PFMEA - Machining

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 14

Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

OPERATION NO. #10 Receive casting

6 3
Down stream operation :
100% parts may have to be reworked 5 Casting damage 3 Dedicated trolley with separator
offline
1) To meet the Assy :
1 Fettling Not done properly 3 Trained Operator
customer Damage when receive NA
200% checked by inspector 6 108
specification for good part Customer :
part A Portion of production run may have to 6 Operator loading skill 2 Dedicated trolley with separator
be scrapped
End User:
5 While transportation 3 Standardised vehicle transport
Degradation of secondary function

During storage / Method of storage 3 Dedicated trolley with separator


10 Receive casting

6 3

Down stream operation :


100% parts may have to be reworked Component exposed to rain & not
5 2 Re shot blasting if exposed to rain
offline stored properly

2) No white rust White rust Assy : 200% checked by inspector 6 108


1 Improper storage Location 3 Allocated or Identified location
NA
Customer :
100% parts may have to be scrapped 6 Method of storage 3 Dedicated trolley with separator

End User:
1
No effect
OPERATION NO. #15 Shift Code Marking

6 3

Down stream operation :


Nil 1 Missing Operation 3 Machine interlinked with VMC

Assy :
No Date code. 1 Wrong setting 3 Allocated or Identified location
Nil
Customer :
Lack of traceability 6

End User:
Nil 1

Down stream operation :


NC on machining face 1 As cast flash 3 Pocket provited in restpad 1

15 Shift Code Assy :


Shift Punching 1 200% checked by inspector 6 108
Marking Casting projection in Nil
Resting place (R1) Customer :
Nil 6

End User:
Nil 1

Down stream operation :


Nil 1 Casting face flash /Projection 3 Insp. Done at casting stage

Location & orientation Assy :


Improber seating of mating part 1
hole as cast face
(OP20 setup 1 LHS & Customer :
RHS) Nil 6

End User:
Nil 1

OPERATION NO. #20 LEFT HAND SIDE & RIGHT HAND SIDE -1 SETUP

6 3
Down stream operation: Not able to
6 No machining Allowance 2 Insp. Done at casting stage
machine (non clearance)
Milling Height over size
Assy: NA 1 Wrong loading 3 Nil 6 108
Gauge checked by operator
Customer:Assembly problem 6 Uneven clamping 3 Preventive maintanence
Established tool change frequency and
End User: Nil 1 Inserts worn out 2
specify in Opn.std
1) Milling Height
31.00±0.25, wrong tool offset 2 Program locked
68.18 ±0.2, Established tool change frequency and
Build up edge 3
72.93 ±0.2, specify in Opn.std
3.57±0.25
6 3

Down stream operation: Nil 1 Bend in the casting 3 Insp. Done at casting stage
Milling Height under Guide pin available in fixture to guide the
Assy: NA 1 Wrong loading 3 Gauge checked by operator 6 108
size part while loading
Customer: May affect / disturb at
6 Uneven clamping 3 preventive maintanence
assembly
End User: Nil 1 wrong tool offset 2 Program locked

6 3
Opn:20A) Milling

Down stream operation: Nil 1 Bend in the casting 3 Insp. Done at casting stage

Flatness Assy: NA 1 Uneven clamping 3 preventive maintanence


2) Flatness 0.1 First off Inspection 6 108
Out of spec
Customer: May affect / disturb at
6 Rest pads not in same plane 3 Fixture designed as per drawing
assembly

End User: Nil 1 Wrong tool offset 2 Program locked

6 3

Coolant secondary filter provided &


Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Surface finish out of Establish tool change frequency and
3) Surface finish Assy: NA 1 insert wear 2 Inspection by inspector as per QCPC 6 108
spec specify in Opn.std
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Leakage in assembly
Establish tool change frequency and
End User: Nil 1 Buildup edge 3
specify in Opn.std
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure
6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
2ndf setup dimensions not ok

Assy: NA 1 No machining Allowance 2 Insp. Done at casting stage Plug gauge check by operator. Diameter 6 72
I) Drill dia oversize is controlled within ± 0.05 for
Customer: Part strengthen not good while
6 Burr entrapment into tool holder 2 Coolant spray in tool holder further process control
running
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function
1) Diameter Ø8.6 Spindle runout 2 preventive maintenance

6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
2nd setup machining cannot be done
Plug gauge check by operator. Diameter
II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list is controlled within ± 0.05 for 6 72
further process control
Customer: Assembly cannot be done 6

End User: Nil 1

Down stream operation: Establish tool change frequency and


6 Drill wear 2
2nd setup machining cannot be done specify in Opn.std
20B) ø8.6 Drilling Assy: NA 1 wrong tool Offset 2 Program locked
2) Depth Not Through Plug gauge check by operator. 6 72
Customer: Assembly cannot be done 6 Tool broken 2 Tool breakage sensor to be provided

Component getting disturbed while Ensure proper clamping of component


End User: Nil 1 2
machining against resting as per OS
6 3
Down stream operation:
1 Uneven clamping 3 preventive maintanence
2nd setup operation cannot be done
3) Position (Datum C) Position Component getting disturbed while Ensure proper clamping of component
Assy: NA 1 2 Plug gauge check by operator. 5 90
0.25 wrt AB Out of spec machining against resting as per OS
Customer:
6
Cant able to assy the mating part
End User: Nil 1

6 2

Established cutting parameters and


Down stream operation:Nil 1 Tool drag 2
program locked
3) Perpendicularity Perpendicularity out of Component getting disturbed while Ensure proper clamping of component
Assy: NA 1 2 First off Inspection 6 72
0..3 spec machining against resting as per OS
Customer: Can't able to assemble, Bolt
6
may foul

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Thread cannot be formed

1
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

Assy: NA 1 No machining Allowance 2 Insp. Done at casting stage


I) Drill dia oversize Core plug gauge check by operator 6 72
Customer: Part strengthen not good while
6 Burr entrapment into tool holder 2 Coolant spray in tool holder
running
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function

Spindle runout 2 preventive maintenance

6 3

Down stream operation:


1 Tool wear 2 Tool life monitoring provided
Nil
1) Ø6 / ø7 drill
II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list

Established cutting parameters and


Customer: Bolt will not enter 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
20C) ø6.0/ø7
Drilling II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108
Established cutting parameters and
Customer: Bolt will not enter 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided FPG check by operator 6 108

Customer: Air & Fuel flow get affected 6

End User: Nil 1


2 ) Depth
ii) Ø29.30 +0.2
6 2

Down stream operation:


1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list FPG check by operator 6 72

Customer:Air & Fuel flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Silicon % 2 Insp. Done at casting stage

Assy: NA 1 Build up edge 3 Tool life monitoring provided


l) M8x1 6H thread
SPG check by operator 6 108
damage
Customer: Filter not assemble 6 Wrong tool selection 2 Tool issue only as per tools list
Coolant level indicator available and
End User: Nil 1 Coolant not flow 2
machine stops on low level
Tool feed rate high 2 Program locked

6 3

Down stream operation: Nil 1 Drill dia undersize 3 Tool life monitoring provided
Establish tool change frequency and
1) M8x1 6H Thread Assy: NA 1 Build up edge 3
specify in Opn.std
size
ll) M8x1 6H thread Go
( 1 places ) Customer:Filter not assemble 6 Coolant not flow 2 Flush coolant used to remove burr SPG check by operator 6 108
not answering
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

Wrong tool selection 2 Tool issue only as per tools list


Established cutting parameters and
Improper feed/Speed rate 2
program locked
6 3
Establish tool change frequency and
20D) M8x1 6H Down stream operation: Nil 1 Build up edge 3
specify in Opn.std
Tapping ll) M8x1 6H thread
Assy: NA 1 Tool runout 3 Preventive check (before tool issue) SPG check by operator 6 108
NOGO answering
Customer: Affect the Filter Assembly 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Spindle runout 2 preventive maintenance

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2)Thread Depth l) Thread depth
Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize
Customer: Affect the Filter Assembly
6
depth
End User: Nil 1

6 3
Down stream operation:
1 Resting pads not in same plane 2 Preventive maintanence
Nil
Assy: NA 1 Uneven clamping 2 Clamping pressure established
3) Position Position
Customer: Component getting disturbed while Ensure proper clamping of component Receiver Gauge checked by operator 6 108
0.2 wrt AB Out of spec 6 2
Cant able to assy the mating part machining against resting as per OS
Customer: Ensure proper adherance of tool life as
6 Position not ok 2
Cant able to assy the mating part per OS

End User: Nil Drill drag 3 Tool life monitoring provided

6 3
Down stream operation:
1 No machining Allowance 2 Insp. Done at casting stage
Nil

Assy: NA 1 Tool wear 2 Tool life monitoring provided


I) Groove ID oversize Gauge check by operator 6 108
Established cutting parameters and
Customer: Seal will not assemble 6 Spindle speed / Feed rate high 3
program locked
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function
1)Groove ID Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil

II) Groove ID undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Gauge check by operator 6 108
Established cutting parameters and
Customer: Seal will not assemble 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3
Down stream operation:
1 No machining Allowance 2 Insp. Done at casting stage
Nil

Assy: NA 1 Build up edge 2 Tool life monitoring provided


I) Groove width
Gauge check by operator 6 108
oversize Established cutting parameters and
Customer: Seal will not assemble 6 Improper Spindle speed / Feed rate 3
program locked
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function
2)3±0.2 Groove width End User: Nil

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Groove width Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Gauge check by operator 6 108
undersize
Established cutting parameters and
Customer: Seal will not assemble 6 Improper Spindle speed / Feed rate 3
program locked

End User: Nil 1

6 2
Down stream operation:
1 No machining Allowance 2 Insp. Done at casting stage
Nil

Assy: NA 1 Build up edge 2 Tool life monitoring provided


I) Groove depth
Gauge check by operator 6 72
oversize Customer: Seal will not assemble
6 Wrong tool offset 2 Program locked
properly

2
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

End User: degradation of secondary


6 Wrong tool selection 2 Tool issue only as per tools list
function
3)Groove depth End User: Nil

6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Groove depth Assy: NA 1 Wrong tool offset 2 Program locked Gauge check by operator 6 72
undersize
Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly

End User: Nil 1

6 2
Down stream operation:
1 Built-up edge 2 Tool life monitoring provided
Nil
20E) ø13.50
Cutting parameter established during
Grooving Assy: NA 1 Spindle speed & feed 2
trials and program locked
I) Radius oversize Inspection by inspector as per QCPC 6 72
Customer: Seal will damaged 6 Wrong tool selection 2 Tool issue only as per tools list

End User: degradation of secondary


6
function
4) Radius (4 places)
End User: Nil
R0.5
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Radius undersize Assy: NA 1 Wrong tool offset 2 Program locked Inspection by inspector as per QCPC 6 72

Customer: Seal will damaged 6 Wrong tool selection 2 Tool issue only as per tools list

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
I) Chamfer depth
Assy: NA 1 Wrong tool offset 2 Program locked Inspection by inspector as per QCPC 6 72
oversize
Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly
End User: degradation of secondary
6
function
5) Chamfer depth
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II)Chamfer depth Assy: NA 1 Wrong tool offset 2 Program locked Inspection by inspector as per QCPC 6 72
undersize
Customer: Seal will not enter Into the
6 Wrong tool selection 2 Tool issue only as per tools list
groove

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
I) Chamfer angle more
6) Chamfer angle Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Inspection by inspector as per QCPC 6 72
or less
Customer: Seal will not assemble
6 Tool wear 2 Tool life monitoring provided
properly
End User: degradation of secondary
6
function

6 3

Coolant secondary filter provided &


Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Surface finish out of Establish tool change frequency and
7) Surface finish Assy: NA 1 Tool wear 2 Inspection by inspector as per QCPC 6 108
spec specify in Opn.std
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Seal not seated properly
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure
6 3
Down stream operation: Established cutting parameters and
1 Spindle speed / Feed rate high 3
Nil program locked
8) Concentricity 0.5 I) Concentricity out of Assy: NA 1 Tool wear 3 Tool life monitoring provided Concentricity gauge check by operator 6 108
wrt M8 spec
Pressure indicator to check the clamping
Customer: Fuel flow get affected 6 Clamping pressure more or less 2
pressure
End User: degradation of secondary Component getting disturbed while Pressure indicator to check the clamping
6 2
function machining pressure/ preventive Maintenance

6 3
Coolant secondary filter provided &
Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Establish tool change frequency and
Surface finish out of Assy: NA 1 Tool wear 2
specify in Opn.std Inspection by inspector as per QCPC 6 108
spec
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper sealing
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked

1) Diameter Ø9 Pressure indicator to check the clamping


Clamping pressure more or less 2
pressure
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
20F) Ø9 Drilling Nil

II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108
Established cutting parameters and
Customer: Bolt will not enter 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2) Depth (2-places)
l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided CPG check by operator 6 108

Customer: Part cannot assemble 6

End User: Nil 1

6 3

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
l) M10x1 6H thread
SPG check by operator 6 108
damage Coolant level indicator available and
Customer: Filter not assemble 6 Coolant not flow 2
machine stops on low level
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

Tool feed rate high 2 Program locked

6 3

Down stream operation: Nil 1 Drill dia undersize 3 Tool life monitoring provided
Establish tool change frequency and
1) M10x1 6H Thread Assy: NA 1 Build up edge 3
specify in Opn.std
size
ll) M10x1 6H thread Go
( 3 places ) Customer:Filter not assemble 6 Coolant not flow 2 Flush coolant used to remove burr SPG check by operator 6 108
not answering
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

Wrong tool selection 2 Tool issue only as per tools list


Established cutting parameters and
Improper feed/Speed rate 2
program locked
20G) M10x1 6H 6 3
Thread milling
Establish tool change frequency and
(3 places) Down stream operation: Nil 1 Build up edge 3
specify in Opn.std
ll) M10x1 6H thread
Assy: NA 1 Tool runout 3 Preventive check (before tool issue) SPG check by operator 6 108
NOGO answering
Customer: Affect the Filter Assembly 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Spindle runout 2 preventive maintenance

6 3

3
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2)Thread Depth l) Thread depth
Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize
Customer: Part cannot assemble 6

End User: Nil 1

6 3
Down stream operation:
1 Resting pads not in same plane 2 Preventive maintanence
3) Position 2nd setup operation cannot be done
Ø0.6 wrt JDA Position First off Inspection/ Interposition gauge
Assy: NA 1 Uneven clamping 3 preventive maintanence 6 108
Ø0.6 wrt FDA Out of spec check by operator
Ø0.6 wrt EAH Customer: Component getting disturbed while Ensure proper clamping of component
6 2
Cant able to assy the mating part machining against resting as per OS
End User: Nil 1

6 3

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

11.10 + 0.1 Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
intersection dia SPG check by operator 6 108
oversize Customer: O ring seat not properly 6 Spindle runout 2 Preventive maintanence

End User: Nil 1 Spindle speed & feed 2 Program locked


1) 11.10 + 0.1
intersection dia
6 3

Down stream operation: Nil 1 Form tool intersection dia undersize 3 Tool life monitoring provided
11.10 + 0.1
Establish tool change frequency and SPG check by operator 6 108
intersection dia Assy: NA 1 Build up edge 3
specify in Opn.std
undersize
Customer:O ring seat not properly 6 Wrong tool selection 2 Tool issue only as per tools list
Established cutting parameters and
End User: Nil 1 Improper feed/Speed rate 2
program locked
20H)M10 'O' ring
detail 6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


Chamfer Depth & 1.60 +0.4,45° & 12°
Angle ,depth over size / Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize
Customer: Part cannot assemble 6 Wrong tool selection 2 incomining tool inspection

End User: Nil 1

6 3
Coolant secondary filter provided &
Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Establish tool change frequency and
Surface finish out of Assy: NA 1 Tool wear 2
Surface finish specify in Opn.std Inspection by inspector as per QCPC 6 108
spec
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper sealing
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
II) Drill dia Oversize Customer: Fuel flow get affected 6 Burr entrapment into tool holder 2 Coolant spray in tool holder
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function
Spindle runout 2 preventive maintenance
1) Drill ø3.00
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list plug gauge check by operator 6 108

Established cutting parameters and


Customer: Fuel flow get affected 6 Spindle speed / Feed rate high 3
program locked
End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


Inspection by inspector in Contour
20 I) Ø3 Drilling l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided 6 108
Tracer
Customer: Fuel flow get affected 6

End User: Nil 1


2) Depth 48
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
Inspection by inspector in Contour
II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list 6 72
Tracer
Customer: Fuel flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3
Down stream operation:
1 Resting pads not in same plane 2 Preventive maintanence
Nil
3) position X 1.25 Y Position
Assy: NA 1 Uneven clamping 3 preventive maintanence First off inspection 6 108
0.25 Out of spec
Customer: Component getting disturbed while Ensure proper clamping of component
6 2
Flow rate affected machining against resting as per OS
End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked

Assy: Nil 1 Tool wear 3 Tool life monitoring provided Inspection by inspector through contour
I) Depth oversize tracer/ Also controlled by measuring 6 108
Customer: Fuel flow get affected 6 Ø5.1 depth

End User: Nil 6


1) Depth 34.3

Down stream operation:


6 2
Nil
Assy: NA 1 Tool wear 2 Tool life monitoring provided Inspection by inspector through contour
II) Depth undersize tracer/ Also controlled by measuring 6 72
Customer: Fuel flow get affected 1 Wrong tool selection 2 Tool issue only as per tools list Ø5.1 depth

End User: Nil 6 Wrong tool offset 2 Program locked

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Drill dia oversize plug gauge check by operator 6 108
Customer: Fuel flow get affected 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: degradation of secondary


6 Wrong tool selection 2 Tool issue only as per tools list
function
1) Diameter Ø3 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
20 J) Ø5.1 pre
drill and Ø3 II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list plug gauge check by operator 6 108
combination
Established cutting parameters and
Customer: Fuel flow get affected 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided FPG check by operator 6 108

Customer: Fuel flow get affected 6

4
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

End User: Nil 1


2) Depth 30.6 ± 0.2
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list FPG check by operator 6 72

Customer: Fuel flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Pressure indicator to check the clamping
Assy: NA 1 Clamping pressure more or less 2
3) Chamfer angle I) Chamfer angle more pressure
Inspection by inspector as per QCPC 6 72
118° or less
Customer: Improper assembly 6 Wrong tool selection 2 Tool issue only as per tools list

End User: degradation of secondary


6
function

6 3
Down stream operation: Established cutting parameters and
1 Spindle speed / Feed rate high 3
Nil program locked

Assy: NA 1 Tool wear 3 Tool life monitoring provided


1) Concentricity 0.05 I) Concentricity out of
Pressure indicator to check the clamping First Off inspection 6 108
wrt Ø 3 spec Customer: Fuel flow get affected 6 Clamping pressure more or less 2
pressure
End User: degradation of secondary Component getting disturbed while Pressure indicator to check the clamping
6 2
function machining pressure/ preventive Maintenance

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
20 K) Ø5 .6 Established cutting parameters and
Reaming Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Dia oversize Air plug gauge check by operator 6 108
Customer: NRV will not assemble
6 Burr entrapment into tool holder 2 Coolant spray in tool holder
properly

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list
1) Diameter
Spindle runout 2 preventive maintenance
Ø5.6 ± 0.05
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Air plug gauge check by operator 6 108
Established cutting parameters and
Customer: NRV will not assemble 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

OPERATION NO. #30 LEFT HAND SIDE & RIGHT HAND SIDE -2nd SETUP

6 3
Down stream operation: Not able to
6 No machining Allowance 2 Insp. Done at casting stage
machine (non clearance)
Milling Height over size
Assy: NA 1 Wrong loading 3 Pokayoke provided 5 90
Gauge checked by operator
Customer:Assembly problem 6 Uneven clamping 3 Preventive maintanence
Established tool change frequency and
End User: Nil 1 Inserts worn out 2
specify in Opn.std
1) Milling Height wrong tool offset 2 Program locked
23.57±0.25,
37.43±0.25, Established tool change frequency and
Build up edge 3
52.30±0.30 specify in Opn.std
6 3

Down stream operation: Nil 1 Bend in the casting 3 Insp. Done at casting stage
Milling Height under Guide pin available in fixture to guide the
Assy: NA 1 Wrong loading 3 Gauge checked by operator 6 108
size part while loading
Customer: May affect / disturb at
6 Uneven clamping 3 preventive maintanence
assembly
End User: Nil 1 wrong tool offset 2 Program locked

6 3
Opn:30A) Milling

Down stream operation: Nil 1 Bend in the casting 3 Insp. Done at casting stage

Flatness Assy: NA 1 Uneven clamping 3 preventive maintanence


2) Flatness 0.1 First off Inspection 6 108
Out of spec
Customer: May affect / disturb at
6 Rest pads not in same plane 3 Fixture designed as per drawing
assembly

End User: Nil 1 Wrong tool offset 2 Program locked

6 3

Coolant secondary filter provided &


Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Surface finish out of Establish tool change frequency and
3) Surface finish Assy: NA 1 insert wear 2 Inspection by inspector as per QCPC 6 108
spec specify in Opn.std
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Leakage in assembly
Establish tool change frequency and
End User: Nil 1 Buildup edge 3
specify in Opn.std
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure
6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
I) dia oversize Assy: NA 1 Spindle speed / Feed rate high 3 plug gauge check by operator 6 108
program locked
Customer: Solenoid valve will not
6 Wrong tool selection 2 Tool issue only as per tools list
assemble properly

End User: Nil 1 Spindle runout 2 preventive maintenance


1) Diameter
Ø14.8 ±0.1 6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list plug gauge check by operator 6 108
Customer: Solenoid valve will not Established cutting parameters and
6 Spindle speed / Feed rate high 3
assemble program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided FPG check by operator 6 108

Customer: Fuel flow get affected 6 Wrong tool selection 2 Tool issue only as per tools list

End User: Nil 1


2) Depth 2.2 ± 0.1
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list FPG check by operator 6 72

Customer:Air & Fuel flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
I) Core hole dia Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3 Core plug gauge check by operator 6 108
oversize program locked

Customer: Play in valve assembly 6 Wrong tool selection 2 Tool issue only as per tools list

End User: Nil 1 Spindle runout 2 preventive maintenance


3) Pre drill diameter
Ø13 6 3

5
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

Down stream operation:


1 Tool wear 2 Tool life monitoring provided
Nil
II) Core hole dia Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108
undersize
Established cutting parameters and
Customer: Valve will not assemble 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

1 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Improper finish
30B) Ø14.8
counterbore , Ø13 Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
pre drill and Ø5.4 program locked Controlled by Ø5.9 Air gauge check by
I) drill dia oversize 6 18
drill operator
Customer: Nil 1 Wrong tool selection 2 Tool issue only as per tools list
(2 - places)
End User: Nil 1 Spindle runout 2 preventive maintenance
4) Pre drill diameter
Ø5.4
6 3
Down stream operation:
6 Tool wear 2 Tool life monitoring provided
Improper finish

Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Controlled by Ø5.9 Air gauge check by
II) drill dia undersize 6 108
operator
Established cutting parameters and
Customer: Nil 1 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided FPG check by operator 6 108

Customer: Air & Fuel flow get affected 6

End User: Nil 1


5) Depth
ii) Ø9.3 +0.1 6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list FPG check by operator 6 72

Customer:Air & Fuel flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided Inspection by inspector as per QCPC 6 108

Customer: Valve will not assemble


6
properly
End User: Nil 1
6) Chamfer Depth 0.5
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Inspection by inspector as per QCPC 6 72
Customer: Valve will not assemble
6 Wrong tool offset 2 Program locked
properly

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
7) Chamfer angle I) Chamfer angle more Pressure indicator to check the clamping
Assy: NA 1 Clamping pressure more or less 2 Inspection by inspector as per QCPC 6 72
45° or less pressure

Customer: Improper assembly 6 Wrong tool selection 2 Tool issue only as per tools list

End User: degradation of secondary


6
function
6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
I) Dia oversize Assy: NA 1 Spindle speed / Feed rate high 3 Air plug gauge check by operator 6 108
program locked
Customer: Assembly fitment will be
6 Wrong tool selection 2 Tool issue only as per tools list
losse

End User: Nil 1 Spindle runout 2 preventive maintenance


1) Diameter
Ø6 (-0.1/0.07) 6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Air plug gauge check by operator 6 108
Customer: Assembly canot be carried Established cutting parameters and
6 Spindle speed / Feed rate high 3
out program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


l) depth Undersize FPG check by operator 6 108
30C ) Ø5.915 Assy: Nil 1 Tool wear 3 Tool life monitoring provided
Reaming
Customer: Affect the assembly 6
End User: Nil 1
2) Depth
Ø13.30 ±0.05 6 2

Down stream operation:


1 Tool wear 2 Tool life monitoring provided
Nil
II) Depth oversize FPG check by operator 6 72
Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list

Customer: Affect the assembly 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3
Coolant secondary filter provided &
Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Establish tool change frequency and
Assy: NA 1 Tool wear 2
Surface finish out of specify in Opn.std
3) Surface finish Inspection by inspector as per QCPC
spec Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper sealing

End User: Nil 1 Spindle speed / Feed rate high 3 Program locked

Pressure indicator to check the clamping


Clamping pressure more or less 2
pressure

6 3

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
l) M14x1 6H thread
First off inspection 6 108
damage Coolant level indicator available and
Customer: 100% part scrapped 6 Coolant not flow 2
machine stops on low level
Pressure indicator to check the clamping
End User: Nil 1 Clamping pressure more or less 2
pressure

Tool feed rate high 2 Program locked

6 3

Down stream operation: Nil 1 Drill dia undersize 3 Tool life monitoring provided
1) M14x1 6H Thread
Establish tool change frequency and
size Assy: NA 1 Build up edge 3
ll) M14x1 6H thread Go specify in Opn.std
( 2 places ) SPG check by operator 6 108
not answering
Customer: Air & Fuel SOV not assemble 6 Coolant not flow 2 Flush coolant used to remove burr

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list

Established cutting parameters and


Improper feed/Speed rate 2
program locked

6
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

6 3

30D) M14 X 1 Establish tool change frequency and


Down stream operation: Nil 1 Build up edge 3
Thread milling specify in Opn.std
ll) M14x1 6H thread
Assy: NA 1 Tool runout 3 Preventive check (before tool issue) SPG check by operator 6 108
NOGO answering

Customer: Air & Fuel SOV not assemble 6 Spindle runout 2 preventive maintenance

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2)Thread Depth l) Thread depth
Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize

Customer: Part cannot assemble 6

End User: Nil 1

6 3

Down stream operation: Nil 1 Resting pads not in same plane 2 Preventive maintanence
3) Position Position
Assy: NA 1 Uneven clamping 3 preventive maintanence Receiver Gauge inspection by operator 5 90
0.6 wrt ABH Out of spec
Customer: Component getting disturbed while Ensure proper clamping of component
6 2
Cant able to assy the mating part machining against resting as per OS

End User: Nil 1

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Groove ID oversize Gauge check by operator 6 108
Customer: Seal will not assemble 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: degradation of secondary


6 Wrong tool selection 2 Tool issue only as per tools list
function
1)Groove ID
Spindle runout 2 preventive maintenance
19.8 ± 0.1
6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil

II) Groove ID undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Gauge check by operator 6 108
Established cutting parameters and
Customer: Seal will not assemble 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Improper Spindle speed / Feed rate 3
I) Groove width program locked
Gauge check by operator 6 108
oversize
Customer: Seal will not assemble 6 Wrong tool selection 2 Tool issue only as per tools list

End User: Nil 6

2)Groove width

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Groove width Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Gauge check by operator 6 108
undersize
Established cutting parameters and
Customer: Seal will not assemble 6 Improper Spindle speed / Feed rate 3
program locked

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
30E) Grooving
I) Groove depth
Assy: NA 1 Wrong tool offset 2 Program locked Gauge check by operator 6 72
oversize
Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly
End User: degradation of secondary
6
4)Groove depth function
1.2 - 0.15 6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Groove depth Assy: NA 1 Wrong tool offset 2 Program locked Gauge check by operator 6 72
undersize
Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly

End User: Nil 1

6 2
Down stream operation:
1
Nil
Built-up edge 2 Tool life monitoring provided
I) Radius oversize Assy: NA 1 Inspection by inspector as per QCPC 6 72

Cutting parameter established during


Customer: Seal will not assemble 6 Spindle speed & feed 2
trials and program locked
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
5) Radius (4 places) function
R0.2 6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Radius undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Inspection by inspector as per QCPC 6 72

Customer: Seal will Damage to assemble 6

End User: Nil 1

6 3

Coolant secondary filter provided &


Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Surface finish out of Establish tool change frequency and
6) Surface finish Assy: NA 1 Tool wear 2 Inspection by inspector as per QCPC 6 108
spec specify in Opn.std
Customer:Nil 6 Less Coolant flow 2 Failsafe alarm available in machine
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure
6 3
Down stream operation:
4 Build up edge 2 Tool life monitoring provided
Thread cannot be formed
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Drill dia oversize Core plug gauge check by operator 6 108
Customer: Part strengthen not good while
6 Burr entrapment into tool holder 2 Coolant spray in tool holder
running
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function

30F) Ø3.3 drilling 1) Ø3.3 drill Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108
Established cutting parameters and
Customer: Bolt will not enter 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
l) M8x1 6H thread
First off inspection 6 108
damage Coolant level indicator available and
Customer: 100% part scrapped 7 Coolant not flow 2
machine stops on low level
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

7
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

Tool feed rate high 2 Program locked

6 3

Down stream operation: Nil 1 Drill dia undersize 3 Tool life monitoring provided
Establish tool change frequency and
Assy: NA 1 Build up edge 3
1) M4*0.7 Thread size specify in Opn.std
( 2 places ) ll) M4x0.7 6H thread Go
Customer: Screw not assemble 6 Coolant not flow 2 Flush coolant used to remove burr SPG check by operator 6 108
not answering
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder
30G) M4*0.7
Tapping Wrong tool selection 2 Tool issue only as per tools list
(4 places)
Established cutting parameters and
Improper feed/Speed rate 2
program locked
6 3
Establish tool change frequency and
Down stream operation: Nil 1 Build up edge 3
specify in Opn.std
ll) M4x0.7 6H thread
Assy: NA 1 Tool runout 3 Preventive check (before tool issue) SPG check by operator 5 90
NOGO answering
Customer: Screw will shear due to cyclic
6 Burr entrapment into tool holder 2 Coolant spray in tool holder
load
End User: Nil 1 Spindle runout 2 preventive maintenance

6 3 5 90

Down stream operation: Nil 1 Wrong tool offset 2 Program locked 8 96


2)Thread Depth
l) depth not through Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Through
Customer: Part cannot assemble 6

End User: Nil 1

6 3

Down stream operation: Nil 1 Build up edge 2 Tool life monitoring provided

Established cutting parameters and


Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Drill dia oversize Plug gauge check by operator 6 108
Customer: Part cannot assemble 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: degradation of secondary


6 Wrong tool selection 2 Tool issue only as per tools list
function
1) Ø3.1 drill Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Plug gauge check by operator 6 108
Established cutting parameters and
Customer: Part cannot assemble 6 Spindle speed / Feed rate high 3
program locked
30H) Ø3.1 drilling End User: Nil 1

6 3

Down stream operation:Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided FPG check by operator 6 108

Customer: Part cannot assemble 6

End User: Nil 1


2) Depth 2.2 ± 0.1
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list FPG check by operator 6 108

Customer: Part cannot assemble 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
ø8.0 size not atcheived
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
30I ) Ø4/7.40 1) Diameter I) Dia oversize / Under program locked
Air plug gauge check by operator 6 108
Drilling Ø4/7.40 size Customer: Assembly fitment will be
6 Burr entrapment into tool holder 2 Coolant spray in tool holder
losse

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list

Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Dia oversize Air plug gauge check by operator 6 108
Customer: Assembly fitment will be
6 Burr entrapment into tool holder 2 Coolant spray in tool holder
losse

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list
1) Diameter
Ø8 (-0.1/0.07)
Spindle runout 2 preventive maintenance
Down stream operation:
6 3
Nil
Assy: NA 1 Tool wear 2 Tool life monitoring provided
II) Dia undersize Air plug gauge check by operator 6 108
30I) Ø8 Reaming Customer: Assembly canot be carried
1 Wrong tool selection 2 Tool issue only as per tools list
out
Established cutting parameters and
End User: Nil 6 Spindle speed / Feed rate high 3
program locked

6 3

Coolant secondary filter provided &


Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Surface finish out of Establish tool change frequency and
2) Surface finish Assy: NA 1 Tool wear 2 Inspection by inspector as per QCPC 6 108
spec specify in Opn.std
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper sealing
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
II) Drill dia Oversize Customer: Fuel flow get affected 6 Burr entrapment into tool holder 2 Coolant spray in tool holder
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function
Spindle runout 2 preventive maintenance
1) Drill ø3.00
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list plug gauge check by operator 6 108

Established cutting parameters and


Customer: Fuel flow get affected 6 Spindle speed / Feed rate high 3
program locked
End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


Inspection by inspector in Contour
30J) Ø3 Drilling l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided 6 108
Tracer
Customer: Fuel flow get affected 6

End User: Nil 1


2) Depth 48
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
Inspection by inspector in Contour
II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list 6 72
Tracer
Customer: Fuel flow get affected 6 Wrong tool offset 2 Program locked

8
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

End User: Nil 1

6 3
Down stream operation:
1 Resting pads not in same plane 2 Preventive maintanence
Nil
3) position X 1.25 Y Position
Assy: NA 1 Uneven clamping 3 preventive maintanence First off inspection 6 108
0.25 Out of spec
Customer: Component getting disturbed while Ensure proper clamping of component
6 2
Flow rate affected machining against resting as per OS
End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Drill dia oversize plug gauge check by operator 6 108
Customer: Fuel flow get affected 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: degradation of secondary


6 Wrong tool selection 2 Tool issue only as per tools list
function
1) Diameter Ø4 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
30K) Ø4 Drilling
II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list plug gauge check by operator 6 108
Established cutting parameters and
Customer: Fuel flow get affected 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2) Depth Inspection by inspector in Contour
l) depth not through Assy: Nil 1 Tool wear 3 Tool life monitoring provided 6 108
through Tracer
Customer: Fuel flow get affected 6

End User: Nil 1

6 3
Down stream operation:
4 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Drill dia oversize Core plug gauge check by operator 6 108
Customer: Air flow get affected 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: degradation of secondary


6 Wrong tool selection 2 Tool issue only as per tools list
function
1) Diameter Ø5 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108
Established cutting parameters and
Customer: Air flow get affected 6 Spindle speed / Feed rate high 3
program locked
30L ) Ø5 Drilling End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided CPG check by operator 6 108

Customer: Air flow get affected 6

End User: Nil 1


2) Depth (2-places)
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 72

Customer: Air flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Drill dia oversize plug gauge check by operator 6 108
Customer: Fuel flow get affected 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: degradation of secondary


6 Wrong tool selection 2 Tool issue only as per tools list
function
1) Diameter Ø7.5 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list plug gauge check by operator 6 108
Established cutting parameters and
Customer: Fuel flow get affected 6 Spindle speed / Feed rate high 3
program locked
End User: degradation of secondary
6
function
30M) Ø7.5 Drilling
6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil

Assy: NA 1 Wrong tool offset 2 Program locked


I) Depth oversize Gauge check by operator 6 72
Customer: Fuel flow get affected 6 Wrong tool selection 2 Tool issue only as per tools list

End User: degradation of secondary


6
function
2)Depth
20.8
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth undersize Assy: NA 1 Wrong tool offset 2 Program locked Gauge check by operator 6 72

Customer: Fuel flow get affected 6 Wrong tool selection 2 Tool issue only as per tools list

End User: degradation of secondary


1
function
6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked 6 108
I) Drill dia oversize Core plug gauge check by operator
Customer: Play in thread assembly 6 Burr entrapment into tool holder 2 Coolant spray in tool holder
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function
1) Diameter Ø12.5 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108

Established cutting parameters and


Customer: Fuel flow get affected 6 Spindle speed / Feed rate high 3
program locked
End User: Nil 1

6 3
Down stream operation: Thread cannot
6 Wrong tool offset 2 Program locked
be formed properly
l) Depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided Core plug gauge check by operator 6 108

Customer: Valve cannot be assembled 6

9
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

End User: Nil 1


2) Depth 14
6 2
Down stream operation:
30N) ø12.50 1 Tool wear 2 Tool life monitoring provided
Nil
Drilling and Ø25
cutter spot facing II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 72

Customer: Fuel flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Bend in the casting 3 Insp. Done at casting stage
Flatness
3) Flatness 0.1 Assy: NA 1 Uneven clamping 3 preventive maintanence First off Inspection 6 108
Out of spec
Customer: May affect / disturb at
6 Rest pads not in same plane 3 Fixture designed as per drawing
assembly
End User: Nil 1 Wrong tool offset 2 Program locked

6 3

Down stream operation:Nil 1 Wrong tool offset 2 Program locked

l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided Receiver gauge check by operator 6 108

Customer: Valve blocks the flow 6

End User: Nil 1


4) Depth 36.07 ± 0.25
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II) Depth oversize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Receiver gauge check by operator 6 72

Customer: Fuel flow get affected 6 Wrong tool offset 2 Program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
l) M14x1.5 6H thread
SPG check by operator 6 108
damage Coolant level indicator available and
Customer: Filter not assemble 6 Coolant not flow 2
machine stops on low level
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

Tool feed rate high 2 Program locked

6 3

Down stream operation: Nil 1 Drill dia undersize 3 Tool life monitoring provided
Establish tool change frequency and
1) M14x1 .5 6H Assy: NA 1 Build up edge 3
specify in Opn.std
Thread size
ll) M14x1.5 6H thread
( 1 places ) Customer:Filter not assemble 6 Coolant not flow 2 Flush coolant used to remove burr SPG check by operator 6 108
Go not answering
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

Wrong tool selection 2 Tool issue only as per tools list


Established cutting parameters and
Improper feed/Speed rate 2
program locked
6 3
30O) M14 X 1.5
Thread milling Establish tool change frequency and
Down stream operation: Nil 1 Build up edge 3
specify in Opn.std
ll) M14x1.5 6H thread
Assy: NA 1 Tool runout 3 Preventive check (before tool issue) SPG check by operator 6 108
NOGO answering
Customer: Affect the Filter Assembly 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Spindle runout 2 preventive maintenance

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2)Thread Depth l) Thread depth
Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize
Customer: Part cannot assemble 6

End User: Nil 1

6 3
Down stream operation:
1 Resting pads not in same plane 2 Preventive maintanence
2nd setup operation cannot be done
3) Position Position
Assy: NA 1 Uneven clamping 3 preventive maintanence Receiver Gauge inspection by operator 5 90
0.6 wrt GBA Out of spec
Customer: Component getting disturbed while Ensure proper clamping of component
6 2
Cant able to assy the mating part machining against resting as per OS
End User: Nil 1

6 3

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
15.80 + 0.1 intersection
SPG check by operator 6 108
dia oversize
Customer: O ring seat not properly 6 Spindle runout 2 Preventive maintanence

End User: Nil 1 Spindle speed & feed 2 Program locked


1) 15.80 + 0.1
intersection dia
6 3

Down stream operation: Nil 1 Form tool intersection dia undersize 3 Tool life monitoring provided
30P) M14 O ring
detail 15.80 + 0.1 intersection Establish tool change frequency and
Assy: NA 1 Build up edge 3 SPG check by operator 6 108
dia undersize specify in Opn.std
Customer:O ring seat not properly 6 Wrong tool selection 2 Tool issue only as per tools list
Established cutting parameters and
End User: Nil 1 Improper feed/Speed rate 2
program locked
6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


Chamfer Depth & 2.40 +0.4,45° & 15°±1°
Angle depth over size / Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize
Customer: Part cannot assemble 6 Wrong tool selection 2 incomining tool inspection

End User: Nil 1

6 3
Coolant secondary filter provided &
Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Establish tool change frequency and
Surface finish out of Assy: NA 1 Tool wear 2
specify in Opn.std Inspection by inspector as per QCPC 6 108
spec
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper sealing
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked

1) Diameter Ø9 Pressure indicator to check the clamping


Clamping pressure more or less 2
pressure
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
30Q) Ø9 Drilling Nil

II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108
Established cutting parameters and
Customer: Bolt will not enter 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2) Depth (2-places)
l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided CPG check by operator 6 108

Customer: Part cannot assemble 6

End User: Nil 1

6 3

10
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
l) M10x1 6H thread
SPG check by operator 6 108
damage Coolant level indicator available and
Customer: Filter not assemble 6 Coolant not flow 2
machine stops on low level
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

Tool feed rate high 2 Program locked

6 3

Down stream operation: Nil 1 Drill dia undersize 3 Tool life monitoring provided
Establish tool change frequency and
1) M10x1 6H Thread Assy: NA 1 Build up edge 3
specify in Opn.std
size
ll) M10x1 6H thread Go
( 3 places ) Customer:Filter not assemble 6 Coolant not flow 2 Flush coolant used to remove burr SPG check by operator 6 108
not answering
End User: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

Wrong tool selection 2 Tool issue only as per tools list


Established cutting parameters and
Improper feed/Speed rate 2
program locked
30R) M10x1 6H 6 3
Thread milling
Establish tool change frequency and
(3 places) Down stream operation: Nil 1 Build up edge 3
specify in Opn.std
ll) M10x1 6H thread
Assy: NA 1 Tool runout 3 Preventive check (before tool issue) SPG check by operator 6 108
NOGO answering
Customer: Affect the Filter Assembly 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Spindle runout 2 preventive maintenance

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2)Thread Depth l) Thread depth
Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize
Customer: Part cannot assemble 6

End User: Nil 1

6 3
Down stream operation:
1 Resting pads not in same plane 2 Preventive maintanence
3) Position 2nd setup operation cannot be done
Ø0.6 wrt JDA Position First off Inspection/ Interposition gauge
Assy: NA 1 Uneven clamping 3 preventive maintanence 6 108
Ø0.6 wrt FDA Out of spec check by operator
Ø0.6 wrt EAH Customer: Component getting disturbed while Ensure proper clamping of component
6 2
Cant able to assy the mating part machining against resting as per OS
End User: Nil 1

6 3
Coolant secondary filter provided &
Down stream operation: Nil 1 Coolant concentration 2
Before coolant top up, check coolant
Establish tool change frequency and
Surface finish out of Assy: NA 1 Tool wear 2
specify in Opn.std Inspection by inspector as per QCPC 6 108
spec Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper sealing
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked
Pressure indicator to check the clamping
1) Diameter Ø6.0 Clamping pressure more or less 2
pressure
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
30S) Ø6.0Drilling Nil
II) Drill dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Core plug gauge check by operator 6 108
Established cutting parameters and
Customer: Bolt will not enter 6 Spindle speed / Feed rate high 3
program locked
End User: Nil 1

6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


2) Depth (Through)
l) depth Undersize Assy: Nil 1 Tool wear 3 Tool life monitoring provided CPG check by operator 6 108

Customer: Part cannot assemble 6

End User: Nil 1

6 3

Down stream operation: Nil 1 Build up edge 3 Tool life monitoring provided

11.10 + 0.1 Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list
intersection dia SPG check by operator 6 108
oversize Customer: O ring seat not properly 6 Spindle runout 2 Preventive maintanence

End User: Nil 1 Spindle speed & feed 2 Program locked


1) 11.10 + 0.1
intersection dia
6 3

Down stream operation: Nil 1 Form tool intersection dia undersize 3 Tool life monitoring provided
11.10 + 0.1
Establish tool change frequency and SPG check by operator 6 108
intersection dia Assy: NA 1 Build up edge 3
specify in Opn.std
undersize
Customer:O ring seat not properly 6 Wrong tool selection 2 Tool issue only as per tools list
Established cutting parameters and
End User: Nil 1 Improper feed/Speed rate 2
program locked
30U)M10 'O' ring
detail 6 3

Down stream operation: Nil 1 Wrong tool offset 2 Program locked


Chamfer Depth & 1.60 +0.4,45° & 12°
Angle ,depth over size / Assy: Nil 1 Tool wear 3 Tool life monitoring provided SPG check by operator 6 108
Undersize
Customer: Part cannot assemble 6 Wrong tool selection 2 incomining tool inspection

End User: Nil 1

6 3
Coolant secondary filter provided &
Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Establish tool change frequency and
Surface finish out of Assy: NA 1 Tool wear 2
Surface finish specify in Opn.std Inspection by inspector as per QCPC 6 108
spec
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper sealing
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure

30V) Side Milling 6 3


Down stream operation: Not able to
6 No machining Allowance 2 Insp. Done at casting stage
machine (non clearance)
Milling Height over size
Assy: NA 1 Wrong loading 3 Pokayoke provided 6 108
Gauge checked by operator
Customer:Assembly problem 6 Uneven clamping 3 Preventive maintanence
Established tool change frequency and
End User: Nil 1 Inserts worn out 2
specify in Opn.std
wrong tool offset 2 Program locked
1) Milling Distance
9.0+0.1/-.3 Established tool change frequency and
Build up edge 3
specify in Opn.std
6 3

Down stream operation: Nil 1 Bend in the casting 3 Insp. Done at casting stage
Milling Height under Guide pin available in fixture to guide the
Assy: NA 1 Wrong loading 3 Gauge checked by operator 6 108
size part while loading
Customer: May affect / disturb at
6 Uneven clamping 3 preventive maintanence
assembly
End User: Nil 1 wrong tool offset 2 Program locked

1 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked Inspection by inspector as per control
I) spot face dia oversize 6 18
plan
Customer: Nil 1 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list

1) DiameterØ16 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
30W) Spot facing

11
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

30W) Spot facing


II) spot face dia Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Inspection by inspector as per control
6 108
undersize plan
Established cutting parameters and
Customer: Bolt will not assemble 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3

Down stream operation: Nil 1 Coolant concentration 2 Program locked

2) Flatness l) Flatness out of Assy: Nil 1 Tool wear 2 Tool life monitoring provided First off inspection 6 108
specification
Established cutting parameters and
Customer: Part cannot assemble 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil

Assy: NA 1 Wrong tool offset 2 Program locked


I) Dia oversize Inspection by inspector as per QCPC 6 72
Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly
End User: degradation of secondary
6
function
Tool dia
11.50 & ø25.0
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Dia undersize Assy: NA 1 Wrong tool offset 2 Program locked Inspection by inspector as per QCPC 6 72
Customer: Seal will not enter Into the
6 Wrong tool selection 2 Tool issue only as per tools list
groove

End User: Nil 1


30X) Ø11.5 drill
and Ø25 spot face
6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil

Assy: NA 1 Wrong tool offset 2 Program locked


I) Depth oversize Receiver Gauge check by operator 6 72
Customer: Flow get affected due to
6 Wrong tool selection 2 Tool issue only as per tools list
improper sealing
End User: degradation of secondary
6
function
Height 64.1 ± 0.3

6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Depth undersize Assy: NA 1 Wrong tool offset 2 Program locked Receiver Gauge check by operator 6 72
Customer: May affect / disturb at
6 Wrong tool selection 2 Tool issue only as per tools list
assembly

End User: Nil 1

6 3

Coolant secondary filter provided &


Down stream operation: Nil 1 Coolant concentration 2 Before coolant top up, check coolant
concentricity through refractor meter
Surface finish out of Establish tool change frequency and
1) Surface finish Assy: NA 1 Tool wear 2 Inspection by inspector as per QCPC 6 108
spec specify in Opn.std
Customer:
6 Less Coolant flow 2 Failsafe alarm available in machine
Improper Sealing
End User: Nil 1 Spindle speed / Feed rate high 3 Program locked
Pressure indicator to check the clamping
Clamping pressure more or less 2
pressure
6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
30Y) Ø12 H9 Established cutting parameters and
Reaming Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Dia oversize Air plug gauge check by operator 6 108
Customer: Outlet valve will not assembe 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list
1) Diameter
Spindle runout 2 preventive maintenance
Ø12 H9
6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Air plug gauge check by operator 6 108
Established cutting parameters and
Customer: Outlet valve will not assembe 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Outer dia oversize Gap gauge check by operator 6 108
Customer: Part strengthen not good while
6 Burr entrapment into tool holder 2 Coolant spray in tool holder
running

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list

1) Outer ø 20 ± 0.1 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Outer dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Gap gauge check by operator 6 108
Established cutting parameters and
Customer: Leak during assembly 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Spindle speed / Feed rate high 3
program locked
I) Outer dia oversize Gap gauge check by operator 6 108
Customer: Valve will not assemble 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list

2) Dia 16 - 0.2 Spindle runout 2 preventive maintenance

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) Outer dia undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Gap gauge check by operator 6 108
Established cutting parameters and
Customer: Leak during assembly 6 Spindle speed / Feed rate high 3
program locked

End User: Nil 1

6 3
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
Established cutting parameters and
Assy: NA 1 Improper Spindle speed / Feed rate 3
program locked
I) width oversize Thickness Gauge check by operator 6 108
Customer: Outlet valve will not assembe 6 Burr entrapment into tool holder 2 Coolant spray in tool holder

End User: Nil 1 Wrong tool selection 2 Tool issue only as per tools list

3) width

6 3
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil

II) width undersize Assy: NA 1 Wrong tool selection 2 Tool issue only as per tools list Thickness Gauge check by operator 6 108

12
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

Established cutting parameters and


Customer: Play in Outlet valve assembly 6 Improper Spindle speed / Feed rate 3
program locked
End User: degradation of secondary
30Z) OD Forming 1
function
6 2
Down stream operation:
1
Nil
Built-up edge 2 Tool life monitoring provided
Assy: NA 1
I) Radius oversize Inspection by inspector as per QCPC 6 72
Cutting parameter established during
Customer: Seal will not assemble 6 Spindle speed & feed 2
trials and program locked
End User: degradation of secondary
6 Wrong tool selection 2 Tool issue only as per tools list
function
4) Radius (4 places)
R0.5 - 0.15
6 2
Down stream operation:
1
Nil
Tool wear 2 Tool life monitoring provided
II) Radius undersize Assy: NA 1 Inspection by inspector as per QCPC 6 72

Customer: Seal will not assemble 6


Wrong tool selection 2 Tool issue only as per tools list
End User: Nil 1

6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
5) Depth Assy: NA 1 Wrong tool offset 2 Program locked
II) Depth undersize Gap Gauge check by operator 6 72
8 Min
Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil

Assy: NA 1 Wrong tool offset 2 Program locked


I) Chamfer depth
Inspection by inspector as per QCPC 6 72
oversize Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly
End User: degradation of secondary
6
function
6) Chamfer depth
i) 0.8
6 2
Down stream operation:
1 Tool wear 2 Tool life monitoring provided
Nil
II)Chamfer depth Assy: NA 1 Wrong tool offset 2 Program locked Inspection by inspector as per QCPC 6 72
undersize
Customer: Seal will not enter Into the
6 Wrong tool selection 2 Tool issue only as per tools list
groove

End User: Nil 1

6 2
Down stream operation:
1 Build up edge 2 Tool life monitoring provided
Nil
7) Chamfer angle I) Chamfer angle more Pressure indicator to check the clamping
Assy: NA 1 Clamping pressure more or less 2 Inspection by inspector as per QCPC 6 72
ii)45° or less pressure
Customer: Seal will not assemble
6 Wrong tool selection 2 Tool issue only as per tools list
properly
End User: degradation of secondary
6
function
Functional Characteristic

7 3 Firstoff inspection 5 105

Down stream operation: Nil 1 Damage due to deburring 3 Trained Operator 200% Visual inspection 7 147
Handling damage while loading the Single setup and provided proper material
No damage Damage Assy: Nil 1 2 100% Visual inspection 8 112
machine handling in machine
Customer :
7 Clamping pressure high 2 Preventive maintenance Process audit 8 112
100% parts may have to be scrapped

End User: Nil 1

7 2 Firstoff inspection 5 70
Down stream operation :
1 Clamping pressure less/high 2 Preventive maintenance Process audit 8 112
Nil
No Tool mark Tool mark Customer : Establish tool change frequency and
7 Tool wear 2 200% Visual inspection 7 98
100% parts may have to be scrapped specify in Opn.std
Assy : Establish tool change frequency and
1 Build up edge 2 200% Visual inspection 7 98
NA specify in Opn.std
End user :
1 Jack supporting pressure low/high 2 None Preventive check and process audits 7 98
Nil
6 3 Firstoff inspection 5 90
30Y) Functional
Characteristic Down stream operation :
100% parts may have to be reworked 6 Coolant concentration not ok 3 None Checked once per day 6 108
offline
Free from Loose Customer :
Loose Burrs Optimize coolant flow during machining
Burrs 100% of production run may have to be 6 Coolant not flow 2 Process audit 7 84
scrapped. trials

Assy :
1
NA
End user :
1
Nil
6 2
Down stream operation :
Nil 1 Tool wear 2 Tool life Monitoring established

Ø1.75 min shoul pass Customer :


Ø1.75 did not pass 100% Gauge check by final inspector 6 72
through Ø3 drill Fuel flow get affected 6 Wrong Tool offset 2 Program Locked

Assy : Washing process developed with high


1 Imp solution blocked 2
NA pressure to remove all blockages
End user :
1
Nil
OPERATION NO. #40 Deburring

6 2 Firstoff inspection 5 60

As per established Air pressure indicated Monitoring the right pressure thru pressure
Down stream operation: Nil 1 Insufficient Air pressure 2 6 72
in OS gauge
Air cleaning of parts Free from presence of
40) Deburring & Customer:
to be free from burrs or coolant 6
Air cleaning a) Fails at performance testing Untrained operator 2 Trained operator Process audit 7 84
sharpe edge, burrs particles inside the
process b) Leads to White rust formation
and coolant particles component
Air pressure gauge level unknown to
Assy: Nil 1 2 Established air pressure used in line Process audit 7 84
operator

End User: Nil 1

OPERATION NO. #50 Washing

6 3

Down stream operation: Nil 1 Nozzle tip blockage 2 Preventive maintanence

Washing time fixed using sensor as per


Assy: Nil 1 Washing time less 2
customer requirement

I) Cleanliness not ok / Customer:


Firstoff inspection 6 108
Presence of loose burrs a) Affects part performance after Preventive check using burr removal and
6 Nozzle not fixed for that hole 2
assembling the part grease test analysis
b) Inconvenience while handling the part
PLC controller available /
End User: Nil 1 Water pressure low 2 Monitoring the water pressure gauge
every shift beginning by operator
Preventive maintanence/ Process Audit in
Filter not cleaned 3
PH monitoring check sheet
6 3

As per the given Down stream operation: Nil 1 Contaminated water (PH) 3 Water change frequency monitoring
50) Washing Cleanliness standard
16599 Firstoff inspection 6 108
ii)Contamination due to Assy: Nil 1 Oil skimmer not functioning 2 Preventive maintanence
Oil/ Dirt/ Coolant
Customer:
a) Affects part performanc after 6 Water not good 3 Water change frequency monitoring
assembling the part

End User: Nil 1

5 3

13
Action Results

Occurrence

Detection

Occurrence
Severity
Responsibility

Detection
Class

Severity
Process Function Potential Failure Potential Cause(s) / Mechanism(s) Recommended

RPN
Opn Process Seq Potential Effects of Failure Current Process Controls prevention Current Process Controls detection and target

RPN
Requirements Mode. of Failure Actions* Actions taken
completion date

Down stream operation: Nil 1 Mixer of coolant level high 3 None

Assy: Nil 1 Water temperature low 3 Preventive maintanence 100% check for white rust by final
iii) White rust 6 90
Customer: inspector
5 Contaminated water (PH) 3 Water change frequency monitoring
a)Poor outside side look of the part
Water change frequency not
End User: Nil 1 3 None
monitoring
Component kept at washing station Timing sensor available/ Heater available
2
for long to remove moisture
OPERATION NO. #60 Impregnation

6 3
Down stream operation: Leak due to
1 Resin concentration 3 As per established in OS
cavity unfill
Free from IMP Customer:
solution blockage / IMP solution blockage / a) Leak may occur 6 Untrained operator 3 Trained operator 100% checked by operator,
60) Impregnation Unwash / IMP Unwash / IMP b) Leads to White rust formation 100% IMP punch verified by final 6 108
concentration not concentration not good Clear identification to be followed inspector
good a) Punch mark provided on Ok parts by
Assy: Nil 1 Leak testing operation missing 3
machine before declamping
b) 200% Visual inspection
End User: Nil 1 Impregnation missing 3 Nil

OPERATION NO. #70 Leak testing

6 3

Single piece flow followup


a) Punch mark provided on Ok parts by
Down stream operation: Nil 1 Leak testing operation missing 2
machine before declamping
b) 200% Visual inspection

Parts failed in leak test getting mixed


Assy: Nil 1 2 Separate Red bin provided for Not ok part
up with good parts
Customer:
Leak test rig designed as per our
Component fails in leak test during 6 Not feasible to check leak 2
feasibility commitment
assembly, A portion of parts may scrap
Sensor available, if pressure get down
Leak testing pressure lesser than the from fixed minimum outlet pressure, 100% checked by operator, 100% Leak
70) Leak testing Free from Leak Leak at customer end End User: Nil 1 2 6 108
specification of 7 bar alarm will appear punch verified by final inspector

Untrained operator 2 Trained and specific person only alloted

Clamping not working 3 Preventive maintanence

Less time for leak testing 2 It controlled by PLC

Seal not as per customer seal 3 Aware of customer sealing

Identification for IMP is on part, the part


After IMP leak test not done 2
will get re-leak
Monitor seal life and mention seal
Seal getting damage 2
changing frequency in OS
OPERATION NO. #80 Washing

6 3

Down stream operation: Nil 1 Nozzle tip blockage 2 Preventive maintanence

Washing time fixed using sensor as per


Assy: Nil 1 Washing time less 2
customer requirement

I) Cleanliness not ok / Customer:


Firstoff inspection 6 108
Presence of loose burrs a) Affects part performance after Preventive check using burr removal and
6 Nozzle not fixed for that hole 2
assembling the part grease test analysis
b) Inconvenience while handling the part
PLC controller available /
End User: Nil 1 Water pressure low 2 Monitoring the water pressure gauge
every shift beginning by operator
Preventive maintanence/ Process Audit in
Filter not cleaned 3
PH monitoring check sheet
6 3

As per the given Down stream operation: Nil 1 Contaminated water (PH) 3 Water change frequency monitoring
80) Washing Cleanliness standard
16599 Firstoff inspection 6 108
ii)Contamination due to Assy: Nil 1 Oil skimmer not functioning 2 Preventive maintanence
Oil/ Dirt/ Coolant
Customer:
a) Affects part performanc after 6 Water not good 3 Water change frequency monitoring
assembling the part

End User: Nil 1

5 3

Down stream operation: Nil 1 Mixer of coolant level high 3 None

Assy: Nil 1 Water temperature low 3 Preventive maintanence 100% check for white rust by final
iii) White rust 6 90
Customer: inspector
5 Contaminated water (PH) 3 Water change frequency monitoring
a)Poor outside side look of the part
Water change frequency not
End User: Nil 1 3 None
monitoring
Component kept at washing station Timing sensor available/ Heater available
2
for long to remove moisture
OPERATION NO. #90 Air Cleaning

5 3
Down stream operation :
5 Air cleaning Pressure 3 Preventive maintanence
Nil
Heater time established, Timing sensor
90) Air Cleaning Air cleaning Free from moisture Assy : NA 1 Cleaning temperature 2 100% checked by final inspection 6 90
available

Customer : Nil 1

End User : Nil 1

OPERATION NO. #100 Drying

5 3
Down stream operation :
100% of production run may have to be 5 Heater Temperature not in spec 3 Preventive maintanence
reworked in station.
100) Drying Drying Free from moisture Heater time established, Timing sensor 100% checked by final inspection 6 90
Assy : NA 1 Heater Cycle time less 2
available

Customer : Nil 1

End User : Nil 1

OPERATION NO. #110 Final Inspection

5 3

Operator not aware of identifying the a) OJT for final inspectors


Parts free from visual Down stream operation: Nil 1 3
visual defects b) Operator traceability code on the part
defects like Sharp 6 90
edges, damages, tool No knowledge of customer a) Every complaint One point lesson 100% check by final inspection
110) Final Free from visual Assy: Nil 1 2
mark / chattering complaints displayed at final inspection station
Inspection defects
mark and blow holes, Customer:
5
damage and Cold a) Fails at performance testing
shut
End User: Nil 1

OPERATION NO. #120 Packing

5 3
1) Parts free from
1) No damage while Operator not aware of identifying the a) OJT for final inspectors
visual defects like Down stream operation: Nil 1 3
transporting visual defects b) Operator traceability code on the part
damages, white rust
2)Parts getting mixed 100% check by final inspection 6 90
120) Packing 2) Free from part mixup Assy: Nil 1 Part getting mixed up 3 Only one variant running at that time
up
Customer:
5
a) Fails performance testing
End User: Nil 1

Special Characteristics Symbol: Critical Characteristics Major Characteristics

*Priorites for determining recommended action: 1) Severity ≥ 8 ; (OR) 2) Detection > 6 ; (OR) 3) RPN ≥ 125
F/PED/04-M; Rev No.1; Dated: 25.02.2010

14

You might also like