Key Measurable Quantities

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 2

Key Measurable Quantities

Contract Company Measurable Unit Measure Bill of Remeasure % Remarks


Quantities Quantities accuracy
01_Early Civils SBG Concrete m³ 19,403.00 10,758.00 100% PIPERACK FOUNDATIONS
2,043.00 100% FLARE FOUNDATIONS
11,393.00 100% TANK FOUNDATIONS
23,930.00 50% BUND WALLS

02_Buildings AGC Concrete m³


No quantities, all LUMP SUM
Steel Ton

02_Main Civils SBG Concrete m³ 29,674.82 30,542.77 85%


Remeasure is not yet complete
U/G Pipe LM 21,525.60 20,506.46 50%

03_Cooling Tower DSA Concrete m³


No quantities, all LUMP SUM
Equip. Ton

04_Cooling Area Civils DSA Concrete m³ 11,789.71 10,915.27 100%


Steel Ton 8,401.950 98.12 50% 100% on Substation 38, no measure on other
shelters

05_Utility Buildings AGC Concrete m³ 3,722.42 453.73 90% REMEASURE IS COMPLETE, Substation 30
837.05 90% REMEASURE IS COMPLETE, Substation 31
1,148.22 90% REMEASURE IS COMPLETE, RIB
Steel Ton 243.47 88.69 100% STRUCTURAL STEEL, Substation 30
153.31 100% STRUCTURAL STEEL, Substation 31

06_ME&I MMG
Structural Steel Steel Ton 3,654.97
Pipe Fab PIPE Dia Inch 30,623.00 122,357 meters of different sizes
Pipe Erection PIPE LM 127,414.00 122,357.00 of different sizes
**Test Packs PIPE Dia Inch/LM NO IDEA FOR THE TEST PACKS
Mechanical Erection Equip. Nr 274.00 no weight of Tonnage, only quantities of equipment
Electrical Cable LM 829,910.00 including Communication System Cables
Electrical Conduit LM 2,500.00
Electrical Ladder Rack & Tray LM 29,385.00
Electrical Grounding Cable LM 12,310.00
Electrical Electrical Hook-Up Nr 1,065.00
Instrument Cable LM 256,891.00
Instrument Conduit LM 31,000.00
Instrument Trunking LM 7,835.00
Instrument Piping Hook-Up Nr 1,139.00
**Loop Packs Loops EA 5,506.00 quantity of Instruments
Painting Paint m² 130,080.58 touch-up painting only
Insulation Insulation m² 40,193.93
Fireproofing Fireproofing m² 8,141.00 for steelworks only

07_Tankage ACBI Tanks & Vessel Nr 18.00 18.00

09_Flare GBA Steel Ton


No quantities, all LUMP SUM
Equip. Ton

09_PAR's BILFAL
Structural Steel Steel Ton 12,238.80 16,560.44 100%
Pipe Fab PIPE LM 115,387.00 48,500.90
Pipe Erection PIPE LM 38,102.00 48,500.90
Electrical Cable Ladder LM 2,791.00
Electrical Cable LM 10,745.00 Heat Tracing Cable
Instrumentation Trunking LM 12,798.00
Painting Paint m² 124,616.70 touch-up painting only
Insulation Insulation m² 39,805.40
Fireproofing Fireproofing m² not in BILFAL's scope
Modules PAR's EA 89.00 85.00 80% Remeasure is not yet complete

10_Off Plot Piping MMG


Civils Concrete m³ 873.13
Steel Steel Ton 432.38
Pipe Fab Pipe LM 47,325.77
Insulation Insulation LM 809.50
Painting Paint m² 149,322.04

STEEL 16,326.15 16,560.44 ton


PIPE 328,228.77 97,001.80 meter

502877897.xls Page 1 of 2 12/12/2020


3" 8,078.52 25,379.48
4" 22,421.42 70,439.13
6" 5,430.03 17,058.98
8" 7,568.47 23,777.11
10" 318.00 999.03
12" 208.22 654.14
14" 1,194.28 3,751.95
24" 2,311.63 7,262.22

149,322.04