Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Electric Power Systems Research 180 (2020) 106174

Contents lists available at ScienceDirect

Electric Power Systems Research


journal homepage: www.elsevier.com/locate/epsr

Optimal selection and positioning of conductors in multi-circuit overhead T


transmission lines using evolutionary computing
Jhair S. Acosta*, Maria C. Tavares
University of Campinas, Campinas, São Paulo 13083-852, Brazil

A R T I C LE I N FO A B S T R A C T

Keywords: This paper presents a new approach for designing transmission lines to transmit more power in a narrower space.
Genetic algorithms Multi-circuits lines are a good alternative to attain this objective. However, the optimum solution is not obtained
High surge impedance loading lines by just positioning several regular single-circuit transmission lines in a single tower structure. Although double-
Multi-circuit lines circuit and multi-circuit transmission lines have been used over the last years, there are not many studies about
Optimization
non-conventional multi-circuit transmission lines. Thus, in this research a mathematical model to represent the
problem related to increasing the surge impedance loading level of each circuit, and reducing the costs, the ROW
and the height of the towers by optimizing their bundle geometry and conductor type by applying genetic
algorithms is proposed. The overall transmission lines presented as examples have an improvement between
52% and 149% in the objective function.

1. Introduction basically it is necessary to solve a multi-objective optimization problem.


In the literature there are different optimization techniques. They
Nowadays there is a continuous expansion of the power demand in can be classified mainly in two big groups: classical optimization and
the word. This expansion is mainly caused by the demographic heuristic optimization. In classical optimization it is necessary to have a
growing, new technologies and services, improvement of social condi- complete and derivable mathematical model of the problem. However,
tions and industry increasing. Thus, with a high population density the in some cases the mathematical model does not exist, or is not deri-
electric services have to use a reduced amount of land, if possible with vable, or even is too complex to be computed with classical techniques.
lower cost. Therefore, one of the electric sectors affected is the energy In these cases, the heuristics techniques are a good optimization option
transmission, that not only needs to increase the power that can be because they do not need that a complete mathematical model of the
transmitted on the transmission lines (SIL), but also has to reduce their problem exists [5].
right of way (ROW). The case of transmission line optimization involves a complex
Conventional transmission line design does not take into account mixed-integer non-linear mathematical model. Thus, although heur-
the former objectives. The designs are often performed only based on istics techniques do not ensure the global optimal solution, they can
the selection of a voltage level to attend a certain load. However, within solve complex systems and produce good solutions. Therefore, they are
the design some constraints must be attended. Organizations as CIGRE, a good alternative to implement this kind of optimization process.
EPRI, and IEEE provides guidelines for overhead transmission line de- Among the heuristics techniques one of the most used is the evolu-
sign [1–4]. Common design constraints are the ampacity, audible noise, tionary algorithms (EAs). It is a population approach that solves an
electromagnetic fields, insulation and safety distances. According to optimization problem based on the concepts of genetic and natural
those restrictions the conductor type and quantities of conductors are selection [6]. The solution obtained with EAs is a population of solu-
selected. tions that has passed through an iterative process of genetic re-
In this research we propose the use multi-circuit transmission lines combination (crossover), mutation and natural selection. Because EAs
with augmented power capacity and reduced ROW, attending me- work with populations, global and local search is performed. This im-
chanical and electrical restrictions. However, as any project, the eco- plies that the solution space tends to be explored in an adequate form.
nomical part is important, being necessary to find a good trade-off In this paper we propose a methodology and a mathematical model
between the costs of the project and the others objectives. Therefore, to optimize multi-circuit transmission lines with different voltage levels


Corresponding author.
E-mail addresses: jsacosta@dsce.fee.unicamp.br (J.S. Acosta), ctavares@unicamp.br (M.C. Tavares).

https://doi.org/10.1016/j.epsr.2019.106174
Received 27 May 2019; Received in revised form 11 October 2019; Accepted 17 December 2019
Available online 25 December 2019
0378-7796/ © 2019 Elsevier B.V. All rights reserved.
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

above 230 kV at same tower from a mono-objective approach with EAs. transmission lines was performed with a multi-objective approach and
The optimization is done by modifying the position and type of each the Non-dominated Sorting Genetic Algorithm-II (NSGA-II) [35]. Dif-
wire in the transmission line through evolutionary computing and ferent from [34], in the present research the ampacity and the live
taking into account several electrical and mechanical constraints. The working distances are added as constraints, and the decision making
mathematical model has four objective functions: maximize SIL and process is made a-priori, leading to a faster generation of solutions. This
minimize: costs, ROW and tower's height. The individual objective helps in cases where the preferences for the objectives are well known
functions were aggregated and modeled as a mono-objective function. or when a faster design is required.
As result, improved compact transmission lines with modified bundles
were obtained. 3. Mathematical model
The authors claim the following contributions: A methodology and a
scalable mathematical model to optimize multi-circuit transmission In this section, the optimal selection and position of the individual
lines with up to four circuits at different voltage level by using evolu- wires in multi-circuit overhead transmission lines are initially re-
tionary algorithms. The proposed model is able to optimize the in- presented as a mixed-integer non-linear programming (MINLP) pro-
dividual position, number and type of conducts in multi-circuit lines, blem given by (1).
producing geometries of any type and not restricted to specific con-
max f = f1 + f2 + f3 + f4 (1)
figurations as in other researches. The optimized multi-circuit trans-
mission lines are different from those presented in literature and better where:
than conventional lines.
f1 = SIL op/SILo − 1 (2)
2. Related work
f2 = (Ct o − Ct op)/Ct o (3)
The first approach to solve the problem adopted the use of bundle f3 = (ROWo − ROWop)/ROWo (4)
conductors, i.e., more than one conductor per phase, increasing the
capacitance and decreasing the inductance, and therefore, increasing f4 = (Ht o − Ht op)/Ht o (5)
the natural power of the line or surge impedance loading (SIL) [7].
Thus, more power could be transmitted using a very similar right of In above equations, f1 acquires values between (0, ∞ ) , meanwhile
f2 to f4 acquire values between (− ∞ , 1) . Thus, f1 is focused on the SIL
way (ROW). As reported in [8,9], the first investigations on bundle
increments and f2 to f4 penalize the solutions that are worse than
conductors used two to five conductors per phase with bundle radius of
conventional lines in those objectives. In (2)–(5) SILo , Ct o , ROWo and
0.457 m in the American standards and 0.4 m in the European stan-
Ht o are the sum of the n circ SIL, costs, ROW and height of conventional
dards. Later investigations proposed the use of transmission lines with
lines operating at their specific voltage levels; whereas SIL op , Ct op ,
closer phases (compact lines) and non-conventional bundles, i.e., con-
ROWop and Ht op are the sum of the n circ SIL, costs, ROW and height of
ductors non-uniformly separated in a circular geometry [10].
the optimized line operating at the same voltage levels as the conven-
Based on the previous works several approaches to increase the SIL
tional lines, e.g., a four circuit transmission line with 2 × 500 kV circuits
were developed. In [11] the objective was to increase the SIL and
and 2 × 1000 kV circuits. n circ is the number of circuits in the tower.
maintain balance of electric charge and current distribution in each
Note that Eq. (1) presents four objective functions modeled as a
sub-conductor of the same bundle. Predefined geometries were used,
mono objective function. The inner objectives in (1) are in conflict
such as circular, elliptic, rectangular, among others. The research re-
because improving one objective implies deteriorating another, e.g.,
sulted in a computer program named OTLIN, later known as ELEKTRA.
augmenting the SIL requires more investment on conductors. An useful
In [12] an approach using classical optimization with the gradient
tool to see the conflicting behavior of multi-objective problems is the
method was presented. Meanwhile, Sarmiento and Tavares [13] pro-
Pareto front, that represents the behavior of one objective according to
posed the use of an heuristic algorithm that produced geometries that
other. A simple Pareto front for this problem is shown in Section 3.7
did not follow any fixed form. In [14] the methodology proposed in
after describing the complete mathematical model.
[13] was extended to a multi-objective problem by looking for SIL in-
Additionally, any combinations of the inner objective functions in
crease and cost reduction.
(1) can be optimized by adding binary constants to each variable in (1),
Another approach to make a better use of the land is the multi-
e.g., max f = 1*f1 + 0*f2 + 1*f3 + 0*f4 will optimize SIL and ROW
circuit overhead power lines, i.e., several circuits constructed in the
without considering the costs and the tower height.
same tower sharing the same ROW. The largest overhead double-circuit
Since the characteristics of single-circuits are well-known and have
transmission line, built in 1999, is the Kita-Iwaki power line, operating
been explained in [13,14], the forthcoming sections directly introduce
at 500 kV with a height of 108 m and a ROW of 38 m. In several
the multi-circuit features.
countries such as Germany, India, Japan and China the use of double- or
quadruple-circuit is common, and in rare cases six-circuit lines can be
built. 3.1. Surge impedance loading
The behavior of multi-circuit transmission lines has been char-
acterized in several researches [15,16]. Specific topics as protection SIL of multi-circuit transmission lines depends on the number of
[17,18], lightning performance [19–23], electromagnetic behavior circuits at the same tower (n circ ) and is comprised by the sum of the SIL
[24,25], transient behavior [26] and secondary arc current extinction of each circuit as presented in (6). Therefore, the SIL is defined by the

[27] have been studied for overhead multi-circuit AC power lines. Even voltage of each circuit (Vli ) and its positive sequence characteristic
∼ ∼
researches on multi-circuit DC lines have been made [28]. Currently, impedance (z ci ). At the same time, z ci depends on the positive sequence

some attention has been focused on hybrid AC/DC multi-circuit trans- line impedance of each circuit (z+i ) and the positive sequence line ad-

mission lines [29–31]. mittance of each circuit ( y+i ). Equal to the case of single-circuit, those
An optimization process was applied to shunt reactor and neutral parameters only depend on their positions [2].
reactor of multi-circuit lines [32]. Whereas in [33] multi-circuit trans- ∼2 ∼
n circ n circ
mission lines operating at 138/230 kV are optimized by a multi-ob- Vl i ∼2 y+i
SIL = ∑ ∼ = ∑ Vl i ∼
jective approach using evolutionary computing inside a range of fixed i=1 z ci i=1 z +i
(6)
topologies.
Recently, in [34] the optimization of multi-circuit multi-voltage To calculate the positive sequence components of each circuit, it is

2
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

∼ ∼
⎡ Yϕ11 ⋯ Yϕ1m ⎤

⎢ ⎥
Yϕ = ⎢ ⋮ ⋱ ⎥
∼ ∼
⎢Y Yϕkm ⎥
⎣ ϕk 1 ⎦ (10)

where: Zϕkm self phase impedance matrix of circuit k for k = m , or

mutual phase impedance matrix for k ≠ m Yϕkm self phase admittance
matrix of circuit k for k = m , or mutual phase admittance matrix for
k≠m
∼ ∼
Note that Zϕkm and Yϕkm are 3 × 3 square matrices ∀ k , m no matter
the quantity of circuits. As an example, for two circuits the impedance

sequence matrix Z012 is:
∼ ∼−1∼ ∼
Z012 = T Zϕ T (11)
where:
∼ ∼ ∼ ∼ ∼ ∼
⎡ z a1 a1 z a1 b1 z a1 c1 z a1 a2 z a1 b2 z a1 c2 ⎤
⎢∼ ∼ ∼ ∼ ∼ ∼ ⎥
⎢ z b1 a1 z b1 b1 z b1 c1 z b1 a2 z b1 b2 z b1 c2 ⎥
⎢∼ ∼ ∼ ∼ ∼ ∼ ⎥
∼ zc a z c1 b1 z c1 c1 z c1 a2 z c1 b2 z c1 c2 ⎥
Zϕ = ⎢ ∼ 1 1 ∼ ∼ ∼ ∼ ∼
⎢z z a2 b1 z a2 c1 z a2 a2 z a2 b2 z a2 c2 ⎥
⎢ a2 a1 ⎥
⎢ z∼b a ∼ ∼ ∼ ∼ ∼
z b2 b1 z b2 c1 z b2 a2 z b2 b2 z b2 c2 ⎥
Fig. 1. Images method representation with complex soil. ⎢∼2 1 ⎥
∼ ∼ ∼ ∼ ∼
⎢ z c2 a1 z c2 b1 z c2 c1 z c2 a2 z c2 b2 z c2 c2 ⎥ (12)
⎣ ⎦
necessary to calculate their phase components, that depends mainly on
the physical characteristics and position of the conductors. At the same ⎡1 ∼2
1 1 0 0

0⎤
time, the phase components are obtained using the primitive im- ⎢1 a a 0⎥
0 0

⎢ ∼ ∼2 ⎥
pedance and admittance matrices, i.e., the full impedance and ad- 1 a a 0 0 0⎥
T=⎢
mittance matrices comprised by all the conductors in the tower, in- ⎢0 0 0 1 1 1⎥
∼ ⎢ ∼2 ∼⎥
cluding the shielding wires. The primitive impedance (Ze ) and ⎢0 0 0 1 a a⎥
∼ ⎢0 ∼ ∼2
admittance (Yt ) matrices can be calculated exactly as the case of single- ⎣ 0 0 1 a a ⎥ ⎦ (13)
circuits using Eqs. (7) and (8), and the image method (to take into
account the ground return impedance) presented in Fig. 1, where σc is Note that the sub-indexes 1 and 2 in the inner terms of (12) refer to the
the earth conductivity, Rk the radius of the k wire, hk the height of the k impedance elements of the circuit 1–2 and their self and mutual
wire, dkp the distance between the wires k and p and D kp the distance iteration; whereas the sub-indexes a , b and c refer to the phase a , b and c
between the wire p and the image of the wire k . The positive sequence of each circuit. The same procedure can be extended to any quantity of

parameters of the line are not influenced by the ground return im- circuits. Additionally, T will be always a square 3n circ matrix with
∼ ∼
pedance, so it could be neglected. However, proper zero sequence va- a = e−jπ/3. In the end, Z012 will be a diagonal matrix composed by the
lues must be calculated for future transient studies, but they are not sequence components of each circuit (e.g.,
∼ ∼ ∼ ∼ ∼ ∼ ∼
important at this stage of line optimization. Z012 = diag([z 01, z11, z 21, z 02 , z12 , z 22]) in the example of two circuits).

∼ jωμ0 ⎛ 2hk ′ ⎞ ∼ jωμ0 ⎛ D kp ′ ⎞ 3.2. Constraints


Ze kk = Ln ⎜ Ze kp =
⎟ Ln ⎜ ⎟
2π ⎝ Rk ⎠ 2π ⎝ dkp ⎠ (7)
The optimization problem in (1) is subjected to the following con-
∼ straints:
Yt = j2πωε0 C C=A−1
D kp ⎞ 0.45 ≤ bs ≤ Bs (14)
Akp = Ln ⎜⎛ ⎟ Akk = Ln
⎛ 2hk ⎞
⎜ ⎟

d ∼
⎝ kp ⎠ ⎝ Rk ⎠ (8) |Vli |
df i ≥
1e−320δr 3 (15)
Note that in the case of multi-circuit transmission lines, Eqs. (7) and
(8) yield to square primitive matrices with dimensions of df i ≥ d lwci (16)
n = 3ncirc n sc + n sw , where n sw is the number of shielding wires on the
transmission line and n sc is the number of sub-conductors in the bundle. Df ik ≥ max(df i , df k ) (17)
Those matrices must be reduced to square 3n circ matrices by using the ∼ 1.667
Kron reduction [36] to obtain the phases matrices. The system is as- ⎛ 2.0*1.1 2 *1.15 ⎞
|Vli|*
dsi ≥ 1.03
sumed to be fully transposed and the phases matrices are converted to ⎜ 600 3 ⎟
∼ ⎝ ⎠ (18)
symmetrical components by using Fortescue transformation matrix T
[37]. The full sequence matrix generation process is well described in mi, Vl ≤ nsci ≤ Mi, Vl (19)
[38].
Accordingly, the primitive matrices are n square matrices, whereas 0 ≤ hvi ≤ 5 (20)
∼ ∼
the phases matrices Zϕ and Yϕ are 3n circ square matrices with the gen- Esoil ≤ 8.33 (21)
eral form presented in (9) and (10).
E sup < Ecrit c
∼ ∼ c (22)
⎡ Zϕ11 ⋯ Zϕ1m ⎤
∼ ⎢ ⎥
Zϕ = ⋮ ⋱ b Ei ≤ 10 (23)
⎢∼ ∼ ⎥
⎣ Zϕk1
⎢ Zϕkm ⎥
⎦ (9) Ik < Ak (24)

3
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

n ∼
Table 1 ∼ qk ⎛ x p − xk x p − xk ⎞
Allowed number of conductors according to the voltage level. Ex = ∑ ⎜
2πε0 ⎝ rc2
− ⎟ = Erx + jE
ix
k=1
rI2 ⎠ (25)
Voltage [kV] 230 345 440/500/550 750/765 1000 1150
n ∼
∼ qk yp − yk yp + yk
min nsc 2 2 3 4 8 10 Ey = ∑ ⎛ − ⎞ = E + jE
⎜ ⎟ ry iy
max nsc 3 4 6 8 10 12 k=1
2πε0 ⎝ rc2 rI2 ⎠ (26)

Ep = Erx2 + Eix2 + Ery2 + Eiy2 (27)


where: bs bundle size [m]Bs maximum bundle size [m]Vli line voltage at
circuit i [kV]df i clearance between phases of circuit i [m]d lwi clearance where:
between phases of circuit i for live working, calculated according the rc2 = (x p − xk )2 + (yp − yk )2 (28)
IEEE 516-2009 standard [39] [m]Df ik clearance between phases of cir-
cuits i and k [m]dsi clearance between phases of circuit i and support rI2 = (x p − xk )2 + (yp + yk )2 (29)
elements or tower [m]n sci wires per bundle at circuit imi, Vli minimal wires
per bundle at voltage Vli (see Table 1)Mi, Vli maximum wires per bundle In the above equations, x p and yp are the x and y positions of a point
at voltage Vli (see Table 1)hvi horizontal or vertical distance between p ; xk and yk are the x and y positions of the k conductor; rc in (28) is the
central phase and external phases at circuit i [m]Esoil maximum electric distance between the conductor k and the point p ; and rI in (29) is the
field on the soil [kV/m]E sup maximum electric field on the surface of c distance between the image of the conductor k and the point p .
c If p is on the conductor surface and k belongs to the circuit i , then
conductor [kV/cm]Ecrit c critical electric field of c conductor [kV/cm]b Ei
E sup = Ep . The magnitude of E sup defines the occurrence of the Corona
difference of the maximum electric field on the surface of conductors k k
that belong to the same phase at circuit i [%]δr air relativity densi- effect, that depends on the environmental conditions and the wire
tyIk current flowing in conductor k Ak ampacity of conductor k , calcu- characteristics, especially the external radius. Peek was the first to
lated according the IEEE 738 standard [40] propose, from experimental studies, the critical electric field of con-
To take into account the effect of the temperature on the con- ductors with small diameter [41]. Later studies developed by Miller
ductors, the clearance distances are measured at tower height, and sag [42] found that the conductor radius is more important than what was
level. Balancing of conductors was not considered, and if necessary we considered by Peek. Therefore, for an external diameter greater than
suggest to use an additional insulator string to fix the bundle position. 0.935 cm and lower than 6.8 cm, the critical electrical field is calcu-
In this case, the quantity of insulators should be doubled to get the lated by Eq. (30).
appropriate cost, as presented at Section 3.4.
⎛ 0.54187 ⎞
Note that since each one of the circuit has its own type of conductor, Ecritk = 18.11fs δpa ⎜1 +
most of the constraints depend on the circuit i . Rk δpa ⎟ (30)
⎝ ⎠
In general, the most important and harder constraint to calculate is
where: fs surface factor that is typically 0.82δpa atmospheric pressure
(22), i.e., the electric field on the surface of the n conductors on the [mm Hg]Rk external radius of k conductor [cm]

tower, produced by their electric charge qk . The electric field around In order to avoid Corona effect in most weather conditions, E sup was
each conductor can be calculated at any point p using the image k
method without complex soil presented in Fig. 2, according to Eqs. (25) increased 10%. The same equations used above allow to calculate the
and (26). The electric field magnitude Ep at any point p is composed by electric field at soil level. However, the position of the conductors is
∼ ∼
the real and imaginary components of Ex and Ey as shown in (27). taken at tower level minus the obtained sag for 80 ∘ C.
Taking into account the conductor's sag, all calculations are done at
conductors mid-span height. 3.3. ROW

According to EPRI guidelines, ROW is defined as the distance from


the tower center in which the electric field above 1 m of ground level
falls below 2 kV/m [2]. This was implemented in the present research.

3.4. Costs

The total cost Ct (44), related to the proposed transmission lines,


involves the cost of: insulators Itc (31); phase wires and shielding wires
Wtc (32); support elements for shielding wires Stc (33); conductor laying
Cltc (34); foundations Ftc (35); tower re-positioning Rptc (36); commis-
sioning Cotc (37); steel and assembling of towers Totc (38); power losses
Pltc (40); corona losses Pctc (42); and maintenance of elements Mtc (43)
[14].
n circ
3CI qt Vli d si
Itc = 1.1 ∑ 103dl
i=1 (31)
n
Wtc = 1.1 ∑ lMck Cw
k=1 (32)

Stc = 120Qt nsw (33)

Cltc = (6000n + 3500n sw ) l (34)

Ftc = 7200Qt (35)

Fig. 2. Images method representation for electric field calculation. Rptc = 500Qt (36)

4
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

Cotc = 1000Qt l (37) → → → →


Xa = X1 − D Ya = Y1
n
→ → → →
Vk ⎞ Xb = X2 Yb = Y2 + hv
Totc = 1.1Ct ∑ 2.52Kt yk ⎛⎜Lk2/3 + Tk2/3 + ⎟
1.141 ⎠
→ → → →
k=1 ⎝ (38) X c = − Xa Yc = Ya (48)
→ → → →
(3.28 + DF)2 Xa = X1 Ya = Y1
Kt = 2.89 +
400 (39) → → → →
Xb = X2 + hv Yb = Y2 + D
→ → → →
(1 + Ir )Y − 1 ⎞ X c = Xa Yc = Y1 + 2D (49)
Pltc = 8760Pl Lf Cpl ⎛ ⎜
Y

⎝ Ir (1 + Ir ) ⎠ (40) → → → →
Xa = X1 − D /2 Ya = Y1
2 2
n circ
⎡ 3⎛ ⎛ SILi ⎞ ⎞⎤ → → → → D 2
Pl = ∑ r+i ⎢ V Xb = X2 + hv*D/10 Yb = Y2 + D2 + ⎛ ⎞
li
⎜SILi + 3r+i ⎜ Vl ⎟ ⎟⎥ ⎝2⎠
i=1 ⎣ ⎝ ⎝ i ⎠ ⎠⎦ (41) → → → →
X c = − Xa Yc = Ya (50)
n 1.8
60 ⎡ Esupk ⎤
Pctc = ∑ Cpl ⎢ ⎜⎛0.33 − 0.2⎟⎞ Rk ⎥ → → → → D 2
k=1
50 ⎣⎝ Ecritk ⎠ ⎦ (42) Xa = X1 − D /2 Ya = Y1 + D2 + ⎛ ⎞
⎝2⎠
Mtc = 0.2*[(31) + (32) + (33) + (34) + (35) + (36) + (37) + (38)] (43) → → → →
Xb = X2 + hv*D/10 Yb = Y2
→ → → →
Ct = (31) + (32) + (33) + (34) + (35) + (36) + (37) + (38) + (40) + (42) X c = − Xa Yc = Y1 (51)

+ (43) + (44) (44) Eq. (45) is used to help to maintain the conductors in the bundles
uniformly spaced at the beginning, aiming to obtain a small electric
where: Cl insulator disk cost (21 [USD])qt quantity of towers (935)dl in-
field unbalance on the wires. Furthermore, if n sc is odd, k2 = 1 otherwise
sulator leakage distance (20 [mm/kV])n total quantity of conductors in
k2 = 0 . It is important to clarify that → ry , →
rx , → rxc , →
ryc , and θ are vectors with
the towerl line length (350 [km])Mck mass per kilometer of k conductor
dimension of n sc . Additionally, while rx , ry , →
→ → rxc , and →ryc may accept any
[kg/km]Cw wire cost (4000 [USD/ton] for phase wires and 2000 [USD/ →
ton] for shielding wires)Ct steel cost (7000 [USD/ton]) yk height of k continuous value, θ is a vector with equally spaced angles from 0 to
conductorLk longitudinal loads at conductor k [daN]Tk transverse loads 360°. It should be noted that the outer phases have been formulated to
at conductor k [daN]Vk vertical loads at conductor k [daN]DF maximum be symmetrical. Additionally, the variable D helps to ensure the re-
horizontal distance between all phases [m]Lf load factor (0.8)Cpl power striction (15). In the case of multi-circuit lines, all the variables from
losses cost (36.10 [USD/MWh])Y expected life timeIr interest rate (8 Eqs. (48) to (51) will have a sub-index i indicating that belong to the i th
[%])r+i positive sequence resistance of each i circuit [Ω] circuit.
Note that since one of the objective functions is the cost mini- Since Eqs. (48)–(51) produce circuits with the bundle of the lower
mization, other variables, such as power losses, conductor resistance, phase centered in (0, 0) , it is necessary to move the circuits to their
tower arm lengths, among other, tend to be reduced too. position in the tower. The variables Cxi and Cyi are the displacement of
each circuit center in a direction (x , y ) . However, since the problem has
many constraints, it is necessary to generate base topologies for the
3.5. Geometry
towers, helping to allocate the solutions into the feasible region. As
shown in Fig. 3, two tower configurations were proposed for double-
To help solving the problem in (1) the conductors’ positions of each
circuit lines, four for triple-circuit lines and six for quadruple-circuit
circuit were mathematically represented. Four possible base circuit
lines. The mathematical model of each tower configuration can be de-
types were modeled: vertical in (48), horizontal in (49), delta in (50)
→ → → → → → duced taking into account that those configurations were generated
and inverted delta in (51). The variables ( Xa , Ya, Xb , Yb , Xc , Yc ) denote
using the restrictions in (17), (18) and (21).
the (x , y ) positions of the conductors in each phase.
→ → → → → → 3.6. Constraint handling and final model
X1 = rx cos( θ − ϕ1) Y1 = ry sin( θ − ϕ1)
→ → → → → →
X2 = rx cos( θ − ϕ2) Y2 = ry sin( θ − ϕ2) (45) In order to explore prominent solutions, even if some of them are
outside of the feasible region, the objective function has to be penalized
ϕ1 = k2 π / n sc ϕ2 = k2 π / nsc + π (1 − k2)/2 (46) if some constraints have been overcome. Therefore, the penalization
function presented in (52) is proposed. Thus, when the value Cvc of a
D = D + df (47) constraint c ∈ C (sec. 3.2) overcomes the limit Cl c , the penalization is

Fig. 3. Proposed tower configuration according the number of circuits.

5
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

applied (e.g., if the Ecritk (Cl8 ) is 20 and E sup (Cv8 ) is 50, the inner sum of among others, GAs were chosen to implement for sake of simplicity and
k
(52) yields to −1.5). their good results. Any method based on populations could be used to
solve this problem using the proposed mathematical model.
P= ∑ ⎛ Cl c − Cvc ⎞ ∣Cvc > Cl c
⎜ ⎟
Accordingly, the MINLP problem in (53) is solved using a GA. Thus,
c∈C ⎝ Cl c ⎠ (52) a set of N possible solutions compounds a population Po as shown in

(54). Each one of the Sn candidate solution (∀ n ∈ N ) is represented by
where: C set of constraints
a chromosome comprised by the variables shown in (55).
Note that the inner terms of the sum in (52) is negative if some
constraint is overcome, and otherwise it is 0. With this model, even → →
Po = { S1, …, SN }T (54)
solutions outside the feasible region are explored. For the next gen-
→ → → → → → → → → → →
erations the solutions outside the feasible region are improved and may Sn = {Tty , ht, Cx, Cy, →
cty , →
n sc , D , hv, co ty , rx , ry , rxc, ryc} (55)
enter into the feasible region.

Finally, adding the penalization of the objective function, the model where: Tty base tower typeht vector formed by the height of each i circuit
is the following MINLP problem: → →
(ht i )Cx vector formed by the X center of each i circuit (Cxi )Cy vector
max (1) + (52) (53) →
formed by the Y center of each i circuit (Cyi ) cty base topology of each i

subject to: circuit→ nsc vector formed by the number of wires at each i circuit (nsci )D

vector formed by the Di value of each i circuithv vector formed by the
(14), (15), (17), (18), (19), (20), (21), (22), and(23). → vector formed by the conductor type of
hvi value of each i circuitco ty
each i circuit (cotyi ). The 100 ACSR conductor types were numbered
3.7. Pareto front example from 1 to 100 [14].→ rx vector formed by the → rxi component of each i
circuit→ ry vector formed by the → ryi component of each i circuit→ rxc vector
A simple Pareto front for the transmission line enhancement can be formed by the → rxci component of each i circuit→ryc vector formed by the →ryci
obtained by just optimizing Eq. (2) and changing Bs in (14) in fixed component of each i circuit
steps. Thus, to obtain a Pareto front example for a single-circuit line Tty base tower type
operating at 500 kV, Bs was varied from 1.0 m to 2.0 m. The result in →
ht vector formed by the height of each i circuit (ht i )
Fig. 4 shows the conflict between increasing the SIL and reducing the →
Cx vector formed by the X center of each i circuit (Cxi )
costs, remembering that f1 to f4 are better with higher values. The same →
Cy vector formed by the Y center of each i circuit (Cyi )
behavior is obtained for other objectives. Therefore, this simple ex- →
cty base topology of each i circuit
ample highlights the conflicting objective problem of optimizing →
nsc vector formed by the number of wires at each i circuit (n sci )
transmission lines. →
D vector formed by the Di value of each i circuit

hv vector formed by the hvi value of each i circuit
4. Optimization procedure → vector formed by the conductor type of each i circuit (cotyi ).
co ty
The 100 ACSR conductor types were numbered from 1 to 100
There are different optimization techniques available in literature. [14].
In classical optimization it is necessary to have a complete mathema- →
rx vector formed by the → rxi component of each i circuit
tical model of the problem. However, in some cases the mathematical →
ry vector formed by the → ryi component of each i circuit
model does not exist, is not derivable, or is too complex to be computed →
rxc vector formed by the → rxci component of each i circuit
with classical techniques. In those cases, heuristics techniques are a →
ryc vector formed by the → ryci component of each i circuit
good option because they do not need that a complete mathematical
model of the objective function exists. Therefore, although heuristics
techniques do not ensure to obtain the optimum global solution, they Algorithm 1. Multi-circuit transmission line optimization
provide good solutions.
1: Initialize parameters and limits
One of the techniques most used in recent years is the Genetic 2: Po ⟵N random solutions inside the feasible region
Algorithm (GA), often named as evolutionary algorithm. The GAs solve 3: it⟵1
optimization problems based on the concepts of populations, genetic 4: while it ≤ max(generations) do
and natural selection. In this context, the solution obtained with GAs is 5: Evaluate all solutions in Po
6: Pa ⟵N /10 random solutions in the feasible region
a population of solutions that has gone through an iterative process of
7: Po ⟵Po ∪ Pa
genetic recombination (crossover), mutation and natural selection. 8: Po ⟵ Natural selection of Po
Because the GAs work with populations, global and local searches are 9: So ⟵ Crossover of Po with 90% of probability
ensured. This implies that the solution space is explored in an adequate 10: So ⟵ Mutation of So with 5% of probability
form. Although there are other evolutionary algorithms such as evo- 11: Po ⟵Po ∪ So
12: it = max(generations) then
lution strategy, differential evolution, particle swarm optimization,
13: Evaluate all solutions in Po
14: Po ⟵ Natural selection of Po
15: it⟵it + 1

The general procedure used to optimize (53) follows the pseudo


code presented in Algorithm 1. Note that since the optimization pro-
blem has a large number of constraints, it is necessary to ensure that the
initial population is inside the feasible region. From former knowledge
of the problem it is known that circular geometries with small bundles
usually meet all constraints [14]. This is because circular bundles
maintain a better electric field balance on the surface of the conductors
than other geometries, and smaller bundles have lower superficial
Fig. 4. Example of Pareto front optimizing f1 and verifying the behavior of f2 . electric field than bigger bundles. Thus, to generate feasible individuals,

6
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

→ → → →
it is often sufficient that all internal elements of rx , ry , rxc , and ryc are solutions evolve until reaching a stability in which minor improvements
→ → → →
equal (it does not imply that rx = ry = rxc = ryc ). are obtained. Although after 100 generations a stabilization was ob-
Thus, as shown in Algorithm 1, the initial population Po is composed tained for the single-circuit case, with more circuits more generations
by N random solutions generated inside the feasible region. Then, the are needed due to the larger number of variables.
algorithm begins the main optimization process, composed by the The simulations were performed in a workstation with 16 Gb of
stages of solutions evaluation, insertion of new random solutions, nat- RAM, a quad-core i7 operating at 3.7 MHz, and all the processors
ural selection, crossover and mutation. The stages are executed until the running in parallel for the (53) computation. Each simulation lasted
maximum number of generations stabilized is obtained. Then, the final between 382 and 1001 s, depending on the number of circuits and the
Po is evaluated and the natural selection process is performed. voltage level, because of the larger number of variables. However, since
When working with GAs the solution space should be explored as the transmission line optimization does not require an immediate re-
much as possible. However, at each iteration the solutions become more sponse, the time needed to get the results is not considered an im-
similar between themselves, making it more difficult to explore new portant restriction.
solutions. To circumvent this, there are different strategies like in- Since evolutionary algorithms do not produce equal but similar
creasing the initial population, choosing a natural selection procedure answers in each simulation, 10 runs for single-, double-, triple- and
with low selective pressure, or even introducing new random solutions quadruple-circuit optimization were performed. The best results of the
to the population in each generation. Thus, the algorithm introduces in 10 runs were selected to be shown in this paper. The characteristics of
Po a population Pa with 10% of new random solutions at each genera- the example optimized lines are shown in Tables 2 and 3, whereas the
tion, and uses a natural selection process with a slow selection pressure. geometries are presented in Figs. 6–9. From Table 2 it is possible to
Inside the main optimization processes, at each generation, the first observe that increasing the SIL in most of the cases requires more in-
stage computes the value of (53) for each one of the solutions in Po . vestment. However, the ROW and height in most of the cases will be
Then, N /10 new random solutions are added to the population Po . The lower. Only in the single-circuit line case the height was higher because
new Po experiments a natural selection process and Po is reduced to N the algorithm chose a delta circuit to increase the SIL. Note that, in
solutions. The natural selection is performed through a tournament in overall, the transmission lines of the examples were improved in ranges
which each solution faces 0.4N random solutions in Po . The number of between 52% and 149%. Any combination of circuits will produce
wins of each solution is counted and ranked, and the N solutions with significant increments, even more if the number of circuits increases.
more wins remain on Po , whereas the others are eliminated. When the Therefore, with more circuits on the same tower, more improvements
natural selection ends, a uniform crossover is performed over Po (par- tend to be obtained. However, note that in circuits with higher voltage
ents), i.e., a random pair of parents produces, with a probability of 90%, levels (e.g., 2 × 750 –1 × 1000 kV transmission line), it is more difficult
two sons with combined genetic material. Thus, N sons are produced to increase the SIL, but still better solutions than conventional lines will
comprising the population So . As happens in nature, a genetic mutation be produced.
can occur with low probability in any generation. Therefore, the po- Note that the major advantage of the optimized multi-circuit
pulation So can suffer a mutation with a probability of 5%. The muta- transmission lines is the ROW reduction ( f3 ), obtaining reductions up to
tion of each variable is controlled by Gaussians with standard deviation 64%, with a good height reduction ( f4 ), that in the best case was 61%.
of 0.1 for continuous variables (Tty , → → ) and 1 for integer
cty , →
nsc , co ty
At the same time it was possible to obtain high SIL increments ( f1) up to
→ → → → → → → → → 32%, using bundles smaller than 1.5 m. However, in most of the cases it
variables (ht, Cx, Cy, D , hv, r , r , r , r ) . After mutation, the new P
x y xc yc o
was necessary to make a higher initial investment because of the use of
will be composed by the union of the previous generation Po (parents)
larger bundles, more quantity of conductors, larger conductors, and
plus the population So (sons). At this point, the population Po has a size
more steel in the towers. The highest initial investment was 7.5%
of 2N that will be reduced to N in the next natural selection stage. That
higher than conventional lines. It is also very interesting to observe that
happens in the next generation or immediately (in the same generation)
different conductors were proposed for the same voltage level circuit.
if the algorithm has reached the maximum generation number. At the
This is not a predictable result.
end, almost all the solutions in Po will be very similar and optimized.
Additionally, no matter the quantity and voltage level of the circuits
in the tower, the algorithm is always going to optimize all the circuits.
5. Test and results Thus, the objective function of one circuit will not be deteriorated by
the optimization of other circuit. Therefore, the proposed solutions are
The model presented in this paper was tested with the constraints worth even for tower with circuits belonging to different owners.
given along the text. To show the efficiency and scalability of the
proposed model and algorithm, single, double, triple and quadruple 6. Conclusions
transmission lines with Bs = 1.5 m were optimized. The typical evolu-
tion of the optimization response is shown in Fig. 5, where it is possible Regarding the continuous growing of population, density and power
to see the evolution of the fitness at each generation for an optimization demand, there is a need of increasing the SIL of the transmission lines
of a 500 kV single-circuit transmission line. As can be seen, the and reducing their ROW. A good solution is to use multi-circuit lines
instead of single-circuit lines. Additionally, if the multi-circuit lines are
non-conventional, the benefits will be higher. Therefore, in this paper
were presented a mathematical model and an algorithm to effectively
produces optimized transmission lines taking into account four objec-
tives: increase of the transmission line SIL, and reduction of: costs, ROW
and height.
The optimization is done using an algorithm based on GAs to solve
the proposed model. The model is adaptive, so it is able to optimize
multi-circuit lines from 1 to any quantity of circuits. These new lines are
named as non-conventional multi-circuit transmission lines. As ex-
ample, lines from 1 to 4 circuits were optimized. The results showed
that the non-conventional multi-circuit transmission lines are better in
Fig. 5. Fitness response at each generation for optimized single circuit trans- values up to 149% than single-circuit transmission lines. Even in the
mission line at 500 kV. case of single-circuit lines, the algorithm produced non-conventional

7
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

Table 2
Simulation settings and objective function values.
Line [kV] Ni g time [s] f ′1 [%] f ′2 [%] f ′3 [%] f4 [%] f [%]

500 300 500 382.49 26.30 −6.73 48.90 −16.38 51.97


2 × 500 300 500 525.71 24.41 1.24 51.02 35.54 112.22
2 × 750 –1 × 1000 300 500 1001.3 18.87 −7.45 59.34 37.82 108.60
2 × 230 –2 × 500 300 500 773.79 31.10 −6.66 63.68 60.69 148.89

Table 3
Characteristics of the example optimized transmission lines.
Line n scci Conductor bs [m]

500 kV 4 Tern 0.91


2 × 500 kV 4/4 Coot/Coot 1.05
2 × 750 –1 × 1000 kV 4/4/8 Bobolink/Catbird/Coot 1.39
2 × 230 –2 × 500 kV 2/2/4/4 Swift/Swift/Coot/Coot 1.16

Fig. 8. Optimized triple-circuit transmission line at 2 × 750 kV and 1 × 1000 kV.

Fig. 6. Optimized single-circuit transmission line at 500 kV.

Fig. 9. Optimized quadruple-circuit transmission line at 2 × 230 kV and


2 × 500 kV.

Fig. 7. Optimized double-circuit 500 kV transmission line. mathematical model as the conductor swing calculation could be in-
cluded. In general, any constraint not taken into account in this docu-
lines, so better results were obtained (up to 52%). Although the GAs do ment could be added.
not obtain the same response in all executions, they produced good and
similar solutions in each case.
Eventually, the obtained lines are good options to real projects, Conflict of interest
because they meet all the electrical safety distance and constraints,
reduce the ROW and height, and increment the SIL. Moreover, because The authors declare that there is no conflict of interest.
of the ROW reduction, the lines are environmentally friendly.
Since the methodology is scalable, future improvements to the

8
J.S. Acosta and M.C. Tavares Electric Power Systems Research 180 (2020) 106174

Acknowledgements of multi-circuit tower, Int. Conf. Light. Prot. Vienna, Austria, 2012, pp. 1–6, ,
https://doi.org/10.1109/ICLP.2012.6344297.
[22] Z. Li, Z. Yu, X. Wang, J. He, A design of unbalanced insulation to improve the
The authors acknowledge the financial support provided by the lightning performance of multi-circuit transmission lines, 31st Int. Conf. Light. Prot.
following institutions: CAPES (code 001),CNPq andFAPESP (no.2015/ ICLP, Vienna, Austria, 2012, pp. 0–3, , https://doi.org/10.1109/ICLP.2012.
26096-0 and2017/20010-1). 6344216.
[23] Y. Zhao, J. Su, S. Gu, H. Ren, C. Zhao, Influence of different coupling ground wire
erecting mode on lightning withstand performance for multi-circuit transmission
References line in a tower, Int. Conf. Light. Prot. ICLP, Shanghai, China, 2014, pp. 1036–1040, ,
https://doi.org/10.1109/ICLP.2014.6973276.
[24] G. Feng, Y. Wang, B. Zhang, Study on electromagnetic environment of multi-circuit
[1] K.O. Papailiou (Ed.), Overhead Lines, CIGRE Green Books, Springer International
transmission lines on same tower, Int. Conf. Power Syst. Technol. POWERCON, New
Publishing, Paris, France, 2017, , https://doi.org/10.1007/978-3-319-31747-2.
Delhi, India, 2008, pp. 1–5, , https://doi.org/10.1109/ICPST.2008.4745302.
[2] Electric Power Research Institute, EPRI AC Transmission Line Reference Book-200
[25] W. Liu, M. Pan, K. Liu, G. Xu, Research on electromagnetic character of 500/220kV
kV and Above, third edition, EPRI, 2005.
mixed-voltage quadruple-circuit transmission line, 12th Int. Conf. Environ. Electr.
[3] IEEE Power Engineering Society, IEEE Guide for Transmission Structure Foundation
Eng. EEEIC, Wroclaw, Poland, 2013, pp. 227–231, , https://doi.org/10.1109/
Design and Testing, IEEE Std 691-2001, (2001), pp. 1–194, https://doi.org/10.
EEEIC.2013.6549621.
1109/IEEESTD.2001.93372.
[26] M. Kizilcay, C. Neumann, Backflashover analysis for 110-kV lines at multi-circuit
[4] IEEE Power Engineering Society, IEEE Guide for the Installation of Overhead
overhead line towers, Int. Conf. Power Syst. Transients, Lyon, France, 2007,
Transmission Line Conductors, IEEE Std 524-2016 (Revision of IEEE Std 524-2003),
pp. 4–9.
(2017), pp. 1–162, https://doi.org/10.1109/IEEESTD.2017.7912224.
[27] Q. Yang, W. Sima, M. Yang, R. Wang, T. Yuan, Secondary arc current of ultra-high
[5] K.Y. Lee, M.A. El-Sharkawi (Eds.), Modern Heuristic Optimization Techniques, John
voltage transmission line with a mixed voltage of 1000/500 kV on a single tower,
Wiley & Sons, Inc., Hoboken, NJ, USA, 2008, , https://doi.org/10.1002/
IET Gener. Transm. Distrib. 9 (7) (2015) 686–693, https://doi.org/10.1049/iet-gtd.
9780470225868.
2014.0415.
[6] P.A. Vikhar, Evolutionary algorithms: A critical review and its future prospects,
[28] W. Li, B. Zhang, J. He, R. Zeng, S. Chen, Ion flow field calculation of multi-circuit
Proc. – Int. Conf. Glob. Trends Signal Process. Inf. Comput. Commun. ICGTSPICC
DC transmission lines, Int. Conf. High Volt. Eng. Appl. IEEE (2008) 16–19.
2016 IEEE (2017) 261–265.
[29] S. Wei, L. Qingmin, Z. Liang, Z. Li, L. Xinchang, Research on lightning performance
[7] P.H. Thomas, Output and regulation in long-distance lines, Trans. Am. Inst. Electr.
of AC/DC hybrid transmission lines on the same tower, IET Gener. Transm. Distrib.
Eng. XXVIII (1) (1909) 615–640, https://doi.org/10.1109/T-AIEE.1909.4768191.
7 (2) (2013) 166–174, https://doi.org/10.1049/iet-gtd.2012.0308.
[8] P.A. Abetti, Bibliography on extra-high-voltage systems, Trans. Am. Inst. Electr.
[30] A. Mackow, M. Kizilcay, P. Malicki, Lightning performance of overhead hybrid
Eng. Part III: Power Appar. Syst. 77 (3) (1958) 1517–1535, https://doi.org/10.
transmission line, IEEE PowerTech, Eindhoven, Netherlands, 2015, pp. 1–6, ,
1109/AIEEPAS.1958.4500194.
https://doi.org/10.1109/PTC.2015.7232572.
[9] D.H. Sandell, A.N. Shealy, H.B. White, D.H. Sandell, Bibliography on bundled
[31] P. Malicki, A. Mackow, M. Kizilcay, Estimating the lightning performance of a
conductors, IEEE Trans. Power Appar. Syst. 82 (69) (1963) 1115–1128, https://doi.
multi-circuit transmission tower, 33rd Int. Conf. Light. Prot. ICLP, Estoril, Portugal,
org/10.1109/TPAS.1963.291504.
2016, pp. 1–4, , https://doi.org/10.1109/ICLP.2016.7791471.
[10] G.N. Alexandrov, G.V. Podporkyn, Improvement of the efficiency of 35 to 220 kV
[32] X. Lv, Q. Sun, Q. Li, W. Shi, Multi-objective parameter optimization of shunt re-
lines, Int. Conf. AC DC Power Transm. London, UK, 1991, pp. 226–231.
actors for multi-circuit transmission lines on the same tower, 4th Int. Conf. Electr.
[11] J.C. Salari, Optimizing Transmission Lines Conductors Bundle Geometries (Master
Util. Deregul. Restruct. Power Technol. Weihai, Shandong, China, 2011, pp.
thesis), Federal University of Rio de Janeiro, Brazil, 1993 (in Portuguese).
271–276, , https://doi.org/10.1109/DRPT.2011.5993902.
[12] R.P. Maciel, Maximization of Characteristic Power of Transmission Lines Using a
[33] M.F. Ribeiro, J.A. Vasconcelos, D.A. Teixeira, Optimization of compact overhead
Non-linear Optimization Method (Master thesis), University of Campinas, Brazil,
lines of 138/230kV: optimal selection and arrangement of cables and definition of
2013 (in Portuguese).
the best transmission line tower topology, 17th IEEE Int. Conf. Environ. Electr. Eng.
[13] J.S.A. Sarmiento, M.C. Tavares, Enhancement the overhead transmission lines’ ca-
1st IEEE Ind. Commer. Power Syst. Eur. EEEIC /I CPS Eur. Milan, Italy, 2017, pp.
pacity by modifying the bundle geometry using heuristics algorithms, IEEE PES
1–6, , https://doi.org/10.1109/EEEIC.2017.7977842.
Asia-Pacific Power Energy Eng. Conf. Suzhou, China, 2016, pp. 646–650, , https://
[34] J.S. Acosta, M.C. Tavares, Multi-objective optimization of overhead transmission
doi.org/10.1109/APPEEC.2016.7779583.
lines including the phase sequence optimization, Int. J. Electr. Power Energy Syst.
[14] J.S. Acosta, M.C. Tavares, Methodology for optimizing the capacity and costs of
(115) (2020) 105495, https://doi.org/10.1016/j.ijepes.2019.105495.
overhead transmission lines by modifying their bundle geometry, Electric Power
[35] K. Deb, A. Pratap, S. Agarwal, T. Meyarivan, A fast and elitist multiobjective genetic
Syst. Res. (163) (2018) 668–677, https://doi.org/10.1016/j.epsr.2017.10.005.
algorithm: NSGA-II, IEEE Trans. Evol. Comput. 6 (2) (2002) 182–197, https://doi.
[15] Y.H. Wang, S.M. Meng, B. Tang, Study on type design of multi-circuit transmission
org/10.1109/4235.996017.
line tower, Adv. Mater. Res. 594–597 (2012) 900–903, https://doi.org/10.4028/
[36] G. Kron, Tensor Analysis of Networks, MacDonald, London, 1939.
www.scientific.net/AMR.594-597.900.
[37] C.L. Fortescue, Method of symmetrical co-ordinates applied to the solution of
[16] A. Novitskiy, D. Westermann, Interaction of multi-circuit overhead transmission
polyphase networks, Trans. Am. Inst. Electr. Eng. XXXVII (2) (1918) 1027–1140,
lines of different voltages located on the same pylons, IEEE Electr. Power Qual.
https://doi.org/10.1109/T-AIEE.1918.4765570.
Supply Reliab. Tartu, Estonia, 2012, pp. 1–4, , https://doi.org/10.1109/PQ.2012.
[38] W.S. Meyer, H.W. Dommel, Numerical modelling of frequency-dependent trans-
6256240.
mission-line parameters in an electromagnetic transients program, IEEE Trans.
[17] M. Agrasar, F. Uriondo, J.R. Hernandez, R. Alvarez, A useful methodology for
Power Appar. Syst. PAS-93 (5) (1974) 1401–1409, https://doi.org/10.1109/TPAS.
analyzing distance relays performance during simple and inter-circuit faults in
1974.293870.
multi-circuit lines, IEEE Trans. Power Deliv. 12 (4) (1997) 1465–1471, https://doi.
[39] IEEE Power Engineering Society, 516-2009 – IEEE Guide for Maintenance Methods
org/10.1109/61.634162.
on Energized Power Lines 2009 IEEE, 2009, https://doi.org/10.1109/IEEESTD.
[18] X.F. Zuo, H. Kuribyashi, Protection of parallel multi-circuit transmission lines, Proc.
2009.5137335.
6th Lnternauunal Conferr. Adv. Power Spm Control. Oper. Hlanagcmenr, Hong
[40] IEEE Standards association, IEEE Standard for Calculating the Current-Temperature
Kong, China, 2003, pp. 630–634.
Relationship of Bare Overhead Conductors, (2013), https://doi.org/10.1109/
[19] A.C. Liew, P.C. Thum, Comparative studies of lightning performance of a quad-
IEEESTD.2013.6692858.
ruple-circuit dual voltage 275/132 kV transmission line design with wooden
[41] Starr, Lloyd, Peek, An investigation of corona loss: law of corona and dielectric
crossarms, IEEE Trans. Power Deliv. 8 (4) (1993) 1973–1980, https://doi.org/10.
strength, J. AIEE 46 (12) (1927) 1457–1461, https://doi.org/10.1109/JAIEE.1927.
1109/61.248310.
6538167.
[20] Z. Zheren, Y. Qing, Y. Libin, S. Wenxia, Y. Tao, Lightning back-flash performance of
[42] C.J. Miller, The calculation of radio and corona characteristics of transmission-line
220 kV AC quadruple-circuit transmission lines on the same tower, Asia-Pacific
conductors, Trans. Am. Inst. Electr. Eng. Part III: Power Appar. Syst. 76 (3) (1957)
Symp. Electromagn. Compat. APEMC, Beijing, China, 2010, pp. 1570–1573, ,
461–472, https://doi.org/10.1109/AIEEPAS.1957.4499589.
https://doi.org/10.1109/APEMC.2010.5475671.
[21] X. Wang, Z. Li, J. He, Impact of coupling ground wire on lightning protection effect

You might also like