Estimation ESTIMATE OF Wall

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 15

ESTIMATE OF SINGLE WALL

Prepare a detailed estimate of a single wall as per the plan and elevation given u
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside and top @15 Rs /m

u7)Inside two coats of white wash @9 Rs /m^2 with one coat of col

u8)Outside and top two coats of colour wash @ 9Rs /^2

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height

1
Earthwork in excavation 1 6 0.8 2.4
2 PCC in foundation 1 6 0.8 0.4
Ist class brickwork in
foundation
Step 1 1 6 0.7 0.6
3
step 2 1 6 0.6 0.5
step 3 1 6 0.5 0.5
Step 4 1 6 0.4 0.6
Total
4 DPC 6 0.3
5 Ist Class brickwork in
superstructure 1 6 0.3 3.4

6 Plastering Inside 1 6 3.4

Outside 1 6 3.8
7
Top 1 6 0.3
Total
White wash Inside 1 6 3.4
8 White wash Outside 1 6 3.8
White wash Top 1 6 0.3
Total
9 Colour wash Inside 1 6 3.4
Abstract of estimated cost
Sno Description Quantity Unit Rate Per unit
1 Earthwork in excavation 11.52 M^3 375 Rs /M^3
2 PCC in foundation 1.92 M^3 380 Rs /M^3
3 Ist class brickwork in
foundation 7.26 M^3 300 Rs /M^3
4 DPC 1.8 M^2 20 Rs /M^2
5 Ist Class brickwork in
superstructure 6.12 M^3 390 Rs /M^3
6 Plastering Inside 20.4 M^2 12 Rs /M^2
Outside 22.8 M^2 15 Rs /M^2
7
Top 1.8 M^2 15 Rs /M^2
8 White wash 45 M^2 9 Rs /M^2
9 Colour wash Inside 20.4 M^2 11 Rs /M^2

Total

Add
Contingency 3%
Add work
charge
establishment 2%
Overall
cost

QNO 2
Prepare a detailed estimate of a single wall as per the plan and elevation given u
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside and top @15 Rs /m

u7)Inside two coats of white wash @9 Rs /m^2 with one coat of col

u8)Outside and top two coats of colour wash @ 9Rs /^2

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height
1
Earthwork in excavation 1
2 PCC in foundation 1
Ist class brickwork in
foundation
Step 1 1
3
step 2 1
step 3 1
Step 4 1
Total
4 DPC
5 Ist Class brickwork in
superstructure 1

6 Plastering Inside 1

Outside 1
7
Top 1
Total
White wash Inside 1
8 White wash Outside 1
White wash Top 1
Total
9 Colour wash Inside 1

Abstract of estimated cost


Sno Description Quantity Unit Rate Per unit
1 Earthwork in excavation M^3 375 Rs /M^3
2 PCC in foundation M^3 380 Rs /M^3
3 Ist class brickwork in
foundation M^3 300 Rs /M^3
4 DPC M^2 20 Rs /M^2
5 Ist Class brickwork in
superstructure M^3 390 Rs /M^3
6 Plastering Inside M^2 12 Rs /M^2
Outside M^2 15 Rs /M^2
7
Top M^2 15 Rs /M^2
8 White wash M^2 9 Rs /M^2
9 Colour wash Inside M^2 11 Rs /M^2

Total
Add
Contingency 3%

Add work
charge
establishment 2%
Overall
cost

Qno3
QNO 2
Prepare a detailed estimate of a single wall as per the plan and elevation given u
u1) Earthwork in excavation@375 RS /m^3.
u2)Ist class brickwork in foundation (1:6) @300 Rs /m^3

u3) PCC in foundation (1:2:4) @ 380 Rs /m^3

u4)DPC @ 20 Rs /m^2

u5) Ist class brick work in super structure (1:4)@390 Rs /m^2

u6) Plastering inside @12 Rs /m^2 and outside and top @15 Rs /m

u7)Inside two coats of white wash @9 Rs /m^2 with one coat of col

u8)Outside and top two coats of colour wash @ 9Rs /^2

DETAIL OF MEASUREMENT FORM


Sno Description No Length Breadth Height

1
Earthwork in excavation 1
2 PCC in foundation 1
Ist class brickwork in
foundation
Step 1 1
3
step 2 1
step 3 1
Step 4 1
Total
4 DPC
5 Ist Class brickwork in
superstructure 1

6 Plastering Inside 1
Outside 1
7
Top 1
Total
White wash Inside 1
8 White wash Outside 1
White wash Top 1
Total
9 Colour wash Inside 1

Abstract of estimated cost


Sno Description Quantity Unit Rate Per unit
1 Earthwork in excavation M^3 375 Rs /M^3
2 PCC in foundation M^3 380 Rs /M^3
3 Ist class brickwork in
foundation M^3 300 Rs /M^3
4 DPC M^2 20 Rs /M^2
5 Ist Class brickwork in
superstructure M^3 390 Rs /M^3
6 Plastering Inside M^2 12 Rs /M^2
Outside M^2 15 Rs /M^2
7
Top M^2 15 Rs /M^2
8 White wash M^2 9 Rs /M^2
9 Colour wash Inside M^2 11 Rs /M^2

Total

Add
Contingency 3%

Add work
charge
establishment 2%
Overall
cost
an and elevation given use following specifications

00 Rs /m^3

4)@390 Rs /m^2
de and top @15 Rs /m^2
2 with one coat of colour wash @11 Rs /m^2
@ 9Rs /^2
M
Quantity Unit Remarks

Height is
from ground
level till
11.52 M^3 bottom
1.92 M^3
ELEVATION /PLA

2.52
1.8
1.5
1.44
7.26 M^3
1.8 M^2

6.12 M^3

20.4 M^2

22.8
1.8
24.6 M^2
20.4
22.8
1.8
45 M^2
20.4 M^2
Amount Unit
4320
729.6
3D VIEW
2178
36

2386.8
244.8
342
27
405
224.4

10893.6 RS

326.808 RS

217.872 RS

11438.28 RS

an and elevation given use following specifications

00 Rs /m^3

4)@390 Rs /m^2
de and top @15 Rs /m^2
2 with one coat of colour wash @11 Rs /m^2
@ 9Rs /^2

M
Quantity Unit Remarks
Height is
from ground
level till
M^3 bottom
M^3

M^3
M^2

M^3

M^2

M^2

0 M^2
M^2

Amount Unit

RS
RS

RS

RS

an and elevation given use following specifications

00 Rs /m^3

4)@390 Rs /m^2
de and top @15 Rs /m^2
2 with one coat of colour wash @11 Rs /m^2
@ 9Rs /^2

M
Quantity Unit Remarks

Height is
from ground
level till
M^3 bottom
M^3

M^3
M^2

M^3

M^2
M^2

0 M^2
M^2

Amount Unit

RS

RS

RS

RS
ELEVATION /PLAN
3D VIEW