Bectochem: Consultants & Engineers Pvt. LTD
Bectochem: Consultants & Engineers Pvt. LTD
Bectochem: Consultants & Engineers Pvt. LTD
Model:
TIPPER- 250 KG
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
Dear Sir,
Thank you for the opportunity to bid for the above equipment, following to our recent discussion I
have a pleasure in providing our technical and commercial proposal in accordance with your
requirements.
As you may be aware, Bectochem Consultants & Engineers Pvt. Ltd. has significant experience in
providing end to end engineering solution to the global pharmaceutical market which includes
various models and sizes of Sievers, Mills, Blenders, Fluid bed driers, Fluid bed processor, Syrup
tanks, Vessels, Autocoaters, Various imported valves even for stringent requirements, RTPs,
Pneumatic Vibrators, Isolators, Compression machines, Continuous liner systems, complete
granulation line, Packing machines, CIP WIP machines, Homogenizers for various applications.
We strive to provide continuous improvement in our quality and customer satisfaction, supplying
right first time and on time with fast manufacturing lead times. We trust that you will find the
details to your satisfaction, however for further queries please don’t hesitate to contact us.
Yours Sincerely,
MAYUR HEDAOO
Tel : (91) 22-28500008/2850 0057/2850 2400
Fax : (91) 22-2850 6785
Mob : (91) 9167390040
E-mail: mayur@bectochem.com , sales@bectochem.com
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
SECTION A: INTRODUCTION
This is a technical specification and offer made to M/S. Daily Needs Ltd. a/c Elomatic Pharmalab
from Bectochem Consultants & Engineers Pvt. Ltd. for purpose-designed TIPPER 250 KG For
discharging product from the Fluid Bed Container to a down stream unit.
The proposal document covers the following equipment, detailing the proposed technical
specifications, our general specifications, options, suggestions and our commercial offer:
TIPPER - 250 KG
A2: NON-COMPLIENCES/DEVIATIONS
N.A.
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
TIPPER is a versatile machine developed for discharging product from the Fluid Bed Container
to a down stream unit.
B1.2: USE:
The equipment shall handle a 250 KG FBD bowl consisting pharmaceutical raw material &
carry it up to specific height.
B1.3: CAPACITY:
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
4.6 Main Control Panel Independent MCP, the MCP will be powder coated and
housed in a remote location. MCP houses Contactor,
Overload Relay,
4.7. Operation controls The standard machine controls are Push Button Panel
(PBP)
The basic machine uses a dedicated panel with relay
logic controls with a control voltage of 230 V AC unless
otherwise specified.
The machine has the following controls:
Emergency Stop (Push to operate, twist to release)
Lift UP Push and hold
Lift Down
Tilt Down
Tilt Up
4.8 Interlocks The unit motion will be governed by Limit switches.
There are three switches for UP, Down and for
Lowered position over the upstream unit, e.g. Mill.
Over Load Protection Relays : Yes
Position sensors :Limit Switch
5 MATERIAL OF CONSTRUCTION
Product Contact Parts SS 316
Other Parts SS 304 / Cladded as GMP compliant Model
6 FINISH
Internal 240 Grit mirror
External SS Parts: 240 grit mirror polish.
MS Parts: 180 grit mat polish.
7 UTILITY REQUIRED
Power Supply 415 V / 50 Hz/ 3 Phase
Total Load 1.5 KW
Cable Size 1.5 mm2 Cu 4 Core
8 GENERAL DETAILS
Free space required Minimum 1 M From all sides
9 DOCUMENTATION Material Test certificate for contact parts
Installation & Maintenance Manual
GA
Spare Part List
Warranty Certificate of machine
Certificates, Manual for Bought out items
Electrical Circuit Diagram
Instrument list with manufacturers’ calibration
certificate.
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
10 INSPECTION Client
11 TRIAL No Load Running Trial for 1/2 Hours
No Stagewise Inspection Will be offered.
12 PACKING DETAILS Wrapped in Plastic.
Packing Size: 29 x 29 x 165 (L x W x H) (inches)
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
INCLUDED IN NOT
ITEM DESCRIPTION
SCOPE INCLUDED
1 Prepare a detailed scope of VTOP works document
2 Detailed design
3 Manufacture of equipment
4 Assembly and out-fits
5 Preparation and execution of FAT protocol
6 Compilation of technical construction file
7 Compile O & M manuals
8 Crating and shipping equipment
INCLUDED IN NOT
ITEM DESCRIPTION
SCOPE INCLUDED
1 Supervision of/or Installation of equipment at site
2 Assist with /or Commissioning & equipment start-up
3 Provide operator training on equipment
4 Commissioning, testing & execution of SAT protocol
5 IQ/OQ Validation
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
The said product will be fully built-up at Bectochem works, prior to dispatch to site with all
ancillary items and equipment.
A full FAT will be carried out before strip-down for packing. Final client attendance, inspection
and approval is required at this stage.
The equipment will be packed in cases suitable for delivery to the job site or the INCO term
mentioned in the commercial section.
Note: Client will be responsible for off-loading and storage of the equipment at site.
Cost for on-site supervisory installation of this equipment is listed in commercial section of
this document. This would be carried out by our own installation team and includes
mechanical installation of this product and associated equipment, if any.
We have provided an itemized cost for on-site commissioning and testing of the equipment is
listed in the commercial section of this document. After start up and commissioning a full SAT
ill be executed to agreed protocols.
B2.8: TRAINING:
We have included for training as a part of itemized pricing. Training will be carried out at site
post SAT stage.
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
B3: DOCUMENTATION
ITEM DESCRIPTION
1 Material test certificate for contact parts
2 Surface Finish Test report
3 Installation & Maintenance Manual with Spares List
4 Warranty Certificate of machine
5 Certificates & Manuals of bought out items including calibration
6 Electrical Circuit Diagram
7 GA and P&ID
ITEM DESCRIPTION
1 Functional design Specifications FDS
2 Design Qualification DQ
3 Quality Assurance Plan QAP
4 Factory Acceptance Test FAT
5 Functional design Specifications PLC FDS
6 PLC ladder logic
7 IQ&OQ Protocols [Format only]
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
A comprehensive Installation and Maintenance Manual shall be produced for each machine
provided by Betochem Consultants and Engineers Pvt. Ltd. This shall consist of following:
1. General Information
3. Equipment Maintenance
6. Warranty Statement
One hard copy of the manual shall be provided to the client (In English) further hard copies
and electronic copy can be provided at additional cost.
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
250 KGS
SR.
Specification
MODEL
Unite Price
NO.
FOB, MUMBAI PORT (in USD)
1 COST OF SYSTEM WITH POWER PACK 2 HP
FBD TIPPER
Ht 4.5 Mtr
Detailed Documentation
OPTIONS
Swing System
2 With bottom Bearing Housing 2,150
Acutated Butterfly Valve
3 1,750
Auto Swing
4 2,750
Flameproof System
5 1,450
Detailed Documentation
6 Included
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION
DOCUMENT NO.:
BCEPL/DAILY NEEDS/TIPPER-250 PROPOSAL DOCUMENT
KGS/Q- 11650/20.07.2011/11-12 FOR
OFFER NO.: TIPPER 250 KG
DATE: 23-Jul-11
Q-11650
GLIMPSE:
Prepared By: JAGANDEEP KAUR DATE: 23 July 2011 Checked By: MAYUR HEDAOO
PRIDE IN EVERY ACTION