Professional Documents
Culture Documents
Impact Tool
Impact Tool
Impact Tool
Instructions
5. Generate Report
For sample document requests, please contact SALT Pavement Engineer, Joel Ulring at joel.ulring@state.mn.us or 65
el.ulring@state.mn.us or 651-366-3831.
Pavement Impacts of Large Traffic Generators Return to Summary
Version 1.0
25 Oct 2010
User Information
1. Developer Information
This is information that the county should require of the developer. If describes
each roadway segment and the number of loads that will use that segment.
2. Agency Information
This information is provided by the county, and describes the current state of the roadways that will be used by the
This area is also where the county determines which analysis method to use.
a. R-Value.
The R-value used in pavement designs for the roadway.
b. Cumulative ESALs Since Last Reconstruction
An estimate of the cumulative ESALs on the roadway segment since it was last reconstructed.
c. Design ESALs from Previous Design
The ESAL value used in the design at the last reconstruction.
d. 20-Year Projected ESALs without Development
The projected ESALs for the next 20 years, without the loads associated with the development.
e. Existing Pavement GE
Value of pavement GE with actual pavement layer thicknesses and standard GE values.
f. Effective GE, as a percentage of Original GE
As pavements age, the GE values of their layers decrease. The older the pavement (since last reconstruction
g. Appropriate Design Method: 1, 2, or 3
Select 1 for the GE Difference method, 2 for the Mn/DOT Overlay method, or 3 for the Percent of Life Used m
1. GE Difference Method
The difference in layer thicknesses, using the GE method, with and without the development.
2. Mn/DOT Overlay Method
The required overlay thickness to return the pavement to its original structural condition.
3. Percent of Life Consumed Method
The portion of the original design life (in ESALs) that is consumed by the development.
Return to Summary
, denoted by a letter.
concrete, etc.)
constructed.
evelopment.
development.
Impacts of Large Traffic Generators Wind Development Version
Project: Generic Wind Project Date Prepared: 8/17/2010
Developer: Wind Tower Developer County: Any County
Prepared by: County Engineer Version 1.0
Developer Information
Cumulative Loads Per Segment Method
Segment
Number
Return to Summary
Paved Roadways
2.0 Terminal Serviceability
3.0 Pavement Structural Number
Aggregate
1.9 tons Aggregate / CY
20 CY / truck
Concrete
2.03 tons concrete / CY
10 CY / truck
Turbine Trucks
Base Segments
16,000 Load on Steer Axle (Single Axle)
54,000 Load on 1st Tridem (Tridem Axle)
54,000 Load on 2nd Tridem (Tridem Axle)
54,000 Load on 3rd Tridem (Tridem Axle)
54,000 Load on 4th Tridem (Tridem Axle)
Nacelle
18,000 Load on Steer Axle (Single Axle)
40,000 Load on 1st Tridem (Tridem Axle)
60,000 Load on 2nd Tridem (Tridem Axle)
60,000 Load on 3rd Tridem (Tridem Axle)
40,000 Load on 4th Tridem (Tridem Axle)
Blades
2 Blades per Truck
RT Crane
53,000 Load on Steer Axle (Single Axle)
43,000 Load on Steer Axle (Single Axle)
Crane Assembly/Breakdown
12,000 Load on Steer Axle (Single Axle)
34000 Load on Drive Axle (Tandem Axle)
34000 Load on Trailer Axle (Tandem Axle)
1 0.640897 0.189005
2 6.866224 0.92489
2 6.866224 0.92489
1 0.640897 0.189005
2 21.60726 5.274971
1 0.400061 1.06E-06
1 0.400061 1.06E-06
1 0.972986 0.612588
3 28.92788 1.411522
3 28.92788 1.411522
3 28.92788 1.411522
3 28.92788 1.411522
1 1.220669 1
3 11.87881 0.369636
3 39.81519 2.275347
3 39.81519 2.275347
3 11.87881 0.369636
1 0.640897 0.189005
2 6.866224 0.92489
2 6.866224 0.92489
Single
Tandem
Tridem
34
24
1 0.640897 0.189005
2 6.866224 0.92489
2 6.866224 0.92489
1 0.640897 0.189005
2 6.866224 0.92489
2 6.866224 0.92489
0 0
0 0
0 0
1 0.400061 1.06E-06
2 6.866224 0.92489
2 6.866224 0.92489
1 0.400061 1.06E-06
1 0.400061 1.06E-06
1 0.400061 1.06E-06
Pavement Impacts o
Project Name Generic Wind Project Ve
Developer Wind Tower Developer 25
Developer Information
Cumulative Loads Per Segm
Segment
Number
Segment
Length, Road Number of Aggregate Concrete Turbine
Existing Road Segment Miles Authority Turbines
1
Add 1 Row
Other Other
Crane Vehicle Vehicle
Assembly RT Crane #1 #2
Pavement Impacts of Large Traffic Generators
Version 1.0 Return to Summary
25 Oct 2010
Agency Information
Pavement Cumulative
Segment
Number
Add 1 Row
Total Cost
$ -
Cost/ESAL-mile
$ -
Return to Summary
20-Yr
Projected Appropriate
1 2
GE Difference Mn/DOT Overlay
ESALs Existing Effective Design % of Original Design
Without Pavement GE, % of Method ESALs
Development GE Original GE 1, 2, or 3 Consumed
#N/A #DIV/0!
ummary, by Method
3
Percent of Life
Consumed Cost, by
Selected
Method
- $ -