ID Outline

Task Task Name Duration Start Finish Predecessors


Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20
17 24 31 07 14 21 28 05 12 19 26 02 09
0 0 Vredendal maintenance 49 days Mon 31/08/20 Thu 05/11/20
program
1 1 Contract award 1 day Mon 31/08/20 Mon 31/08/20

2 2 Safety file preparation 3 days Tue 01/09/20 Thu 03/09/20 1

3 3 Safety file submission 1 day Fri 04/09/20 Fri 04/09/20 2

4 4 Safety file evaluation 1 day Mon 07/09/20 Mon 07/09/20 3

5 5 Safety file approval 1 day Tue 08/09/20 Tue 08/09/20 4

6 6 Site handover 1 day Wed 09/09/20 Wed 09/09/20 5

7 7 Material procurement 5 days Thu 10/09/20 Wed 16/09/20 6


and delivery
8 8 Site establishment 3 days Thu 10/09/20 Mon 14/09/20 6

9 9 Internal works 27 days Thu 17/09/20 Fri 23/10/20

10 9.1 Plumbing and sanitary 10 days Thu 17/09/20 Wed 30/09/20 7,8
ware

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Vredendal maintenanc
Summary Manual Summary Rollup Progress
Date: Sun 26/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Outline
Task Task Name Duration Start Finish Predecessors
Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20
17 24 31 07 14 21 28 05 12 19 26 02 09
11 9.2 Tiling 10 days Thu 24/09/20 Wed 07/10/20 7FS+5 days

12 9.3 Glazing 5 days Tue 22/09/20 Mon 28/09/20 7FS+3 days

13 9.4 Carpentry 10 days Mon 28/09/20 Fri 09/10/20 7FS+7 days

14 9.5 Brickwork 2 days Thu 01/10/20 Fri 02/10/20 10

15 9.6 Plaster 3 days Mon 05/10/20 Wed 07/10/20 14

16 9.7 Painting 10 days Mon 12/10/20 Fri 23/10/20 10,11,12,13,14,15

17 10 External works 21 days Thu 01/10/20 Thu 29/10/20

18 10.1 Plumbing 5 days Thu 01/10/20 Wed 07/10/20 10

19 10.2 Paving 5 days Thu 08/10/20 Wed 14/10/20 18

20 10.3 Palisades 5 days Thu 08/10/20 Wed 14/10/20 18

21 10.4 Carpentry 5 days Thu 08/10/20 Wed 14/10/20 18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Vredendal maintenanc
Summary Manual Summary Rollup Progress
Date: Sun 26/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Outline
Task Task Name Duration Start Finish Predecessors
Number
Mode
Aug '20 Sep '20 Oct '20 Nov '20
17 24 31 07 14 21 28 05 12 19 26 02 09
22 10.5 Brickwork 3 days Thu 08/10/20 Mon 12/10/20 18

23 10.6 Plaster 3 days Tue 13/10/20 Thu 15/10/20 22

24 10.7 Seal roof leaks 5 days Thu 08/10/20 Wed 14/10/20 18

25 10.8 Painting 10 days Fri 16/10/20 Thu 29/10/20 18,19,20,21,22,23,24

26 10.9 Tree felling 2 days Thu 08/10/20 Fri 09/10/20 18

27 11 Housekeeping 2 days Mon 26/10/20 Tue 27/10/20 9,10

28 12 Project inspections 3 days Wed 28/10/20 Fri 30/10/20 27

29 13 Project completion 1 day Mon 02/11/20 Mon 02/11/20 28

30 14 Project handover 1 day Tue 03/11/20 Tue 03/11/20 29

31 15 Site de-establishment 2 days Wed 04/11/20 Thu 05/11/20 30

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Vredendal maintenanc
Summary Manual Summary Rollup Progress
Date: Sun 26/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
Nov '20 Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21
09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Vredendal maintenanc
Summary Manual Summary Rollup Progress
Date: Sun 26/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
Nov '20 Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21
09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Vredendal maintenanc
Summary Manual Summary Rollup Progress
Date: Sun 26/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
Nov '20 Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21
09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Vredendal maintenanc
Summary Manual Summary Rollup Progress
Date: Sun 26/07/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6