Executive Summary Report

Site Akal, Rajasthan 220 KV SS

Date 13.03.2020

Sr. No. M/c Detail Dir. No Particuler Cause Photos Remarks Order Details

1 OC/EF HS was on directional It should be on Non-directional Corrected.

EF HS pickup value was high as OC i.e


2 Reduced to 2.5 Amps. Corrected.
4 Amps.

Remote tap indicator and LV WTI not


3 working. needs to analyse yet. Need to fix.

1 TR 1

4 Both WTI Not working. Capilary machanism problem Need ro replace unit.

Buchholz cable gland abnormal Buchh. Contacts alredy filled with


5 mounted. clay. Needs waterproofing fix.

6 Worst oil leakage from cooling inlet fix yet to be done.

OLTC OTI Trip mechanism rod


1 need to replace.
abnormal.

2 TR2

1. R & B Breaker pole it self not


HV Breaker needs serious service on getting trip sometimes.
2 2.AC Main MCB Faulty. Pls take NA ASAP.
priority basis.
3.DC MCB 1 Faulty.
4, Contactor A16 Faulty.

1 B Phase Breaker not geeting Trip. Problem with Mechanism it self. Need to attend on urgent basis.

3 Line 2

Isolator's Y phase fmale connector


2 burnt bluntly. Needs to rectify fix activity yet to attend.

END