CMS_LawTax_CMYK_28-100.

eps

English construction
law developments 2012
An international perspective

June 2013
Contents
Introduction 3
On-demand guarantees: developments in form and substance 4
Reasonable endeavours and financial expense in construction contracts 8
Good faith and co-operation 10
Implied terms as to progress and quality 14
Global claims 18
Indirect and consequential loss exclusions 20
Contractual damages: expected losses, unexpected liability? 22
Settlement agreements 24
Commercial pressure and economic duress 26
Time bars and documentary requirements in construction contracts 28
Document harvesting and disclosure in international construction disputes 32
Maintaining privilege in international construction disputes 34

What CMS offers 36


Why we are market leaders 37
Where to find us 38

2 | CMS London - English construction law developments 2012: An international perspective


Introduction

Welcome to the Spring 2013 edition of our international update on English construction law developments.
As with our previous bulletins, the aim is to highlight legal developments over the past year that are relevant
to those organisations involved in English law construction projects outside the United Kingdom. Last year
provided a bumper crop of cases concerning issues which challenge those operating in this arena - both
familiar topics which we have touched on before and some new ones too.

We hope you find this edition informative and thought provoking. As always we would welcome your
feedback - and look forward to working with you over the coming year.

Victoria Peckett
Partner
T +44 (0)20 7367 2544
E victoria.peckett@cms-cmck.com

After much internal consideration and debate, the key English cases in 2012 are dissected and analysed
below. Three common threads link them.

First, English law has traditionally upheld contractual provisions, whatever the consequences, in the
name of certainty. This approach was reinforced in 2012 by a case in which an entire claim failed due
to non-compliance with a time bar provision. There also, in 2012, remained a reluctance to imply terms
into contracts and, in this regard, we saw a move towards a general duty of good faith halted by the
Court of Appeal.

Second, as the answer to many English law disputes often begins and ends with what the contract
says, the rules of interpretation are important. 2012 saw challenges to these rules only for traditional
positions to be reasserted upon appeal. Wuhan v Emporiki was an example of this in an all too
common dispute about whether a bond was on-demand or conditional. While the parties were not
from the UK (like two-thirds of those in the English Commercial Court) they were expected to know
the niceties of English law’s rules of interpretation when choosing it. For these rules, sometimes one
word can make all the difference, like the word “other” in clauses excluding liability for “consequential
loss” – a very English law concept.

Third, 2012 saw plenty of cases that provide salutary guidance on avoiding, managing and resolving
claims. The most important was Walter Lilly v Mackay and what it had to say about global claims.
For many it represents a diluting of the previously understood position, in favour of contractors when
pursuing their employers and also subcontractors when pursuing contractors. Much still turns on
what the contract says, but this case was notable in 2012 for developing, if not moving away from,
a tradition.

Rupert Choat
Partner and Solicitor Advocate
T +44 (0)20 7367 3573
E rupert.choat@cms-cmck.com

3
On-demand guarantees: developments in
form and substance

In keeping with the last two years, 2012 has provided some interesting developments concerning
the interpretation and enforceability of on-demand securities. The prevalence of such securities
on international construction projects, and the relative frequency with which they are disputed,
underscores the importance of these developments. This year’s developments concern the proper
interpretation of such instruments and the execution formalities needed to make them effective
under English law.

Interpretation: on-demand vs conditional


Undoubtedly the most important aspect of drafting an To this list one might add where payment is to be made
effective on-demand guarantee or performance bond is to based upon a certificate or other documents rather than
make sure that the instrument is truly on-demand, rather facts (I.E. Contractors v Lloyds Bank).
than merely conditional upon proof of some underlying
liability (i.e. a guarantee in the traditional sense). Sadly, all The formulation from Paget’s has received judicial
too often, there is some difficulty working out under approval on a number of occasions, although it now
English law whether a bond is on-demand or conditional. appears to be accepted that item (iv) is not conclusive.
To say that this can be the result of bonds employing As noted by the Court of Appeal in Gold Coast Ltd v Caja
archaic wording begs the question why they do so. Often De Ahorros, there are:
in the construction context there is ambiguity because:
‘reasons for including [clauses excluding or limiting the
(a) the procuring party (usually the contractor) expects
defences available to a guarantor] in an instrument which is
that clarity would only result in a clearly on-demand
intended to be autonomous. It might, for example, have
bond (with the beneficiary (employer) likely to resist
been included to avoid any argument that variation of the
anything less)
[underlying] contract … would imperil recovery under the
(b) the beneficiary (employer), who may already suffer … guarantees. It could have been inserted simply to ensure
from lender-fatigue, accepts what it is given by the that the rule applicable to true guarantees did not apply to
bank or other institution, feeling that it has no this instrument.’
bargaining power and
This also accords with our experience of truly on-demand
(c) the issuer has little, if any, interest in clarity – expecting
bonds being drafted with very detailed clauses excluding
to be paid for its services and, in the event of a call, to
or limiting the defences available to the issuing bank.
recover on whatever security it holds.
Nonetheless, such clauses will weigh against the finding
of a truly ‘on demand’ obligation where the operative
Historically, English law has used a complex set of rules
parts of the bond are not drafted with clarity (see for
drawn from banking law to decide whether or not a bond
example Trafalgar House Construction v General Surety
is on-demand (with terms such as ‘guarantee’ not being
and Guarantee).
determinative). Many of these rules are aimed at
determining whether the bond provider’s liability is
Item (ii) from Paget’s formulation has recently been subject
intended to be secondary in relation to the underlying
to debate with certain authorities suggesting that the
contract (and thereby conditional) or primary. In relation to
status of the issuer is of less importance than previously
international transactions, Paget’s Law of Banking, 13th
thought. The Court of Appeal has very recently sought to
edition, states:
restore favour to Paget’s formulation, but the debate has
nonetheless proved useful in clarifying the correct
‘Where an instrument i) relates to an underlying transaction
approach to be taken to interpreting ‘on-demand’ bonds
between parties in different jurisdictions, ii) is issued by a
given by banks or other financial institutions.
bank, iii) contains an undertaking to pay ‘on demand’ (with
or without the words ‘first’ and/or ‘written’) and iv) does
By way of background, the relatively early decision in Esal
not contain clauses excluding or limiting the defences
Commodities v. Oriental Credit CA provides a good
available to a guarantor, it will almost always be construed
example of the issuer’s status as a bank being used for the
as a demand guarantee’.
purpose of interpretation. The document in that case was

4 | CMS London - English construction law developments 2012: An international perspective


described as a ‘performance bond’ for 10% of the contract context, there was a strong presumption against their
price and was held to be payable on-demand despite being on-demand as opposed to conditional.
express words which suggested conditionality. The bond
was payable ‘on your written demand in the event that the A similar result was achieved in Vossloh AG v Alpha Trains
supplier fails to execute the contract in perfect (UK) Ltd. The claimant provided a parent company
performance…’ The surrounding circumstances, including guarantee in favour of the defendant, which guaranteed
the fact that the document was issued by a bank, made it the performance of the contracted works. The defendant
sufficiently clear that the instrument was intended to subsequently alleged defective work and made a call on
provide prompt and certain payment in the manner of an the guarantee. Despite the fact that amounts were said to
on-demand bond. be payable ‘on demand’, the court applied the
presumption from Marubeni to interpret the instrument as
The reason why such a generous interpretative approach is a conditional bond requiring proof of default.
taken to bonds issued by banks as opposed to other
entities was explained by Hirst J in Siporex Trade SA v. The strength of the presumption in the opposite
Banque Indosuez: direction for guarantees issued by banks was recently
tested in Wuhan Guoyo Logistics Group Co Ltd v
‘There is in my judgment no real hardship on the bank in Emporiki Bank of Greece SA. Although expressed to be
imposing this strict liability to pay. A performance bond is a ‘on demand’ the wording of the guarantee in that case
commercial instrument. No bank is obliged to enter into it gave a number of indications which supported a
unless they wish to and no doubt when they do so, they conditional interpretation requiring proof of default. The
properly exact commercial terms and protect themselves by issuing bank also had a direct connection with the
suitable cross-indemnities …’ underlying transaction, being the lender to the buyer.
These factors won the day at first instance, with Clarke J
Very different considerations apply to the interpretation finding that proof of default was required. His decision
of bonds issued between parties or their related entities. was, however, overturned on appeal for failing to have
In Marubeni Hong Kong v Government of Mongolia the sufficient regard for Paget’s formulation. In preference
Court of Appeal noted that the cases involving banks, to a detailed textual analysis of the wording used in the
‘provide no useful analogy for interpreting a document guarantee, the Court of Appeal found it ‘much better
which was not issued by a bank and which contains no (and indeed simpler) to be guided by the general tenor
overt indication of an intention to create a performance of previous authority enunciated by past judges of great
bond or anything analogous to it.’ In that case, the distinction.’ The judge at first instance ought to have had
Mongolian Ministry of Finance (for commercial trading ‘much more regard’ to the formulation from Paget’s
reasons it would appear) had ‘unconditionally pledge[d] than he did.
to pay to you upon your simple demand all amounts
payable under the Agreement if not paid when the same In summary, therefore, the passage from Paget’s Law of
becomes due…’ Despite the similarity of this wording to Banking quoted above remains good law and there would
the performance bond in Esal, the Court of Appeal appear to be an equally strong presumption in favour of
declined to find an on-demand obligation, finding bonds expressed to be payable ‘on demand’ being truly
instead that the promise was in the nature of a on-demand when given by banks in a cross-border context,
guarantee and conditional upon proof of default. The as there will be against such bonds being on-demand when
court held that for bonds issued outside of a banking given by non-commercial entities.

5
Execution formalities An example last year from Australia illustrates well this risk
(which applies where English law governs the relevant
Deeds play a central role in construction and engineering bond). In Segboer v AJ Richardson Properties a contractor
projects. Many construction and engineering contracts, arranged for a bank to issue an on-demand performance
and similar contracts such as collateral warranties, are bond in favour of a developer as security for the
entered into as deeds. The primary advantage of doing so contractor’s obligations under its building contract with the
is to secure the benefit of a longer limitation period developer. The performance bond was issued by the bank
(sometimes referred to as ‘prescription’ in other as a deed, however, following a call on the bond by the
jurisdictions) than if the contract were not a deed (12 years developer, the contractor contended that the bond had not
instead of 6). Rights under deeds therefore last longer. been properly ‘delivered’ as a deed and was therefore
invalid. The ‘delivery’ of a deed is a formal requirement of
Deeds also perform a special role when it comes to English law and will ordinarily take place upon execution
on-demand performance bonds. Such bonds are usually unless circumstances suggest that some later time for
issued unilaterally by a bank or financial institution in delivery was intended (which was the argument made by
favour of parties with whom it will have no direct the contractor in Segboer).
commercial relationship and from whom it will receive
nothing in return. There will therefore usually be The contractor’s argument did not succeed and the
insufficient ‘consideration’ to form a binding contract at performance bond was ultimately held to be enforceable.
common law. In such circumstances, the bond will need It is notable, however, that once the contractor had made
to be executed as a deed if it is to be enforceable by the its objection the bank refused to pay under the bond. This
beneficiary. If, however, there is an irregularity concerning necessitated court proceedings by the developer, in which
the bond so that it does not constitute a deed, the bond the bank claimed against the contractor under its cross-
will not be enforceable. indemnity (that being the only route by which the bank
could be assured of recovering against the contractor if it
It is surprising in this context that one often finds paid out under the bond). Accordingly, even though the
performance bonds which are expressed to be subject to contractor’s argument was unsuccessful, it still resulted in
English law and yet are not properly executed as a deed. considerable delay and expense in enforcing what was
The requirements for execution under English law are not intended to be a cash-equivalent security.
particularly complex and all that is usually needed is for the
document to state that it is ‘executed as a deed’ and to be The proceedings in Segboer provide a helpful warning for
signed and /or witnessed by the appropriate persons employers and owners to scrutinise the execution
depending on the nature of the company executing the formalities of English law performance bonds delivered by
deed. Non-compliance with such formalities can, however, contractors. If the formal requirements for the execution of
have far reaching implications. deeds have not been met, the contractor may be able to
successfully challenge payment by the bank.
It is sometimes said that the formalities of execution are
less important when dealing with large well-known References: Esal Commodities v. Oriental Credit CA [1985] 2
financial institutions, as they are less likely to rely on legal Lloyd’s Rep. 546; Siporex Trade SA v. Banque Indosuez
technicalities to avoid their obligations. Such comments [1986] 2 Lloyd’s Rep. 146; I.E. Contractors v Lloyds Bank
overlook the fact that an institution’s willingness to pay out [1990] 2 Lloyds Rep 496; Trafalgar House Construction v
on a bond is usually tied to the confidence it has in being General Surety and Guarantee [1996] 1 AC 199; Gold Coast
able to recover the sums paid from its client and/or under Ltd v Caja De Ahorros [2001] EWCA Civ 1806; Paget’s Law
the applicable cross-indemnities. No bank will willingly pay of Banking (13th ed, 2007); Marubeni Hong Kong v
out on a performance bond if it will be left out of pocket. Government of Mongolia [2005] EWCA Civ 395; Vossloh
AG v Alpha Trains (UK) Ltd [2010] EWHC 2443; Segboer v
In such circumstances, any defect in the formalities of A J Richardson Properties Pty Ltd [2012] NSWCA 253;
execution may enable the procuring party (i.e. the bank’s Wuhan Guoyo Logistics Group Co Ltd v Emporiki Bank of
client and usually, but not always, the provider of the Greece SA [2012] EWHC 1715 (and on appeal at [2012]
counter-indemnities) to place pressure on the bank to EWCA Civ 1629).
refuse payment of the bond. The procuring party may, for
example, threaten to rely upon the invalidity of the bond as
precluding any recovery under its cross-indemnity to the
bank. If the bond is invalid, then payment could potentially
be viewed as voluntary and outside the scope of the
cross-indemnity.

6 | CMS London - English construction law developments 2012: An international perspective


For me CMS leads the field for construction law.
The CMS lawyers I have worked with across Europe
and beyond, over the last seven years, have combined
industry knowledge, legal expertise and can-do spirit
the like of which I haven’t seen in other firms.
Global Legal Counsel
European multinational investor and developer
Reasonable endeavours and financial expense
in construction contracts

A recent High Court decision has considered the meaning of ‘reasonable endeavours’ in the
context of an obligation to complete construction works. The financial impact to the
contractor of its obligation to complete was held by the court to be irrelevant in
considering whether ‘reasonable endeavours’ had been exercised. The contractor’s ability
to fund the works was to be presumed. The judgment suggests that an obligation to use
‘reasonable endeavours’ (widely found in FIDIC-based and other international construction
contracts), usually considered to be the weakest of endeavours clauses, may require a party
to sacrifice its own commercial interests despite the economic downturn.

Telford Homes (Creekside) Ltd (Telford) was the developer of limiting the scope of matters to be taken into account in
a mixed-use development known as ‘Creekside Village West’ considering ‘reasonable endeavours’. As the construction
in Greenwich, London. Telford agreed to provide a long works themselves had not been affected, Telford was unable
lease of the commercial parts of the development to to find any support for its position in the reasonable
Ampurius Nu Homes Holdings Ltd (Ampurius). Telford and endeavours clause. The court’s ruling leaves unclear, however,
Ampurius entered into an Agreement for Lease on how such a clause would apply in circumstances where the
7 October 2008 where, in return for Ampurius’ agreement to cost of the works had risen due to unforeseen circumstances.
take up the lease, Telford agreed to ‘use its reasonable A lack of funding in respect of the additional costs in such
endeavours to procure completion of the Landlord’s Works by circumstances may not be as easily characterised as
the Target Date or as soon as reasonably possible thereafter.’ antecedent or extraneous to the carrying out of the works.

Telford had already commenced work on the development Two previous Court of Appeal decisions provide a useful
at the time the Agreement for Lease was signed. Work comparison with the decision in Ampurius:
continued until March 2009 when, with the onset of the
—— In Phillips Petroleum Company United Kingdom v Enron
credit-crunch, demand for residential units began to dry up
Europe, a contract for the supply of North Sea gas
and Telford was unable to meet the level of pre-sales
contained a number of duties requiring the parties to
required by its development financing. As a result, Telford
use ‘reasonable endeavours’. One was a duty to use
was unable to access additional funds and decided to
reasonable endeavours to co-ordinate the construction
suspend part of the commercial works which Ampurius
of certain facilities. Another duty required the parties to
was to lease. Ampurius subsequently sought to terminate
use reasonable endeavours to agree the date on which
for repudiation and one issue between the parties was
deliveries of gas were to begin (a long-stop date was
whether the ‘reasonable endeavours’ clause justified
also specified in the absence of agreement). Because of
Telford’s suspension. Telford argued that the expression
a fall in the price of gas Phillips refused to agree a date
‘reasonable endeavours’ encompassed financial resources,
earlier than the specified long-stop date. Enron argued
so that a failure to complete due to funding problems
that each party was under a duty to use reasonable
would not amount to a breach provided reasonable
endeavours having regard only to criteria of technical
endeavours had been made to procure finance.
and operational practicability and without regard to
The court accepted that Telford had made reasonable selfish or commercial motives. The Court of Appeal
endeavours to procure finance, but rejected Telford’s disagreed, with Kennedy LJ finding it ‘impossible to say
submission that funding came within the scope of the that [the contract terms] impose on the buyer a
clause. According to Mr Justice Roth, the reasonable contractual obligation to disregard the financial effect on
endeavours obligation was: him, and indeed everything else other than technical or
operational practicality, when deciding how to discharge
‘…designed to cover matters that directly relate to the physical
his obligation to use reasonable endeavours to agree to
conduct of the works, thereby providing an excuse for delay in
a commissioning date prior to 25 September 1996.’
such circumstances as inclement weather or a shortage of
materials for which the Defendant was not responsible. The —— In Jet2.com Ltd v Blackpool Airport Ltd (which we
clause does not, in my view, extend to matters antecedent or reported on in last year’s publication), a contract
extraneous to the carrying out of the work, such as having the between budget airline Jet2.com and Blackpool Airport
financial resources to do the work at all.’ (BAL) contained an agreement that both parties would
‘…co-operate together and use their best endeavours
The court appears to have reached its decision by confining
to promote Jet2.com’s low cost services…and BAL will
the clause strictly to the construction works and thereby

8 | CMS London - English construction law developments 2012: An international perspective


use all reasonable endeavours to provide a cost base In such circumstances, a question arises about the extent to
that will facilitate Jet2.com’s low cost pricing...’. This which the contractor is required to expend cost in making such
clause was held by the Court of Appeal to require BAL endeavours when such costs will not be recoverable from the
to allow Jet2 to operate outside of normal hours even if employer. There are a number of ways in which that question
this required BAL to incur a loss as a result. However, might be considered, including by reference to the level of any
the court suggested that if it became clear that Jet2 delay damages agreed by the parties, but one might expect an
could never expect to operate low cost services employer to argue that the contractor is required to supplement
profitably, BAL would ‘not be obliged to incur further its labour force, add extra shifts or to work out of hours. Say
losses in seeking to promote a failing business.’ the line is drawn at supplementing its labour force, but due to
the contractor’s existing delay, use had already been made of all
Neither of these authorities were cited in Ampurius,
locally available labour to supplement the original resource plan.
however, both are of some relevance in considering the
Would the contractor be justified in refusing to further
approach to be taken to matters which may be said to be
supplement its labour force with more expensive labour
‘antecedent or extraneous’ to an endeavours clause. For
needing to be sourced elsewhere? The finding in Ampurius
example, one might question whether the Court of
could be argued to suggest that the contractor’s existing delay
Appeal’s reference to Jet2’s profitability was not something
should be treated as antecedent or extraneous and should be
extraneous to the clause considered in that case. Similarly,
ignored. Therefore, if without the contractor’s own delays,
one might ask whether Phillips’ own financial interest in
supplementing the labour force would have been a reasonable
postponing the delivery of gas was not antecedent or
course to adopt to minimise delay caused by the Force Majeure
extraneous to the clause considered in that case.
event, that is likely to remain the case (so it might be argued
In a construction context, the implications of the court’s following Ampurius) even if that course has been made much
finding in Ampurius may extend beyond similar wording in more expensive by the contractor’s pre-existing delays.
other development agreements or agreements for lease.
Endeavours clauses will always be heavily dependent on their
Construction contracts frequently make provision for
context and the circumstances of each individual case for
parties to make their best or reasonable endeavours to
their precise meaning and application. As was observed in
mitigate delay or to overcome obstacles to the progress of
the recent decision of the Singapore High Court on the
the works. The logic of the decision in Ampurius may allow
meaning of ‘all reasonable endeavours’ in BR Energy (M) Sdn
parties to argue that financial constraints should not be
Bhd v KS Energy Services Ltd, previous decisions on the
taken into account in deciding whether best or reasonable
effect of the same words used in a different context must be
endeavours have been exercised in such cases.
viewed with caution. However, the decision in Ampurius
A good example is provided by the force majeure clause in potentially gives scope for argument over more general
the FIDIC 1999 suite. For example, clause 19.3 of the Red points of distinction, such as whether the incurring of
Book 1999 provides that ‘Each Party shall at all times use financial expense is something ‘antecedent or extraneous’ to
all reasonable endeavours to minimise any delay in the any given clause. For now, it is clear that parties should not
performance of the Contract as a result of Force Majeure.’ assume that a ‘reasonable endeavours’ clause (as opposed to
If a Force Majeure event occurs which is not one of those ‘all reasonable’ or ‘best’ endeavours clauses) will protect
listed in sub-clauses (ii) to (v) of clause 19.1 then the them from being required to incur such expense.
contractor is not entitled to the recovery of any Cost in
References: Phillips Petroleum Company United Kingdom v
relation to the Force Majeure event. Yet clause 19.3 still
Enron Europe [1997] CLC 329; Jet2.com Ltd v Blackpool Airport
requires that he use all reasonable endeavours to
Ltd [2012] EWCA Civ 417; Ampurius NU Homes Holdings Ltd v
minimise, not the impact of the event itself, but any delay
Telford Homes (Creekside) Ltd [2012] EWHC 1820 BR Energy
caused as a result of the event.
(M) Sdn Bhd v KS Energy Services Ltd [2013] SGHC 64.

9
Good faith and co-operation

English law is well known for having no general duty of good faith (unlike many other
legal systems). However, in 2012 a number of cases considered wide duties of good faith
and this trend appears to be continuing in 2013. The cases concern both implied duties,
where strong debate persists over whether such duties exist at all, and express contractual
duties, where equally strong debate is to be found over their interpretation. We discuss
both areas below and as the cases in this area continue to develop, readers can expect to
see more on this topic in next year’s publication.

Implied duties of good faith or more contracts for the provision of not less than 33500
hours of construction, design and engineering services’. In
In SNCB Holding v UBS AG the English Commercial Court the absence of such additional work, Skidmore was to pay
was asked to consider the implication of a duty of good a further amount to Jacobs.
faith arising under complicated banking arrangements.
Put simply, the agreement conferred a power on UBS to Skidmore argued that literal effect should not be given to
manage a certain part of the arrangements and it had the word ‘award’, in the sense of contracts actually
sought to do so for its own financial benefit and against entered into, as that would allow Jacobs to refuse to
the interests of SNCB, but still within the confines of the accept contracts which Skidmore offered it and thereby
parties’ express contractual terms. SNCB argued that UBS trigger the additional payment. Skidmore therefore
was required, by an implied term, to exercise its discretion argued for an obligation requiring it merely to offer
in good faith and in accordance with the aims of the contracts to Jacobs. The court disagreed, and found that
parties’ agreement. word ‘award’ could be given literal effect, if buttressed by
an implied term of good faith:
The court first reiterated the traditional position under
English law, that: ‘I consider that there were general obligations of good faith
on both sides in order to make this agreement work. …
‘Unlike some bodies of foreign law, commercial contracts [Skidmore] had to consider awarding contracts and Jacobs
are not subject to general duties of good faith and fair had to consider accepting such awards, both in good faith.
dealing and it is trite law that a party does not have to Only when an agreement was reached in good faith could
exercise his contractual rights, once properly ascertained, there be an award of a contract. Beyond that, on this
reasonably. If he has rights, the law will not concern interpretation, I can see no need for implied terms to
itself with the motivation or rationale lying behind his achieve mutuality.’
exercise of them …’
This decision stops a long way short of finding for a
The court accepted, however, that this principle was subject generally implied duty of good faith. Good faith was only
to the usual rules as to the implication of terms, such that a implied because without it the parties’ agreement as to the
term, including one as to good faith, could only be implied ‘award’ of contracts would have been unworkable. This
if it were necessary to make the contract work and not very much accords with the traditional English law
otherwise inconsistent with any express terms. No such approach to implied duties of good faith, which views
implied terms were found to apply to UBS and, aside from them as a measure of last resort. A much more liberal
a requirement to act honestly, UBS was entitled to act in its approach was, however, suggested in February 2013 in
own interests to the exclusion of SNCB’s. Yam Seng PTE Ltd v International Trade Corporation Ltd:

This position may be contrasted with Jacobs UK Ltd v ‘Under English law a duty of good faith is implied by law as
Skidmore Owings & Merrill LLP where a duty of good faith an incident of certain categories of contract, for example
was found to satisfy the test for implication of terms. contracts of employment and contracts between partners
Jacobs had sued Skidmore for the recovery of unpaid fees. or others whose relationship is characterised as a fiduciary
The parties agreed to settle the proceedings for the one. I doubt that English law has reached the stage,
payment of a certain amount together with a promise by however, where it is ready to recognise a requirement of
Skidmore, over the next two years, to ‘award Jacobs ... one good faith as a duty implied by law, even as a default rule,

10 | CMS London - English construction law developments 2012: An international perspective


into all commercial contracts. Nevertheless, there seems to deductions would not be made in an arbitrary, capricious
me to be no difficulty, following the established or irrational manner.
methodology of English law for the implication of terms in
fact, in implying such a duty in any ordinary commercial The Court of Appeal rejected the proposed implied
contract based on the presumed intention of the parties. … term, finding that it was not necessary to make the
I respectfully suggest that the traditional English hostility contract workable. Once service failings had been duly
towards a doctrine of good faith in the performance of recorded, the hospital was entitled to make the
contracts, to the extent that it still persists, is misplaced.’ deductions provided for by the contract for whatever
reasons it wished. The hospital’s discretion was merely
The judge’s point in Yam Seng appears to be that, while one as to the exercise of its own contractual rights
English law does not imply a duty of good faith as a and there was no need for any implied term in favour
default rule in all contracts, the approach taken in each of the contractor.
individual case should be more liberal and that such an
implication should, generally speaking, be made ‘in any
ordinary commercial contract’. Essentially, a default rule Express duties of good faith
by the back door.
The Court of Appeal’s decision in Mid Essex also provided
However, the English Court of Appeal wasted no time (in useful guidance as to the interpretation of express terms
March 2013) in seeking to restore the traditional approach; requiring good faith. Such terms are becoming
in Mid Essex Hospital Services NHS Trust v Compass Group increasingly common in English contracts (or terms that
UK and Ireland Ltd. Commenting generally, the court are considered to be similar such as the duty under the
reminded itself that: NEC/ECC forms to ‘act in a spirit of mutual trust and
cooperation’) and a body of law is beginning to emerge as
‘…there is no general doctrine of ‘good faith’ in English to how they ought to be interpreted under English law.
contract law, although a duty of good faith is implied by Key cases include:
law as an incident of certain categories of contract [i.e.
—— Berkeley Community Villages Ltd v Pullen: a clause
such as in employment contracts and partnership deeds]
requiring the parties to ‘act with the utmost good faith
… If the parties wish to impose such a duty they must do
towards one another’ in the context of a contract for
so expressly.’
land development was found to impose a duty
requiring the observance of reasonable commercial
Mid Essex concerned a long term catering contract for a
standards of fair dealing, faithfulness to the agreed
hospital. The contract provided for service failings to be
common purpose and consistency with the justified
recorded and for certain deductions to be made from
expectations of the other party.
payments due to the contractor based upon these failings.
The contract gave the hospital a discretion as to whether —— Gold Group Properties Ltd v BDW Trading Ltd: a clause
to make these deductions i.e. they were not automatic. requiring each party to ‘at all times act in good faith
The hospital’s position was therefore similar to that of an toward the other’ in the context of a development
employer under a construction contract enabling the agreement was found to impose a requirement that the
deduction of liquidated damages for delay. The contractor parties act in a way that allowed both of them to enjoy
contended that the hospital’s right to make these the anticipated benefits of the contract but did not
deductions was subject to an implied term that require either to give up a freely negotiated financial
advantage clearly embedded in the contract.

11
—— CPC Group Ltd v Qatari Diar Real Estate Investment References: Berkeley Community Villages v Pullen [2007]
Company: a clause requiring the parties to act ‘in the EWHC 1330 (Ch); Gold Group Properties Ltd v BDW
utmost good faith towards each other’ in the context Trading Ltd [2010] EWHC 1632 (TCC); CPC Group Ltd v
of a proposed development project was found to Qatari Diar Real Estate Investment Company [2010] EWHC
impose a requirement that the parties adhere to the 1535 (Ch); SNCB Holding v UBS AG [2012] EWHC 2044;
spirit of their contract, which was held to include the Jacobs UK Ltd v Skidmore Owings & Merrill LLP [2012]
seeking of planning consent for the maximum EWHC 3293; Yam Seng PTE Ltd v International Trade
developable area in the shortest possible time, the Corporation Ltd [2013] EWHC 111; Compass Group UK
observance of reasonable commercial standards of fair and Ireland Ltd (t/a Medirest) v Mid Essex Hospital Services
dealing, faithfulness to the common purpose and NHS Trust [2012] EWHC 781 (QB) and on appeal [2013]
consistency with the other’s justified expectations. EWCA Civ 200.

The clause in Mid Essex required the parties to ‘co-operate


with each other in good faith and … take all reasonable
action as is necessary for the efficient transmission of
information and instructions and to enable the [hospital] to
derive the full benefit of the Contract.’ The question before
the court was whether the clause should be interpreted
broadly so that the requirement to co-operate in good faith
applied to the whole of the contract, or narrowly, confining
it only to the transmission of information and matters
required for the hospital’s benefit.

The judge at first instance gave the clause a broad


interpretation, emphasising the long term nature of the
contract and the importance of co-operation between the
parties. The Court of Appeal reversed this decision,
however, finding that the judge had not given proper
consideration to the other more detailed provisions of the
contract. In the Court of Appeal’s opinion, express good
faith provisions in large commercial contracts should be
read subject to the more detailed provisions of the
contract. Lord Justice Beatson noted that:

‘The contract in the present case is a detailed one which


makes specific provision for a number of particular
eventualities. … In a situation where a contract makes such
specific provision, in my judgment care must be taken not
to construe a general and potentially open-ended
obligation such as an obligation to ‘co-operate’ or ‘to act in
good faith’ as covering the same ground as other, more
specific, provisions, lest it cut across those more specific
provisions and any limitations in them.’

Conclusion
Duties of good faith seem likely to remain a focal point for
English law for sometime to come, as more liberal efforts to
widen the traditional approach continue to be pressed in
individual cases. For the time being, however, the Court of
Appeal’s decision in Mid Essex would appear to have
affirmed the traditional approach, restricting implied terms
to those which are necessary to make a contract workable
and reading express obligations of good faith subject to
other more specific contract provisions.

12 | CMS London - English construction law developments 2012: An international perspective


Clients say that what makes CMS special is a combination of
three things: strong, trusted client relationships; high quality
advice; and industry specialisation.
Chambers & Partners UK
Implied terms as to progress and quality

In addition to the ongoing debate over implied duties of good faith, discussed in the preceding
article, a number of recent cases deal with the extent to which terms may be implied into
construction contracts. Three cases in particular have shown the potentially surprising results
which can sometimes depend upon the implication of terms. Insofar as they involve issues of
quality and design such terms will often flow from the specific terms of UK legislation, but will
apply internationally where English law is chosen by the parties.

Leander Construction Limited v Mulalley Dalmare SpA v Union Maritime Limited


and Company Limited and Valor Shipping Limited
Leander related to a groundworks sub-contract. The main Dalmare concerned the purchase of a ship. The dispute
contractor, Leander, initially claimed that the subcontractor, arose due to the ship breaking down thirty hours into a
Mulalley, was obliged to perform its works in accordance voyage and about a month after delivery due to an engine
with an Activity Schedule which set out the dates by which problem. Although the seller was Norwegian and the ship
certain activities were required to be completed. It was was inspected and delivered in Greece and Turkey
claimed that Mulalley was late in performing the sub- respectively, the sale agreement contained an express
contract works, as against the Activity Schedule, and that choice of English law and the buyers therefore argued that
Leander consequently suffered loss due to the delay. the seller was in breach of the implied term of satisfactory
quality provided by the Sale of Goods Act 1979 (UK).
Later, it was accepted by Leander that the Activity Schedule
was not binding on Mulalley but Leander claimed that, in The seller argued that the implied term under the Sale of
any event, there was an implied duty on the subcontractor Goods Act was inconsistent with the express terms of the
to proceed ‘regularly and diligently’. Leander alleged that sale agreement, which provided that the ship would, ‘be
Mulalley had failed to proceed in a regular and diligent delivered and taken over as she was at the time of
fashion, as it did not follow the Activity Schedule. Leander inspection, fair wear and tear excepted.’ The seller argued
sought to draw support for its argument from the fact that that the ship had been delivered in the same condition as
the sub-contract gave Leander an entitlement to terminate at the time of inspection and that this express clause of the
if Mulalley failed to proceed regularly and diligently (subject sale agreement left no room for the implied term provided
to certain notice requirements). for by the Sale of Goods Act.

The court dismissed Leander’s claim and held that it was The court found that these words were insufficient to
not necessary to imply a term to proceed regularly and exclude the obligation of satisfactory quality implied by the
diligently to make the contract workable. Mulalley was Sale of Goods Act and in doing so, upheld the traditionally
already required to complete the sub-contract works by a strict approach to ousting the Act’s applicability. Although
specified completion date. Mulalley therefore had a section 55(1) of the Act allows the parties to exclude its
discretion as to how fast or slow it would proceed during implied obligations ‘by express agreement’, section 55(2)
certain periods of the works, subject to its ultimate duty to states that, ‘An express term does not negative a term
complete the works by the date specified. The express implied by this Act unless inconsistent with it.’ This
power to terminate for a failure to proceed regularly and provision has been interpreted strictly in the past, to the
diligently was, perhaps surprisingly, found by the court to extent that even a clause excluding all ‘guarantees,
work against the implication of a term. That was because warranties or misrepresentations, express or implied [of]
the right of termination showed that the parties had merchantability, fitness or suitability’ has been held to be
expressly considered the issue, but yet had not provided for insufficient because the terms implied by the Act are legally
any express duty to proceed regularly and diligently (as categorised as ‘conditions’ rather than ‘warranties’: see
opposed to a right of termination). As the court noted, ‘it is most recently, Bominflot v Petroplus Marketing (‘The
impossible to argue that the alleged term is necessary, in Mercini Lady’). Although this rule has been criticised as not
circumstances where the parties must be taken to have representing the true intention of the parties with regard to
considered this eventuality and instead decided to deal such clauses, the approach of the courts has been to
with the potential problem in an entirely different way.’ ‘consider that the parties to this English law contract,

14 | CMS London - English construction law developments 2012: An international perspective


foreign as both of them are and quite possibly ignorant of supply of goods under the Supply of Goods and Services
the consequences of their choice of language, intended to Act 1982 and that accordingly the system was required to
contract by reference to what English law had to say about be fit for purpose. ADT argued that, while each component
the language which they have adopted.’ of the system was to be fit for purpose, it was only required
to exercise due care, skill and diligence in the overall design
Adopting this strict approach, the sale agreement entered of the system.
into by Dalmare was insufficient to negative the statutory
implied term of satisfactory quality. While on one The court’s analysis of this issue centred on the proper
interpretation the agreement could mean that the ship was characterisation of the system designed by ADT. Section 4
to be delivered in an entirely ‘as is’ condition, an alternative of the Supply of Goods and Services Act provides for an
interpretation was that the seller was simply to make no implied term of fitness for purpose in respect of any ‘goods
alteration to the condition of the ship between inspection supplied under the Contract’. The question was therefore
and delivery (and thereby saying nothing about standard of whether the system as a whole, as opposed to its individual
quality warranted by the seller). Accordingly, the clause was components, could be properly characterised as ‘goods’.
not sufficiently clear and could not be said to be sufficiently Lord Justice Tomlinson, in delivering the judgment of the
‘inconsistent’ to displace the term implied by the Sale of Court of Appeal, did not think so:
Goods Act:
‘… I do not regard it as either natural or accurate to regard
‘Given the strict approach to construction of terms Cadbury as having bought from ADT a system which can
alleged to exclude the statutory implied terms consistently be equated with goods which are either of good quality or
adopted by the courts … the fact that even on the sellers’ not as the case may be. I can understand that that
best case the words must have more than one meaning is description might possibly be apt if Cadbury had contracted
fatal to the sellers’ case that these words exclude the to purchase, or ADT had contracted to supply, a standard
statutory implied terms. Furthermore, given that an kit or assembly. In such circumstances there would,
obvious sensible meaning of the words is as part of the ordinarily, be no element of design in order to meet specific
temporal obligation [i.e. that the vessel be delivered in the requirements. …The present is, as it seems to me, a very
same condition as it was when inspected], section 55(2) different situation. … what was offered was not a standard
defeats the sellers’ argument, since it cannot be said that product to be taken off the shelf and chosen by reference
the first sentence of clause 11 is inconsistent with the to its description. If what was offered could properly be
implied term in section 14(2).’ described as a product at all, which I doubt, it was at best a
bespoke product in respect of which what was of
importance was not so much the inherent quality of the
Trebor Bassett Holdings Ltd v ADT Fire constituent parts (which was of course required to be
good) but rather their selection as being suitable for the
and Security Plc task and the manner in which they were to be combined,
located and installed in such manner as ‘to suit the specific
Statutory implied terms were again before the court in
requirements of the risks to be protected’. In these
Trebor. That case concerned a fire suppression system
circumstances it is I think wholly artificial to regard ADT as
designed by ADT. The system failed and as a result the
having contracted to supply a system which can be equated
claimant’s factory burnt down. Part of the case concerned
with ‘goods’ and of which it can simply be asked in the
the extent of ADT’s liability for the design of the system.
abstract, was it or was it not of good quality.’
The claimant argued that the system amounted to the

15
Two interesting observations can be made about this decision: responsible for the design or specification of the Permanent
Works’ (expect where specific parts of the Works are stated
—— This decision would appear to be at odds with a
to be the contractor’s design). This therefore forms the
previous decision in which a ‘system’ had been held
minimum express design obligation within the FIDIC 1999
to be ‘goods supplied’ under the Supply of Goods
suite i.e. ensuring the suitability of Plant and Materials. To
and Services Act. In John Lelliott v Byrne Bros
this, however, must be added – where English law applies
(Formwork) Ltd an agreement to provide a
– the more general implied obligations arising under the
‘temporary support system’ (comprising steel tubes
Supply of Goods and Services Act of satisfactory quality
and woodwork, similar to scaffolding) was found to
and, in certain circumstances, fitness for purpose for any
be subject to an implied duty (under the Act and at
materials in which ownership is to pass to the employer.
common law) of fitness for purpose. That obligation
These implied obligations may also apply to distinct parts of
was breached because the system, as opposed to
the works if that part of the works can be distinctly
individual items of which it was made up, did not
characterised as ‘goods’ in its own right. Specific words
provide sufficient support. As the Court of Appeal
must be used to exclude these terms, as Dalmare shows,
noted in Trebor, the question in any given case as to
and they are unlikely to be entirely excluded by the
whether a ‘system’ amounts to goods or not is
standard wording quoted above.
largely a matter of impression, however, it remains to
be seen how far the court’s distinction between
Although all of the FIDIC 1999 suite expressly impose on
bespoke and ‘off the shelf’ products will be applied.
the contractor a ‘fitness for purpose’ duty where it is
—— Quite aside from the Act, it is well established at required to design all or part of the Works, the duty is
common law that a contractor who agrees to design limited to those purposes ‘specified in the Contract’ (Red
and construct works impliedly agrees that the works Book 1999 and MDB) or ‘as defined in the Contract’
will be fit for purpose (IBA v EMI Electronics Ltd). The (Silver and Yellow Books 1999 and Gold Book 1999 and
Court of Appeal’s decision in Trebor would appear to 2008). The duty implied by English law operates more
leave this rule untouched as it does not depend on any broadly by reference to any purpose ‘made known’ to the
requirement for the works to be characterised as contractor by the employer, whether expressly or by
‘goods’ (it is unclear why the common law point was implication. As this implied duty falls within a special
not pursued in Trebor itself). At common law, the category of implied terms under English law (known as an
courts have specifically resisted attempts to divide up ‘implication by law’), it must be expressly excluded. To the
the works, as was done in Trebor, ‘into so many pieces extent that any express term covers part (but not all) of
with differing criteria of liability’ when ‘the … implied the ground covered by such an implied term (as is the case
term of fitness for purpose … prescribes a relatively in the FIDIC 1999 suite), the implied term will continue to
simple and certain standard of liability based on the apply to ‘fill the gaps’: Davy Offshore Ltd v Emerald Field
reasonable fitness of the finished product irrespective Contracting Ltd. Accordingly, under the FIDIC 1999 suite,
of considerations of fault and of whether its unfitness the narrower express terms as to fitness for purpose
derives from the quality of work or materials or design’ restricted to the purpose specified or defined in the
(Viking Grain Storage Ltd v TH White Installations Ltd). contract could be supplemented by a wider duty based
upon any additional purposes made known to the
contractor when the contract was concluded. In some
Conclusions instances this may impose an unexpected (and
unwelcome) extra burden on the contractor.
These decisions all have the potential to affect international
construction contracts and show the difficult and surprising References: IBA v EMI Electronics Ltd (1978) 11 BLR 29
issues which can be posed by the implication of terms (Court of Appeal); (1980) 14 BLR 1 (House of Lords); Viking
under English law. Grain Storage Ltd v TH White Installations Ltd (1985) 3 Con
LR 52; Davy Offshore Ltd v Emerald Field Contracting Ltd
The relevance of Leander will be minimised for contracts (1991) 55 BLR 1; John Lelliott v Byrne Bros (Formwork) Ltd
with express provisions as to progress, such as that in (1992) 31 Con LR 89; Bominflot v Petroplus Marketing (‘The
clause 8.1 of the FIDIC Red, Yellow and Silver Books 1999 Mercini Lady’) [2010] EWCA Civ 1145; Leander
(‘… shall then proceed with the Works with due expedition Construction Limited v Mulalley and Company Limited
and without delay’). However, parties should not expect [2011] EWHC 3449; Dalmare SpA v Union Maritime Limited
any further or additional duties in this regard to be implied. and Valor Shipping Limited [2012] EWHC 3537; Trebor
Bassett Holdings Ltd & Anor v ADT Fire and Security Plc
Trebor and Dalmare are likely to be relevant in most cases [2012] EWCA Civ 1158.
where English law is specified as the governing law. Under
the FIDIC Red Book 1999, for example, the contractor is
expressed to be responsible for ‘such design of each item
of Plant and Materials as is required for the item to be in
accordance with the Contract’ but is not ‘otherwise …

16 | CMS London - English construction law developments 2012: An international perspective


A major player in the area, offering a strong
construction service to both purchaser and
supplier-led clients. The group is also singled out
for its expertise in international arbitration.
Chambers & Partners UK
Global claims

The judgment in Walter Lilly v Mackay was one of the most talked about in English legal
circles last year. It was notable for its restatement of the rules governing the making of
‘global’ and ‘total cost’ claims in construction disputes.

In 2004 Walter Lilly & Company (WLC) entered into a contract impossible to present the claim in a more conventional
with an employer (DWM) for the construction of three large fashion. Moreover, it was thought by some that the contractor
houses on the site of what was previously the Earls Court should also show that he was not responsible for whatever
Telephone Exchange. One of the three plots of land was impossibility was present. For example, in London Borough of
owned by Mr Mackay, who was a part-owner of DWM. Merton v Leach the approach was described as follows:
The contract price for Mr Mackay’s property was c. £5 million
and the date for completion was 23 January 2006. ‘If … at the time when the loss or expense comes to be
ascertained it is impracticable to disentangle or disintegrate
Unfortunately, things did not progress according to plan and by the part directly attributable to each head of claim, then,
the time that Practical Completion was achieved in July 2008, provided of course that the contractor has not unreasonably
the relationship between WLC and Mr Mackay was delayed in making the claim and so has himself created the
acrimonious in the extreme. Mr Mackay blamed WLC for the difficulty the architect must ascertain the global loss directly
delays and also for what he felt were defects in the works. attributable to the two causes …’ [emphasis added]
In the words of Mr Justice Akenhead, he was ‘and [had] been
for a long time angry’. WLC on the other hand, did not accept This line of authority provided an opportunity for
that it was responsible for the delays to the works and believed defendants to bring an early attack on global claims
that it was entitled to an extension of time, along with relief through attacks on the claimant’s submissions. If a global
from liquidated damages, up to Practical Completion. claim had been pleaded, defendants could justifiably call
for the claimant to assert and/or provide details of why it
Among other defences raised by DWM, it was argued that was said to be impracticable or impossible to disentangle
WLC’s claim should fail on the grounds that it was a ‘global’ the various breaches or events relied upon.
claim. A global claim is one whereby an aggregated loss or
period of time is based on a group of individual breaches or Mr Justice Akenhead’s judgment in Walter Lilly means that
events without attempting to prove the individual impact of this approach is now no longer good law. Having considered
each breach or event. Where the claim is one for money the cases usually relied upon in support of such an approach
rather than time, such claims are often referred to as ‘total (such as Merton), the judge concluded as follows:
cost claims’ reflecting the fact that they often proceed simply
from the contractor’s total cost for the project, less the ‘Obviously, there is no need for the Court to go down the
amount paid to date by the employer. As Mr Justice global or total cost route if the actual cost attributable to
Akenhead (the head of the Technology and Construction individual loss causing events can be readily or practicably
Court) noted, such claims are usually formulated on the basis determined. I do not consider that Vinelott J was saying in the
of ‘numerous potential or actual causes of delay and/or Merton case (at page 102 last paragraph) that a contractor
disruption, a total cost on the job, a net payment from the should be debarred from pursuing what he called a ‘rolled up
employer and a claim for the balance between costs and award’ if it could otherwise seek to prove its loss in another
payment, which is attributed without more and by inference way. It may be that the tribunal will be more sceptical about
to the causes of delay and disruption relied on.’ the global cost claim if the direct linkage approach is readily
available but is not deployed. That does not mean that the
global cost claim should be rejected out of hand.
Disentanglement
[The] argument that a global award should not be allowed
Before Walter Lilly, certain cases suggested that a ‘global where the contractor has himself created the impossibility
claim’ would only be permitted where a contractor could of disentanglement (relying on Merton per Vinelott J at
show that it was impossible to disentangle or separate out 102, penultimate paragraph and John Holland per Byrne J
those individual losses caused by individual breaches or at page 85) is not on analysis supported by those
events. In other words, a contractor could not simply be lazy authorities and is wrong. Vinelott J was referring to
in presenting its claim, but would need to show that it was unreasonable delay by the contractor in making its loss

18 | CMS London - English construction law developments 2012: An international perspective


and/or expense claim; that delay would have led to there This passage potentially suggests that greater flexibility and
being non-compliance with the condition precedent but pragmatism will be accorded to claimants in bringing global
all that he was saying otherwise was that, if such delay claims. Whereas formerly, a defendant might rely on a number
created difficulty, the claim may not be allowed. He of counter-examples to attempt to show the claim was
certainly was not saying that a global cost claim would be fundamentally unsound, a claimant might now respond simply
barred necessarily or at all if there was such delay. … In that whatever counter-examples are proved can be deducted
principle, unless the contract dictates that a global cost from the global loss and the remainder will ‘generally be …
claim is not permissible if certain hurdles are not attributable to … events [for] which the contractor is entitled to
overcome, such a claim may be permissible on the facts recover loss.’ If pressed too far, this approach has the potential
and subject to proof.’ in practical terms to shift part of the burden of proof to the
defendant. A defendant should now ensure that its list of
counter-examples is as complete as possible and will be less
Counter-examples able to rely upon arguments that the mere existence of counter-
examples fundamentally undermines the claim.
One of the most forceful ways in which a global claim can be
undermined is to show that there are other causes for the loss
claimed by the contractor for which there is no entitlement to Conclusion
recover under the contract. Prior to Walter Lilly, it was
sometimes argued that such ‘counter-examples’ would In January 2013 the Court of Appeal refused leave to appeal
undermine the claim entirely and that no apportionment of from the decision in Walter Lilly. In doing so it remarked that
the global loss could be made to save the claim. Either the it was ‘not reasonably arguable that the judge erred in his
global claim wholly succeeded or it wholly failed. analysis of the law as to what is required in respect of a
global claim.’ It appears therefore that Mr Justice Akenhead’s
Whatever the basis for this line of argument, it has now findings are here to stay and must now be applied.
been considerably weakened by the decision in Walter Lilly.
The approach preferred by Mr Justice Akenhead was for Whilst the requirements for proof of a global claim remain
any established counter-examples to be deducted from the onerous, they are now less so than was previously thought.
global loss, insofar as they can be quantified, ‘either They remain, however, subject to the express terms of the
precisely or at least by way of assessment’. Such an parties’ contract. It remains notable how little standard
approach was thought by the judge to be: forms say about the issues commonly encountered in
construction disputes (like the admissibility of global claims).
‘not inconsistent with the judge’s reasoning in the Merton One might expect Walter Lilly to prompt some employers to
case that ‘a rolled up award can only be made in the case write into their contracts terms prescribing when (if at all)
where the loss or expense attributable to each head of global claims can be made. Absent such express terms,
claim cannot in reality be separated’, because, where the employers would be well advised to take global claims
tribunal can take out of the ‘rolled up award’ or ‘total’ or seriously and to consider them on their merits.
‘global’ loss elements for which the contractor cannot
recover loss in the proceedings, it will generally be left with References: London Borough of Merton v Stanley Hugh
the loss attributable to the events which [sic] the contractor Leach (1985) 32 BLR 68; Walter Lilly & Company Ltd v
is entitled to recover loss.’ Mackay [2012] EWHC 1773 and on application for leave to
appeal [2013] EWCA Civ 142.

19
Indirect and consequential loss exclusions

Construction and engineering contracts often contain provisions excluding or limiting liability
for ‘consequential loss’ with or without the addition of the phrase ‘loss of profit’. These two
concepts are often used interchangeably by commercial parties, however, English law has long
held that they are distinct. Loss of profit is a broader category than consequential loss and an
exclusion clause which is limited to ‘consequential loss’ will not usually exclude all claims for
‘loss of profit’. A decision of the English Technology and Construction Court last year provides
a further example of this distinction applied in practice.

ADS Aerospace v EMS Global Tracking 2. Any other damages which may reasonably be supposed
to have been in the contemplation of both parties at
Aerospace and Global joined forces to develop and sell a the time they made the contract. This category depends
new satellite tracking device for use in the high-end upon additional facts being known to both parties.
aeronautical market. The parties entered into an exclusive In the above example of the factory it may be that lost
worldwide distribution agreement, under which Global production included the loss of a particularly profitable
agreed to produce and supply the device to Aerospace until contract. The loss of such a production contract would
Global gave Aerospace 12 months’ notice of its intention to not be recoverable unless the parties knew, at the time
cease production. the construction contract was entered into, that the
production contract might be lost as a result of a
The venture was a failure and only 17 devices were sold. breach of the construction contract. These are
Following unsuccessful discussions about a new product, ‘consequential’ or ‘indirect’ losses.
Global gave notice that it would cease production of the
devices in 12 months. Aerospace complained that Global In deciding against Global, the court adopted this line of
had, in breach of contract, ceased production of the authority, noting that, ‘parties who draft contracts which
devices earlier than the end of the 12 month notice period are subject to English law can be taken to appreciate
and claimed damages as a result. the difference between the two limbs [from Hadley v
Baxendale].’ The court found no reason to distinguish the
The contract between the parties provided that Global specific circumstances applying to the contract between
would not be liable ‘for any consequential loss or damage, Aerospace and Global and found that the reference to
whether for loss of profit or otherwise and whether ‘consequential’ loss was a reference to losses falling
occasioned by the negligence of [Global] or his employees within the second limb of Hadley v Baxendale.
or agents or otherwise, arising out of or in connection with
any act or omission of [Global]…’. In this context the court viewed the subsequent reference
to ‘loss of profit’ as merely a subcategory of ‘consequential
Several decisions of the English Court of Appeal have loss’. The court ruled that: ‘What is excluded … is liability
ruled that contractual exclusions such as this referring to ‘for any consequential loss or damage’ and an example of
‘consequential and indirect losses’ will usually be limited to this is given as ‘loss of profit’. However, loss of profit does
losses which fall within what is known as the ‘second limb’ not define ‘consequential loss or damage’ it is simply a type
of Hadley v Baxendale. Hadley v Baxendale is an old and of consequential loss or damage.’
well known decision in English law establishing a
fundamental division between two types of recoverable Pushed firmly therefore into the second category of Hadley v
losses for breach of contract: Baxendale, Global attempted to argue that the loss of profit
claimed by Aerospace was not, in any event, direct loss of
1. Damages that may fairly and reasonably be considered
profit within the contemplation of the parties. Once again
as arising naturally, i.e. according to the usual course
the court reaffirmed the usual position that such losses are
of things, from a breach of contract. For example,
direct losses and not ‘consequential’. As the court noted:
if the breach involved the destruction of a factory,
‘the whole purpose of the exclusive distribution agreement
both the cost of rebuilding and losses from the lack of
was distribution and onward sale by ADS to customers and it
production during rebuilding would fall within this first
must have been within the reasonable contemplation of the
category. Such damages are said to be ‘direct losses’.
parties that a wholesale refusal to supply the goods would

20 | CMS London - English construction law developments 2012: An international perspective


result in the inevitable loss of profit on those onward sales. and consequential losses. Accordingly, ordinary loss of
Such loss therefore is not ‘consequential’; it is direct and profit/production falling within the first category of Hadley
firmly within the first limb of Hadley v Baxendale.’ v Baxendale had been successfully excluded.

The same finding has been made in a number of other


cases. In Corfield v Grant, the owner of a hotel that was Conclusion
closed for longer than anticipated due to works being
carried out was found to be entitled to recover profit that he Loss of profit can be either a direct loss or an indirect loss.
could reasonably have expected to earn had the hotel been Parties to construction contracts will be taken to be aware
finished on time as a direct loss. Similarly, in Robertson of the difference between both categories and should
Group (Construction) Limited v Amey-Miller (Edinburgh) JV a therefore be clear when drafting exclusion clauses as to
‘stop gap’ contract allowed the recovery of ‘all direct costs whether one or both are to be excluded.
and directly incurred losses’. The contractor claimed that it
was entitled to recover damages for loss of profit as a direct Set out below are a selection of exclusion clauses found in
loss where it had been prevented from carrying out work it common standard forms, together with an indication of
was entitled to perform under its contract. Both the appeal their likely effect based on the above cases. However, it
court and the court at first instance held that the loss of should be borne in mind that insofar as any breach occurs
profit could be recovered as a direct loss, accepting that ‘[t] before completion and causes delay-based losses (e.g. due
he intention to make a profit lies at the heart of all, or nearly to loss of production), English law assumes they will be
all, commercial activity’. compensated by any liquidated damages for delay (unless
any words to the contrary appear; which they do not in any
These cases may be contrasted with those where the of the standard forms dealt with below).
parties have successfully excluded direct losses. A good
example is BHP Petroleum Ltd v British Steel plc where the References: Hadley v Baxendale (1854) 9 Exch 341; Corfield
relevant clause excluded ‘loss of production, loss of profits, v Grant (1992) 59 BLR 102; BHP Petroleum Ltd v British
loss of business or any other indirect losses or Steel plc [1999] 2 All ER (Comm) 544; Robertson Group
consequential damages’. With the reference to ‘loss of (Construction) Limited v Amey-Miller (Edinburgh) JV [2005]
profit’ now preceding ‘consequential damages’ the court in CSOH 60 and [2005] CSIH 89; ADS Aerospace Limited v
that case held that the claim was not confined to indirect EMS Global Tracking Limited [2012] EWHC 1012 (Ch).

Contract Wording Effect


FIDIC ‘…loss of use of any Works, loss of profit, loss of Loss of profit/production not recoverable, whether
any contract or for any indirect or consequential direct or indirect.
loss or damage …’
Orgalime ‘… loss of production, loss of profit and other Loss of profit/production not recoverable, whether
indirect loss …’ direct or indirect (applying BHP v British Steel).
JCT (D&B) ‘… loss of use, loss of profit or other Loss of profit/production not recoverable, whether
consequential loss…’ direct or indirect (applying BHP v British Steel).
NEC ‘… indirect or consequential loss …’ Direct loss of profit/production still recoverable.

21
Contractual damages: expected losses,
unexpected liability?
As noted in the preceding article, parties often overestimate the protection given by contractual
exclusions for ‘consequential’ or ‘indirect’ loss. As with ‘loss of profit’, losses which are contingent on
matters outside the control of the parties are sometimes referred to as being ‘consequential’ or
‘indirect’ but may in fact be ‘direct’ losses when properly categorised under English law. For example,
claims for loss of production are often subject to market forces such that an employer may claim to
have missed out on higher profits. Conversely, an employer’s claim may be reduced by poorer market
conditions. Such claims are therefore contingent on matters outside the control of the parties, but
may still be ‘direct’ losses within the categorisation referred to in the preceding article.

English law adopts a reasonably liberal approach to such contingent losses. Provided the type of loss is recoverable either as
‘direct’ or ‘indirect’ loss and was therefore reasonably foreseeable (as discussed in the previous article), there is limited scope for
defendants to argue that the outcome in any given case is harsh or disproportionate i.e. because the actual size of the loss was
particularly unexpected or abnormal. As a case last year shows, this can lead to surprising results.

—— the engineer knew that its road and drainage design was
John Grimes Partnership Ltd v Gubbins needed for planning approval, and therefore that the
late provision of the design would mean a delay in the
The facts of the case were as follows:
employer obtaining planning approval and
—— An owner of land engaged a consulting engineer to
—— the engineer, being experienced in property development
prepare a road and drainage design for a parcel of land
work, understood that a delay in obtaining planning
that the owner wished to develop.
approval could mean that the employer would suffer
—— The engineer’s design was (as the engineer knew) to be the very type of loss it did, namely a loss of property value
submitted to the local council as part of the planning due to a downturn in the property market.
approvals process. The design was required to be The type of loss was ‘reasonably foreseeable’, and therefore
provided to the employer by March 2007. recoverable (there being no term in the engineer’s
appointment that would exclude or limit its liability, in this
—— However, the completed design was in fact only provided
respect). In these circumstances, it was
a year or so later, in May 2008. The council approved the
not necessary for the court to determine whether the loss
design two days after it was submitted.
was ‘direct’ or ‘indirect’ (i.e. even if the loss was ‘indirect’,
—— The engineer invoiced the employer for an additional the engineer had sufficient notice as to its likelihood and
£3,000, on top of what it had invoiced and been paid there was no contractual exclusion of liability).
previously. The employer refused to pay the £3,000
(citing the engineer’s delays), and the engineer sued for
that amount. Comment
—— The employer counterclaimed against the engineer for
On one view, the facts of the case were straightforward,
around £400,000. This was on the basis that the value of
and should have led to the result that the Court of Appeal
the property had fallen by that sum during the period of
reached. It was known to all parties that if the engineer was late
delay by the engineer in preparing its design (from March
in providing its design, the property market could go down
2007 to May / June 2008). The employer contended that
during the delay, and the employer would therefore suffer a
if the engineer had prepared its design on time, and
financial loss due to the engineer’s breach of contract. The type
planning approval had been obtained (in around April
of loss may have been contingent in the sense that it was a
2007), the employer would have been able to realise a
knock-on result of the engineer being late, but it was certainly a
£400,000 greater return on its development. The
reasonably foreseeable type of loss – one that was not too
employer’s case was that the engineer should be legally
‘remote’ from the breach. On this view, the employer’s loss was
responsible for the employer’s loss suffered during the
rightly held recoverable.
downturn of the property market.
There is, however, another way of looking at the case which
The court at first instance and on appeal upheld the
leads to the opposite conclusion. The employer’s loss may indeed
employer’s argument, finding the engineer liable for the
have been ‘reasonably foreseeable’, but it was not one which
£400,000 loss. The logic of the court’s reasoning was that:
directly flowed from the breach, in the sense that it was by no
means an inevitable result of the engineer being late in providing

22 | CMS London - English construction law developments 2012: An international perspective


its design. The property market could have gone up, down or
stayed at the same level. Although as a matter of strict logic the
Commercial implications for international
engineer’s breach of contract may have pushed the project into a projects
period that was adverse to the employer’s financial interests, the
engineer’s breach of contract did not cause the property market If one extrapolates the reasoning used in the Grimes case, all
to go down. So why should the engineer be liable because a sorts of consequences can be envisaged for parties working on
matter outside of its or the employer’s control occurred, i.e. the international projects. Negative fluctuations in the value of the
property downturn? output of the asset that a contractor or designer has promised
to build or design – whether it be a hotel, an office building, a
Conversely, if instead of going down, the property market had in
power plant or a factory – may all be legally attributed to the
fact gone up during the period of delay, the employer would
contractor or designer in the event of the contractor or designer
have reaped the benefit of the delay, but the engineer would
being late, provided that those losses are reasonably foreseeable
have no entitlement to share in that benefit. Does English law
(which often they are).
allow an employer to take the upside of a delay, but not the
downside? Minds may differ on whether such a position is justified. To best manage the risks associated with market fluctuations,
contractual provisions should be used to control liability.
The competing view takes its support from the judgment
Some ways in which this is commonly done are:
of Lord Hoffmann in Transfield Shipping Inc v Mercator Shipping
Inc (also known as ‘The Achilleas’), which accepts that in some —— Limiting liability for delay to a contractually-defined amount.
circumstances it is not correct to hold a contract breaker liable Liquidated damages clauses are the prime way of effecting
for all of the direct losses which flow from its breach: such a limitation of liability for delay to the works. However,
they do not usually cover delays after completion from, say,
‘It seems to me logical to found liability for damages upon the
carrying out remedial works.
intention of the parties (objectively ascertained) because all
contractual liability is voluntarily undertaken. It must be in —— Excluding or limiting liability for ‘indirect’ or ‘consequential’
principle wrong to hold someone liable for risks for which the losses. As noted in the preceding article, these types of
people entering into such a contract in their particular market, exclusion clauses are relatively common, however they will
would not reasonably be considered to have undertaken. … In not serve to exclude the impact of those contingencies,
other words, one must first decide whether the loss for which including market fluctuations, which may increase the usual
compensation is sought is of a ‘kind’ or ‘type’ for which the amount of ‘direct losses’. They are therefore likely, at best,
contract-breaker ought fairly to be taken to have accepted to provide an incomplete protection.
responsibility.’
—— More specific exclusions for ‘loss of profit’, ‘loss of production’,
The Court of Appeal in Grimes referred to this passage, ‘loss of use’, ‘loss of capital’, ‘loss of goodwill’ etc are usually
but emphasised the fact that no evidence had been presented by more effective (see for example, clause 17.6 of the FIDIC Red
the engineer to the effect that there was any general Book 1999). Parties might also seek to eliminate the effect of
understanding or expectation in the property world that a party contingent losses altogether by stating that the measure of
in the engineer’s position would not be taken to have assumed damage for any breach of contract shall be limited to losses
responsibility for losses arising from movement in the property which would ordinarily be incurred and not extend to any
market where there had been culpable delay. In the absence of unusual or extraordinary losses (although care would need
such evidence, the Court of Appeal considered itself bound to to be taken in the drafting of such a clause).
apply the traditional rule from Hadley v Baxendale (referred to in
References: Hadley v Baxendale (1854) 9 Exch 341; Transfield
the preceding article) that a party is entitled to recover all losses
Shipping Inc v Mercator Shipping Inc (‘The Achilleas’) [2008]
of a type which were reasonably foreseeable (either because
UKHL 48; John Grimes Partnership Ltd v Gubbins [2012]
they ordinarily occur and are ‘direct’ losses or if they are
8PL03589 (TCC) and on appeal [2013] EWCA Civ 37.
‘indirect’ losses not ordinarily occurring, because the defendant
was specifically made aware of their likelihood). 23
Settlement agreements

Settlement agreements, whether formal or informal, are commonplace in international


construction projects. Whenever claims arise for additional time or extra cost, the parties
will often agree certain entitlements in ‘full and final settlement’ of the contractor’s claims
or in respect of a certain part or phase of the Works. Similarly where deductions are made
from payments on account of defective work, the parties may seek to reach agreement and
fix the proper amount ‘due’ to the contractor taking into account the defective work and
‘any other outstanding matters’. The effect of such agreements and such familiar forms of
words are sometimes misunderstood and may lead to parties giving away more (or less)
than they had expected. A decision of the Technology and Construction Court last year
provides a useful example.

Point West was the developer of a large residential claiming that Mivan’s liability in respect of those issues was
complex constructed on the site of an old West London not released by the settlement agreed between them. Point
airport terminal. Mivan was engaged as the contractor for West argued that, at the date of the settlement, there was
the fourth phase of the development which consisted of no reason for either party to suppose that Point West was
the design and construction of a marketing suite, sky considering making a claim against Mivan for those issues.
lobby and 48 apartments. Mivan’s final account was There was no actual dispute between Point West and
agreed in 2002 but not paid. Between 2002 and 2007, Mivan in relation to those issues and neither had Point
various remedial works were carried out and finally, in West intimated a claim or even the possibility of a claim in
October 2007, the parties agreed a settlement to ‘enable respect of them. Point West therefore argued that the
Mivan to walk away’. terms of the settlement should be read down to apply only
to claims which were specifically contemplated at the time
The settlement was stated to be ‘regarding Mivan’s Final the settlement was agreed.
Account in respect of all Works carried out, and any
corresponding outstanding matters. The agreement The court disagreed with Point West and considered that
comprises a further payment of £50,000 (including VAT), the wording of the agreement made it clear that it was
representing the final assessment of monies due or to intended to achieve ‘full and final settlement in respect of
become due thus achieving full and final settlement in the above works’, being all of the contracted works,
respect of the above works, together with any and all together with ‘any and all outstanding matters’. The
outstanding matters. We would confirm that this final defects in Flat 1601 were deemed to be ‘outstanding
agreement concludes Mivan’s responsibilities and matters’, despite not being the subject of a dispute
obligations in respect of their works at the above project.’ between the parties, and were therefore included in the
settlement. The judgment confirms that the courts are
At the time of the agreement, both parties were aware that reluctant to find that parties have surrendered unknown
there was a potential issue with the curtain walling and the claims (as already stated by the House of Lords in Bank of
heating and cooling system (although the scope of the Credit and Commerce International (SA) v Ali), but at the
defects was uncertain). The owner of Flat 1601 had made a same time recognised that the intention of parties using
number of complaints over the years in respect of both clauses referring to ‘full and final settlement of all matters’
issues but Point West viewed the complaints as unjustified often was to resolve all possible matters, including those
and minor in nature. As part of the settlement agreement, that might be advanced in the future in respect of the same
Mivan had agreed to assist Point West in the event of a set of circumstances.
dispute with the owner of Flat 1601, though it was
expressly stated that Point West would not look to Mivan The court’s ultimate finding as to the terms of the
to carry out any remedial works. settlement was that it released the issues raised by Flat
1601 together with any ‘other defects in the Point West
The owner of Flat 1601 subsequently obtained a substantial Development which were patent’ as at the date of the
award of damages against Point West in respect of the settlement. Patent defects are those which are either
curtain walling and the heating and cooling system. Point known about or which should have been known about
West sought to recover those damages from Mivan (e.g. upon a reasonable inspection). This naturally raises a

24 | CMS London - English construction law developments 2012: An international perspective


question about latent defects (i.e. those which might only in relation to the Priory Hotel’. Subsequently, the owner
come to light after the settlement). Whilst the court made discovered widespread damp penetration in the
no express finding as to latent defects, its finding suggests building resulting directly from the surveyor’s
that latent defects might not have fallen within the negligence, but was unable to claim against the
wording agreed. This might potentially be justified by surveyor due to the prior release:
confining the reference to a ‘full and final settlement’ to
Mivan’s right to payment for the works, with the words ‘… as Chadwick LJ said in Mostcash v. Fluor , in this context
‘any and all outstanding matters’ being intended to dispose there is or must be regarded as being complete familiarity
of other contractual claims. Those other claims would then with the possibility of the emergence, sometimes years
only be released to the extent they were ‘outstanding’ later, of damage caused by previously latent defects in
which could not apply to latent defects. works, due to negligence in the design, specification, or
other professional services provided by those involved in
Nevertheless, parties should be wary of unintentionally construction. Where Mr Owen’s negligence was expressly
releasing claims for latent defects. While English law is slow and specifically in contemplation [i.e. the overcharging and
to find that parties have surrendered rights to unknown backdating known by the owner], the fact that the damp
claims, claims for latent defects are sufficiently common penetration did not emerge for another two years can by
that it can be assumed that parties take them into account no means take Priory’s resulting claim from having been
when agreeing settlements. For example, in Mostcash Plc v within the contemplation of the parties on 10 March 2003,
Fluor Limited, the English Court of Appeal commented (in and within the express language of the letter of that date.’
another dispute over the scope of a settlement agreement):
The lesson to be taken from the above cases is clear.
‘…the claims in the present proceedings are just the sort of The words used by the parties in recording any agreement
claims that may be expected to be within the to settle claims are likely to be given priority over any
contemplation of parties to a construction contract, or to a general presumption that only claims then under
contract for the provision of design, procurement and discussion or within the contemplation of the parties are
construction management services. It must be a matter of intended to be settled. Particularly in construction
common experience amongst those who commission, contracts, where the nature of the claims which can arise
design and manage the construction of commercial are well known, general words of release, such as ‘full
buildings that defects come to light after – perhaps years and final settlement’ and ‘all outstanding matters’, may
after – the contract has been performed and the building be read literally to include claims for latent defects. Parties
handed over. The books are full of such cases; and the should therefore give careful thought to how settlement
difficulties to which latent defects give rise in the context of agreements are expressed.
limitation.’ (Lord Justice Chadwick, paragraph 53)
References: Point West London Limited v Mivan Limited
These comments were echoed more recently by the [2012] EWHC 1223; Bank of Credit and Commerce
Court of Appeal in Priory Caring Services Limited v International (SA) v Ali [2002] 1 AC 251; Mostcash PLC &
Capita Property Services Ltd. In that case, the owner of Ors v Fluor Limited [2002] EWCA Civ 975; Priory Caring
a development had become aware of overcharging and Services Limited v Capita Property Services Ltd [2010]
the deliberate backdating of documents by its surveyor. EWCA Civ 226.
However, in exchange for the surveyor agreeing to
provide evidence in an arbitration against the owner’s
insurers, the owner agreed not to issue proceedings
against the surveyor, ‘in relation to matters arising from
[its] appointment as surveyors to Priory Caring Services
25
Commercial pressure and economic duress

A recent English High Court decision has clarified the circumstances in which a commercial
party’s actions may constitute economic duress and so cause any resultant agreement to be
voidable (i.e. not binding on the ‘victim’ of the duress). The decision confirms that, though it
would be unusual in commercial circumstances, the exertion of pressure by lawful means may
still constitute economic duress. The decision therefore gives parties cause for care when
entering agreements, where the balance between driving a hard bargain and exerting
illegitimate pressure may need to be considered.

Progress Bulk Carriers Ltd v Tube City IMS LLC concerned an The parties then discussed a replacement vessel and an
appeal from an arbitral award striking down a settlement extension of time to 7th/8th May. The charterers’ customer
agreement between the owners of a sea vessel and a in China agreed to extend the shipment date on condition
commercial shipping firm (the ‘charterers’) for duress. The that there be a corresponding reduction in the purchase
owners argued that their behaviour had been lawful and so price. The charterers informed the owners that they would
was not ‘illegitimate pressure’ (that being a precondition accept the replacement vessel, with a discount for the
for economic duress under English law). cargo, but reserved their rights in respect of all claims for
damages arising out of the breach of the charter.
The owners had chartered their vessel to the charterers to
carry a cargo of shredded scrap from the Mississippi River The owners then made a ‘take it or leave it’ offer requiring the
to China. The agreed charter did not provide the owners charterers to waive all claims for loss and damage arising out of
with any right to substitute the vessel and had an agreed the nomination of a substitute vessel with a different laycan and
laycan of 15-21 April 2009. (Laycan means the ‘lay days a late arrival. The charterers said that by that stage they were
and cancelling date’ or the earliest and latest dates on forced to accept the owners’ terms. They responded saying:
which the vessel must be ready to load at the port or be
delivered to the time charterers.) ‘… given the exigencies of the circumstances and our
urgent need to mitigate our losses and accommodate our
Immediately after the charter was agreed, the owners customer in China, we are forced to accept the Owners [sic]
indicated they would like to substitute the vessel for a terms under protest.’
different one with a later laycan. They then agreed to charter
the original vessel to a different charterer without informing In arbitration, the majority of the arbitrators held that the
the original charterers, only later telling them that they charterers’ agreement, under protest, to waive all their
intended to perform the voyage with a possible vessel claims for damages in respect of the repudiatory breach, was
substitution and a laycan of 15-24 April. The charterers obtained by economic duress and was therefore voidable.
meanwhile continued to press for the contracted vessel, with
the original laycan, stating that they had barges waiting with The owners appealed this decision, arguing that economic
the cargo to be loaded. Any substitution, the charterers duress only applied where the victim was subjected to
maintained, was strictly subject to their own and their pressure by unlawful action on the part of the other party.
receiving customer’s approval. On 18 April, the owners In the alternative, they argued that if lawful conduct could
admitted to the charterers that they had made a mistake and amount to ‘illegitimate pressure’, the bar had to be set very
said that they would find an alternative vessel to load high and pressure should only be defined as ‘illegitimate’
between 27 and 30 April. They also assured the charterers where it could be considered on a par with conduct
that they would compensate them for all damages resulting expressly recognised at law as illegal or criminal.
from their failure to supply the contracted vessel.
The High Court dismissed the owners’ appeal, agreeing with
In substituting the vessel without the charterers’ consent the the arbitrators and finding that the exertion of pressure by
owners were in repudiatory breach of the charter contract. lawful means did not prevent the operation of the doctrine of
However, at the time the charterers did not accept that economic duress. Cooke J said that ‘illegitimate pressure’
breach as terminating the contract. The contract therefore could be constituted by conduct which was not in itself
remained alive, although there was no practical chance of unlawful (although he added that it would be an unusual case
fulfilment by the named vessel which was by then engaged where that were so, particularly in a commercial context).
elsewhere, nor of achieving the agreed laycan.

26 | CMS London - English construction law developments 2012: An international perspective


Each case would be context-dependent, but economic Even so, each case will depend on its facts. Had the owners
pressure could amount to duress provided that the not breached the contract and so acted unlawfully initially,
economic pressure was illegitimate, and was a significant the outcome here may have been different – their later
cause inducing the claimant to enter the relevant contract. unscrupulous behaviour may or may not have been
Here the owners’ repudiatory breach of contract was an sufficient on its own.
unlawful act which they subsequently sought to take
advantage of. A past unlawful act, as well as a threat of a However, there is clear warning to contracting parties in a
future unlawful act, could amount to ‘illegitimate pressure’. dominant position that unethical conduct and extreme
The refusal to comply with assurances previously given demands may not be upheld. Furthermore, where an
about providing a substitute vessel to load between 27 and innocent party’s predicament is caused by the other party’s
30 April and insistence that the charterers waive any claim breach of contract, and where the perpetrator then seeks
to damages, in spite of previous assurances that they would to take advantage of those circumstances for commercial
be fully compensated, also amounted to ‘illegitimate’ gain, that is likely to meet the requirements of illegitimate
behaviour which compelled the charterers to enter the conduct and so constitute duress.
contract. The combination clearly amounted to illegitimate
behaviour and so to economic duress. Therefore the The lesson for parties in a subservient position is that they
contract was voidable. should only accept terms like these under protest, reserving
their rights where they can, and seeking to avoid the
Over the last decade the courts have looked to distinguish agreement as soon as possible afterwards.
illegitimate pressure from ‘the rough and tumble of the
pressures of normal commercial bargaining’, by examining: References: Progress Bulk Carriers Ltd v Tube City IMS LLC
[2012] EWHC 273 (Comm).
— — whether an actual or threatened breach of
contract occurred

—— whether the party alleging illegitimacy had a


reasonable practical alternative at the time of
submission to the pressure

—— whether the party alleging illegitimacy protested at the


time of submission

—— whether the party alleging illegitimacy sought to rely


on the contract and

—— whether the party accused of illegitimate conduct


acted in bad faith.

The High Court’s decision in Progress Bulk has confirmed


that unlawful behaviour is not necessarily a pre-requisite to
an allegation of illegitimacy. The court followed the view
espoused in the major text books and case law, that lawful
but unethical conduct can constitute illegitimate pressure.

27
Time bars and documentary requirements in
construction contracts

International construction contracts frequently contain clauses requiring claims to be submitted


within specific time periods and/or accompanied by certain supporting documentation. Sometimes
compliance with these requirements is expressed to be a condition precedent to entitlement, such
that the claim will be lost if the requirements are not complied with. In previous editions of this
publication, we have noted that the English courts support such clauses in so far as they concern
time limitations. A further decision in 2012 backs this general trend while a second suggests a
somewhat looser approach to requirements for documentation.

Inframatrix Investments Limited v Dean Informal discussions on a ‘without prejudice basis’ were
then held. In February 2010, DCL’s solicitors formally
Construction Limited responded to Inframatrix’s claim by way of a letter marked
‘without prejudice’, stating that DCL was willing to attend
Inframatrix Investments Limited (‘Inframatrix’)
site on a ‘without prejudice’ basis to carry out an inspection
appointed Dean Construction Ltd (‘DCL’) to carry out
of any works Inframatrix identified. Inframatrix agreed to
roofing and cladding works at a proposed camera
the proposed site meeting and inspection, which occurred
factory and a formal contract was entered into in July
in March 2010, following which DCL prepared a ‘without
2008. The construction of the factory was to be carried
prejudice’ report. DCL subsequently offered to carry out
out by seven contractors, of which DCL was one, each
further investigative work and any remedial works thereby
of whom was to have exclusive access to the site while
found to be necessary but stated that the offer would lapse
carrying out their works. To this end, the contract
if proceedings were initiated. Inframatrix did not accept the
distinguished the ‘Project’ (the construction of the
offer and proceedings were issued in December 2010. DCL
entire building) and the ‘Services’ (the construction of
subsequently argued that the claim was barred by the
the roof by DCL).
limitation clause.

The contract contained a limitation clause precluding the


As Practical Completion for the Services had never been
commencement of any action or proceedings against
certified, DCL’s contractual limitation defence turned on
DCL after the expiry of one year from the date of
whether DCL had provided any ‘Services’ within one year
‘Practical Completion of the Services’ or where Practical
of the claim being brought as required by the second limb
Completion ‘does not occur, the expiry of one year from
of the clause quoted above. DCL asserted that they had last
the date the Contractor last performed Services in
performed the Services in January-February 2009, which
relation to the Project’.
would mean the claim was more than ten months out of
time when proceedings were commenced. Inframatrix
DCL carried out the works on the site between
contended that the inspection in March 2010 and the
November and December 2008. Inframatrix’s
report prepared were part of DCL’s Services and therefore
representative inspected the works in January 2009 and
the claim was not time-barred. However, the court held
expressed concern over the quality of the works. DCL
that as the March 2010 meeting and inspection were held
asserted that all their works (including remedied defects)
(and the subsequent report was prepared) on a ‘without
were complete, but this was rejected by Inframatrix’s
prejudice’ basis as an attempt to avoid litigation, they did
solicitor in July 2009, who alleged poor workmanship,
not form part of DCL’s Services under their contract. The
and said that Inframatrix had appointed a consultant
‘without prejudice’ privilege had been waived for the
who advised that around £105,000 of further remedial
purposes of the trial, but this did not change the
works would be required. Inframatrix initially offered to
fundamental characterisation of the work carried out.
allow DCL to remedy the defects. However, DCL replied
Inframatrix’s claim was therefore made outside the agreed
stating that the final inspection had taken place in
contractual limitation period and was time-barred. There
December 2008 and all defects had been remedied in
was no consideration as to whether DCL would be
January 2009. In October 2009, Inframatrix’s solicitors
prejudiced by a late claim. This is very much consistent with
issued a formal letter of claim seeking the cost of further
English law’s strict approach to time bar provisions.
remedial works and loss of profits.

28 | CMS London - English construction law developments 2012: An international perspective


Walter Lilly: documentary evidence such as was necessary to prove its claim beyond
reasonable doubt. In Mr Justice Akenhead’s opinion, the
requirements contrasted clause imposed a much lower standard of information:

The strict approach to time limitations in Inframatrix can be


‘… it is necessary to construe the words in a sensible and
contrasted with the interpretation of documentary claim
commercial way that would resonate with commercial
requirements in the Walter Lilly case. As mentioned earlier
parties in the real world. The Architect or the Quantity
in this publication, the Walter Lilly decision has raised a
Surveyor must be put in the position in which they can be
number of interesting legal issues including the proper
satisfied that all or some of the loss and expense claimed is
approach to be taken to global claims. As part of its
likely to be or has been incurred. They do not have to be
defence to the claim, the defendant, DWM, alleged that
‘certain’. One has to bear in mind that the ultimate dispute
Walter Lilly (WLM) had failed to comply with the
resolution tribunal will decide any litigation or arbitration
contractual requirements as to documentation. The
on a balance of probabilities and at that stage that tribunal
contract in question was in the standard JCT form of
will (only) have to be satisfied that the Contractor probably
contract commonly used in England. Clause 26.1.3 required
incurred loss or expense as a result of one or more of the
the contractor to:
events listed in Clause 26.2. …’

‘submit to the Architect or to the Quantity Surveyor such


The judge also noted the difficulties which would arise on a
details of … loss and/or expense as are reasonably necessary
strict interpretation if only a small part of the claim were
for … ascertainment [of the amount of loss and/or expense
inadequately substantiated. That could result in an absurd
which has been or is being incurred by the Contractor]’.
situation where a claim for £1 million might be invalidated
because there was insufficient substantiation for a minor
Both parties agreed that this requirement was a condition
item worth £10.
precedent to WLM’s entitlement to claim and DWM sought
to argue that the clause required the contractor to provide
The judge also considered that it would be sufficient
extensive details and back up documentation to prove its
compliance for the contractor to merely offer for the
loss and/or expense entitlement. DWM emphasised the
Architect or Quantity Surveyor to inspect records at the
word ‘ascertain’ and argued that this meant that the
contractor’s premises. Such an interpretation will make
Architect or Quantity Surveyor was required to be given
it very difficult indeed for an employer to prove a
sufficient information to enable the amount of the claim to
breach of contract if the contractor offers an inspection
be calculated with certainty (which reflects the general
of its documents.
dictionary definition of the word ‘ascertain’).

As mentioned earlier in this publication, the Court of


However, in Mr Justice Akenhead’s view:
Appeal has this year refused leave to appeal from the
‘There is no need to construe Clause 26.1.3 in a peculiarly
decision in Walter Lilly. In doing so it remarked specifically
strict way or in a way which is in some way penal as against
that, although no appeal would be allowed on the
the Contractor, particularly bearing in mind that all the
documentary requirements issue for factual reasons, it
Clause 26.2 grounds which give rise to the loss and expense
nonetheless had ‘very serious doubts’ about whether there
entitlements are the fault and risk of the Employer.’
was any room for argument over Mr Justice Akenhead’s
interpretation. Once again, therefore, the judge’s views
DWM’s argument was almost akin to saying that a
would appear to be here to stay.
contractor was required to produce all conceivable

29
Conclusion References: Attorney General of the Falkland Islands v
Gordon Forbes Construction (Falklands) Ltd [2003] BLR 280;
This difference in approach between time limitation Inframatrix Investments Limited v Dean Construction
requirements and documentary requirements is even more Limited [2011] EWHC 1947 (TCC) and on appeal [2012]
pronounced under the standard FIDIC claims procedure. EWCA Civ 64; Walter Lilly & Company Ltd v Mackay [2012]
Clause 20.1 of the Red, Yellow and Silver Books 1999 EWHC 1773 (TCC) and on application for leave to appeal
requires a notice of claim to be given within 28 days of the [2013] EWCA Civ 142.
contractor becoming aware of an event (or within 28 days
of when the contractor should have become aware).
The second paragraph of clause 20.1 makes clear that this
requirement is a condition precedent and that failure to
comply will result in the loss of any entitlement.

The fourth paragraph of the clause also provides that the


contractor ‘shall keep such contemporary records as may
be necessary to substantiate any claim’. This requirement is,
however, not expressed as a condition precedent and
failure to comply means only that the assessment of any
entitlement must ‘take account of the extent (if any) to
which the failure has prevented or prejudiced proper
investigation of the claim’.

The 28 day notice requirement will receive a strict


interpretation under English law and contractors can expect
any entitlements to be lost if the clause is not complied
with (unless escape routes are available, e.g. that the
employer waived the requirements). The judgment in
Walter Lilly shows however that a more liberal approach
will be adopted in assessing compliance with documentary
requirements. Indeed, even if the documentary
requirements in clause 20.1 were to be made a condition
precedent to entitlement, Walter Lilly would still give
contractors considerable comfort that claims are not likely
to be lost through documentary failings.

This position may be contrasted with that previously


adopted in the FIDIC Red Book 4th Edition (which is still
regularly used in some places). Clause 53 of the Red Book
4th Edition has the same requirement to keep such
contemporary records as may be necessary to substantiate
any claim. In addition, however, the clause provided that
in the absence of such records the contractor’s
entitlement was not to exceed ‘such amount as the
Engineer or any arbitrator or arbitrators … assessing the
claim considers to be verified by contemporary records’.
This provision was given a strict interpretation in Attorney
General of the Falkland Islands v Gordon Forbes
Construction (Falklands) Ltd, such that any claims which
were not supported by contemporary records were held
to be invalidated. A partial absence of records was held to
partially invalidate a claim and the gaps were not
permitted to be filled by retrospective analysis or witness
evidence. This case is perhaps the exception which proves
the rule, by showing that very specific clauses are required
to give ‘teeth’ to documentary requirements. A general
requirement for supporting documentation, even if made
a condition precedent to entitlement, is unlikely to
meaningfully affect a contractor’s entitlement, save only
in the clearest of cases.

30 | CMS London - English construction law developments 2012: An international perspective


With numerous offices spread throughout the world,
this firm has impressive global coverage and acts on
construction projects in Asia, Latin America, Africa
and the Middle East.
Chambers & Partners, UK
Document harvesting and disclosure in
international construction disputes

2012 presented the English High Court with an opportunity to consider the difficult logistical issues
which can face parties preparing for disclosure in large international construction disputes. As this
case shows, a failure to plan early for disclosure can lead to embarrassment and a loss of credibility
at a later stage in proceedings, not to mention serious cost consequences. We consider the lessons
this case holds more broadly for those preparing for disclosure in international construction
disputes, whether before a court or an arbitral tribunal.

The West African Gas Pipeline Company (WAPCo) engaged a The importance of properly and thoroughly carrying out an
subsidiary of Willbros Global Holdings (WGH) under an EPC initial ‘harvesting’ of the documents received particular
contract to construct the onshore works for a gas pipeline in emphasis from the court:
West Africa (for supplying gas from Nigeria to Benin, Togo
and Ghana). More than three years after the contract had ‘The second main area of difficulty has been the failure
been entered into WAPCo terminated it and completed the by WAPCo to gather together or ‘harvest’ a consistent
work with other contractors. WGH had guaranteed its and complete set of electronic data for the purpose of
subsidiary’s duties under the contract and WAPCo ultimately electronic disclosure. This was not a case where there
sued in the English Technology and Construction Court to are particular complexities in the important initial
recover approximately US$ 274 million from WGH for its extra process of identifying the repositories of electronic
costs of completing the pipeline following termination. documents, contacting custodians and identifying
relevant folders and sub-folders so as to ensure that a
In the litigation the parties were each ordered to give comprehensive compilation of electronic documents is
‘standard disclosure’ under the English court rules - as is obtained. There were a number of errors identified
usual (or rather was; since April 2013 the courts will more above, in particular, the provision of a copy of Livelink
actively consider narrower forms of disclosure from a with incomplete e-room documents, the failure until 14
‘menu’). ‘Standard disclosure’ requires a party to disclose October 2011 to obtain a copy of the relevant folders
any documents relied upon by it or which support the and sub-folders on Livelink and the failure, in
opposing party’s case or which are adverse to either party’s consultation with the relevant custodians, properly to
case. After disclosure it became apparent that WAPCo’s gather those custodians’ documents. It is evident that a
disclosure was deficient. After a number of attempts by considerable amount of disclosable documentation has
WGH to obtain further disclosure, it emerged that WAPCo now been disclosed from the additional custodians and
had not properly prepared for disclosure or managed the that is documentation which should have been gathered
process. WGH sought an order for wasted costs as a result. together initially. Another aspect which has come to
light is the incomplete disclosure of the documents
The court was critical of WAPCo and noted the following stored at the Lagos Beach Compressor Station. I consider
key deficiencies in its disclosure: these to be serious mistakes and from the evidence it is
apparent that the mistakes resulted from an inadequate
—— WAPCo’s disclosure team had failed properly to
initial review and gathering together of a complete set of
assemble or ‘harvest’ the relevant documents under
electronic documentation.’
WAPCo’s control.

—— The review of documentation which had been Unfortunately such a state of affairs is not uncommon in
harvested was outsourced to a low-cost entity in India, international construction disputes. Geographical and
which ultimately failed to review the documents language barriers can easily conspire to make an
properly and excluded relevant key documents. exhaustive harvesting exercise difficult. Almost always,
information initially received from individual custodians
—— WAPCo’s disclosure was not sufficiently de-duplicated,
or from in-house IT staff proves to be incomplete or
so that multiple copies of individual documents were
subject to qualification.
disclosed to WGH.

—— Other more technical problems such as WAPCo’s failure


to provide searchable text copies of documents or to
provide appropriate searchable fields within the
disclosure database.

32 | CMS London - English construction law developments 2012: An international perspective


At a very high level, harvesting will usually need to be to be fashioned if the likely number of documents
directed at five levels in an organisation: falling within that category will be too large. In a
similar vein, statistics can be generated to indicate
1. At site-level: to capture all information stored in
what categories of documents or keywords are likely
hard copy and electronically on local computers or
to be most prevalent and on that basis more targeted
project servers.
orders for disclosure can be sought in relation to the
2. At a central IT level: to capture all back-up systems, other party’s documents.
e-mail archive stores and other centrally
— — Having carried out a detailed harvesting exercise
maintained information.
will help a party win the confidence of a tribunal
3. At an individual custodian / personnel level: to capture and, particularly where the opposing party has not
all information held on individual laptop computers or done likewise, will make it difficult for any
portable devices and any physical photographs or notes meaningful criticism to be made of the disclosure
held individually. ultimately provided.

4. At a third party level: to capture all available —— Such an exercise will also enable attacks to be made
information held by third parties such as storage on the opposing party’s disclosure, particularly if they
providers or consultants (to the extent they are obliged have not carried out a similarly detailed harvesting
to provide information). exercise. If gaps exist and the tribunal can readily see
that there is a large imbalance in the way each party
5. At a governance level: to capture those reporting
has approached disclosure, it is more likely to make
structures from site-level upwards which record
further orders.
information and decision making processes in relation
to the project. —— A detailed harvesting exercise also enables a deeper
analysis of a party’s own case at an early stage in
Completing the harvesting process at each of these levels proceedings. Particularly when coupled with an
may take months and require persistent monitoring. appropriate database system and reviewing solution,
Individual custodians / personnel can prove to be large amounts of information can be analysed
particularly time-consuming as they require one-on-one relatively swiftly, particularly if certain key periods or
treatment with any information recovered compared to the issues have been identified. The more information that
time periods when they were involved with the project to has been harvested, the more effective these initial
ensure completeness. searches will be.

Once properly carried out, however, an exhaustive References: West African Gas Pipeline Company Ltd v
harvesting exercise provides a party with a number of Willbros Global Holdings Inc [2012] EWHC 396.
advantages during the course of any subsequent court or
arbitration proceedings:

—— First and foremost, the exercise allows a party to make


detailed and informed submissions to the court or
tribunal about the scope of disclosure. For example, it
enables ready analysis to be carried out on any
proposed category of disclosure and for an objection

33
Maintaining privilege in international
construction disputes

As noted earlier in this publication, the Walter Lilly litigation has raised a number of issues which
affect construction claims made under English law. A further issue considered during the course of
the litigation in 2012 was the extent to which privilege applied to advice given by claims
consultants retained during the course of the works. Privilege was found not to apply and the
decision is therefore worth bearing in mind when retaining similar consultants on international
construction projects. We also consider below some of the broader implications of debates over
privilege in the context of international construction projects.

Walter Lilly Prudential was that legal advice privilege extends only to advice
obtained from persons who are retained in their capacity as
As mentioned earlier in this publication, the Walter Lilly practicing lawyers. It is worth noting, however, that whilst
litigation concerned a claim by a contractor for additional English law draws a clear distinction between lawyers and
time and money in relation to the construction of a luxury non-lawyers for the purposes of the classification of legal advice
residential project in London. Part way through the project, privilege it does not draw a similarly stark distinction between
one of the proposed owners and occupiers of the English and non-English lawyers for this purpose, as will be
development, Mr Mackay, became disillusioned with the way discussed below.
the project was being managed and retained the services of Although Walter Lilly involved domestic parties, the case reflects a
a claims consultancy, Knowles Ltd, to provide him with pattern not infrequently occurring in international construction
‘contractual and adjudication advice’. In the later litigation projects. When a project suffers stress, large consultancy firms are
Mr Mackay unsuccessfully claimed that the documents often engaged to advise on a range of issues, from programming
recording Knowles’ advice to him attracted legal advice and project management through to claims preparation. In such
privilege and therefore he was not obliged to disclose those circumstances, it will often seem appropriate for such firms to
documents to Walter Lilly. In English law, legal advice provide advice on legal issues as well. Although not in the business
privilege applies to all communications passing between a of legal practice, members of such firms will often have legal
client and its lawyers, acting in their professional capacity, in qualifications and will be able to draw from a wealth of previous
connection with the provision of legal advice. Fundamentally, experience on other projects. Despite this, English law is now very
therefore, it depends upon who is giving the advice. clear that such advice will not be privileged from disclosure in any
Mr Mackay submitted evidence to the court that the advice subsequent dispute unless formal legal proceedings are already
sought from Knowles was of a legal nature and that he had contemplated and the advice is sought to that end (in which case a
believed the people advising him were lawyers. Although those different type of privilege called litigation privilege can be claimed
people were not practicing solicitors or barristers at the time but this may not be until near the end of a project).
Mr Mackay received their advice, it was argued that Mr Mackay’s Parties would be well advised, therefore, to involve practicing lawyers
mistaken belief that they were practicing lawyers was sufficient. when seeking legal advice during the course of a project when
For the purpose of claiming legal advice privilege, the crucial formal legal proceedings are not yet contemplated. This need not
issue was to determine the capacity in which Knowles were exclude the input of experienced consultancy firms on such issues,
retained by Mr Mackay. If Knowles were not retained by however. Provided that the legal views of such firms are given by way
Mr Mackay as barristers or solicitors then Mr Mackay’s of instructions to practicing lawyers and for the purpose of receiving
mistaken belief was irrelevant. As the court noted: advice from those lawyers, they will also be protected by legal advice
privilege under English law. Careful thought should therefore be
‘The reality is that the Defendants retained Knowles not as
given before the engagement of such consultancy firms as to how
barristers but as an organisation to provide them with claims
privilege may best be claimed in respect of any legal advice received.
and project handling advice. In this respect, their position is no
different from the claimants in the Prudential case who
employed accountants. The fact that Mr Mackay honestly
English law privilege in an international context
understood that the two gentlemen with whom he was dealing
Whilst most parties involved in international construction
at Knowles were qualified and practising barristers or solicitors is
projects will be keen to obtain the protection of documentary
immaterial because their employer was not retained by the
privileges in appropriate circumstances, the protection of those
Defendants to provide the services of barristers or solicitors.’
privileges in an international context can pose difficult issues of
The Prudential case referred to by the court was very local and private international law. Where arbitration
recently upheld in the English Supreme Court. In that case proceedings are concerned, the law of the seat of the arbitration
legal advice privilege was held not to apply to accountants may be different to the law of the contract, which may be
who were retained to give legal advice in relation to different again from the location of the works or each of the
complex tax matters. Once again, the reasoning in parties’ relevant place of business. Parties may seek to assert

34 | CMS London - English construction law developments 2012: An international perspective


privileges arising under the laws of each of these locations, of privileged material in an arbitration can result in allegations
leaving an arbitral tribunal with the difficult task of that any award is or will be tainted by bias on the basis that the
attempting to identify which, if any, ought to be upheld. arbitrator has wrongly seen material which has or will make a fair
The tribunal’s power to decide such matters will flow from the hearing impossible (see Brown v CBS (Contractors) and Francis
procedural law applicable to the arbitration, usually the seat of James v Griffin Shopfitters).
the arbitration unless otherwise stated by the parties. Such These considerations usually lead (where the procedural law
procedural laws often confer a wide discretion upon the arbitral of the arbitration allows it) to the more pragmatic outcome
tribunal to decide upon issues surrounding the disclosure of noted in Russell on Arbitration:
documents and the extent to which it will accept claims to ‘In practice a combination of wishing to preserve the
privilege arising under laws foreign to the seat of the arbitration. privilege of a party who under the rules of his own
More restrictive procedural laws may sometimes be found, jurisdiction had a legitimate expectation of it, and not
however, which limit the tribunal’s powers to the specific rules of wishing to treat the parties differently, means that in most
evidence adopted under the law of the seat. cases both parties will be able to claim privilege in
To complicate matters further, both local laws as to privilege and accordance with whichever applicable rules are most
local conflict of law rules as to foreign privileges vary considerably restrictive about the requirement to disclose.’
from country to country. In England, for example, legal advice This broad approach is also reflected in the IBA Rules on the
privilege and litigation privilege will apply to advice given by Taking of Evidence in International Arbitration 2010.
foreign lawyers in a foreign country or in relation to foreign Paragraph 9.3 permits a tribunal when considering privilege
proceedings, even if no privilege applies in those foreign countries claims to take into account the following matters (subject to
(In re Duncan). English ‘without prejudice’ privilege (which any mandatory rules determined to be applicable):
protects against the disclosure of genuine settlement negotiations)
‘(c) the expectations of the Parties and their advisors at the time
also applies to protect settlement negotiations held in a foreign
the legal impediment or privilege is said to have arisen; …(e) the
country, however, unlike legal advice and litigation privilege, an
need to maintain fairness and equality as between the Parties,
English court will not restrain the use of without prejudice material
particularly if they are subject to different legal or ethical rules.’
in a foreign country unless the parties have expressly agreed that
negotiations are to be privileged (Prudential Insurance Co of This broad approach to privilege reinforces the point made
America v Prudential Assurance Company Ltd). The ‘without above that parties should give careful thought as to how best to
prejudice’ rule is a local or ‘procedural’ rule of English law whereas claim privilege over advice received during the course of a
legal advice and litigation privilege are ‘substantive’ rights which project and in any negotiations over claims. Particular
English law will protect extraterritorially. consideration should be given to appointing local lawyers and/
or entering into express ‘without prejudice’ agreements with
These difficulties can mean that a simple analysis of privilege
counterparties to settlement negotiations. Provided the
flowing from the law of the seat of the arbitration is unattractive,
appropriate persons are involved and the appropriate rules are
as it may result in the violation of privileges specifically protected
followed, parties can be confident that their legitimate
by jurisdictions closely connected with the arbitration. For
expectations as to privilege will be given weight in any
example, the legal advice and litigation privileges granted by civil
subsequent arbitration.
law jurisdictions are usually more restrictive than under English
law. An arbitrator sitting in a civil law country and applying only References: In re Duncan [1968] P 306; Brown v CBS
the law of the seat to determine questions of disclosure might (Contractors) [1987] 1 Lloyd’s LR 279; Francis James v Griffin
therefore order the production of documents which would Shopfitters Ltd, 8 March 1991, unreported; Prudential Insurance
otherwise be privileged under the laws of a common law country Co of America v Prudential Assurance Company Ltd [2003]
such as England. As such documentary privileges are often based EWCA Civ 1154; Russell on Arbitration (23rd Edition, 2007);
upon public policy considerations, such an approach could Walter Lilly & Company Ltd v Mackay [2012] EWHC 649.
potentially prejudice the enforcement of any award in those
countries. Under English law, for example, the wrongful admission

35
What CMS offers

Reach Real expertise Recognition


Whilst principally a European We operate in industry We are recognised as market
law firm, we have 54 offices sectors. This means we have leaders and are top-ranked by
around the world and also actual international independent directories for
frequently operate in those construction and engineering our expertise in construction,
countries where we have no expertise with probably more projects, energy, insurance
permanent base. legal specialists in this field and international arbitration
and in more European
countries than any other legal
organisation.

36 | CMS London - English construction law developments 2012: An international perspective


Know-how
Having been one of the first to recognise construction
and engineering law as a specialist field over 30 years
ago, we are long-standing experts and have the contacts
to match. Our lawyers are best placed to act quickly
and expertly whether be it commercial, procurement or
dispute avoidance/resolution advice.

Commercial focus
Our approach is rooted in a deep knowledge of the
construction and engineering industry. This helps us
to get the right commercial result both quickly and
cost effectively.

Why are
CMS the Clients
Every one of our clients is important to us, and benefits
market from our reputation and connections within the industry.
We act for many of the internationally renowned
leaders? consultants.

Local knowledge
We regularly advise local governments on new
legislation and/or regulatory aspects. This knowledge
and expertise means that we can assist you with
entering new markets and countries.

A dedicated team
Our construction and engineering lawyers from
different jurisdictions meet regularly and share ideas and
experiences. This means we can field the right team for
the job: our clients do not pay for a learning curve.

37
Where to find us

Greenland

A l a s k a
Iceland

C a n a d a

Ireland

United States Portugal


S

Morocco

Bahamas

Mexico

Mauritania

Honduras Senegal
Guatemala Nicaragua
El Salvador
Guinea
Panama Trinidad & Tobago
Costa Rica
Venezuela

International scope, local knowledge Colombia

Ecuador

We are a European legal organisation with construction


and engineering experience in almost every country Peru B r a z i l
around the world.
Bolivia
Our offices are staffed with local lawyers who are familiar
with the local, cultural, and political landscape. This has Chile

proved of particular value to our international clients.

Emerging markets Argentina

We are specialised in operating in emerging markets. We


were one of the first firms to set up a permanent presence
in Eastern Europe in the early 1990s where we have built a
very strong position across all sectors. Our focus now
includes Africa, Brazil, Russia, India and China.

38 | CMS London - English construction law developments 2012: An international perspective


Sweden
Finland
R u s s i a
Norway

Estonia

Latvia
Denmark
Lithuania

Belarus
U. K. Neth.
Germany Poland
Belgium
Czech Rep.
Lux. Slovakia Ukraine
Kazakhstan
Austria
Hungary
Switz. Slovenia Mongolia
France Romania
Croatia
Bosnia &
Serbia
Italy Herz.
Bulgaria
Kos.
Georgia

Armenia
Greece Turkmenistan
Spain Tajikistan
Turkey
Syria Kurdistan Japan
Malta C h i n a
Iran
Tunisia
Iraq
Jordan Pakistan
Kuwait
Algeria

Libya Egypt Qatar


Saudi Arabia Bangladesh
U.A.E.
I n d i a Taiwan
Oman

Mali

Niger
Chad Sudan Thailand
Yemen Philippines
Vietnam
Sudan

Nigeria
South Sudan Ethiopia
Ghana Sri Lanka
Palau
Cameroon Brunei
Mal a y s ia
Uganda Singapore
Kenya
Rwanda
Dem. Republic Burundi
of Congo I n d o n e s i a Papua
Tanzania New Guinea

Timor Leste (East Timor)

Angola Mozambique
Zambia
Malawi

Van
Madagascar
Zimbabwe
Namibia
Botswana

Swaziland
A u s t r a l i a
Lesotho
South Africa

New Zea

CMS office

Countries where we have experience

39
CMS Cameron McKenna’s free online
information service

Receive expert commentary and analysis on


key legal issues affecting your business.
Register for free email alerts and access the
full Law-Now archive at www.law-now.com

CMS Cameron McKenna LLP


Mitre House
160 Aldersgate Street
London EC1A 4DD

T +44 (0)20 7367 3000


F +44 (0)20 7367 2000

The information held in this publication is for general purposes and guidance only and does not purport to constitute legal or professional advice.

CMS Cameron McKenna LLP is a limited liability partnership registered in England and Wales with registration number OC310335. It is able to
provide international legal services to clients utilising, where appropriate, the services of its associated international offices. The associated
international offices of CMS Cameron McKenna LLP are separate and distinct from it. We use the word “partner” to refer to a member, or an
employee or consultant with equivalent standing and qualifications.
© CMS Cameron McKenna LLP 2013

Further information about the firm can be found at www.cms-cmck.com

CMS Cameron McKenna LLP is a member of CMS, the organisation of nine European law firms providing businesses with legal and
tax services in 30 jurisdictions, with 54 offices in Western and Central Europe and beyond. CMS aims to be recognised as the best
European provider of legal and tax services. Clients say that what makes CMS special is a combination of three things: strong, trusted client
relationships, high quality advice and industry specialisation. CMS combines deep local expertise and the most extensive presence in Europe with
cross-border consistency and coordination.

The members of CMS are in association with The Levant Lawyers with offices in Beirut, Abu Dhabi, Dubai and Kuwait City.
Further information can be found at www.cmslegal.com

Registered address: Mitre House, 160 Aldersgate Street, London EC1A 4DD.

1305-000130-7