time s n.a.
2.4 Vibration behavior (attachment)** n.a.
2.5 Winding /bearing / oil temperatures (attachment)** n.a.
2.6 Characteristic curve, several operating points (attachment)** n.a.
2.7 Check switching points of fan /compressor** n.a.

3 Results: the aforementioned checks have yielded


The component is released for operation.
n.a. not applicable ** delete if not applicable *** see checklist E06.1 or similar in terms of electrical commissioning according electrical consumer list

Confirmed by: Signature: _______________________* Date: ____-__-__

Name: _______________________PRINTED

Company Name: _______________________PRINTED


* in case of multiple responsibility please add remark and countersignature

Siemens AG . Power Generation (PG) Commissioning, Operation


IBSC02_E.DOT Revision: -/Nov 01

Page 334 of 408