Professional Documents
Culture Documents
Idc-000-Mgp-Onp-Pro-005518en-01 Weld Numbering
Idc-000-Mgp-Onp-Pro-005518en-01 Weld Numbering
[Subject]
[Status]
[Comments]
PROCEDURE FOR WELD NUMBERING
CONTENT
1.PURPOSE AND SCOPE 3
2. TERMS, DEFINITIONS AND ABBREVIATIONS 3
3. ARRANGEMENT OF PROCESS AND WORK EXECUTION METHOD 4
3.1 Welding of the main pipeline, industrial welding for HDD 4
3.1.1 General provisions 4
3.1.2 Tie-in of the main pipeline 5
3.1.3 Temporary Joints 6
3.1.4 Cut pipe sections / re-weld 6
3.1.5 Repair of the joint 7
3.1.6 Joints of special structures requiring separate production 8
3.1.7 Crossings with water bodies, motor roads and railways 9
3.1.8 Pipelines, fittings of process units and block valve stations 9
3.1.9 Changing the weld designation and removing the weld 10
3.2 As-built Information 11
4. PRODUCTION SAFETY REQUIREMENTS 11
5. GENERAL FIRE SAFETY REQUIREMENTS 11
6. ENVIRONMENTAL REQUIREMENTS 12
7. RESPONSIBILITY 12
7.1 Head of Construction and Installation Department 12
7.2 Head of the Spread Welding Section 12
7.3 Welding Engineer 12
7.4 Welding Master 13
Training on the practical application of the welded joint marking system 13
8 REFERENCES 14
9 APPENDIX 15
APPENDIX 1 16
APPENDIX 2 17
APPENDIX 3 18
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT: Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 3 of 18
Procedure for weld numbering
This Procedure defines application procedure for welds numbering and marking at
the linear part of "Transmission gas pipeline (interconnector) "border of Bulgaria – border
of Hungary" for preparation of reports and records, as well as alignment of such elements
to the known coordinates on a map. Accordingly, each permanent weld shall be followed
at all stages of the welding process and non-destructive testing.
Combined plans-sections of the pipeline approved for construction shall constitute
a basis of the system of pipeline elements designation. For the purposes of this
Procedure, 1 (one) kilometer equals 1 (one) section, thus, section 85 starts at KP 85 +
000.00 and continues until KP 85 + 999.00. The designation of each section is numerically
conducted (from 0) with the corresponding designation in kilometer points (from 0 +
000.00). All numbering of welded joints, consisting of the kilometer number and the seam
number, shall not be repeated and shall be determined by the terrain data and
abbreviations listed in this Procedure. The kilometer number shall be used in the reporting
documentation for all welded joints of the pipeline. Joints ырфдд рфму sequencing
numbers, starting at 10 for each kilometer. Tie-in joints shall include T prefix. General
view of the welded joints numbering system is specified below, however, the numbering
system is described in detail in Appendices 1, 2 and 3.
Example of joint numbering for pipes with a diameter of 48 inches
Pipeline start Kp 0
SPREAD
Pig receiver OPF 1C 0
Kp Kp 1
Match line
END PLUG - A lid covering the open ends of the pipe string.
CUT OUT - a defected joint cut from a pipe.
PISTON - Self-propelled device mounted inside the pipeline.
POSITIVE FLOW (+ ve) - flow direction along the medium flow.
NEGATIVE FLOW (-ve) - low direction against the medium flow.
HSE Health Safety Environment
AFC Approved for construction
ML Construction of main pipeline
KP Kilometer point
RDX Asphalt road crossing
RVX Water course crossing
BVS Block valve stations
SF Marking of the weld, requiring separate manufacturing (pre-assembly).
C Cutting-out
ROW Right of Way
W Temporary weld
R Repair weld
TDC Top dead center.
FOC Fiber optic cable
HDD Horizontal directional drillling
NDT Non-destructive testing
RT Radiographic (X-ray) testing
UT Ultrasonic testing
SL Scraper launcher
SR Scraper receiver
PWS pipe-welding station (area for pre-assembly of parts)
NDTL Laboratory of Non-Destructive Testing
joint number and the pipe number shall be applied manually with indelible paint or an
indelible white or yellow marker on the outer surface of the pipe insulation at the 1 o'clock
point, approximately 500.00 mm + ve from each joint. Sequential numbering of the joints
shall be arranged, where possible, in the direction from –ve to + ve. The height of numbers
and letters shall be 50.0 mm. In the place for VISUAL CONTROL marks, a rejection mark
shall be put instead of OK, if a joint is recognized to be nonconforming to the
requirements, the area requiring correction shall be also outlined. All numbers assigned
to the joints shall be the same as those inscribed on the pipe by a welding inspector at
the welding work site.
3.1.2 Tie-in of the main pipeline
Construction engineer (technologist) for welding shall be present at all sites
where the tie-in welding is carried out at the main pipeline, and start numbering and
shall put a mark at each joint.
Numbers, specifying the location of a joint of a tie-in and pipes, shall be
manually applied with white or yellow indelible paint on the outer surface of the pipe
insulation at the 1 o'clock point, approximately 500.00 mm +ve from each joint.
Sequential numbering of the joints at the place of tie-ins shall be in the direction
from –ve to + ve and shall be determined by the closest number of the joint on the main
pipeline in the –ve direction. The height of numbers and letters shall be 50.0 mm. Ref.
to Appendix 3 Weld Marking
The welding engineer, who controls the numbering of the tie-ins of the main
pipeline, manually marks approximately 500.0 mm + ve from each tie-in joint at the
1 o'clock point on the right of way. The identification numbers of the welders who
performed the welds shall be filled in into the cells.
The left and right sides of the pipeline are those that face + ve:
right side Side of the right of way (working)
left side Side of the trench (piled soil)
Unplugged pipe string ends shall be marked. Plugs of the approved design shall
be installed at the open ends of the pipe string.
In some areas, more than one weld is required to join two free pipe ends or pipe
strings. Such joints shall be indicated by the last joint number of the main pipeline –ve
direction, but with addition of the letter suffix ML1T1, ML2T1, ML3T1, etc.
For tie-in joints for the pipeline sections, sequential numbering shall also be
used as on the main pipeline in the direction from –ve to +ve.
All cut off or excess parts of the pipe shall be labeled, including the pipe number
with index, length and wall thickness, placed on both inside and outside of the cut or
excess part of the pipe prior to removal from the right of way.
A tie-in of original pipe can be fabricated on the site to take into account conditions
of tie-in welding. If a pipe is cut from the original pipe (initial pipe), then the resulting two
pipes shall be designated pipe No. 1 and pipe No. 2, respectively. All other parts to be
cut off from pipe section 1 or 2 are designated pipe No. / 3 (or pipe No. /4, etc.). The
welding engineer shall ensure that the designations of all the cut pipe parts are transfered
before cutting the pipe. These designations include new length data and shall be recorded
in the cut pipe logbook in accordance with Appendix No. 4.
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT: Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 6 of 18
Procedure for weld numbering
If, for example, the number of the weld S146 ML 17 to be cut, the designation of
the replacement weld will be S146 ML 17C, after cutting the section with this new joint
(17C), the second joint will be designated S146ML17C2.
If the joint shall be removed when changing the project, then the letter E shall
be placed in front of the number.
The welding engineer records in the daily report data on all the cut joints, as if
they were production joints. The prefix C shall be added to the number marked earlier on
the pipe, and a new one is applied next to the original marking of the welders. Data in the
original marking shall be deleted.
The welding engineer shall manually add the prefix C to the indicated marking.
The identification numbers of the welders who have been welding the cut area shall be
filled in into these cells. Each marking shall indicate stamps of welders performed welding
on the left or right side of the pipeline.
The left and right sides of the pipeline are those that face + ve:
right side Side of the right of way (working)
left side Side of the trench (dump soil)
The inspector shall be obliged to carry out a visual inspection of all finished joints
and make a decision on suitability or unsuitability in accordance with the requirements of
coding and specification. The inspector is obliged to make a mark about the suitability of
a joint after visual inspection, putting the following data on the pipe next to the table
containing the symbols of the welders:
NOTE: When rejecting a weld profile, a mark on failure to pass VISUAL CONTROL shall
be put and the area subject to correction shall be outlined.
If after cutting the joint S116 ML 2 it is necessary to insert a spool, the new welding
joints will receive the numbers S116 ML 2C and S116 ML 2A, respectively (in the direction
from –ve to + ve). All inspectors are required to put signs and enter data from all sections
of the pipeline or cut-off joints in the daily report.
3.1.5 Repair of the joint
If it is necessary to perform the first repair on the joint, then the prefix R is
added to the original joint number. Example of designation of a repair weld: 10 ML
51R, the letter R designates the first repair.
Areas with multiple defects on the same joint shall be designated for reporting
purposes as D1, D2, D3, etc., in a clockwise direction.
A person responsible for the control of repair joints shall be present when all sites
with repair joints are removed and in the process of marking the defective areas, if they
are found, and all the data shall be recorded in the welding logbook.
The welding engineer shall manually add an additional cell to the existing marking.
Data of the welder who performed the repair of the weld shall be filled in this cell.
The left and right sides of the pipeline are those that face + ve:
right side Side of the right of way (working)
left side Side of the trench (dump soil)
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT: Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 8 of 18
Procedure for weld numbering
The inspector shall be obliged to carry out a visual inspection of all finished repair
welds and make a decision on suitability or unsuitability in accordance with the
requirements of coding and specification. The inspector is obliged to make a mark about
the suitability of a joint after visual inspection, putting the following data on the pipe next
to the table containing the symbols of the welders:
VISUAL CONTROL OK or REJECTED
FULL NAME/SIGNATURE XXX
DATE XXX
NOTE: When rejecting a weld profile, a mark shall be put in place of the VISUAL
CONTROL and an area that requires re-fusing of a joint or other repair shall be outlined.
3.1.6 Joints of special structures requiring separate production
In areas of welding, where pipeline sections cannot be labeled as permanently
installed items according to the classification described above, special symbols shall be
used for such sections.
The welds in such areas shall not change the initial designation; however, the
place of their installation on the main pipeline shall be marked for traceability purposes.
Special structures are pipe layouts consisting of one or several welds that could
not be welded during the welding of the main pipeline (moving sections), but which at
some stage during construction form a whole with the permanent part of the pipeline. If
it becomes necessary to move the special design in an intact form to another area, the
designation of the special design always remains the same. When it is finally installed in
place, regardless of the length, kilometer point designation shall be assigned to the tie-in
(and X-ray photograph) according to the designation of the main pipeline.
The weld number of the special structure shall be applied manually to the outer
surface of the insulated pipe at a distance of approximately 500.0 mm + ve from each
weld at the “1 hour” point. The height of numbers and letters shall be 50.0 mm.
The use of seams of special structures shall be limited to the cases specified
above.
The work engineer (master) for welding shall manually apply a mark at a distance
of one meter + ve from each weld at the “1 hour” point. The identification numbers of
welders performing the welds shall be specified in these tables. Each marking shall
indicate stamps of welders performed welding on the left or right side of the pipeline.
The left and right sides of the pipeline are those that face + ve:
right side Side of the right of way (working)
left side Side of the trench (dump soil)
The inspector shall be obliged to carry out a visual inspection of all finished welds
of specifal structures and make a decision on suitability or unsuitability in accordance with
the requirements of coding and specification. These welds shall be numbered
sequentially and shall have the same designation as the original ones, but with the prefix
SF added to the weld number. Example of special structure weld 42 SF1 / 1, etc.
The inspector is obliged to fill in cell with welders data and make a mark about the
suitability of a joint after visual inspection, putting the following data on the pipe next to
the table containing the symbols of the welders:
DATE XXX
NOTE: When rejecting a weld profile, a mark on failure to pass VISUAL CONTROL shall
be put and the area subject to correction shall be outlined.
3.1.7 Crossings with water bodies, motor roads and railways
In all areas where these intersections are made, the manufacturer of the welding
work shall be present and the procedure for marking the welds shall be started. The
inspector is obliged to apply a full designation of each weld near the crossing weld.
Depending on the physical location of the crossing in front of the weld number, the prefix
shall be defined, determined by the category indicated on the combined profile plans
approved for construction.
Prefixes RDX, RVX, RLX shall be placed after km/KP and before the actual weld
number, for example:
25 RVX3 / 1, 2 etc.
The welding engineer for crossings shall prepare a daily welding report in
accordance with the Welding Procedure No. IDC-000-MGP-ONP-PRO-005503EN. In
this report, the number of the pipe joining section, the weld number, pipe number, pipe
diameter and wall thickness, welder identification number, welding procedure used and
welding part number of welding consumables shall be indicated for all welds. The
inspector shall carry out a visual inspection of all the finished joints and make a decision
on whether or not it is in accordance with the requirements of the coding adopted in this
procedure. The scheme of the physical location of the crossings with the length shall be
drawn up.
The work engineer for welding shall manually apply a mark at a distance of one
meter + ve from each weld at the “1 hour” point.
The identification numbers of welders performing the welds shall be specified in
cells. Each marking shall indicate stamps of welders performed welding on the left or
right side of the pipeline.
The left and right sides of the pipeline are those that face + ve:
right side Side of the right of way (working)
left side Side of the trench (dump soil)
The inspector is obliged to fill in table with welders data and make a mark about
the suitability of a joint after visual inspection, putting the following data on the pipe next
to the table containing the symbols of the welders:
NOTE: When rejecting a weld profile, a mark on failure to pass VISUAL CONTROL shall
be put and the area subject to correction shall be outlined.
3.1.8 Pipelines, fittings of process units and block valve stations
At the sites defined by the project along the pipeline route, block valves and
scrapers traps shall be installed. These installations require the installation of a process
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT: Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 10 of 18
Procedure for weld numbering
pipeline, which can be prepared in advance in the workshop and then mounted on the
corresponding section of the pipeline.
The marking procedure begins with the welding engineer at the station or
workshop with the pre-assembly.
The welding engineer is obliged to apply a full designation of each weld near the
joint. Depending on the physical location of these units in front of the weld number, a
prefix shall be defined, which is determined by the category of this unit, indicated on the
combined profile plans approved for construction. The following prefixes BVS, SL (scraper
launcher) or SR (scraper receiver) shall be applied before the spread number and before
the actual weld number. Examples:
NOTE: When rejecting a weld profile, a mark on failure to pass VISUAL CONTROL shall
be put and the area subject to correction shall be outlined.
3.1.9 Changing the weld designation and removing the weld
If it is necessary to change the designation of the weld, x-ray flaw detection shall
be performed under a new designation.
Flaw-detective X-ray photograph and report of the X-ray with a new designations
shall be put in the box showing the developed radiofilm, the initial
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT: Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 11 of 18
Procedure for weld numbering
film and report shall be removed. The initial X-ray photograph shall be stored in
the NDT laboratory of CONTRACTOR. The cross reference of the weld designations shall
be given in the initial report on the decoding of the flaw detection image and the flaw
detection image report, which replaces it.
In case of deletion (cutting) due to a change in the design or installation that was
previously included in the reports, the replacement weld number has the suffix “C”.
3.2 As-built Information
The final as-built information in the welding logbook shall contain the marking of
the kilometer points every 100 m against the nearest weld to the processing installation,
and after the survey, the as-built data and coordinates of the tie-ins shall be aligned
(correlated) compared to the actual pipe lengths in each layout. The welding logbook,
reports on the quality of welding works and other necessary as-built information will be
transferred to EMPLOYER as part of the package “as built” after the completion of the
work.
Safety measures for local work conditions shall be developed by the company
using welding materials in accordance with the industry’s regulatory and technical safety
documentation.
Security measures shall be approved by the head of the company.
In order to avoid accidents during preparation, storage, transportation of materials,
persons performing work shall be provided with personal protective equipment.
Before admission to work, production personnel performing calcining, storage and
transportation of welding materials shall be trained in the safe conduct and pass the
knowledge assessment test. Knowledge assessment shall be documented by a record in
special logbook and in the certificate.
Prior to commencement of work, persons authorized to perform them shall
undergo safety instructions.
6. ENVIRONMENTAL REQUIREMENTS
When designing any facility, its environmental impact assessment (EIA) shall be
performed both at the construction stage and at the operation stage. Environmental
legislation provides for various forms of control over the documentation prepared for
compliance with environmental requirements. For this purpose, specially authorized state
bodies in the field of environment protection carry out state environmental impact
assessment, approve documentation and materials, define limits and standards for
environmental management, issue permits and licenses. To assess compliance with
environmental requirements, there is a system of environmental regulations.
• Maximum Permissible Emission - emission of harmful substances into the
atmosphere, established for each source of air pollution, provided that the surface
concentration of these substances does not exceed the maximum allowable
concentration.
• Maximum Permissible Dose - an environmental standard that determines the
maximum amount of a substance that does not have a harmful effect on a body. Maximum
Permissible Dose shall be set for one-time or gradual receipt and accumulation of a
hazardous substance in a body.
• Maximum Permissible Concentration is an environmental standard denoting the
maximum concentration of a substance in water, soil, atmosphere or foodstuffs, at which
it cannot harm human health. Maximum Permissible Concentration is used to control
pollution of the environment and food.
• Maximum Permissible Discharge - the maximum permissible amount of a
substance discharged with wastewater per unit of time while maintaining acceptable
water quality. If the MPD is exceeded, drains may damage the aquatic ecological system.
Environmental requirements include implementation of measures aimed at prevention
and elimination of environmental accidents and disasters, and, if necessary, to
compensate for the damage and adverse effects on the environment.
7. RESPONSIBILITY
at the ends of the pipe for each kilometer point. It shall be considered to be
first point and it starts the subsequent numbering
each production weld of the main pipeline, starting from the alignment
line.
- Identification and installation of landmarks for all kilometer marks and the exact
kilometer points
along ROW.
NOTE: When rejecting a weld profile, a mark on failure to pass VISUAL CONTROL shall
be put and the area subject to correction shall be outlined.
8 REFERENCES
9 APPENDIX
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT: Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 16 of 18
Procedure for weld numbering
APPENDIX 1
GENERAL WELD NUMBERING SYSTEM
СИСТЕМА НУМЕРАЦИИ СВАРНЫХ ШВОВ
S3 350 ML 01 FIRST WELD AT KILOMETER POINT № 350 (SECTION 3)/ Первый св.шов на км/пикете № 350 (Поток 3)
S3 350 ML 01R FIRST REPAIR WELD/ Отремонтированный сварной шов
S3 350 ML 01C CUT OUT WELD
S3 350 ML 01T1 FIRST WELD OF TIE-IN AFTER MAINLINE WELD № S3 350 ML 01/ Первый захлест после магистрального шва № S3 350 ML 01.
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT: Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 17 of 18
Procedure for weld numbering
APPENDIX 2
WELD CROSSING NUMBERING SYSTEM
СИСТЕМА НУМЕРАЦИИ СВАРНЫХ ШВОВ ПЕРЕСЕЧЕНИЙ ТРУБОПРОВОДА
Z ML1 Z ML2
Z RD 1 01
Z RD1 03 Z RD 1 04
TIE-IN WELDS
/ЗАХЛЕСТЫ
Z RD 1 02 Z - KILOMETER POINT - КМ/ ПИКЕТ
DOUBLE JOINTING WELDS /ШВЫ, св. поворотной сваркой RD – ROAD CROSSING - ПЕРЕСЕЧЕНИЕ ДОРОГ
1 – FIRST ROAD CROSSING AT Z KILOMETER POINT – 1
ПЕРЕСЕЧЕНИЕ ДОРОГ НА Z КМ/ПИКЕТЕ
/МАГИСТРАЛЬНЫЕ СВ.ШВЫ
MAIN LINE WELDS 01 TO 04 WELD NUMBER – ОТ СВАРНОГО ШВА 01 ДО
/ШВЫ ПЕРЕСЕЧЕНИЙ СВАРНОГО ШВА 04
CROSSING WELDS трубопровода
EMPLOYER: GASTRANS d.o.o. Novi Sad SECTION: 000
LOCATION: SERBIA
PROJECT / UNIT:Transmission Gas Pipeline DOCUMENT NUMBER:
(Interconnector) ‘Border of Bulgaria – Border of IDC-000-MGP-ONP-PRO-005518EN
Hungary’
DOCUMENT TITLE:
Rev. 01 Page 18 of 18
Procedure for weld numbering
APPENDIX 3