Professional Documents
Culture Documents
Unit 3: Scope Management (Pmbok: Guide, Chapter 5)
Unit 3: Scope Management (Pmbok: Guide, Chapter 5)
Scope management ensures that a project includes all the work required but only the
work required to complete the project successfully. In other words, proper scope
management carefully identifies what is and what is not included in the project. The
following six processes comprise scope management and course slide #3-1 also
provides an overview of scope management.
Major Processes
5.1 Plan Scope Management (creating a scope management plan that documents
how project scope will be defined, validated, and controlled)
5.2 Collect Requirements (defining and documenting stakeholders’ needs to meet
project objectives)
5.3 Define Scope (developing a detailed description of the project and product)
5.4 Create WBS (subdividing project deliverables into smaller components)
5.5 Validate Scope (formalizing acceptance of completed project deliverables)
5.6 Control Scope (monitoring status of the project and product scope, and managing
changes to the scope baseline)
• Product scope: The features and functions embodied in the product, service,
or result. Product scope is measured against the product requirements
(Sections 5.2 and 5.3: Collect Requirements and Define Scope).
• Project scope: The management activities required to deliver the product,
service, or result. Project scope is measured against the project
management plan (Section 4.2).
The scope baseline consists of the approved versions of the project scope statement,
the WBS (work breakdown structure), and the WBS dictionary. The approved scope
baseline should only be changed using formal change control procedures. The
approved baseline is the basis for deciding whether scope requirements are being met
(especially relevant during the processes for validating and controlling scope).
The scope management plan documents how project scope will be defined, validated,
and controlled. In essence, it provides guidance on how the other five scope
management processes are to be accomplished.
Four Key Inputs for Plan Scope Management (PMBOK® Guide, p. 108):
2. Project Charter: Described in the PMBOK® Guide, p. 66, Section 4.1, the
charter provides high-level project and product requirements. As such, it forms a
starting point for the development of detailed requirements.
• Organizational culture
• Infrastructure (resource availability)
• Personnel administration
• Marketplace conditions
Two Key Tools for Plan Scope Management (PMBOK® Guide, p. 109):
2. Meetings: The project manager, sponsor, selected team members, and other
selected stakeholders may attend meetings to develop the scope management
plan.
Two Key Outputs for Plan Scope Management (PMBOK® Guide, p. 109):
Collect Requirements
4. Project Charter: Described in PMBOK® Guide, p. 66, Section 4.1, the charter
provides high-level project and product requirements. As such, it forms a starting
point for the development of detailed requirements.
4. Group Creativity Techniques: The following examples are all ways for
groups to generate ideas about any desired topic. In this case, the groups are
identifying and documenting requirements.
• Brainstorming: A group-oriented technique for quickly generating
ideas about both project and product requirements.
• Nominal Group Technique: An enhanced version of brainstorming
which includes voting and prioritizing the group’s ideas.
• Idea/Mind Mapping: The non-linear diagramming of different ideas in a
group into a single map for the purpose of highlighting agreements and
differences and also generating new ideas.
• Affinity Diagram: A technique for sorting a large number of detailed,
specific ideas into logical groups.
• Multicriteria Decision Analysis: Uses a decision matrix to establish
and apply criteria such as risk levels and uncertainty.
6. Questionnaires and Surveys: Written sets of questions that help reach large
audiences quickly and also enable statistical analysis of data.
10. Context Diagrams: Context diagrams are visual depictions of product scope
such as processes, equipment or computer systems. The diagram shows how
various entities (people and other systems) interact to produce inputs and
outputs.
• Business
• Stakeholder
• Solution (product, service, or result)
• Project
• Transition
Scope definition produces a written, detailed scope statement that is crucial to project
success. This statement represents an agreement between the project team and the
customer and defines which requirements collected earlier will actually be included in
the scope and which will be excluded. The project team and appropriate stakeholders
conduct a needs assessment and use it as the basis to develop written project
requirements. Assumptions, constraints, and risks are identified and validated as
necessary. The level of uncertainty (difficulty) in defining scope will naturally be greater
with more complex projects.
Define Scope
2. Product Analysis: This tool is helpful when the project is producing a product
rather than a service or other result. These techniques help translate project
objectives into measurable deliverables and requirements. Examples of these
techniques include product breakdown, requirements analysis, systems
engineering, value engineering, and value analysis. Project engineers use these
techniques to better understand and develop product requirements.
• Stakeholder register
• Requirements documentation
• Requirements traceability matrix
Key points:
• The WBS subdivides the work into smaller components (this process is
called decomposition). Each descending level of the WBS represents an
increasingly detailed description of the work.
• Tasks (items) at the lowest level of the WBS are called work packages.
• The work package is the level at which the work can be adequately
scheduled, cost estimated, monitored, and controlled. Accurate work
packages are a major factor in accurate project planning.
• The recommended size of a work package is 80 hours.
• A detailed description of each work package is contained in a WBS
dictionary.
• A code of accounts provides a unique numerical identifier for each task in
the WBS. Similarly, a chart of accounts groups project expenses into
specific categories for the accounting system in the performing
organization. Even though this distinction exists, some people use the
terms interchangeably.
• An OBS (organizational breakdown structure) shows which work
packages have been assigned to which organizational units.
• An important benefit of decomposing the project into smaller components
is that project participants are forced to carefully think through all aspects
of the pending effort. This process reduces the chance that activities
might be overlooked during the initial planning.
Create WBS
1. Scope Management Plan: Specifies how to create the WBS from the
detailed scope statement (previous process) and how to maintain the WBS
throughout the project.
• When all detailed work is rolled up into higher levels, all the
work should be accounted for (PMI refers to this as the 100%
rule).
• Work should be decomposed to a level at which:
• It can be accurately estimated.
• It is not logical to subdivide it further.
• Individual responsibility can be assigned.
• Different deliverables can have different levels of decomposition (one
deliverable may be at level 4 while another is at level 6). Course slide
#3-5 shows an example.
The PMBOK® Guide indicates that the first level of decomposition can be
displayed in the following ways:
• Major deliverables
• Major subprojects done by organizations outside the project team
• Phases of the project life cycle
• Hybrid mixtures of all the above (e.g., phases at the first level of
decomposition and then deliverables within each phase)
• WBS:
The WBS is a hierarchical decomposition of the total scope of the
work and includes:
See course slides #3-2 through #3-6 for more WBS information.
Scope validation is the process of obtaining formal acceptance of the project scope by
stakeholders. It involves reviewing work results to see whether tasks were completed
correctly. If a project is terminated early, scope verification should document the extent
of the work completed. Scope verification differs from quality control in that verification
is primarily concerned with acceptance of the work whereas quality control is primarily
concerned with correctness of the work. Quality control is usually performed slightly
ahead of verification, but the two processes may overlap somewhat.
Validate Scope
This process monitors the status of project and product scope and also manages any
changes to the scope baseline. This process uses integrated change control to deal
with all requested changes and recommended corrective or preventive actions. As
described in the integrated change control process, scope change control is concerned
with:
Control Scope
1. Project Management Plan: The scope baseline is the object being controlled
and it consists of the scope statement, WBS, and WBS dictionary. Other
relevant portions of the project management plan include the scope, change,
configuration, and requirements management plans.
4. Work Performance Data: Relevant work performance data at this point may
include the number of change requests received, number of requests accepted,
and the number of deliverables completed.
Self-Study
Drill Practice: Scope Management
Question Answer
4. What is the difference between product 4. Product scope is the features and
scope and project scope? functions designed into the product or
service (measured against product
requirements). Project scope is
management activities performed by the
team (measured against the project
management plan) (p. 3-1).
8. As used in a WBS, what does the term 8. A cost category that represents the
“cost account” mean? work assigned to a single responsible
organizational unit, i.e., the lowest level in
the WBS at which organizational
responsibility is assigned. Also called a
control account (p. 3-14).
10. What role do stakeholders play in 10. Defining stakeholders’ needs is the
collecting requirements? primary purpose of the process called
Collect Requirements. Knowing who the
stakeholders are and interviewing them in
various ways is how requirements are
documented (pp. 3-3 and 3-5, inputs #3 & #5).
12. How does an OBS differ from a WBS? 12. OBS = Organizational breakdown
structure and is used to show which work
elements (tasks) have been assigned to
which organizational units (p. 3-11)
13. Activities at the lowest level of the 13. work packages (pp. 3-11/13)
WBS are referred to as ______.
16. What is the difference between scope 16. Scope validation is primarily
validation and quality control? concerned with acceptance of the work;
quality control is concerned with the
correctness of the work (p. 3-15).
17. What is scope control (the formal 17. Monitoring the status of the project
name of the process is control scope)? and product scope and managing changes
to the scope baseline (p. 3-17)
20. What is the scope management plan? 20. Documents how project scope will be
defined, validated, and controlled (pp. 3-1/3)
21. What two important issues does 21. As part of control scope:
performance measurement deal with?
a ) Identifying the magnitude of variances
(plan versus actual)
22. Change requests are outputs for 22. Validate scope and control scope.
which two scope management processes? Change requests may be issued as a
result of either of these activities and
should be handled using integrated
change procedures (pp. 3-16/18).
25. What are the inputs for collect 25. The scope management plan,
requirements? requirements management plan,
stakeholder management plan, project
charter and stakeholder register (p. 3-5).
26. What is the Code of Accounts and 26. A numbering system used to identify
what is another name for it? each element of the WBS. Also known as
a Chart of Accounts (pp. 3-11/14).
27. What is a requirements traceability 27. A table that links each requirement to
matrix? its origin such as business needs or
opportunities, project goals, etc. (p. 3-8)
28. What is the scope baseline composed 28. The scope statement, the WBS, and
of? the WBS dictionary (pp. 3-13/14).
30. Changes in the scope may affect the 30. scope, schedule, and cost. (p. 3-19,
other components of the triple constraint. output #3, control scope)
The triple constraint of project
management includes __________.