Aug. 31, 2006
Aug. 31, 2006
As of 31 August 2006
PERCENT OF COMPLETION
(Including Materials on site) : 50.53%
P5 Package 1 Page 1
REASONS FOR VARIANCE : The materials delivered on site contributed
on their % progress accomplishment this Month
VALIDITY : 2/1/2008
P5 Package 1 Page 2
Project Status Report
As of 31 August 2006
PERCENT OF COMPLETION
(Including Materials on site) : 45.68%
P5 Package 2 Page 3
REASONS FOR VARIANCE : The materials delivered on site contributed
on their % progress accomplishment this Month
VALIDITY : 2/1/2008
P5 Package 2 Page 4
Project Status Report
As of 31 August 2006
PERCENT OF COMPLETION
(Including Materials on site) : 48.57%
P5 Package 3 Page 5
REASONS FOR SLIPPAGE : Service rerouting utilities works to complete
Insufficient manhours / labour / equipment
Shop Drawing Submittals (has still pending)
Material Procurement (to expedite)
Late Start Activities
VALIDITY : 2/1/2008
P5 Package 3 Page 6
Project Status Report
As of 31 August 2006
PERCENT OF COMPLETION
(Including Materials on site) : 32.64%
P4 Package 1 Page 7
REASONS FOR SLIPPAGE : Service rerouting utilities works to complete
Insufficient manhours / labour / equipment
Late Shop Drawing Submittals
Late Material Procurement
VALIDITY : 3/12/2007
P4 Package 1 Page 8