Professional Documents
Culture Documents
Dextra - Groutec Datasheet
Dextra - Groutec Datasheet
DM-PDS010-GROUTEC–Rev-02-March 2019
www.dextragroup.com
OVERVIEW
03 Introduction
04
Coupler dimensions
05 Packing
18
Vertical applications – by injection
Vertical applications – by gravity
20
Horizontal applications – by injection
CONTENT
21 Grout consumption
22 Grouting process
24
Quality assurances
Approvals
Disclaimer
25 TROUBLESHOOTING
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 3 / 28
Introduction
Groutec is a mechanical splicing system with one threaded end specially
designed for the connection of pre-cast concrete elements. Metric ribbed
reinforcing bars of grades up to 600 MPa and ASTM deformed reinforcing
bars of grades up to 80 ksi can be spliced with Groutec.
Groutec couplers have been designed to work
Splicing is usually done in two steps: the Groutec coupler is first screwed with grouts commonly-available on the market
onto the reinforcement prepared at the precast factory, installed flush with place. Grouts must be non-shrink types, with
the formwork, after which the element is concreted. a minimum compressive strength of 65 MPa.
www.dextragroup.com
Coupler dimensions
Groutec is available in two versions: Groutec L
« Large tolerance »
• Groutec L, which allow for larger misalignment tolerances thanks to a wide cavity.
• Groutec S, which accomodate slim panels and narrow columns thanks a longer more compact design.
For both L and S models and all rebar diameters, the inlet & outlet holes are designed to fit with PE pipes
(PE80/PN12.5) as per ISO 4427-2 and BS EN12201-2:2003 standards.
The threaded bar is used a reference for the rebar diameter. Groutec S
» Slim outside diameter «
In case of Transition Splicing, please refer to the table in rebar cutting section to verify the model in use.
14 - FPPC1215177 52 25 155 39
C - #5 FPPC1216207 52 25 155 39
16 - FPPC1617177 57 30 184 44
18 - FPPC1619257 57 30 184 44
19 #6 FPPC2020257 61 34 204 48
20 - FPPC2021207 61 34 204 48
22 - Rolltec FPPC2024307 61 34 204 25 20 48
24 #8 FPPC2525257 67 40 240 55
D
25 - FPPC2526257 67 40 240 55
26 FPPC2527307 67 40 240 55
28 #9 FPPC3229307 80 50 310 68
32 #10 FPPC3233307 80 50 310 68
B
F 36 - FPPC4037307 95 60 377 83
A 40 - FPPC4041307 95 60 377 83
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 5 / 28
Packing
Groutec products are packed in wooden crates that can be lifted by a forklift. All products must
be stored under a roof and protected from the elements.
Please ensure that order quantities are a multiple of the packaging quantities stated in the table.
Column connection
40 - 125 6.7 838 903
#3 Outlet plug
Inlet pipe (by others)
#2 Inlet plug
Optional items
Standard scope
Item No. Description available upon
of supply
request
1 Groutec coupler x
2 Inlet plug x x
3 Outlet plug x x
10 Sealing disc x
Groutec L
25 #8 GACC2090033 GACC2090014 GACC0990006
#1
28 #9 GACC2090034 GACC2090015 GACC0990001
Groutec
coupler
32 #10 GACC2090034 GACC2090015 GACC0990001
#3 Outlet plug
Inlet pipe (by others) 19 GACC2090029 GACC2090052 GACC0990020
#6
Groutec S
#4 Dust
#2 Inlet plug protection 20 GACC2090029 GACC2090052 GACC0990020
#5 Coupler cap
Protection 22 #7 GACC2090029 GACC2090052 GACC0990020
Cap
#11 Formwork positioner 24,25,26 #8 GACC2090030 GACC2090053 GACC0990021
(screw type)
#1 Groutec coupler
28 #9 GACC2090033 GACC2090054 GACC0990006
#10 Sealing
40 - GACC2090034 GACC2090055 GACC0990001
disc
Protruding length (P) Embedment length (E) + Sealing mortar height (M)
Rebar length after threading Element height + Sealing mortar height (M) + E – L + Thread engagement (T)
Note: The above calculations assume that the sealing mortar height (M) is the same between each concrete element.
Transition splicing
This is the case when the bar inserted in the cavity is of a diameter different from the one on the threaded side.
Connection of precast members reinforced with bars of different diameters can be made in two options :
See Table of column G for Injection grouting See Table of column H for Gravity grouting
Element height
T
Embedment length (E2)
Protruding length (P)
Coupler #2
M
Protruding length (P)
T
Body length (L)
Coupler #1
Protruding length (P) Embedment length of coupler #1 (E1) + Sealing mortar height (M)
Protruding length (P) Embedment length of coupler #2 (E2) + Sealing mortar height (M)
Rebar length after threading Element height + Sealing Mortar Length (M) + E2 - L+ Thread engagement coupler #1 (T)
Note: The above calculations assume that the sealing mortar height (M) is the same between each concrete element.
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 11 / 28
12 / 28 | Product Datasheet | DM-PDS010 Groutec-Rev.02- March 2019
Transition splicing
Smaller bar threaded / Injection grouting.
Rebar diameter
Type of Smaller bar Product L E min E max T
Model Larger bar (grouted)
thread (threaded) Code (mm) (mm) (mm) (mm)
mm (US) mm (US)
14,16,18,20 #5, #6 12 #4 FPPC1214201 182 143 155 14
18,20 - 16 #5 FPPC1620251 182 145 155 20
22,25 #7,#8 20 #6 FPPC2024301 195 150 162 24
Bartec
28,32 #9,#10 25 #8 FPPC2530351 220 165 181 30
Fortec
32,36,40 #10,#11 28 #9 FPPC2833351 290 225 243 33
36,40 - 32 - FPPC3236401 290 225 243 36
Groutec L
Table of column G
Rebar diameter
T E
Type of Larger bar Product L E min T
Model Smaller bar (threaded) max
thread (grouted) Code (mm) (mm) (mm)
(mm)
mm (US) mm (US)
Bartec
25 #8 22 #7 FPPC2027307 204 150 170 27
Fortec
28 #9 25 #8 FPPC2530357 240 150 200 30
32,36 #10 28 #9 FPPC3233357 310 230 260 33
36 - 32 - FPPC3236407 310 230 260 36
40 - 36 - FPPC4042457 377 280 320 42
Groutec S
Table of column G
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 13 / 28
Transition splicing
Smaller bar grouted / Gravity grouting.
Rebar diameter
Type of Larger bar Smaller bar Product L E min E max T
Model (threaded) (grouted)
thread Code (mm) (mm) (mm) (mm)
mm (US) mm (US)
12 #4 10 #3 FPPC1214201 182 143 155 14
16 #5 12,14 #4 FPPC1620251 182 145 155 20
20 #6 16,18 #4,#5 FPPC2024301 195 150 162 24
Bartec
25 #8 20,22 #6,#7 FPPC2530351 220 165 181 30
Fortec
28 #9 20,25 #7,#8 FPPC2833351 290 225 243 33
32 - 25,28 - FPPC3236401 290 225 243 36
40 - 25, 28,32,36 - FPPC4045451 340 270 286 45
Groutec L
Table of column H
Rebar diameter
Larger bar E
Type of Smaller bar (grouted) Product L E min T
Model (threaded) max
thread Code (mm) (mm) (mm)
(mm)
mm (US) mm (US)
T
12 #4 10 #3 FPPC1214207 155 115 130 14
14 - 10,12 - FPPC1216207 155 115 130 16
16 #5 12,14 #4 FPPC1620257 184 140 155 20
18 - 12,14,16 - FPPC1622257 184 140 155 22
20 #6 16,18 #4,#5 FPPC2024307 204 150 170 24
Bartec
22 #7 16,18,20 #5,#6 FPPC2027307 204 150 170 27
Fortec
25 #8 20,22 #6,#7 FPPC2530357 240 150 200 30
28 #9 20,25 #7,#8 FPPC3233357 310 230 260 33
32 - 25,28 - FPPC3236407 310 230 260 36
36 - 32 - FPPC4042457 377 280 320 42
Groutec S
Table of column H
14 / 28 | Product Datasheet | DM-PDS010 Groutec-Rev.02- March 2019
#2 Inlet plug
A. Connect the coupler to the bar B1. If no positioner is used C. Install the inlet and outlet pipes
1. If no positioner is used, make sure that the
1. Check from the coupler marking that the Dust Protection Cap (#4) is present and If the couplers are intended to be filled by gravity
pouring, skip this part.
coupler (#1) corresponds to the bar size. tight. Position coupler flush with formwork.
2. Remove the Thread Protection Cap from 2. Rotate coupler so that holes face the right
the threaded bar (if any) and the Coupler direction. Tightly lock coupler together with
1. For each coupler, make sure that the inlet
and outlet pipes have the proper length to
Protection Cap (#5, if any). the reinforcement by the use of wires.
reach the internal face of the formwork at
3. Inspect the threads of both the bar end
the desired location.
and the coupler (#1). Clean any rust or B2. If formwork can be drilled
dirt with a wire brush. Make sure that the 3. Install the screw type positioner (#11) 2. Remove the plugs (#2, #3) and insert
the pipes into the coupler holes. A mallet
provider of bars has made their threads in through the formwork at the correct location.
may be used to facilitate insertion. At this
compliance with the ‘Type A’ tolerances Rotate coupler so that holes face the right
stage, it should not be possible to remove
from Dextra’s Bar-end preparation Quality direction.
the pipes by hand anymore.
Manual. 4. Then fit the coupler and bar onto the
4. Screw the coupler (#1) onto the threaded positionner (#11).
3. Check that there is no gap between the
pipes and their holes. Use any kind of
bar until until snug fit. Check with a 5. Finally tighten the positioner by the use of
sealant or glue to close any gap.
measure ruler that the depth of the coupler the locknut (#11) to firmly lock the assembly.
cavity is not less than the value Emin
4. Close the opposite end of both pipes with
inlet/outlet pipe plug (#6, #7) or adhesive
specified at pages 8 & 9. B3. If steel formwork is used
tape.
1. Lock the magnetic type positioner (#12)
inside the coupler (#1) first,
5. Check that the pipe plugs (#6, #7) are
tight enough so that they won’t fall off
2. Pre-position coupler and bar onto the
during handling.
formwork at the correct position, rotate
accordingly so that holes face the right
direction.
3. Tightly lock coupler together with the
reinforcement by the use of wires.
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 15 / 28
Formwork
INLET OUTLET
Formwork
INLET OUTLET
is intended for their grout injection, that they are tightly fixed so
that vibration won’t cause them to move, and that there is no gap
between them and the coupler that could allow cement paste to
penetrate into the coupler.
5. Check that the Dust Proteciton Cap (#5) (or the Groutec positioner,
#11 or #12) and the pipe plugs (#6, #7) are flush with the formwork,
and that they are tight enough to prevent cement paste penetrating
into the coupler.
6. Mark the location of all couplers (#1) and their inlet and outlet pipes
Positioner Drill Positioner Drill
on the external face of the formwork. Model Model
screw type diameter screw type diameter
7. Check the length of reinforcing bar that emerges from the formwork
on the opposite side (taking into account the thickness of the 12 #4 12 #4 7/16” or
9/16” or
formwork). Make sure it is within the minimum embedment length 14 - 11 mm
14 mm
16 #5
and maximum protrusion length specified on page 5. 16 #5
8. Pour the concrete, making sure not to displace any pipes.v 20 #6 18 -
E. Formwork removal & inspection 22 - 19 #6 9/16” or
S
Groutec L
20 14 mm
Groutec
Case where it is possible to proceed with grout Case where access is limited and grout injection
injection from any side of the precast element. must be performed from one side only.
Bar size R S Y
Model
mm US (mm) (mm) (mm)
12 #4 28 29 115
16 #5 28 29 115
20 #6 30 34.5 120
Groutec L
22 - 30 34.5 120
25 #8 30 28.5 145
28 #9 38 40 195
32 #10 38 40 195
36 - 45 40.5 238
40 - 45 40.5 238
12 #4 19 27 95
14 - 19 27 95
OUT
16 #5 22 32 115
18 - 22 32 115
19 #6 24 33 129
Y
20 24 33 129
Groutec S
22 #7 24 33 129
24 - 27 40 152
25 #8 27 40 152
IN
S
26 - 27 40 152
28 #9 34 40 212
R Pipe
length 32 #10 34 40 212
W 36 - 41 40 272
40 - 41 40 272
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 17 / 28
In case the formwork can be drilled to let the pipes go through, letting them protrude
at least 30cm out of the formwork may permit to pull them out after the concrete has
Formwork width
set. The grout injection can then be done through the holes left in the concrete, but
larger pipe plugs are then necessary.
In case flexible hoses are preferred, cut the PVC pipes short so that they fit with the flexible hose without being loose. Select hoses that can be bent
without any dent, like polyester- or steel wire-reinforced hoses.
18 / 28 | Product Datasheet | DM-PDS010 Groutec-Rev.02- March 2019
1. Compare the dimensions of the foundation with the drawings. Make 1. Select the panel to install and check that the protruding lengths of its
sure that any misalignment is within the tolerances allowed. bars are also within the range given at chapter 1.2.
2. Check that the protruding lengths of the rebars are within the range 2. Lift the panel and position it on top of the foundation.
given at chapter 1.2 of this document. 3. Check that the cavities inside the Groutec couplers are clean.
3. Clean the protruding bars of any cement or dirt. (Rust is no problem) Clean them with compressed air if necessary.
4. Make sure that the surface of the foundation is clean. Sweep out any 4. Prepare the bedding mortar and place the shim plates on the top of
dust and residues. the foundation as required.
5. Put the sealing discs over the top of the protruding rebars and 5. Lower the panel down and check its verticality with a spirit level.
push them down by 2.5 to 5 cm (1 to 2 inches) from the bar ends.
6. Once the bedding mortar has hardened, inject cement grout into the
Groutec couplers.
6. Ensure that the sealing discs are not in contact with the foundation
before installation.
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 19 / 28
1. Compare the dimensions of the foundation with the drawings. Make sure that any
misalignment is within the tolerances allowed.
2. Remove the protection caps from the Groutec couplers and check that the coupler cavities
are clean. (Rust is no problem) Clean them with compressed air if necessary.
3. Make sure that the surface of the foundation is clean. Sweep out any dust and residues.
1. Select the top element to install and check that the protruding lengths of its bars are within
the range given at chapter 1.2. Shim Formwork
Sealing Mortar
Bedding Mortar
20 / 28 | Product Datasheet | DM-PDS010 Groutec-Rev.02- March 2019
1. Compare the dimensions of the precast elements to the drawings. 1. Lift the second concrete element and position it in front of the first
Make sure that any misalignment is within the tolerances allowed. element.
2. Check that the protruding lengths of the rebars are within the range 2. Move the sealing discs completely against the mouth of the Groutec
given at chapter 1.2 of this document. couplers.
3. Check that the cavities inside the Groutec couplers are clean. 3. Push the second element to its final position against the first element.
(Rust is no problem) Clean them with compressed air if necessary. 4. Check the level and alignment of both elements.
4. Make sure that the surfaces of both elements are clean. Wipe out 5. Prepare the formwork around the grouting area.
any dust and residues. 6. Put bedding mortar to seal the gap between the two elements.
7. Once the bedding mortar has hardened, inject cement grout into the
Groutec couplers.
C
B. Install the sealing discs
Pouring Area
1. Put the sealing discs over the top of the protruding rebars and push
them down by 1”- 2” from the bar ends.
2. Make sure that the sealing discs are not in contact with the concrete
face.
Transition splice
A
Formwork
Sealing Disc
D Mortar
Sealing Disc
Remove Formwork
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 21 / 28
4. Grout consumption
36 - 1,275 8
40 - 1,275 8
12 #4 100 130
14 - 100 130
16 #5 160 86
18 - 160 86
19 #6 210 65
20 210 65
Groutec S
22 #7 210 65
24 330 37
25 #8 330 37
26 330 37
28 #9 630 19
32 #10 630 19
36 - 1,200 11
40 - 1,200 11
22 / 28 | Product Datasheet | DM-PDS010 Groutec-Rev.02- March 2019
5. Grouting process
A. Mixing B. Grouting
1. Make sure to strictly follow the work instructions provided by the 1. Remove all residues from inside the coupler by water or air. In case you
grout manufacturer in the product datasheet and printed on the use water ensure that the couplers are dry before you start grouting .
bag. Particularly, do not exceed the recommended water content.
Always start with the median value of water content specified by the
manufacturer.
2. Check the manufacturing date of grouts before use. Do not use bags
that are past their expiry date.
3. Do not use bags that have previously been opened, or are damaged,
unless they have been protected with a plastic stretch film to prevent
contamination with moisture.
4. Use mixers with a speed of not over 500 rpm to avoid the creation of
air bubbles inside the grout.
5. In parallel, prepare the cube specimens (around 6 - 12 at a time) and
record the details such as date of preparation, testing date, batch
no. of cement grout, water ratio, name or number of building, etc.
2. Inject the cement grout by pump through the bottom hole (Inlet).
3. If the cement grout flows out from the top hole (Outlet), the inside of
the coupler is completely filled.
4. Tightly close the top hole (Outlet) with a pipe plug. Then inject more
grout during approx. 3 seconds. After that remove the injection valve
and quickly close the bottom hole (Inlet).
C. Bracing
For enhanced performance higher than specified by the most common Codes, the recommended
grouts are :
Grade: MasterFlow 4800 Grade: Cemrok Easi Flow Grade: Mapei - SP Grade: SikaGrout 220
Quality Assurance
Groutec couplers is manufactured according to strict technical specifications and under a production process that has been certified to satisfy to the
ISO9001 and ASME NCA-3800 quality assurance standard.
Agency Certificate N°
Products described in this document are warranted to be free from manufacturing defects and to perform in accordance with the manufacturer’s
specifications providing that they are installed in accordance with our written instructions.
Approvals
Groutec mechanical splices has been approved by the most demanding international regulators:
IAPMO 312
ROMANIA Nr 003-01/102-2017
Disclaimer
As a result of our continuous thrive for technological improvement, Dextra reserves its right to modify the contents of this specification sheet at
any time without prior notice. In particular, various sources of raw materials may lead to variations in outside diameters. The information provided
on this document, and any outside information linked to, is for guidance only.
Dextra products shall be installed and used only as indicated in Dextra’s documentation and training materials. Aforementioned documents are
available at www.dextragroup.com and from your Dextra customer service representative. Improper installation, misuse, misapplication or other
failure to completely follow Dextra’s instructions and warnings may cause product malfunction, property damage, serious bodily injury and death.
Dextra cannot accept any liability in respect thereof.
| Product Datasheet | PDS DM-PDS 010-Groutec-Rev.02- March 2019 25 / 28
Troubleshooting
Topic Method Picture
1. Check and mark the position of the ports according to the drawings.
1/ Inlet and/or Outlet port(s) do not 2. Chip out the concrete at the marked positions to find the embedded
reach the surface. ports.
3. Blow out the ports with air compressors or water and confirm that there
is a clear passage from the inlet to outlet port.
1. Try to clear the Inlet port by inserting a steel rod into it.
2/ Due to dirt on the protruding rebar,
the sealing disc gets stuck, slides into
the coupler and reduces the gap of
inlet port.
2. Follow step 3 of item 1.
1. Try to clear the Inlet port by inserting a steel rod into it.
3/ The sealing disc was forgotten,
and the bedding mortar from the joint
clogs the Inlet port.
2. Follow step 3 of item 1.
Due to debris etc.: Insert a steel rod into the port and hammer it to clean
the port.
Due to plugs:
4/ Inlet and/or Outlet port(s) are
clogged.
1. Use a hooked rod to scrape plugs out of the ports.
5/ Leakage during pumping of grout 2. Clean the inside of coupler with water. (Preferably high pressure).
through the joint due to incomplete
grouting of the joint. 3. Confirm a clear passage by blowing air through the ports.
4. Re-grout.
Inspection Sheet
Dextra
Project Ambient °C
Location Dry Grout °C
Tempreture
Date of Grouting Mixing Water °C
Date of Inspection Mixed Grout °C
Brand
Report By Model
Grout Cement Batch No.
Approved By MFG Date
EXP Date
Type of thread
Actual thread diameter mm M________ x ________pitch
(measuring by vernier caliper)
DM-QA-FR-81 Rev02
Guangzhou
Paris
LosAngeles
Angeles
Hong Kong
Los
Dubai
Mumbai
Bangkok
Panama
São Paulo
www.dextragroup.com