Pending Engineering and Commissionning Activity for HPCL Visakh Refinery Modernization Project

Number of
#Sr No. List of Activity Task Owner Responsibility Dependency Remarks
days

ETAP Model ID ,Substation name and Modelling of


equipments MM, CT, PT and Relay for remaining 6 ETAP Rajkumar
substations
SLE and tag parameters should be checked for Source/
ETAP Rajkumar
Incomer & Load /Outgoing for remaining 6 substations 11
Select unit(MV/kV) for MM at Source/Incomer &
ETAP Rajkumar
Load/Outgoing for remaining 6 substations

Create composite network and fit to page for the remaining


ETAP Rajkumar
6 Substations
1 Engneering Activity Interconnectivity of remaining 6 sub stations with Complete
ETAP Vasu 4
ETAP Model (Meter ,CT ,PT , CB-ID ) Testing
1. ETAP has completed the FAT
for sub station N. 82 on 24th
Prepare tag address excel sheet as per the Kepware tag
Rajkumar/vasu Activity will start once Emerson - Nov 2020.
addressing path for Analog Signals & Digital Signals for ETAP 15
/Siddhanth SCADA system is ready
remaining 17 sub stations.
2. No Engineering Activity is
pending for sub station.
Addressing of Tags from excel sheet to SI Database for
Activity will start once Emerson -
Analog Signals (MW, MVAR, Amp,Volt & HZ) & Digital Signals ETAP Rajkumar/Siddhanth 35
SCADA system is ready
for remaining 17 sub stations.

Commissioning Activity will start once Emerson -


2 Console and Server Setup Setup as per the architecture ETAP Rajkumar /Vasu 2
Activity SCADA system is ready
LF,SC,RA,CA,RC and Motor Starting - application Testing
including troubleshooting ETAP Gnanasekar/Vasu 10

Load Flow Result Testing ETAP Gnanasekar/Vasu


3 Internal Testing Real Time communication testing
Gnanasekar/vasu
ETAP 5
/Rajkumar
Software Internal Testing ETAP Rajkumar/vasu
P to P testing ETAP+ Emerson/HPCL Rajkumar /Vasu 10 After SAT Document Approval