05_Utility Buildings AGC Concrete m³ 3,722.42 453.73 90% REMEASURE IS COMPLETE, Substation 30
837.05 90% REMEASURE IS COMPLETE, Substation 31
1,148.22 90% REMEASURE IS COMPLETE, RIB
Steel Ton 243.47 88.69 100% STRUCTURAL STEEL, Substation 30
153.31 100% STRUCTURAL STEEL, Substation 31
06_ME&I MMG
Structural Steel Steel Ton 3,654.97
Pipe Fab PIPE Dia Inch 30,623.00 122,357 meters of different sizes
Pipe Erection PIPE LM 127,414.00 122,357.00 of different sizes
**Test Packs PIPE Dia Inch/LM NO IDEA FOR THE TEST PACKS
Mechanical Erection Equip. Nr 274.00 no weight of Tonnage, only quantities of equipment
Electrical Cable LM 829,910.00 including Communication System Cables
Electrical Conduit LM 2,500.00
Electrical Ladder Rack & Tray LM 29,385.00
Electrical Grounding Cable LM 12,310.00
Electrical Electrical Hook-Up Nr 1,065.00
Instrument Cable LM 256,891.00
Instrument Conduit LM 31,000.00
Instrument Trunking LM 7,835.00
Instrument Piping Hook-Up Nr 1,139.00
**Loop Packs Loops EA 5,506.00 quantity of Instruments
Painting Paint m² 130,080.58 touch-up painting only
Insulation Insulation m² 40,193.93
Fireproofing Fireproofing m² 8,141.00 for steelworks only
09_PAR's BILFAL
Structural Steel Steel Ton 12,238.80 16,560.44 100%
Pipe Fab PIPE LM 115,387.00 48,500.90
Pipe Erection PIPE LM 38,102.00 48,500.90
Electrical Cable Ladder LM 2,791.00
Electrical Cable LM 10,745.00 Heat Tracing Cable
Instrumentation Trunking LM 12,798.00
Painting Paint m² 124,616.70 touch-up painting only
Insulation Insulation m² 39,805.40
Fireproofing Fireproofing m² not in BILFAL's scope
Modules PAR's EA 89.00 85.00 80% Remeasure is not yet complete
149,322.04