Professional Documents
Culture Documents
Benefits and Engineering Challenges of Podium Design
Benefits and Engineering Challenges of Podium Design
CaseStudy
Wood Buildings
Aim High
Benefits and
Engineering
Challenges of
Podium Design
Worldwide, there is a trend toward
the construction of taller wood
buildings. At the high end of the
scale are structures being made from
cross-laminated timber, or CLT, such
as the UK’s Stadthaus building, which
includes eight stories of wood over
one story of concrete. While CLT is
not yet widely used in North America1,
four-to-six-level wood buildings are
common and the evolution upward
seems inevitable.
woodworks.org
The Rising Popularity engineer of record for was 1,500 units resisting lateral systems of wood
of Podium Design on two podiums connected by structural sheathing to a height of 65
In North America, “podium” an underground tunnel that had feet, which may govern in areas of
buildings, which include multiple about 1.4 million square feet of high seismicity.
stories of wood over an elevated elevated deck.” One issue that can impact the height
concrete “podium deck,” have measurement is the elevation of the
become especially prevalent. With What the Code Says grade plane. For structural purposes,
ever-increasing land costs and the According to the International height can be determined beginning
rising cost of steel and concrete, Building Code (IBC), the wood-framed at the podium, but this is not true for
developers are turning to wood portions of multi-family podium the architectural height. Per section
designs that offer greater density and structures may be Type V or Type III 502 Definitions, the IBC considers
a higher percentage of rentable square Construction, both of which have grade plane to be the average finished
footage than traditional garden-style basic limitations with regard to height, grade at exterior walls, and finished
apartments while also being cost- number of stories and square footage. grade to be the lowest point between
effective—both in terms of material For example, in the Residential Group R the building and the property line or
and labor. Wood’s other benefits, category, per IBC Table 503, a building 6 feet, whichever comes first. Local
such as speed of construction, design
3
As an example, the Avalon Anaheim project if the contractor has certain
4
go and the tendons are placed around stiffness of the upper portion, and consideration of both flexible and
them. This creates the necessary the period of the entire structure is rigid analysis, allows designers to take
clearance for the anchor while not greater than 1.1 times the period advantage of rigid portions of the
providing full benefit of the concrete of the upper portion. A complete building and some engineers think
slab for uplift resistance.” A similar summary of criteria can be found in it offers more leeway in laying out
technique was used on both the Inman the WoodWorks design example.2 shear walls. But it’s also a more
Park project and The Quarter. complex procedure.”
Rigid or Flexible Analysis
A related challenge, says VanDorpe, To meet the code requirements for
is ensuring coordination among the Another consideration is whether a semi-rigid diaphragm assumption,
many trades involved in a podium to use semi-rigid or flexible diaphragm many engineers combine the two
structure. “Much of the complexity analysis to determine shear approaches and design for worst-case
and needed coordination are due distributions to the shear walls. loads. This approach is known as
to the presence of the transfer Explaining the pros and cons envelope design and is often
slab, which is the interface for the of each, Michelle Kam-Biron, SE, recommended, though VanDorpe
architectural, structural, waterproofing, a technical director with WoodWorks says it results in more shear walls
landscaping, mechanical, electrical in California, says—“The code has than necessary because it combines
and plumbing consultants, as well as prescriptive and calculated the worst case results of both models.
the work of the concrete, framing, requirements for classifying a wood Both models have shortcomings based
landscaping, mechanical, electrical diaphragm as semi-rigid or flexible. on assumptions that facilitate the
and plumbing contractors. In the Flexible analysis is more straight- calculation but don’t indicate the real
most successful projects there is a high forward. On the downside, it may not behavior of the building.
degree of collaboration among these reflect the actual conditions—based Although VanDorpe believes a well
players, and it can also be helpful to on the span-to-depth ratios and shear chosen shear wall scheme is essential
combine some of these tasks.” walls—to consider diaphragms as to good seismic performance, he says
flexible where they could behave it is equally true that a code-compliant
Two-stage Design more rigidly, which would result in an shear wall scheme can result in poor
Both Church and VanDorpe use underestimation of the interior loading. performance. “Shear wall placement is
two-stage analysis for lateral design, Semi-rigid analysis, which includes an art as much as a science. Whatever
which enables them to treat the
flexible upper portion of the structure
5
analysis you choose is an idealized straps are applied to the outside of Other areas of concern include
mathematical representation required the wall. On taller buildings with lots horizontal duct runs, piping, non-
by the code and cannot replace the of openings, says Church, the cavities wood fire wall separations,
experience and judgement gained along the sides of doors and windows cementitious floor toppings, etc.”
by following patterns of earthquake can quickly disappear due to the With the four-story Inman Park
damage that occur.” increased number of jamb or king project, the engineered lumber used
studs required, leaving little or no for the floor joists lessened the
Tie-down Systems room to install the anchor. shrinkage value to the point that it
For multi-story wood structures, was almost insignificant. However, The
continuous tie-down systems offer Shrinkage
Quarter project included dimensional
several advantages over conventional Where wood walls and bearing lumber chords for the floor trusses,
partitions support more than two which led to an increase of more
Credit: VanDorpe Chou Associates, Inc.
floors and a roof, section 2304.3.3 than 50 percent of the estimated
of the IBC requires an analysis shrinkage potential.
to ensure that shrinkage of the
“Shrinkage calculations aren’t
wood framing will not have adverse
complex,” says Kam-Biron, “but it’s
affects on the structure, plumbing,
an area designers often overestimate,
electrical or mechanical systems, or
which makes it difficult to detail for
other equipment. The analysis must
differential movements. With sawn
also show that the roof drainage
lumber, the majority of shrinkage
system will either not be affected
occurs in the cross grain direction.
or be designed to accommodate
Therefore, the majority of shrinkage
tie-downs, such as ease of installation the differential.
will occur in the top plates, sill plate
and the achievement of higher uplift According to Church, a typical and sole plates, and possibly the floor
capacities. Both systems are discussed four-story wood building utilizing floor joists—depending on how the floor
in the WoodWorks design example.2 trusses and platform construction is framing members are framed to the
While conventional straps and tie- teetering on “I need to do something wall. If the framing is modified balloon,
down anchors were used for the Inman about shrinkage territory,” whereas, then sawn lumber joists won’t play a
Park project, The Quarter featured a at five or six stories, shrinkage can
continuous tie-down system for both definitely have an effect
6
Credit: Matt Church
In addition to its cost-effectiveness, wood’s other benefits—such as speed of construction, design flexibility, and reduced environmental impact—add to the value proposition.
huge role in overall shrinkage.” Table 720.1(2) of the IBC lists fire crushing, fasteners, and connectors.
For more information, a free shrinkage ratings for various wall construction He recommends that engineers be
estimator is available from the types. Both the architect and engineer familiar both with their local suppliers
Western Wood Products Association should be aware that some of the and framing contractor preferences.
at www.wwpa.org. wall construction types using wood
construction reference footnote ‘m.’ Engineering Support for
Construction Types Multi-story Wood Buildings
Footnote ‘m’ of the table requires
and Fire Resistance the reduction of F’c to be 78 percent Through WoodWorks and its partner
In a Type III wood building, the of the allowable with a maximum organizations, design professionals
IBC requires the use of fire-retardant slenderness ratio le /d of 33. using wood for non-residential
treated (FRT) wood for exterior walls. buildings have numerous avenues
AWC has also tested a number
In a Type V building, FRT wood is for free technical support. Visit
of wood-frame fire rated assemblies
not required. woodworks.org for a list of technical
that do not require the reduction and
directors available for one-on-one
Fire-rated assemblies can be found are included in IBC Table 720.1(2).
support as well as online resources
in a number of sources including the A description of these wall assemblies
such as design examples, case studies,
IBC, the Underwriters Laboratories is contained in DCA 3.
webinars, CAD/REVIT details, and more.
(UL) Fire-resistance-rated Systems According to VanDorpe, who used
and Products, the UL Fire Resistance FRT wood on the Avalon Anaheim
Directory, the Gypsum Association’s Stadium project, FRT products made
1
Efforts are underway to make cross-laminated timber
Fire Resistance Design Manual, and by different manufacturers vary widely available in the United States and Canada.
the American Wood Council’s (AWC) considerably in terms of their adjustment 2
Design example – Four-story Wood-frame Structure
over Podium Slab, developed for WoodWorks by
DCA 3: Fire-Rated Wood-Frame Wall values, such as compression Douglas S. Thompson, PE, SE, SECB, STB
Structural Engineers, Inc., 49 pages, available at
and Floor/Ceiling Assemblies. perpendicular to grain, sill plate http:// www.woodworks.org/Publications/caseStudies.aspx
7
870 Inman Park Condominiums
Atlanta, GA
The Inman Park project features four stories of wood over two levels of post-
tensioned concrete, which separate the residential units above from two levels of
parking below. This upscale development includes 110 condominium units specially
designed to fit into the eclectic Inman Park neighborhood, Atlanta’s first in-town
suburb. Additional features of this project included the design of a ground level
restaurant, retail and office space that project out from the building.
Owner: Mech Properties
Architect: Brown Doane Architects, Inc.
Structural Engineer: Davis & Church, LLC
Neither the Wood Products Council nor its contractors make any warranty, expressed or
Cover photos: Matt Church (large);
implied, or assume any legal liability or responsibility for the use, application of and/or reference
VanDorpe Chou Associates, Inc. (small)
to the information included in this publication. Consult your local jurisdiction or design This page: Matt Church (top and center);
professional to assure compliance with code, construction, and performance requirements. Arden Photography (bottom)
AMERICAN
WOOD
COUNCIL
WoodWorks is an initiative of the Wood Products Council, which includes all of the major North American wood associations.
WoodWorks Case Study WW-002 – Podium Design • © 2011 WoodWorks