FURNISHING OF AGGREGATES

Convergence and Special Support Program - Construction/Improvement of Access Road leading to


Project: : Declared Tourism Destinations - Access Road leading to Tanglagan Falls, Brgy. Tanglagan, Gattaran,
Cagayan

Location: : Brgy. Nassiping Gattaran Cagayan


Source: : Pena Este Gravel Pit, Gattaran, Cagayan

Peña Este Gravel Pit - Project Site = 61.00 KM


Hauling Distance 61.000
say = 61.000 KM

1.. STOCKPILING AND LOADING:

use 1 -Bulldozer, D65A-8, Crawler Mounted, 155 HP, Capacity = 500 cu.m./day
use 1 - Payloader,1.50 cu.m.,148 HP Capacity = 500 cu.m./day
Unit Cost = P 27,032.00 + 13,864.00 /day = P 81.79 /cu.m.
500.00 cu.m./day
ROAD DUMP TRUCK TRAVEL
TERRAIN SPEED (km/h)
2. HAULING COST SURFACE
CONDITION
COMPUTATION OF CYCLE TIME CONDITION LOADED EMPTY
Terrain = Flat/Rolling Paved 35 55
FLAT
Road Condition = Paved/Unpaved Unpaved 30 45
Grade = Paved 30 40
ROLLING
Unpaved 25 35
Paved 20 30
MOUNTAINOUS
Unpaved 15 25
Average Hauling Distance = 61.00 km LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time
Ave Speed, Loaded = 30.00 kph
Ave Speed, Empty = 40.00 kph

Loading Time = 3.00 min


Travel Time, Loaded
First 200m at 20.00 kph = 0.60 min
60.6 km @ 30.00 kph = 121.20 min
Last 200 m at 20.00 kph = 0.60 min

Unload/Maneuver = 2.00 min

Return Time, Empty


First 200m at 30.00 kph = 0.40 min
60.6 km @ 40.00 kph = 90.90 min
Last 200 m at 30.00 kph = 0.40 min
CYCLE TIME 219.10

Allowance for Delay 21.91 min


TOTAL CYCLE TIME 241.01 min

COMPUTATION OF HAULING COST


8 x 60 trips / day/ 10 cu.m.
No. of Trips = = 1.99
241.0 DT
say 1.99 trips / day/ 10 cu.m. DT

Rental of Dump Truck (10 cu.m.) = P11,360.00 /day

HAULING COST = P11,360.00 = P P570.85 /cu.m.


=
(10 * 1.99)

3. Excise Tax 3% (1 & 2): = P 19.58 /cu.m.


4. Royalty access rd. Prov'l and brgy. Tax: = P 20.00 /cu.m.
5. Extraction Fee = P 20.00 /cu.m.
6. Quarry Fee = P 50.00 /cu.m.
COST OF AGGREGATES = P 762.22 /cu.m.
PROCESSING : Employing Unskilled laborer, Skilled Laborer and Loader

1. Fine Aggregates :
Screening = P( 13,864.00 + 406.89 + 528.49 ) = P 74.00 /cu.m.
P 200.00 cu.m./day
Washing = P( 13,864.00 + 406.89 + 528.49 + 335.50 = P 50.45 /cu.m.
P 300.00 cu.m./day = P 124.45 /cu.m.

F.A. = P( 762.22 + 124.45 ) /cu.m. = P 886.67 /cu.m.

2. Coarse Aggregates :
Screening = P( 13,864.00 + 406.89 + 528.49 ) = P 98.66 /cu.m.
P 150.00 cu.m./day
Washing = P( 13,864.00 + 406.89 + 528.49 + 335.50 = P 50.45 /cu.m.
P 300.00 cu.m./day P 149.11 /cu.m.

C.A. = P( 762.22 + 149.11 ) /cu.m. = P 911.33 /cu.m.

3.Sub-Base Course :
Screening = P 13,864.00 + 406.89 + 528.49 ) = P 74.00 /cu.m.
P 200.00 cu.m./day

4.Base Course :
Screening = P 13,864.00 + 406.89 + 528.49 ) = P 74.00 /cu.m.
P 200.00 cu.m./day
Blending = P 13,864.00 + 406.89 + 528.49 ) = P 29.60 /cu.m.
P 500.00 cu.m./day P 103.60 /cu.m.

5. Surface Course :
Screening = P 13,864.00 + 406.89 + 528.49 ) = P 98.66 /cu.m.
P 150.00 cu.m./day
Blending = P 13,864.00 + 406.89 + 528.49 ) = P 29.60 /cu.m.
P 500.00 cu.m./day P 128.26 /cu.m.

Therefore, the unit price derivation of the following are:


Item 200 = cost of aggregates + screening
= P 762.22 + 74.00 = P 836.22 /cu.m.

For structural concrete:


F.A. = cost` of aggregates + cost of screening + cost of washing
= P( 762.22 + 74.00 + 50.45 ) /cu.m. = P 886.67 /cu.m.

C.A. = cost` of aggregates + cost of screening + cost of washing


= P( 762.22 + 98.66 + 50.45 ) /cu.m. = P 911.33 /cu.m.
ANNEX A
CAGAYAN FIRST DISTRICT ENGINEERING OFFICE

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL) Appropriation : 2,835,650.15

BRGY. GUISING, GATTARAN, CAGAYAN Source of Fund :


Project ID : Target Start Date :
Location : BRGY. GUISING, GATTARAN, CAGAYAN Total Project Duration : 60 CD
Project Description : IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
FOUNDATION, COLUMNS(ALL SPAN),SLAB ON FILL , CHB WALL, SECOND FLOOR BEAMS
ELEVATED SLAB, WINDOWS, PLASTERING, ELECTRICAL, PAINT, STAIR, RAMP

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.00% -
Part II Other General Requirements 4.47% 96,970.65
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 3.43% 74,415.57
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 13.06% 283,663.23
PART C FINISHING WORKS 75.93% 1,648,858.92
PART D PLUMBING/SANITARY WORKS 0.00% -
PART E ELECTRICAL WORKS 3.11% 67,505.14

Total 100% 2,171,413.51

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 634,131.22 A. Total Direct Cost 2,171,413.51
2. Materials 1,406,910.60 B. OCM and Profit 529,205.68
3. Rental of Equipment 130,371.69 C. Value Added Tax (5%) 135,030.96
4. Provisional Sum - D. Total Construction Cost 2,835,650.15
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 529,205.68 E. Eng'g & Administrative Overhead, 1.00%
6. Value Added Tax (5%) 135,030.96 F. RROW Acquisition
7. EAO, 1.00 % G. Physical Reserved (Contingency)
8. RROW Acquisition H. Provisional Sum -
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 2,835,650.15 H. TOTAL ESTIMATED COST 2,835,650.15
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

RESTIE M. TABANGCURA MARITES T. ARGONZA FELISA M. SALVADOR PEDRITO R. BAUTISTA ROSAURO R. GUERRERO
Engineering Assistant Architect II Chief, Planning & Design Section OIC- Assistant District Engineer District Engineer
Planning & Design Section Planning & Design Section
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
(DIRECT+INDIRECT)
TOTAL UNIT COST
ITEM NO. DESCRIPTION UNIT
AS AS
AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
EVALUATED EVALUATED

PART I FACILITIES FOR THE ENGINEER

PART II OTHER GENERAL REQUIREMENTS

A.1.4. Provision of Progress Photographs 30.00 Each 450.00 15.00 19.69 0.02

B.3 Permits and Clearances 1.00 L.S. 12,000.00 12,000.00 13,860.00 0.55

B.5 Project Billboard/ Sign Board 1.00 Each 5,536.00 5,536.00 7,265.99 0.25

B.7(1) Occupational Safety and Health Program 3.00 mo 58,240.23 19,413.41 22,422.49 2.68

B.9 Mobilization/Demobilization 1.00 LS 20,744.43 20,744.43 23,959.81 0.96

TOTAL OF PART II 96,970.65

Project ID

(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

PART A EARTHWORKS

800(2) Clearing and Grubbing 1.00 LS 5,132.03 5,132.03 6,735.79 0.24

801(1) Removal of Structures & Obstructions- BEAMS COLUMN WALL part of gym 1.00 LS 45,833.71 45,833.71 60,156.75 2.11

803(1)a Structure Excavation (Common Soil) 28.97 m3 5,861.11 202.35 265.59 0.27

804(1)a Embankment from Structure Excavation - m3 - #DIV/0! #DIV/0! -

804(1)b Embankment from Common Borrow 28.13 m3 14,586.37 518.63 680.70 0.67

804(4) Gravel Fill 2.55 m3 3,002.35 1,179.61 1,548.24 0.14

TOTAL OF PART A 74,415.57

PART B PLAIN AND REINFORCED CONCRETE WORKS

900(1)c2 Structural Concrete (Footing and Slab on Fill) -Class A, 28 days 8.11 m3 43,551.32 5,370.08 7,048.23 2.01
Structural Concrete(Column) -Class A, 28 days
900(1)c4 3.02 m3 18,021.45 5,967.37 7,832.17 0.83
Structural Concrete(Suspended Slab)-Class A, 28 days
900(1)c5 4.89 m3 29,132.54 5,952.40 7,812.53 1.34
Structural Concrete(Beams)- Class A, 28 days
900(1)c6 - m3 - #DIV/0! #DIV/0! -

902(1)a1 Reinforcing Steel, Grade 40 2,198.26 kg 138,783.03 63.13 82.86 6.39

903(1) Formworks and Falseworks 1.00 L.S 43,868.55 43,868.55 57,577.48 2.02

TOTAL OF PART B 283,663.23

PART C FINISHING

C.1 Termite Control Works


1000(1) Soil Poisoning 30.00 L 5,204.94 173.50 227.72 0.24

Sub-Total C.1 9,732.49

C.2. Masonry Works


1046(2)a2 CHB Non-Load Bearing -150mm (including Reinforcing Steel) 338.21 m2 399,327.39 1,180.72 1,549.69 18.39

Sub-Total C.2 399,327.39

C.3 Fabricated Materials

1005(1) Casement Steel Window 7.20 m2 30,329.96 4,212.49 5,528.90 1.40

1007(1)b Aluminum Framed Glass Door 2.94 m2 11,967.99 4,070.75 5,342.85 0.55

1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions) 1.00 set - - - -

Sub-Total C.3 42,297.95

C.4 Finishing Works


1021(1)c Plain Cement Floor Finish with Floor Hardener 42.00 m2 9,512.57 226.49 297.27 0.44

1027(1) Cement Plaster Finish 695.74 m2 143,618.73 206.43 270.93 6.61

Sub-Total C.4 476,974.23

C.5 Painting Works


1032(1)a Painting Works (Masonry) 653.80 m2 239,007.04 365.57 479.81 11.01

Sub-Total C.5 396,022.71

TOTAL OF PART C 1,648,858.92

PART d ELECTRICAL

1100(10) Conduit, Boxes, and Fittings(Conduit Works/Conduit Rough -in) 1.00 LS 11,089.98 11,089.98 14,555.59 0.51

1101(33) Wires and Wiring Devices 1.00 LS 37,127.61 37,127.61 48,729.99 1.71

1102(1) Panelboard w/ Main & Branch Breakers 1.00 LS 11,315.56 11,315.56 14,851.67 0.52

1103(1) Lighting Fixtures 1.00 LS 7,971.99 7,971.99 10,463.24 0.37

TOTAL OF PART E 67,505.14

TOTAL OF PART III 2,006,937.72

TOTAL OF (Project ID) 2,074,442.85


GRAND TOTAL 2,171,413.51 100.00
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP ADJUSTED
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE UNIT COST
PART I FACILITIES FOR THE ENGINEER
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.02 30.00 Each 450.00 - - 15.00 450.00 25% 112.50 28.13 590.63 19.69
A.1.4. Provision of Progress Photographs
As Evaluated
As Submitted 0.55 1.00 L.S. 12,000.00 - - 12,000.00 12,000.00 10% 1,200.00 660.00 13,860.00 13,860.00
B.3 Permits and Clearances
As Evaluated
As Submitted 0.25 1.00 Each 4,550.00 896.36 89.64 5,536.00 5,536.00 25% 1,384.00 346.00 7,265.99 7,265.99
B.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 2.68 3.00 mo 26,531.43 31,708.80 - 19,413.41 58,240.23 10% 5,824.02 3,203.21 67,267.47 22,422.49
B.7(1) Occupational Safety and Health Program
As Evaluated
As Submitted 0.96 1.00 LS - - 20,744.43 20,744.43 20,744.43 10% 2,074.44 1,140.94 23,959.81 23,959.81
B.9 Mobilization/Demobilization
As Evaluated
As Submitted 43,531.43 32,605.16 20,834.06 96,970.65 10,594.96 5,378.28 112,943.90
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.24 1.00 LS - 4,665.48 466.55 5,132.03 5,132.03 25% 1,283.01 320.75 6,735.79 6,735.79
800(2) Clearing and Grubbing
As Evaluated
As Submitted 2.11 1.00 LS - 30,757.92 15,075.79 45,833.71 45,833.71 25% 11,458.43 2,864.61 60,156.75 60,156.75
801(1) Removal of Structures & Obstructions- BEAMS COLUMN WALL part of gym
As Evaluated
As Submitted 0.27 28.97 m3 - 5,328.29 532.83 202.35 5,861.11 25% 1,465.28 366.32 7,692.71 265.59
803(1)a Structure Excavation (Common Soil)
As Evaluated -
As Submitted - - m3 - - - #DIV/0! - 25% - - - #DIV/0!
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.67 28.13 m3 9,843.75 4,311.47 431.15 518.63 14,586.37 25% 3,646.59 911.65 19,144.60 680.70
804(1)b Embankment from Common Borrow
As Evaluated
As Submitted 0.14 2.55 m3 2,128.35 557.38 316.62 1,179.61 3,002.35 25% 750.59 187.65 3,940.58 1,548.24
804(4) Gravel Fill
As Evaluated
As Submitted 11,972.10 45,620.53 16,822.94 74,415.57 18,603.89 4,650.98 97,670.43
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 2.01 8.11 m3 28,151.88 10,447.36 4,952.08 5,370.08 43,551.32 25% 10,887.83 2,721.96 57,161.11 7,048.23
900(1)c2 Structural Concrete (Footing and Slab on Fill) -Class A, 28 days
As Evaluated
Structural Concrete(Column) -Class A, 28 days As Submitted 0.83 3.02 m3 10,439.25 5,143.95 2,438.25 5,967.37 18,021.45 25% 4,505.36 1,126.34 23,653.15 7,832.17
900(1)c4
As Evaluated
Structural Concrete(Suspended Slab)-Class A, 28 days As Submitted 1.34 4.89 m3 16,844.73 8,336.36 3,951.45 5,952.40 29,132.54 25% 7,283.14 1,820.78 38,236.46 7,812.53
900(1)c5
As Evaluated
Structural Concrete(Beams)- Class A, 28 days As Submitted - - m3 - - - #DIV/0! - 25% - - - #DIV/0!
900(1)c6
As Evaluated
As Submitted 6.39 2,198.26 kg 115,746.48 16,520.75 6,515.80 63.13 138,783.03 25% 34,695.76 8,673.94 182,152.73 82.86
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 2.02 1.00 L.S 35,173.91 7,904.22 790.42 43,868.55 43,868.55 25% 10,967.14 2,741.78 57,577.48 57,577.48
903(1) Formworks and Falseworks
As Evaluated
As Submitted 212,294.02 51,316.39 20,052.82 283,663.23 70,915.81 17,728.95 372,307.98
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.24 30.00 L 3,500.00 1,549.94 154.99 173.50 5,204.94 25% 1,301.23 325.31 6,831.48 227.72
1000(1) Soil Poisoning
As Evaluated
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP ADJUSTED
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE UNIT COST
As Submitted 6,800.00 2,665.90 266.59 9,732.49 2,433.12 608.28 12,773.90
Sub - Total C.1
As Evaluated
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP ADJUSTED
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE UNIT COST
C.2. Masonry Works
As Submitted 18.39 338.21 m2 318,914.00 56,473.12 23,940.27 1,180.72 399,327.39 25% 99,831.85 24,957.96 524,117.20 1,549.69
1046(2)a2 CHB Non-Load Bearing -150mm (including Reinforcing Steel)
As Evaluated
As Submitted 318,914.00 56,473.12 23,940.27 399,327.39 99,831.85 24,957.96 524,117.20
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.40 7.20 m2 16,560.00 8,963.60 4,806.36 4,212.49 30,329.96 25% 7,582.49 1,895.62 39,808.07 5,528.90
1005(1) Casement Steel Window
As Evaluated
As Submitted 0.55 2.94 m2 9,996.00 1,792.72 179.27 4,070.75 11,967.99 25% 2,992.00 748.00 15,707.99 5,342.85
1007(1)b Aluminum Framed Glass Door
As Evaluated
As Submitted 26,556.00 10,756.32 4,985.63 42,297.95 10,574.49 2,643.62 55,516.06
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 0.44 42.00 m2 6,920.01 2,356.87 235.69 226.49 9,512.57 25% 2,378.14 594.54 12,485.25 297.27
1021(1)c Plain Cement Floor Finish with Floor Hardener
As Evaluated
As Submitted 6.61 695.74 m2 78,946.73 58,792.72 5,879.27 206.43 143,618.73 25% 35,904.68 8,976.17 188,499.58 270.93
1027(1) Cement Plaster Finish
As Evaluated
As Submitted 312,982.86 149,083.07 14,908.31 476,974.23 119,243.55 29,810.90 626,028.69
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 11.01 653.80 m2 94,763.51 131,130.49 13,113.05 365.57 239,007.04 25% 59,751.76 14,937.94 313,696.74 479.81
1032(1)a Painting Works (Masonry)
As Evaluated
As Submitted 148,745.01 224,797.91 22,479.79 396,022.71 99,005.68 24,751.42 519,779.81
Sub-Total C.5
As Evaluated
As Submitted 1,090,199.41 487,687.78 70,971.73 1,648,858.92 412,214.73 103,053.68 2,164,127.34
TOTAL OF PART C
As Evaluated
PART d ELECTRICAL
As Submitted 0.51 1.00 LS 5,174.00 5,378.16 537.82 11,089.98 11,089.98 25% 2,772.49 693.12 14,555.59 14,555.59
1100(10) Conduit, Boxes, and Fittings(Conduit Works/Conduit Rough -in)
As Evaluated
As Submitted 1.71 1.00 LS 29,239.64 7,170.88 717.09 37,127.61 37,127.61 25% 9,281.90 2,320.48 48,729.99 48,729.99
1101(33) Wires and Wiring Devices
As Evaluated
As Submitted 0.52 1.00 LS 8,500.00 2,559.60 255.96 11,315.56 11,315.56 25% 2,828.89 707.22 14,851.67 14,851.67
1102(1) Panelboard w/ Main & Branch Breakers
As Evaluated
As Submitted 0.37 1.00 LS 6,000.00 1,792.72 179.27 7,971.99 7,971.99 25% 1,993.00 498.25 10,463.24 10,463.24
1103(1) Lighting Fixtures
As Evaluated
As Submitted 48,913.64 16,901.36 1,690.14 67,505.14 16,876.28 4,219.07 88,600.49
TOTAL OF PART E
As Evaluated
As Submitted 1,363,379.17 601,526.06 109,537.63 2,074,442.85 518,610.71 129,652.68 2,722,706.25
TOTAL OF PART III
As Evaluated
As Submitted 1,363,379.17 601,526.06 109,537.63 2,074,442.85 518,610.71 129,652.68 2,722,706.25
TOTAL OF (Project ID)
As Evaluated
As Submitted 1,406,910.60 634,131.22 130,371.69 2,171,413.51 529,205.68 135,030.96 2,835,650.15
GRAND TOTAL
As Evaluated
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 One Bagger Mixer 4 - 6 ft3/min 1 31
2 Bar Cutter 1 32
3 Bar Bender 1 33
4 Cutting Outfit 1 34
5 Demoltion Hammer 1 35
6 36
7 37
8 38
9 39
10 40
11 41
12 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL 5 SUB-TOTAL
TOTAL 5
CAGAYAN FIRST DISTRICT ENGINEERING OFFICE

FORM ABC-2015-02-00
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 60 CD
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED - 10.00% - - - -
PART I FACILITIES FOR THE ENGINEER
AS EVALUATED

AS SUBMITTED 96,970.65 25.00% 10,594.96 5,378.28 15,973.25 112,943.90


PART II OTHER GENERAL REQUIREMENTS
AS EVALUATED

(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
AS SUBMITTED 74,415.57 25.00% 18,603.89 4,650.98 23,254.87 97,670.44
PART A EARTHWORKS
AS EVALUATED

AS SUBMITTED 283,663.23 25.00% 70,915.81 17,728.95 88,644.76 372,307.99


PART B PLAIN AND REINFORCED CONCRETE WORKS
AS EVALUATED

AS SUBMITTED 2,074,442.85 25.00% 518,610.71 129,652.68 648,263.39 2,722,706.24


TOTAL OF PART III
AS EVALUATED

AS SUBMITTED 2,074,442.85 25.00% 518,610.71 129,652.68 648,263.39 2,722,706.24


TOTAL OF (Project ID)
AS EVALUATED

AS SUBMITTED 2,171,413.51 25.00% 529,205.68 135,030.96 664,236.64 2,835,650.15


TOTAL
AS EVALUATED

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

RESTIE M. TABANGCURA MARITES T. ARGONZA FELISA M. SALVADOR PEDRITO R. BAUTISTA ROSAURO R. GUERRERO
Engineering Assistant Architect II Chief, Planning & Design Section OIC- Assistant District Engineer District Engineer
Planning & Design Section Planning & Design Section
CAGAYAN FIRST DISTRICT ENGINEERING OFFICE

FORM ABC-2015-02A-00
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 60 CD
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST

PART I FACILITIES FOR THE ENGINEER


PART II OTHER GENERAL REQUIREMENTS
AS SUBMITTED 30.00 Each 450.00 25% 112.50 28.13 140.63 590.63 19.69
A.1.4. Provision of Progress Photographs
AS EVALUATED

AS SUBMITTED 1.00 L.S. 12,000.00 10% 1,200.00 660.00 1,860.00 13,860.00 13,860.00
B.3 Permits and Clearances
AS EVALUATED

AS SUBMITTED 1.00 Each 5,536.00 25% 1,384.00 346.00 1,730.00 7,265.99 7,265.99
B.5 Project Billboard/ Sign Board
AS EVALUATED

AS SUBMITTED 3.00 mo 58,240.23 10% 5,824.02 3,203.21 9,027.24 67,267.47 22,422.49


B.7(1) Occupational Safety and Health Program
AS EVALUATED

AS SUBMITTED 1.00 LS 20,744.43 10% 2,074.44 1,140.94 3,215.39 23,959.81 23,959.81


B.9 Mobilization/Demobilization
AS EVALUATED

AS SUBMITTED 96,970.65 10,594.96 5,378.28 15,973.25 112,943.90


TOTAL OF PART II
AS EVALUATED

(Project ID)
(Project Component ID - Description)

CIVIL, MECHANICAL, ELECTRICAL AND


PART III
SANITARY/PLUMBING WORKS

PART A EARTHWORKS
AS SUBMITTED 1.00 LS 5,132.03 25% 1,283.01 320.75 1,603.76 6,735.79 6,735.79
800(2) Clearing and Grubbing
AS EVALUATED

Removal of Structures & Obstructions- BEAMS COLUMN AS SUBMITTED 1.00 LS 45,833.71 25% 11,458.43 2,864.61 14,323.04 60,156.75 60,156.75
801(1)
WALL part of gym AS EVALUATED

AS SUBMITTED 28.97 m3 5,861.11 25% 1,465.28 366.32 1,831.60 7,692.71 265.59


803(1)a Structure Excavation (Common Soil)
AS EVALUATED

AS SUBMITTED - m3 - 25% - - - - #DIV/0!


804(1)a Embankment from Structure Excavation
AS EVALUATED

AS SUBMITTED 28.13 m3 14,586.37 25% 3,646.59 911.65 4,558.24 19,144.60 680.70


804(1)b Embankment from Common Borrow
AS EVALUATED

AS SUBMITTED 2.55 m3 3,002.35 25% 750.59 187.65 938.23 3,940.58 1,548.24


804(4) Gravel Fill
AS EVALUATED

AS SUBMITTED 74,415.57 18,603.89 4,650.97 23,254.86 97,670.43


TOTAL OF PART A
AS EVALUATED

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

RESTIE M. TABANGCURA MARITES T. ARGONZA FELISA M. SALVADOR


Engineering Assistant Architect II Chief, Planning & Design Section
Planning & Design Section Planning & Design Section
CAGAYAN FIRST DISTRICT ENGINEERING OFFICE

FORM ABC-2015-02A-00
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 60 CD
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST

PART B PLAIN AND REINFORCED CONCRETE WORKS

Structural Concrete (Footing and Slab on Fill) -Class A, 28 AS SUBMITTED 8.11 m3 43,551.32 25% 10,887.83 2,721.96 13,609.79 57,161.11 7,048.23
900(1)c2
days AS EVALUATED

Structural Concrete(Column) -Class A, 28 days AS SUBMITTED 3.02 m3 18,021.45 25% 4,505.36 1,126.34 5,631.70 23,653.15 7,832.17
900(1)c4
AS EVALUATED

Structural Concrete(Suspended Slab)-Class A, 28 days AS SUBMITTED 4.89 m3 29,132.54 25% 7,283.14 1,820.78 9,103.92 38,236.46 7,812.53
900(1)c5
AS EVALUATED

Structural Concrete(Beams)- Class A, 28 days AS SUBMITTED - m3 - 25% - - - - #DIV/0!


900(1)c6
AS EVALUATED

AS SUBMITTED 2,198.26 kg 138,783.03 25% 34,695.76 8,673.94 43,369.70 182,152.73 82.86


902(1)a1 Reinforcing Steel, Grade 40
AS EVALUATED

AS SUBMITTED 1.00 L.S 43,868.55 25% 10,967.14 2,741.78 13,708.92 57,577.48 57,577.48
903(1) Formworks and Falseworks
AS EVALUATED

AS SUBMITTED 283,663.23 70,915.81 17,728.95 88,644.76 372,307.99


TOTAL OF PART B
AS EVALUATED

PART C FINISHING WORKS


AS SUBMITTED 338.21 m2 399,327.39 25% 99,831.85 24,957.96 124,789.81 524,117.20 1,549.69
1046(2)a2 CHB Non-Load Bearing -150mm (including Reinforcing Steel)
AS EVALUATED

AS SUBMITTED 7.20 m2 30,329.96 25% 7,582.49 1,895.62 9,478.11 39,808.07 5,528.90


1005(1) Casement Steel Window
AS EVALUATED

AS SUBMITTED 2.94 m2 11,967.99 25% 2,992.00 748.00 3,740.00 15,707.99 5,342.85


1007(1)b Aluminum Framed Glass Door
AS EVALUATED

AS SUBMITTED 42.00 m2 9,512.57 25% 2,378.14 594.54 2,972.68 12,485.25 297.27


1021(1)c Plain Cement Floor Finish with Floor Hardener
AS EVALUATED
AS SUBMITTED 695.74 m2 143,618.73 25% 35,904.68 8,976.17 44,880.85 188,499.58 270.93
1027(1) Cement Plaster Finish
AS EVALUATED

AS SUBMITTED 653.80 m2 239,007.04 25% 59,751.76 14,937.94 74,689.70 313,696.74 479.81


1032(1)a Painting Works (Masonry)
AS EVALUATED

AS SUBMITTED 1,648,858.92 412,214.73 103,053.68 515,268.41 2,164,127.34


TOTAL OF PART C
AS EVALUATED

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

RESTIE M. TABANGCURA MARITES T. ARGONZA FELISA M. SALVADOR


Engineering Assistant Architect II Chief, Planning & Design Section
CAGAYAN FIRST DISTRICT ENGINEERING OFFICE

FORM ABC-2015-02A-00
IMPROVEMENT OF MULTI - PURPOSE BUILDING (BRGY. HALL)
BRGY. GUISING, GATTARAN, CAGAYAN

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 60 CD
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST

PART d ELECTRICAL WORKS

AS SUBMITTED 1.00 LS 11,089.98 25% 2,772.49 693.12 3,465.62 14,555.59 14,555.59


Conduit, Boxes, and Fittings(Conduit Works/Conduit Rough
1100(10)
-in)
AS EVALUATED

AS SUBMITTED 1.00 LS 37,127.61 25% 9,281.90 2,320.48 11,602.38 48,729.99 48,729.99


1101(33) Wires and Wiring Devices
AS EVALUATED

AS SUBMITTED 1.00 LS 11,315.56 25% 2,828.89 707.22 3,536.11 14,851.67 14,851.67


1102(1) Panelboard w/ Main & Branch Breakers
AS EVALUATED

AS SUBMITTED 1.00 LS 7,971.99 25% 1,993.00 498.25 2,491.25 10,463.24 10,463.24


1103(1) Lighting Fixtures
AS EVALUATED

AS SUBMITTED 67,505.14 16,876.28 4,219.07 21,095.36 88,600.49


TOTAL OF PART d
AS EVALUATED

AS SUBMITTED 2,074,442.85 518,610.71 129,652.68 648,263.39 2,722,706.24


TOTAL OF PART III
AS EVALUATED

AS SUBMITTED 2,074,442.85 518,610.71 129,652.68 648,263.39 2,722,706.24


TOTAL OF (Project ID)
AS EVALUATED

AS SUBMITTED 2,171,413.51 529,205.68 135,030.96 664,236.64 2,835,650.14


GRAND TOTAL
AS EVALUATED

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

RESTIE M. TABANGCURA MARITES T. ARGONZA FELISA M. SALVADOR


Engineering Assistant Architect II Chief, Planning & Design Section
Planning & Design Section Planning & Design Section
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : A.1.1 (8) Provision of field Office for the Engineer (Rental Basis)
Unit of Measurement : mo
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A 0.00

Name and Capacity No of Unit/s No. of Months/s Monthly Rate Amount (PhP)

B. Equipment

Rental for 1 Unit 40 footer container van with ACU, 0 3.17 26,000.00 0.00
furnitures, and maintenance.

Sub - Total for B 0.00


C. Total (A + B) 0.00
D. Output per Hour = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 0.00
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (C + F) 0.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses of G
I. Contractor's Profit (CP) 10% of G 0.00
J. Value Added Tax (VAT) 5% of (G + H + I) 0.00
K. Total Unit Cost (G + H + I + J) 0.00

PART I - Facilities for the Engineer


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : A.1.4. Provision of Progress Photographs


Unit of Measurement : Each
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

-
Minor Tools (10% of labor cost)

Sub - Total for B -


C. Total (A + B) -
D. Output = 2.00 ea
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Developing fee of 5R size pictures each 30.00 15.00 450.00

Sub - Total for F 450.00


G. Direct Unit Cost (C + F) 450.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 67.50
I. Contractor's Profit (CP) 10% of G 45.00
J. Value Added Tax (VAT) 5% of (G + H + I) 28.13
K. Total Unit Cost (G + H + I + J) 590.63
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.3 Permits and Clearances


Unit of Measurement : L.S.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.

Sub - Total for B -


C. Total (A + B) -
D. Output = 1 each
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Permits & clearances(BFP, MUNICIPAL 1 ls 5,000.00 5,000.00


BUILDING PERMIT)

B. Professional fees(archi, CE, ME, PEE, 1.000 ls 5,000.00 5,000.00


ECE, SE)

C. Environmental Clearances (mines & 1 ls 2,000.00 2,000.00


Geologic Bureau)

Sub - Total for F 12,000.00


G. Direct Unit Cost (C + F) 12,000.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 10% of G 1,200.00
J. Value Added Tax (VAT) 5% of (G + H + I) 660.00
K. Total Unit Cost (G + H + I + J) 13,860.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.5 Project Billboard/ Sign Board


Unit of Measurement : Each
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.00 98.09 392.36


b. Skilled Laborer 1 4.00 71.10 284.40
c. Unskilled Laborer 1 4.00 54.90 219.60

Sub - Total for A 896.36

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

89.64
Minor Tools (10% of labor cost)

Sub - Total for B 89.64


C. Total (A + B) 986.00
D. Output = 1 each
E. Direct Unit Cost (C ÷ D) 986.00

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 8' x 8' Tarpaulin ft2 64.00 35.00 2,240.00


b. Good Lumber (Frames) bd-ft 42.00 45.00 1,890.00
c. Assorted Common Working Nails kg 1.00 70.00 70.00
d. Plywood 1/4 x 4'x 8' pc 1.00 350.00 350.00

Sub - Total for F 4,550.00


G. Direct Unit Cost (C + F) 5,536.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 830.40
I. Contractor's Profit (CP) 10% of G 553.60
J. Value Added Tax (VAT) 5% of (G + H + I) 346.00
K. Total Unit Cost (G + H + I + J) 7,265.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (12 CL)


Unit of Measurement : lot
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 12.00 528.48 6,341.76

Sub - Total for A 6,341.76

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 6,341.76
D. Output = 1 mo.
E. Direct Unit Cost (C ÷ D) 6,341.76

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 1,000.00

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 12,254.00 0.25 3,063.50
b. Safety Shoes man-days 12,254.00 2.77 33,943.58
c. Safety Gloves man-days 12,254.00 7.67 93,988.18
-
-
-
-
-
-
-

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') sets 28.00 123.68 3,463.04
d. Caution Tape, 100ft roll 1.00 800.00 800.00

Sub - Total for F 137,035.54


G. Direct Unit Cost (E + F) 143,377.30
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 11,470.18
J. Value Added Tax (VAT) 5% of (G + H + I) 7,742.37
K. Total Unit Cost (G + H + I + J) 162,589.86
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (10 CL)


Unit of Measurement : lot
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 12.00 528.48 6,341.76

Sub - Total for A 6,341.76

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 6,341.76
D. Output = 1 lot
E. Direct Unit Cost (C ÷ D) 6,341.76

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 1,000.00

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 11,066.00 0.25 2,766.50
b. Safety Shoes man-days 11,066.00 2.77 30,652.82
c. Safety Gloves man-days 11,066.00 7.67 84,876.22
-
-
-
-
-
-
-

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') sets 27.00 123.68 3,339.36
d. Caution Tape, 100ft roll 1.00 800.00 800.00

Sub - Total for F 124,212.14


G. Direct Unit Cost (E + F) 130,553.90
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 10,444.31
J. Value Added Tax (VAT) 5% of (G + H + I) 7,049.91
K. Total Unit Cost (G + H + I + J) 148,048.12
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (8 CL)


Unit of Measurement : mo
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 10.00 528.48 5,284.80

Sub - Total for A 5,284.80

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 5,284.80
D. Output = 1 mo.
E. Direct Unit Cost (C ÷ D) 5,284.80

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 1,000.00

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 9,966.00 0.25 2,491.50
b. Safety Shoes man-days 9,966.00 2.77 27,605.82
c. Safety Gloves man-days 9,966.00 7.67 76,439.22

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') sets 26.00 123.68 3,215.68
d. Caution Tape, 100ft roll 1.00 800.00 800.00

Sub - Total for F 112,329.46


G. Direct Unit Cost (E + F) 117,614.26
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 9,409.14
J. Value Added Tax (VAT) 5% of (G + H + I) 6,351.17
K. Total Unit Cost (G + H + I + J) 133,374.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (6 CL)


Unit of Measurement : lot
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 10.00 528.48 5,284.80

Sub - Total for A 5,284.80

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 5,284.80
D. Output = 1 lot
E. Direct Unit Cost (C ÷ D) 5,284.80

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 1,000.00

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 7,920.00 0.25 1,980.00
b. Safety Shoes man-days 7,920.00 2.77 21,938.40
c. Safety Gloves man-days 7,920.00 7.67 60,746.40

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') sets 24.00 123.68 2,968.32
d. Caution Tape, 100ft roll 0.50 800.00 400.00

Sub - Total for F 89,810.36


G. Direct Unit Cost (E + F) 95,095.16
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 7,607.61
J. Value Added Tax (VAT) 5% of (G + H + I) 5,135.14
K. Total Unit Cost (G + H + I + J) 107,837.91
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.7(1) Occupational Safety and Health Program


Unit of Measurement : mo
Output per hour : 1.00

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

Health and Safety Practitioner


a. Safety Practitioner/ Officer (Part Time) 1 60.00 528.48 31,708.80

Sub - Total for A 31,708.80

Name and Capacity No of Unit/s No. of Months/s Monthly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 31,708.80
D. Output per Hour = 1 mo
E. Direct Unit Cost (C ÷ D) 31,708.80

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
First Aid Kit l.s. 1.00 1,091.43 1,091.43

Personal Protective Equipment


a. Safety Helmet man-days 1800.00 0.25 450.00
b. Safety Shoes man-days 1800.00 2.77 4,986.00
c. Safety Gloves man-days 1800.00 7.67 13,806.00
d. Safety vest man-days 1500.00 2.77 4,155.00

Use for the whole project duration


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4' ) set 1.00 270.87 270.87
c. Warning Signs ( 2' x 3' ) sets 7 123.68 865.76
d. Caution Tape , 1000 ft roll 0.5 800.00 400.00
Note : Use for the whole project duration

Sub - Total for F 26,531.43


G. Direct Unit Cost (C + F) 58,240.23
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses of G
I. Contractor's Profit (CP) 10% of G 5,824.02
J. Value Added Tax (VAT) 5% of (G + H + I) 3,203.21
K. Total Unit Cost (G + H + I + J) 67,267.47

PART II - Other General Requirements


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.7 Occupational Safety and Health (2 CL)


Unit of Measurement : lot
Output : 1

Designation No. of Person/s No. of Day/s Daily Rate Amount (PhP)

A. Labor

a. Part Time Safety Officer 1 8.00 528.48 4,227.84

Sub - Total for A 4,227.84

Name and Capacity Unit Quantity Daily Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B) 4,227.84
D. Output = 1 mo.
E. Direct Unit Cost (C ÷ D) 4,227.84

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

First Aid Kit l.s. 1.00 1,000.00 1,000.00

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 5,610.00 0.25 1,402.50
b. Safety Shoes man-days 5,610.00 2.77 15,539.70
c. Safety Gloves man-days 5,610.00 7.67 43,028.70

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') sets 10.00 123.68 1,236.80
d. Caution Tape, 100ft roll 0.50 800.00 400.00

Sub - Total for F 63,384.94


G. Direct Unit Cost (E + F) 67,612.78
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 5,409.02
J. Value Added Tax (VAT) 5% of (G + H + I) 3,651.09
K. Total Unit Cost (G + H + I + J) 76,672.89
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (12 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

127,576.82
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B 127,576.82


C. Total (A + B) 127,576.82
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 127,576.82

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) 127,576.82


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 10,206.15
J. Value Added Tax (VAT) 5% of (G + H + I) 6,889.15
K. Total Unit Cost (G + H + I + J) 144,672.11
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (10 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

112,378.72
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B 112,378.72


C. Total (A + B) 112,378.72
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 112,378.72

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) 112,378.72


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 8,990.30
J. Value Added Tax (VAT) 5% of (G + H + I) 6,068.45
K. Total Unit Cost (G + H + I + J) 127,437.47
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (8 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

96,588.26
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B 96,588.26


C. Total (A + B) 96,588.26
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 96,588.26

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) 96,588.26


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 7,727.06
J. Value Added Tax (VAT) 5% of (G + H + I) 5,215.77
K. Total Unit Cost (G + H + I + J) 109,531.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (6 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

65,853.18
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B 65,853.18


C. Total (A + B) 65,853.18
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 65,853.18

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) 65,853.18


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 5,268.25
J. Value Added Tax (VAT) 5% of (G + H + I) 3,556.07
K. Total Unit Cost (G + H + I + J) 74,677.51
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : II.9 Mobilization/Demobilization (2 CL)


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

34,975.55
a. Mobilization/ Demobilization (0.75% of Civil Works)

Sub - Total for B 34,975.55


C. Total (A + B) 34,975.55
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 34,975.55

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F) 34,975.55


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 8% of G 2,798.04
J. Value Added Tax (VAT) 5% of (G + H + I) 1,888.68
K. Total Unit Cost (G + H + I + J) 39,662.27
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.9 Mobilization/Demobilization


Unit of Measurement : LS
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

20,744.43
a. Mobilization/ Demobilization (1% of Civil Works)

Sub - Total for B 20,744.43


C. Total (A + B) 20,744.43
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) 20,744.43

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (C + F) 20,744.43


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 10% of G 2,074.44
J. Value Added Tax (VAT) 5% of (G + H + I) 1,140.94
K. Total Unit Cost (G + H + I + J) 23,959.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.11 Provisional Sum


Unit of Measurement : PS
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B -


C. Total (A + B) -
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Provison of Standard Ring w/ stand set 0.00 135,000.00 -


(Fiberglass Board)

-
G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0% of G -
I. Contractor's Profit (CP) 0% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 800(2) Clearing and Grubbing


Unit of Measurement : LS
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 12.00 98.09 1,177.08


b. Skilled Laborer 1 12.00 71.10 853.20
c. Unskilled Laborer 4 12.00 54.90 2,635.20
.

Sub - Total for A 4,665.48

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 466.55

Sub - Total for B 466.55


C. Total (A + B) 5,132.03
D. Output per Hour = 20.00 m3
E. Direct Unit Cost (C ÷ D) 5,132.03

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F -


G. Direct Unit Cost (C + F) 5,132.03
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 769.80
I. Contractor's Profit (CP) 10% of G 513.20
J. Value Added Tax (VAT) 5% of (G + H + I) 320.75
K. Total Unit Cost (G + H + I + J) 6,735.79
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 801(1) Removal of Structures & Obstructions- BEAMS COLUMN WALL part of gym
Unit of Measurement : LS
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 48.00 98.09 4,708.32


b. Skilled Laborer 3 48.00 71.10 10,238.40
c. Unskilled Laborer 6 48.00 54.90 15,811.20
.

Sub - Total for A 30,757.92

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
-
Jackhammer 1 48.00 250.00 12,000.00
-
Minor Tools (10% of Labor Cost) 3,075.79

Sub - Total for B 15,075.79


C. Total (A + B) 45,833.71
D. Output per Hour = 20.00 m3
E. Direct Unit Cost (C ÷ D) 45,833.71

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F -


G. Direct Unit Cost (C + F) 45,833.71
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 6,875.06
I. Contractor's Profit (CP) 10% of G 4,583.37
J. Value Added Tax (VAT) 5% of (G + H + I) 2,864.61
K. Total Unit Cost (G + H + I + J) 60,156.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(1)a Structure Excavation (Common Soil)


Unit of Measurement : m3
Output per hour : 2.50

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 11.59 98.09 1,136.47


b. Skilled Laborer 2 11.59 71.10 1,647.53
c. Unskilled Laborer 4 11.59 54.90 2,544.29

Sub - Total for A 5,328.29

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 532.83

Sub - Total for B 532.83


C. Total (A + B) 5,861.11
D. Output per Hour = 20.00 m3
E. Direct Unit Cost (C ÷ D) 202.35

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Volume = 28.97 cu.m. -

Sub - Total for F -


G. Direct Unit Cost (C + F) 5,861.11
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 879.17
I. Contractor's Profit (CP) 10% of G 586.11
J. Value Added Tax (VAT) 5% of (G + H + I) 366.32
K. Total Unit Cost (G + H + I + J) 7,692.71
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)a Embankment from Structure Excavation


Unit of Measurement : m3
Output per hour : 3.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 2 0.00 71.10 -
c. Unskilled Laborer 4 0.00 54.90 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 1 0.00 123.00 -

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 9.84 m3
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Volume = 0.00 cu.m.

G. Direct Unit Cost (C + F) -


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)b Embankment from Common Borrow


Unit of Measurement : m3
Output per hour : 3.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 9.38 98.09 919.59


b. Skilled Laborer 2 9.38 71.10 1,333.13
c. Unskilled Laborer 4 9.38 54.90 2,058.75

Sub - Total for A 4,311.47

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate

B. Equipment

Minor Tools (10% of Labor Cost) 431.15

Sub - Total for B 431.15


C. Total (A + B) 4,742.62
D. Output per Hour = 9.84 m3
E. Direct Unit Cost (C ÷ D) 168.63

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Embankment Materials m3 28.13 350.00 9,843.75


(w/ 25% Shrinkage Factor)

Sub - Total for F 9,843.75


G. Direct Unit Cost (C + F) 14,586.37
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 2,187.95
I. Contractor's Profit (CP) 10% of G 1,458.64
J. Value Added Tax (VAT) 5% of (G + H + I) 911.65
K. Total Unit Cost (G + H + I + J) 19,144.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(4) Gravel Fill


Unit of Measurement : m3
Output per hour : 1.20

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.12 98.09 208.05


b. Unskilled Laborer 3 2.12 54.90 349.33

Sub - Total for A 557.38

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor 1 2.12 123.00 260.88


Minor Tools (10% of Labor Cost) 55.74

Sub - Total for B 316.62


C. Total (A + B) 874.00
D. Output per Hour = 1.20 m3
E. Direct Unit Cost (C ÷ D) 343.39

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel Bedding (G-1) m3 2.55 836.22 2,128.35


(w/ 5% Shrinkage Factor)

Sub - Total for F 2,128.35


G. Direct Unit Cost (C + F) 3,002.35
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 450.35
I. Contractor's Profit (CP) 10% of G 300.23
J. Value Added Tax (VAT) 5% of (G + H + I) 187.65
K. Total Unit Cost (G + H + I + J) 3,940.58
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(1)c2 Structural Concrete (Footing and Slab on Fill) -Class A, 28 days
Unit of Measurement : m3
Output per hour : 0.357

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 22.72 98.09 2,228.32


b. Skilled Laborer 2 22.72 71.10 3,230.37
b. Unskilled Laborer 4 22.72 54.90 4,988.67

Sub - Total for A 10,447.36

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 22.72 172.00 3,907.34


Minor Tools (10% of Labor Cost) 1,044.74

Sub - Total for B 4,952.08


C. Total (A + B) 15,399.44
D. Output per Hour = 0.357 m3
E. Direct Unit Cost (C ÷ D) 1,898.82

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel m3 8.11 516.39 4,187.92


b. Sand m3 4.06 516.39 2,093.96
c. Portland Cement bags 81.00 270.00 21,870.00

Sub - Total for F 28,151.88


G. Direct Unit Cost (C + F) 43,551.32
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 6,532.70
I. Contractor's Profit (CP) 10% of G 4,355.13
J. Value Added Tax (VAT) 5% of (G + H + I) 2,721.96
K. Total Unit Cost (G + H + I + J) 57,161.11

\ PART B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(1)c3 Structural Concrete (Footing Tie Beam) -Class A, 28 days
Unit of Measurement : m3
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 6.44 98.09 632.14


b. Skilled Laborer 2 6.44 71.10 916.40
b. Unskilled Laborer 4 6.44 54.90 1,415.20

Sub - Total for A 2,963.74

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 6.44 172.00 1,108.44


Minor Tools (10% of Labor Cost) 296.37

Sub - Total for B 1,404.82


C. Total (A + B) 4,368.55
D. Output per Hour = 0.270 m3
E. Direct Unit Cost (C ÷ D) 2,510.66

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel m3 1.74 516.39 898.52


b. Sand m 3
0.87 516.39 449.26
c. Portland Cement bags 17.00 270.00 4,590.00

Sub - Total for F 5,937.78


G. Direct Unit Cost (C + F) 10,306.33
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,545.95
I. Contractor's Profit (CP) 10% of G 1,030.63
J. Value Added Tax (VAT) 5% of (G + H + I) 644.15
K. Total Unit Cost (G + H + I + J) 13,527.06

\ PART B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(1)c4 Structural Concrete(Column) -Class A, 28 days


Unit of Measurement : m3
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 11.19 98.09 1,097.15


b. Skilled Laborer 2 11.19 71.10 1,590.53
b. Unskilled Laborer 4 11.19 54.90 2,456.27

Sub - Total for A 5,143.95

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 11.19 172.00 1,923.85


Minor Tools (10% of Labor Cost) 514.40

Sub - Total for B 2,438.25


C. Total (A + B) 7,582.20
D. Output per Hour = 0.270 m3
E. Direct Unit Cost (C ÷ D) 2,510.66

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel m3 3.02 516.39 1559.50


b. Sand m3 1.51 516.39 779.75
c. Portland Cement bags 30.00 270.00 8,100.00

Sub - Total for F 10,439.25


G. Direct Unit Cost (C + F) 18,021.45
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 2,703.22
I. Contractor's Profit (CP) 10% of G 1,802.14
J. Value Added Tax (VAT) 5% of (G + H + I) 1,126.34
K. Total Unit Cost (G + H + I + J) 23,653.15

PART B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(1)c5 Structural Concrete(Suspended Slab)-Class A, 28 days


Unit of Measurement : m3
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 18.13 98.09 1,778.06


b. Skilled Laborer 2 18.13 71.10 2,577.64
b. Unskilled Laborer 4 18.13 54.90 3,980.66

Sub - Total for A 8,336.36

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 18.13 172.00 3,117.82


Minor Tools (10% of Labor Cost) 833.64

Sub - Total for B 3,951.45


C. Total (A + B) 12,287.81
D. Output per Hour = 0.270 m3
E. Direct Unit Cost (C ÷ D) 2510.66296296296

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel m3 5.00 516.39 2581.95


b. Sand m3 2.00 516.39 1032.78
c. Portland Cement bags 49.00 270.00 13,230.00

Sub - Total for F 16,844.73


G. Direct Unit Cost (C + F) 29,132.54
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 4,369.88
I. Contractor's Profit (CP) 10% of G 2,913.25
J. Value Added Tax (VAT) 5% of (G + H + I) 1,820.78
K. Total Unit Cost (G + H + I + J) 38,236.46

PART B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(1)c6 Structural Concrete(Beams)- Class A, 28 days


Unit of Measurement : m3
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 0.00


b. Skilled Laborer 2 0.00 71.10 0.00
b. Unskilled Laborer 4 0.00 54.90 0.00

Sub - Total for A 0.00

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One Bagger Mixer 1 0.00 172.00 0.00


Minor Tools (10% of Labor Cost) 0.00

Sub - Total for B 0.00


C. Total (A + B) 0.00
D. Output per Hour = 0.270 m3
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gravel m3 0.00 516.39 0.00


b. Sand m3 0.00 516.39 0.00
c. Portland Cement bags 0.00 270.00 0.00

Sub - Total for F 0.00


G. Direct Unit Cost (C + F) 0.00
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 0.00
I. Contractor's Profit (CP) 10% of G 0.00
J. Value Added Tax (VAT) 5% of (G + H + I) 0.00
K. Total Unit Cost (G + H + I + J) 0.00

PART B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)a1 Reinforcing Steel of Reinforced Concrete Structures


Unit of Measurement : kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 17.03 98.09 1,670.31


b. Skilled Laborer 3 17.03 71.10 3,632.15
c. Unskilled Laborer 12 17.03 54.90 11,218.29

Sub - Total for A 16,520.75

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Bar Cutter 1 8.51 219.75 1,870.99


b. Bar Bender 1 8.51 351.50 2,992.74
Minor Tools (10% of Labor Cost) 1,652.08

Sub - Total for B 6,515.80


C. Total (A + B) 23,036.55
D. Output per Hour = 129.094 kg
E. Direct Unit Cost (C ÷ D) 10.48

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Deformed Reinforcing Steel kg 2,198.26 49.00 107,714.74


Grade
b. #16 60/GradeIron
Galvanized 40 Wire kg 36.000 70.00 2,520.00
c. Consumables (5% of Materials Cost) 5,511.74

Sub - Total for F 115,746.48


G. Direct Unit Cost (C + F) 138,783.03
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 20,817.45
I. Contractor's Profit (CP) 10% of G 13,878.30
J. Value Added Tax (VAT) 5% of (G + H + I) 8,673.94
K. Total Unit Cost (G + H + I + J) 182,152.73
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 903(1) Formworks and Falseworks


Unit of Measurement : 1 L.S
Output per hour : 3.24

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
Installation
a. Construction Foreman 1 12.44 98.09 1,220.68
b. Skilled Laborer 2 12.44 71.10 1,769.60
c. Unskilled Laborer 4 12.44 54.90 2,732.80
Stripping
a. Construction Foreman 1 5.10 98.09 500.48
b. Unskilled Laborer 6 5.10 54.90 1,680.67
Sub - Total for A 7,904.22

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 790.42

Sub - Total for B 790.42


C. Total (A + B) 8,694.65
D. Output per Hour = 3.240 kg
E. Direct Unit Cost (C ÷ D) 215.64

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ordinary Plywood 1/2 - 3 uses pcs 23.000 650.00 4,983.33


b. Good Lumber - 3 uses bd ft 608.792 45.00 27,395.63
c. Assorted Common Wire Nails kg 16.00 70.00 1,120.00
d. Consumables (5% of Materials Cost) 1,674.95

Sub - Total for F 35,173.91


G. Direct Unit Cost (C + F) 43,868.55
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 6,580.28
I. Contractor's Profit (CP) 10% of G 4,386.86
J. Value Added Tax (VAT) 5% of (G + H + I) 2,741.78
K. Total Unit Cost (G + H + I + J) 57,577.48

PART B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(29) Micro Piles in Drilled Holes, 0.2m Ø (Ordinary Soil Condition)
Unit of Measurement : m
Output per hour : 3.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
Installation
a. Construction Foreman 1 1.00 91.41 91.41
b. Skilled Laborer 5 1.00 66.06 330.30
c. Unskilled Laborer 6 1.00 50.86 305.16
Fabrication of Cage Bar
a. Construction Foreman 4 0.25 91.41 91.41
b. Unskilled Laborer 8 0.25 50.86 101.72
Sub - Total for A 920.00
Hourly Rental
Name and Capacity Quantity No. of Day/s Amount (PhP)
Rate
B. Equipment

a. Drill Rig, Mechanical Rotary 1 0.74 3,932.00 2,909.68


b. Truck Mounted Crane (25T) 1 0.95 1,631.00 1,549.45
c. Bar Bender 1 0.04 351.50 12.33
d. Bar Cutter 1 0.04 219.75 8.79
e. Bentonite Mixer 1 0.50 173.00 86.50
f. Bentonite Bin 1 0.50 280.00 140.00
g. Water Pump 1 0.50 123.38 61.69
h.Water Truck 1 0.50 2,450.00 1,225.00
i. Welding Machine 1 0.50 371.00 185.50
j. Tremie Pipe Set 1 0.24 320.00 76.80
k. SPT & Desanding Machine 1 0.24 559.00 134.16
l. Tower Light 1 0.50 543.50 271.75
m. Minor Tools (10% of Labor Cost) 92.00

Sub - Total for B 6,753.65


C. Total (A + B) 7,673.65
D. Output per Hour = 3.00 m.
E. Direct Unit Cost (C ÷ D) 2,557.88

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix m3 0.033 3,285.00 36.11


b. Reinforced Steel Bar* kg 12.626 34.22 432.06
c. Welding Rod (1kg/2000kg of RSB) kg 0.006 86.36 0.52
d. Miscellaneous (3% of Materials, Bentonite & etc.) 14.06

Sub - Total for F 482.75


G. Direct Unit Cost (E + F) 3,040.63
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 364.88
I. Contractor's Profit (CP) 8% of G 243.25
J. Value Added Tax (VAT) 5% of (G + H + I) 182.44
K. Total Unit Cost (G + H + I + J) 3,831.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1000(1) Soil Poisoning


Unit of Measurement : L
Output per hour : 5.40

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 5.556 98.09 544.94


b. Skilled Laborer 1 5.556 71.10 395.00
c. Unskilled Laborer 2 5.556 54.90 610.00

Sub - Total for A 1,549.94

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 154.99

Sub - Total for B 154.99


C. Total (A + B) 1,704.94
D. Output per Hour = 5.40 L
E. Direct Unit Cost (C ÷ D) 170.49

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Soil Poisoning L 10.00 350.00 3,500.00

Sub - Total for F 3,500.00


G. Direct Unit Cost (C + F) 5,204.94
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 780.74
I. Contractor's Profit (CP) 10% of G 520.49
J. Value Added Tax (VAT) 5% of (G + H + I) 325.31
K. Total Unit Cost (G + H + I + J) 6,831.48
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Descript : 1000(2) Wood Preservatives


Unit of Measure : L
Output per hour : 2.50

No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor

a. Construction Foreman 1 4.000 98.09 392.36


b. Skilled Laborer 1 4.000 71.10 284.40
c. Unskilled Laborer 2 4.000 54.90 439.20

Sub - Total for A 1,115.96


No of
Name and Capacity No. of Hour/s Hourly Rate Amount (PhP)
Unit/s
B. Equipment

Minor Tools (10% of Labor Cost) 111.60

Sub - Total for B 111.60


C. Total (A + B) 1,227.56
D. Output per Hour = 2.50 L
E. Direct Unit Cost (C ÷ D) 122.76

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Solignum L 10.00 330.00 3,300.00

Sub - Total for F 3,300.00


G. Direct Unit Cost (C + F) 4,527.56
H. Overhead, Contingencies & Miscellaneous (OCM 15% of G 679.13
I. Contractor's Profit (CP) 10% of G 452.76
J. Value Added Tax (VAT) 5% of (G + H + I) 282.97
K. Total Unit Cost (G + H + I + J) 5,942.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(5)a Catch Basin -Concrete


Unit of Measurement : Each
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Set = 0
a. Concrete m3 0.00 3,475.00 -
b.Reinforcement kgs 0.00 48.00 -
c.Masonry m2 0.00 101.38 -
d. Finishing Works m2 0.00 84.25 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : LS
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 2 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) -
Sub - Total for B -
C. Total (A + B) -
D. Output = 1
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Pipe 110mm x 3000mm PVC pc - 715.00 -


Pipe 63mm x 3000mm PVC pc - 350.00 -
P-trap 63mm PVC pc - 155.00 -
Tee 110mm x 63mm x 110mm PVC pc - 90.00 -
Elbow 110mm 1/4 bend pc - 90.00 -
Elbow 63mm 1/4 bend pc - 80.00 -
Wye 110mm x 110mm x 110mm PVC pc - 90.00 -
Wye 110mm x 63mm x 110mm PVC pc - 90.00 -
Tee tapped 40mm PVC pc - 90.00 -
Wye 63mm x 63mm x 63mm pc - 80.00 -
Tee 63mm x 63mm x 63mm PVC pc - 80.00 -
Elbow 110mm 1/8 bend PVC pc - 90.00 -
Cleanout 4" brass pc - 110.00 -
PVC cement, solvent 400cc pc - 145.00 -

p. Consumables (5% of Materials) -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : LS
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 2 0.00 71.10 -
c. Unskilled Laborer 4 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output = 1
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

-
a. PVC Drain Pipe, 100mm dia.x3m pcs 0.00 750.00 -
b. Roof Drain (Dome-type strainer) pcs 0.00 150.00 -
c.uPVC Sanitary Pipe, 75mm dia.x 3m, S-1000 lengths 0.00 390.00 -
d.Elbow, 75mm dia.-45 deg bend pcs 0.00 38.00 -
e. PVC solvent, 400cc cans 0.00 190.00 -
f. Consumables 5% -
-
Sub - Total for F -
G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(11) Septic Vault-Concrete


Unit of Measurement : LS
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 40.00 98.09 -


b. Skilled Laborer 2 40.00 71.10 -
c. Unskilled Laborer 4 40.00 54.90 -

REMOVAL OF (SEPTCI VAULT WASTE)


UNSKILLED LABORER 2 16 50.86 -
SIPHONING 1 10 1,500.00 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Formowrks Plywood 1/2 pcs 10.00 650.00 -


Coarse aggregates cu.m 7.00 911.33 -
Fine aggregates cu.m 7.00 886.67 -
Portland Cement bags 45.00 270.00 -
Rebars 12mm x 6m grade 33 kg 645.25 49.00 -
Gi tie wire kg 6.00 70.00 -
tee 110mmx110mmx 110mm PVC pcs 3.00 105.00 -
elbow 110mm 1/4 bend pcs 3.00 95.00 -
Clean out 4" PVC pcs 6.00 100.00 -
PVC cement solvent 400cc can 2.00 135.00 -
PVC pipe 110mm x 3m pcs 2.00 530.00 -
Fiber-Fibrin 23 (75g/pack) pack 45.00 250.00 -
For distribution box -
-
PVC Pipe 110mm x 3m pcs 11.00 530.00 -
Coarse Aggregates cu.m 5.00 911.33 -
Fine aggregates cu.m 5.00 886.67 -
-

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(4) Plumbing Fixtures


Unit of Measurement : LS
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output = 1
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Water closet w/ Tank, elongated w/ Comp. Accessories set 0.00 8,500.00 -


and Lavatory w/ comp. Accessories, soap & tissue
Holder
Urinal including fittings and acc set 0.00 4,800.00 -
Nipple 1/2" x 6 pc 0.00 150.00 -
Floor strainer SS/floor drain pc 0.00 280.00 -
Coupling 1/2" pc 0.00 75.00 -
Escotcheon 1/2" pc 0.00 10.00 -
Towel bar pc 0.00 500.00 -
Bronze faucet 1/2" x 4" pc 0.00 190.00 -
gate valve 1/2" pc 0.00 450.00 -
gate valve 3/4" pc 0.00 450.00 -
Hand rail PWD set 0.00 4,500.00 -
.
Consumables 5% -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(27) Plumbing Works


Unit of Measurement : LS
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 2 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output = 1
E. Direct Unit Cost (C ÷ D) -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Moldex blue pipe 1/2" x 10' pcs - 110.00 -


Moldex blue pipe 3/4" x 10' pcs - 125.00 -
moldex Elbow 1/2" pcs - 25.00 -
Moldex Tee 1/2 pcs - 25.00 -
PVC cement can - 145.00 -
PVC tee 3/4"x 1/2" pcs - 30.00 -
Tape Teflon roll - 16.00 -

k. Consumables (5% of Materials) -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(1)a1 Ceiling- 4.5mm Fiber Cement Board on Metal Frame
Unit of Measurement : m2
Output per hour : 1.243

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 240.31 98.09 23,571.59


b. Skilled Laborer 1 240.31 71.10 17,085.74
c. Unskilled Laborer 2 240.31 54.90 26,385.57

Sub - Total for A 67,042.89

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 6,704.29

Sub - Total for B 6,704.29


C. Total (A + B) 73,747.18
D. Output per Hour = 1.243 m2
E. Direct Unit Cost (C ÷ D) 246.893805309735

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 4.5mm Fiber Cement Board pc 109.026 450.00 49,061.48


b. Metal Furring pc 337.830 130.00 43,917.86
and specifications
c. Carrying ) 3m length
Channels pc 106.636 150.00 15,995.39
d. Hanger Bars/Rod pc 299 80.00 23,896.00
e. Channel clip pc 1792 6.00 10,753.20
f. Wall Angle pc 71.091 100.00 7,109.06
g. Rivets pc 4182 2.00 8,363.60
h. 1" Metal Screw pc 1195 1.50 1,792.20
Area = 298.7 sq.m.

Sub - Total for F 160,888.78


G. Direct Unit Cost (C + F) 234,635.96
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 35,195.39
I. Contractor's Profit (CP) 10% of G 23,463.60
J. Value Added Tax (VAT) 5% of (G + H + I) 14,664.75
K. Total Unit Cost (G + H + I + J) 307,959.70
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works-Blackboard


Unit of Measurement : LS
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 0.00 98.09 -
b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) -

Sub - Total for B -


C. Sub - Total for C (B ÷ Area) -
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C #DIV/0!
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 0.000 5,000.00 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1004(2) Finishing Hardware


Unit of Measurement : LS
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 set
E. Direct Unit Cost (C ÷ D) -
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Lockset set 0.00 1,200.00 -

a. Hinges
set 0.00 300.00 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005(1) Casement Steel Window


Unit of Measurement : m2
Output per hour : 0.18

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 40.00 98.09 3,923.60


b. Skilled Laborer 1 40.00 71.10 2,844.00
c. Unskilled Laborer 1 40.00 54.90 2,196.00

Sub - Total for A 8,963.60

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 10.00 391.00 3,910.00


Minor Tools (10% of Labor Cost) 896.36

Sub - Total for B 4,806.36


C. Total (A + B) 13,769.96
D. Output per Hour = 1.6 m2
E. Direct Unit Cost (C ÷ D) 1912.49444444444

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Casement Window m2 7.20 2,300.00 16,560.00

Sub - Total for F 16,560.00


G. Direct Unit Cost (E + F) 30,329.96
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 4,549.49
I. Contractor's Profit (CP) 10% of G 3,033.00
J. Value Added Tax (VAT) 5% of (G + H + I) 1,895.62
K. Total Unit Cost (G + H + I + J) 39,808.07

PART C - Finishing and other Civil Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005(5) Window Grills


Unit of Measurement : m2
Output per hour : 1.6

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.00 391.00 -


Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 1.6 m2
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. (12mmx12mm square) kg 0.00 49.00 -


25X4MM FLAT BAR kg 0.00 49.00 -
Metal paint gal 0.00 600.00 -
c. Consumables (3% of Materials Cost) -
AREA = 0 sq.m.

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -

PART C - Finishing and other Civil Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1009(1)a Jalousie Window (Glass)


Unit of Measurement : m2
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 0.27 m2
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Jalousie Window (Glass) m2 0.00 650.00 -


b. Consumables (3% of Materials Cost) -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1007(1)b Aluminum Framed Glass Door


Unit of Measurement : m2
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 8.00 98.09 784.72


b. Skilled Laborer 1 8.00 71.10 568.80
c. Unskilled Laborer 1 8.00 54.90 439.20

Sub - Total for A 1,792.72

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 179.27

Sub - Total for B 179.27


C. Total (A + B) 1,971.99
D. Output = 1 set
E. Direct Unit Cost (C ÷ D) 1971.992

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. aluminum Framed glass door Sq.m 2.94 3,400.00 9,996.00


-

Sub - Total for F 9,996.00


G. Direct Unit Cost (C + F) 11,967.99
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,795.20
I. Contractor's Profit (CP) 10% of G 1,196.80
J. Value Added Tax (VAT) 5% of (G + H + I) 748.00
K. Total Unit Cost (G + H + I + J) 15,707.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
Unit of Measurement : set
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.00 98.09


b. Skilled Laborer 1 4.00 71.10
c. Unskilled Laborer 1 4.00 54.90

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output = 1 set
E. Direct Unit Cost (C ÷ D) 0

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Door Jambs set 1.00 1,800.00


d. panel door set 1.00 5,500.00

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)a Doors- Flush


Unit of Measurement : m2
Output : 0.32

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 0.32 m2
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Hollow Core Flush Door m2 0.00 1,350.00 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)b Doors- Wood Panel


Unit of Measurement : m2
Output : 0.36

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 0.36 m2
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wooden Panel Door m2 0.00 2,400.00 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll)-gauge 26


Unit of Measurement : m
Output per hour : 10.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.71 98.09 266.02


b. Skilled Laborer 1 2.71 71.10 192.82
c. Unskilled Laborer 1 2.71 54.90 148.89

Sub - Total for A 607.73

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 60.77

Sub - Total for B 60.77


C. Total (A + B) 668.51
D. Output per Hour = 10.00 m
E. Direct Unit Cost (C ÷ D) 24.65

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ridge Roll m 28.48 200.00 5,695.20


b. Blind Rivets pc 515.28 2.00 1,030.56

Length = 27.12 m.

Sub - Total for F 6,725.76


G. Direct Unit Cost (C + F) 7,394.27
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,109.14
I. Contractor's Profit (CP) 10% of G 739.43
J. Value Added Tax (VAT) 5% of (G + H + I) 462.14
K. Total Unit Cost (G + H + I + J) 9,704.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)a2 Fabricated Metal Roofing Accessory (Flashing)-Gauge 26


Unit of Measurement : m
Output per hour : 10.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.21 98.09 216.98


b. Skilled Laborer 1 2.21 71.10 157.27
c. Unskilled Laborer 1 2.21 54.90 121.44

Sub - Total for A 495.69

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 49.57

Sub - Total for B 49.57


C. Total (A + B) 545.26
D. Output per Hour = 10.00 m
E. Direct Unit Cost (C ÷ D) 24.65

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Flashing m 23.23 200.00 4,645.20


b. Blind Rivets pc 420.28 2.00 840.56

Length = 22.12 m.

Sub - Total for F 5,485.76


G. Direct Unit Cost (C + F) 6,031.02
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 904.65
I. Contractor's Profit (CP) 10% of G 603.10
J. Value Added Tax (VAT) 5% of (G + H + I) 376.94
K. Total Unit Cost (G + H + I + J) 7,915.71
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)c Fabricated Metal Roofing Accessory (Gutter)


Unit of Measurement : m
Output per hour : 11.80

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 5.29 98.09 518.80


b. Skilled Laborer 1 5.29 71.10 376.05
c. Unskilled Laborer 1 5.29 54.90 290.37

Sub - Total for A 1,185.21

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 118.52

Sub - Total for B 118.52


C. Total (A + B) 1,303.73
D. Output per Hour = 11.80 m
E. Direct Unit Cost (C ÷ D) 20.8897457627119

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gutter (0.6 mm) m 62.41 154.00 9,611.14


b. 12" x 1" Plain GI Strap pc 187.23 50.00 9,361.50
c. Blind Rivets pc 998.56 2.00 1,997.12
d. Consumables (3% of Materials Cost) 629.09
Length = 62.41 m.

Sub - Total for F 21,598.85


G. Direct Unit Cost (C + F) 22,902.58
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 3,435.39
I. Contractor's Profit (CP) 10% of G 2,290.26
J. Value Added Tax (VAT) 5% of (G + H + I) 1,431.41
K. Total Unit Cost (G + H + I + J) 30,059.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1014(1)b1 Prepainted Metal Sheets ( Corrugated, Long Span,0.5mm thk)
Unit of Measurement : m2
Output per hour : 2.076

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 153.44 98.09 15,050.86


b. Skilled Laborer 1 153.44 71.10 10,909.53
c. Unskilled Laborer 2 153.44 54.90 16,847.64

Sub - Total for A 42,808.03

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 4,280.80

Sub - Total for B 4,280.80


C. Total (A + B) 47,088.84
D. Output per Hour = 2.076 m2
E. Direct Unit Cost (C ÷ D) 147.83

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Prepainted Metal Sheets ( Corrugated, Long


m2 334.47 750.00 250,850.25
Span,0.5mm thk)
b. Self drilling tekscrew pc 4,778 2.75 13,139.78

Area = 318.54 sq.m.

Sub - Total for F 263,990.03


G. Direct Unit Cost (C + F) 311,078.86
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 46,661.83
I. Contractor's Profit (CP) 10% of G 31,107.89
J. Value Added Tax (VAT) 5% of (G + H + I) 19,442.43
K. Total Unit Cost (G + H + I + J) 408,291.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(1) Glazed Tiles and Trims


Unit of Measurement : m2
Output per hour : 1.365

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 5 0.00 71.10 -
c. Unskilled Laborer 5 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 1.365 m2
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Glazed Tiles(300x300mm) pcs 0.000 40.00 -


b. Cement bags 0.000 270.00 -
c. Sand m3 0.000 886.67 -
d. Tile Grout bags 0.000 70.00 -
e. Tile Adhesive (25 kg) bags 0 250.00 -
f. Consumables (3% of Materials Cost) -
Area = 0 sq.m.
Sub - Total for F -
G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(2) Unglazed Tiles


Unit of Measurement : m2
Output per hour : 1.95

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 28.69 98.09 2,814.43


b. Skilled Laborer 5 28.69 71.10 10,200.12
c. Unskilled Laborer 5 28.69 54.90 7,876.04

Sub - Total for A 20,890.58

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 2,089.06

Sub - Total for B 2,089.06


C. Total (A + B) 22,979.64
D. Output per Hour = 1.95 m2
E. Direct Unit Cost (C ÷ D) 410.717435897436

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Unglazed Tiles (300x300mm) pcs 1,399.00 40.00 55,960.00


b. Cement bags 19.00 270.00 5,130.00
c. Sand m3 1.47 850.00 1,248.38
d. Tile Grout bags 3.00 70.00 210.00
e. Tile Adhesive (25 kg) bags 7.00 250.00 1,750.00
f. Consumable (3% of Materials Cost) 1,928.95
Area = 55.95 sq.m.
Sub - Total for F 66,227.34
G. Direct Unit Cost (C + F) 89,206.98
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 13,381.05
I. Contractor's Profit (CP) 10% of G 8,920.70
J. Value Added Tax (VAT) 5% of (G + H + I) 5,575.44
K. Total Unit Cost (G + H + I + J) 117,084.16
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1021(1)c Plain Cement Floor Finish with Floor Hardener
Unit of Measurement : m2
Output per hour : 5.95

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 7.06 98.09 692.40


b. Skilled Laborer 1 7.06 71.10 501.88
c. Unskilled Laborer 3 7.06 54.90 1,162.59

Sub - Total for A 2,356.87

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 235.69

Sub - Total for B 235.69


C. Total (A + B) 2,592.56
D. Output per Hour = 5.95 m2
E. Direct Unit Cost (C ÷ D) 61.7275630252101

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bag 13.000 270.00 3,510.00


b. Sand m3 3.000 886.67 2,660.01
c. Floor Hardener bag 3.000 250.00 750.00
Area = 42 sq.m.

Sub - Total for F 6,920.01


G. Direct Unit Cost (C + F) 9,512.57
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,426.89
I. Contractor's Profit (CP) 10% of G 951.26
J. Value Added Tax (VAT) 5% of (G + H + I) 594.54
K. Total Unit Cost (G + H + I + J) 12,485.25
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1027(1) Cement Plaster Finish


Unit of Measurement : m2
Output per hour : 7.125

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 97.65 98.09 9,578.27


b. Skilled Laborer 4 97.65 71.10 27,771.02
c. Unskilled Laborer 4 97.65 54.90 21,443.44

Sub - Total for A 58,792.72

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 5,879.27

Sub - Total for B 5,879.27


C. Total (A + B) 64,672.00
D. Output per Hour = 7.125 m2
E. Direct Unit Cost (C ÷ D) 92.9542456140351

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bag 230.000 270.00 62,100.00


b. Sand cu.m 19.000 886.67 16,846.73

AREA = 695.740104 SQ.M.

Sub - Total for F 78,946.73


G. Direct Unit Cost (C + F) 143,618.73
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 21,542.81
I. Contractor's Profit (CP) 10% of G 14,361.87
J. Value Added Tax (VAT) 5% of (G + H + I) 8,976.17
K. Total Unit Cost (G + H + I + J) 188,499.58
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)a Painting Works (Masonry)


Unit of Measurement : m2
Output per hour : 2.10

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 311.33 98.09 30,538.69


b. Skilled Laborer 3 311.33 71.10 66,407.40
c. Unskilled Laborer 2 311.33 54.90 34,184.40

Sub - Total for A 131,130.49

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 13,113.05

Sub - Total for B 13,113.05


C. Total (A + B) 144,243.54
D. Output per Hour = 2.10 m2
E. Direct Unit Cost (C ÷ D) 220.62

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Area = 653.80 sq.m.
a. Concrete Neutralizer gal 53.00 412.32 21,852.96
b. Concrete Sealer/Primer gal 27.00 644.00 17,388.00
c. Patching Compound gal 33.00 550.00 18,150.00
d. Semi Gloss Latex (two coats) gal 53.00 620.00 32,860.00
e. Consumables (5% of Materials Cost) 4,512.55

Sub - Total for F 94,763.51


G. Direct Unit Cost (C + F) 239,007.04
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 35,851.06
I. Contractor's Profit (CP) 10% of G 23,900.70
J. Value Added Tax (VAT) 5% of (G + H + I) 14,937.94
K. Total Unit Cost (G + H + I + J) 313,696.74
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)b Painting Works (Wood)


Unit of Measurement : m2
Output per hour : 1.89

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 158.04 98.09 15,502.37


b. Skilled Laborer 2 158.04 71.10 22,473.62
c. Unskilled Laborer 1 158.04 54.90 8,676.52

Sub - Total for A 46,652.51

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 4,665.25

Sub - Total for B 4,665.25


C. Total (A + B) 51,317.77
D. Output per Hour = 1.89 m2
E. Direct Unit Cost (C ÷ D) 171.803703703704

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Glazzing Putty gal 15.00 550.00 8,250.00


b. Flat Wall Enamel gal 12.00 600.00 7,200.00
c. Enamel Quick Dry gal 12.00 600.00 7,200.00
d. Paint Thinner gal 3.00 260.00 780.00
f. Consumables (5% of Materials Cost) 1,171.50
Area = 298.7 sq.m.

Sub - Total for F 24,601.50


G. Direct Unit Cost (C + F) 75,919.27
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 11,387.89
I. Contractor's Profit (CP) 10% of G 7,591.93
J. Value Added Tax (VAT) 5% of (G + H + I) 4,744.95
K. Total Unit Cost (G + H + I + J) 99,644.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)c Painting Works (Metal)


Unit of Measurement : m2
Output per hour : 2.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 159.27 98.09 15,622.79


b. Skilled Laborer 2 159.27 71.10 22,648.19
c. Unskilled Laborer 1 159.27 54.90 8,743.92

Sub - Total for A 47,014.91

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 4,701.49

Sub - Total for B 4,701.49


C. Total (A + B) 51,716.40
D. Output per Hour = 2.00 m2
E. Direct Unit Cost (C ÷ D) 162.35

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Red Oxide Primer gal 13.00 620.00 8,060.00


b. Enamel Paint gal 13.00 650.00 8,450.00
c. Paint thinner L 13.00 240.00 3,120.00
d. epoxy primer gal 13.00 750.00 9,750.00
Area = 318.54 sq.m.

Sub - Total for F 29,380.00


G. Direct Unit Cost (C + F) 81,096.40
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 12,164.46
I. Contractor's Profit (CP) 10% of G 8,109.64
J. Value Added Tax (VAT) 5% of (G + H + I) 5,068.53
K. Total Unit Cost (G + H + I + J) 106,439.03
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1038(1) Reflective Insulation


Unit of Measurement : m2
Output per hour : 5.56

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 2 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 5.56 m2
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reflective Insulation, 10 mm thk m2 0.000 135.00 -


b. Consumbles (5% of Materials Cost) -
Area = 0 sq.m.

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a1 CHB Non-Load Bearing -100mm (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.825

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 2 0.00 71.10 -
c. Unskilled Laborer 3 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One-bagger mixer 1 0.00 172.00 -


Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 3.825 m2
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 100 mm thk CHB (Non-Load Bearing) pc 0.00 17.00 -


b. Cement bag 0.00 270.00 -
c. Sand cu.m 0.00 886.67 -
d. Reinforcing Steel kg 0.00 49.00 -
e. #16 Tie wire kg 0.00 90.00 -
AREA = 0 Sq.m.

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a2 CHB Non-Load Bearing -150mm (including Reinforcing Steel)
Unit of Measurement : m2
Output per hour : 3.18

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 106.35 98.09 10,432.30


b. Skilled Laborer 3 106.35 71.10 22,685.39
c. Unskilled Laborer 4 106.35 54.90 23,355.43

Sub - Total for A 56,473.12

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One-bagger mixer 1 106.35 172.00 18,292.96


Minor Tools (10% of Labor Cost) 5,647.31

Sub - Total for B 23,940.27


C. Total (A + B) 80,413.39
D. Output per Hour = 3.180 m2
E. Direct Unit Cost (C ÷ D) 237.763836477987

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 150 mm thk CHB (Non-Load Bearing) pc 4,397.00 20.00 87,940.00


b. Cement bag 508.00 270.00 137,160.00
c. Sand cu.m 15.00 850.00 12,750.00
d. Reinforcing Steel kg 1,096.00 49.00 53,704.00
e. #16 Tie wire kg 304.00 90.00 27,360.00
AREA = 338.206995 sq.m.

Sub - Total for F 318,914.00


G. Direct Unit Cost (C + F) 399,327.39
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 59,899.11
I. Contractor's Profit (CP) 10% of G 39,932.74
J. Value Added Tax (VAT) 5% of (G + H + I) 24,957.96
K. Total Unit Cost (G + H + I + J) 524,117.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1004(2)g Hinges


Unit of Measurement : set
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 set
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Hinges
set 0.00 350.00 -

Sub - Total for F -


G. Direct Unit Cost (E + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 36.00 91.41 3,290.76
b. Skilled Laborer 1 48.00 66.06 3,170.88
c. Unskilled Laborer 1 48.00 50.86 2,441.28

Sub - Total for A 8,902.92

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 890.29

Sub - Total for B 890.29


C. Sub - Total for C (B ÷ Area) 9,793.21
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 9,793.21

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 12.000 3,100.00 37,200.00

Sub - Total for F 37,200.00


G. Direct Unit Cost (E + F) 46,993.21
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 5,639.19
I. Contractor's Profit (CP) 8% of G 3,759.46
J. Value Added Tax (VAT) 5% of (G + H + I) 2,819.59
K. Total Unit Cost (G + H + I + J) 59,211.45
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 30.00 91.41 2,742.30
b. Skilled Laborer 1 40.00 66.06 2,642.40
c. Unskilled Laborer 1 40.00 50.86 2,034.40

Sub - Total for A 7,419.10

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 741.91

Sub - Total for B 741.91


C. Sub - Total for C (B ÷ Area) 8,161.01
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 8,161.01

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 10.000 3,100.00 31,000.00

Sub - Total for F 31,000.00


G. Direct Unit Cost (E + F) 39,161.01
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,699.32
I. Contractor's Profit (CP) 8% of G 3,132.88
J. Value Added Tax (VAT) 5% of (G + H + I) 2,349.66
K. Total Unit Cost (G + H + I + J) 49,342.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 24.00 91.41 2,193.84
b. Skilled Laborer 1 32.00 66.06 2,113.92
c. Unskilled Laborer 1 32.00 50.86 1,627.52

Sub - Total for A 5,935.28

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 593.53

Sub - Total for B 593.53


C. Sub - Total for C (B ÷ Area) 6,528.81
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 6,528.81

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 8.000 3,100.00 24,800.00

Sub - Total for F 24,800.00


G. Direct Unit Cost (E + F) 31,328.81
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,759.46
I. Contractor's Profit (CP) 8% of G 2,506.30
J. Value Added Tax (VAT) 5% of (G + H + I) 1,879.73
K. Total Unit Cost (G + H + I + J) 39,474.30
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 18.00 91.41 1,645.38
b. Skilled Laborer 1 24.00 66.06 1,585.44
c. Unskilled Laborer 1 24.00 50.86 1,220.64

Sub - Total for A 4,451.46

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 445.15

Sub - Total for B 445.15


C. Sub - Total for C (B ÷ Area) 4,896.61
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 4,896.61

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 6.000 3,100.00 18,600.00

Sub - Total for F 18,600.00


G. Direct Unit Cost (E + F) 23,496.61
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,819.59
I. Contractor's Profit (CP) 8% of G 1,879.73
J. Value Added Tax (VAT) 5% of (G + H + I) 1,409.80
K. Total Unit Cost (G + H + I + J) 29,605.72
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(9) Carpentry and Joinery Works


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 6.00 91.41 548.46
b. Skilled Laborer 1 8.00 66.06 528.48
c. Unskilled Laborer 1 8.00 50.86 406.88

Sub - Total for A 1,483.82

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) 148.38

Sub - Total for B 148.38


C. Sub - Total for C (B ÷ Area) 1,632.20
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C 1,632.20

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Blackboard set 2.000 3,100.00 6,200.00

Sub - Total for F 6,200.00


G. Direct Unit Cost (E + F) 7,832.20
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 939.86
I. Contractor's Profit (CP) 8% of G 626.58
J. Value Added Tax (VAT) 5% of (G + H + I) 469.93
K. Total Unit Cost (G + H + I + J) 9,868.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1044(2)c Folding Partition (Plastic)


Unit of Measurement : sq.m.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 0.00 98.09 -
b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost) -

Sub - Total for B -


C. Sub - Total for C (B ÷ Area) -
D. Output = 1.00 l.s.
E. Direct Unit Cost (A ÷ D) + C -

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Accordion Partition (PVC) set 0.000 5,000.00 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1051(5) Metal Railing


Unit of Measurement : m
Output per hour : 6.255

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 2 0.00 54.90 -

Sub - Total for A -

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.00 391.00 -


b. Cutting Outfit 1 0.00 45.45 -
Minor Tools (10% of labor cost) -

LENGTH = 12 l.m.

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 6.255 m
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 50 mm Ø G.I. Pipe pc 0.000 1,200.00 -


c. Welding Rod kg 0.000 120.00 -
d. Consumables (5% of material cost) -

LENGTH = 0 l.m.

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)a Structural Steel- Trusses


Unit of Measurement : kg
Output per hour : 85.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Fabrication
a. Construction Foreman 1 0.00 98.09 -
b. Skilled Laborer 2 0.00 71.10 -
c. Unskilled Laborer 2 0.00 54.90 -

Erection
a. Skilled Laborer 3 0.00 71.10 -
b. Unskilled Laborer 3 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.00 371.00 -


b. Cutting Outfit 1 0.00 70.00 -
Minor Tools (10 % of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 85.00 kg
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Weight = 0 kg
a. Structural Steel Truss kg 0.00 70.00 -
b. Acetylene kg 0.000 55.00 -
c. Oxygen kg 0.000 50.00 -
d. Welding Rod kg 0.000 120.00 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)b Structural Steel - Purlins


Unit of Measurement : kg
Output per hour : 90.45

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 2 0.00 71.10 -
c. Unskilled Laborer 4 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 2 0.00 371.00 -


Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 90.45 kg
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Structural Steel Purlins kg 0.00 70.00 -


b. Welding Rod kg 0.00 120.00 -

Weight = - kg

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)a Metal Structure Accessories (Bolts)


Unit of Measurement : Each
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 8.00 98.09 -


b. Skilled Laborer 1 8.00 71.10 -
c. Unskilled Laborer 1 8.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. High Tensile Anchor Bolts (16mm Ø x 300)- pc 0.00 250.00 -


STAINLESS 0.00
c. High Tensile Machine Bolts (12mmØ x 50)- pc 0.000 135.00 -
STAINLESS

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)c Metal Structure Accessories (Turnbuckle)


Unit of Measurement : Each
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Standard Turnbuckle 16mm pc 0.00 265.00 -

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(4) Metal Structure Accessories (Crossbracing)


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cross Bracing kg 0.00 70.00 -

Weight = - kg

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(6) Metal Structure Accessories (Steel Plates)


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Plates kg 0.00 70.00 -

Weight = - kg.

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(7)b Metal Structure Accessories (Sagrods)


Unit of Measurement : kg
Output : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.00 98.09 -


b. Skilled Laborer 1 0.00 71.10 -
c. Unskilled Laborer 1 0.00 54.90 -

Sub - Total for A -

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) -

Sub - Total for B -


C. Total (A + B) -
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D) #DIV/0!

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Sagrod with nuts and washer kg 0.00 70.00 -


Weight = 0.00 kg

Sub - Total for F -


G. Direct Unit Cost (C + F) -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G -
I. Contractor's Profit (CP) 10% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K. Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(10) Conduit, Boxes, and Fittings(Conduit Works/Conduit Rough -in)
Unit of Measurement : LS
Output per hour : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 24.00 98.09 2,354.16


b. Skilled Laborer 1 24.00 71.10 1,706.40
c. Unskilled Laborer 1 24.00 54.90 1,317.60

Sub - Total for A 5,378.16

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 537.82

Sub - Total for B 537.82


C. Total (A + B) 5,915.98
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 5,915.98

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 20.00 175.00 3,500.00


c. 20mmØ PVC adapter pc 13.00 8.00 104.00
d. 25mmØ locknut & bushing pr 50.00 14.00 700.00
e. 20mmØ locknut & bushing pr 20.00 8.00 160.00
f. utility box, deep type pc 10.00 30.00 300.00
g. junction box, deep type pc 10.00 31.00 310.00
h. 25mmØ entrance cap pc 1.00 100.00 100.00

Sub - Total for F 5,174.00


G. Direct Unit Cost (C + F) 11,089.98
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,663.50
I. Contractor's Profit (CP) 10% of G 1,109.00
J. Value Added Tax (VAT) 5% of (G + H + I) 693.12
K. Total Unit Cost (G + H + I + J) 14,555.59

PART D - Electrical Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101(33) Wires and Wiring Devices


Unit of Measurement : LS
Output per hour : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 32.00 98.09 3,138.88


b. Skilled Laborer 1 32.00 71.10 2,275.20
c. Unskilled Laborer 1 32.00 54.90 1,756.80

Sub - Total for A 7,170.88

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 717.09

Sub - Total for B 717.09


C. Total (A + B) 7,887.97
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 7,887.97

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3.5mm2 TWN wire,stranded m 600.00 23.00 13,800.00


b. 5.5mm2 THWN wire,stranded m 250.00 24.00 6,000.00
c. 5.5mm2 TW wire,stranded m 150.00 24.00 3,600.00
d. one gang switch set 2.00 92.00 184.00
e. two gang switch set 4.00 126.00 504.00
f. duplex C.O. grounding type, 15A, 250V set 5.00 420.00 2,100.00
g. KWHR meter round with base set 1.00 2,200.00 2,200.00
h. Consumable Materials (3% of Material Cost) lot 1.00 851.64 851.64

Sub - Total for F 29,239.64


G. Direct Unit Cost (C + F) 37,127.61
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 5,569.14
I. Contractor's Profit (CP) 10% of G 3,712.76
J. Value Added Tax (VAT) 5% of (G + H + I) 2,320.48
K. Total Unit Cost (G + H + I + J) 48,729.99

PART D - Electrical Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(1) Panelboard w/ Main & Branch Breakers


Unit of Measurement : LS
Output per hour : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 36.00 71.10 2,559.60

Sub - Total for A 2,559.60


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 255.96

Sub - Total for B 255.96


C. Total (A + B) 2,815.56
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 2,815.56

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. DP set 1.00 8,500.00 8,500.00


main: 40AT,2P,230 volts
br. 1- 15at, 2p
2- 20at, 2p
1- 30at, 2p

Sub - Total for F 8,500.00


G. Direct Unit Cost (C + F) 11,315.56
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,697.33
I. Contractor's Profit (CP) 10% of G 1,131.56
J. Value Added Tax (VAT) 5% of (G + H + I) 707.22
K. Total Unit Cost (G + H + I + J) 14,851.67

PART D - Electrical Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures


Unit of Measurement : LS
Output per hour : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 8.00 98.09 784.72


b. Skilled Laborer 1 8.00 71.10 568.80
c. Unskilled Laborer 1 8.00 54.90 439.20

Sub - Total for A 1,792.72

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 179.27

Sub - Total for B 179.27


C. Total (A + B) 1,971.99
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 1,971.99

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

2x36 flourecent set 4.00 1,500.00 6,000.00

Sub - Total for F 6,000.00


G. Direct Unit Cost (C + F) 7,971.99
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% of G 1,195.80
I. Contractor's Profit (CP) 10% of G 797.20
J. Value Added Tax (VAT) 5% of (G + H + I) 498.25
K. Total Unit Cost (G + H + I + J) 10,463.24

PART D - Electrical Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 290.00 91.41 26,508.90


b. Skilled Laborer 1 290.00 66.06 19,157.40
c. Unskilled Laborer 1 290.00 50.86 14,749.40

Sub - Total for A 60,415.70

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 6,041.57

Sub - Total for B 6,041.57


C. Total (A + B) 66,457.27
D. Output per Hour = 1 l.s.
E. Direct Unit Cost (C ÷ D) 66,457.27

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 51.84 4,478.57 232,169.07


b. Hallow Core Flush Door m2 18.27 890.71 16,273.27
c. Door Frames set 43.00 2,000.00 86,000.00
d. Bar Door m2 5.76 890.71 5,130.49
d. Consumbale (5% of Material Cost of Door 4,300.00
Frames)

Sub - Total for F 343,872.83


G. Direct Unit Cost (E + F) 410,330.10
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 49,239.61
I. Contractor's Profit (CP) 8% of G 32,826.41
J. Value Added Tax (VAT) 5% of (G + H + I) 24,619.81
K. Total Unit Cost (G + H + I + J) 517,015.93
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 260.00 91.41 23,766.60


b. Skilled Laborer 1 260.00 66.06 17,175.60
c. Unskilled Laborer 1 260.00 50.86 13,223.60

Sub - Total for A 54,165.80

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 5,416.58

Sub - Total for B 5,416.58


C. Total (A + B) 59,582.38
D. Output per Hour = 1 l.s.
E. Direct Unit Cost (C ÷ D) 59,582.38

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 43.20 4,478.57 193,474.22


b. Hallow Core Flush Door m2 18.27 890.71 16,273.27
c. Door Frames set 39.00 2,000.00 78,000.00
d. Bar door m2 5.76 890.71 5,130.49
e. Consumbale (5% of Material Cost of Door 3,900.00
Frames)

Sub - Total for F 296,777.99


G. Direct Unit Cost (E + F) 356,360.37
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 42,763.24
I. Contractor's Profit (CP) 8% of G 28,508.83
J. Value Added Tax (VAT) 5% of (G + H + I) 21,381.62
K. Total Unit Cost (G + H + I + J) 449,014.06
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 230.00 91.41 21,024.30


b. Skilled Laborer 1 230.00 66.06 15,193.80
c. Unskilled Laborer 1 230.00 50.86 11,697.80

Sub - Total for A 47,915.90

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 4,791.59

Sub - Total for B 4,791.59


C. Total (A + B) 52,707.49
D. Output per Hour = 1 l.s.
E. Direct Unit Cost (C ÷ D) 52,707.49

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 34.56 4,478.57 154,779.38


b. Hallow Core Flush Door m2 18.27 890.71 16,273.27
c. Door Frames set 35.00 2,000.00 70,000.00
d. Bar Door m2 5.76 890.71 5,130.49
e. Consumbale (5% of Material Cost of Door 3,500.00
Frames)

Sub - Total for F 249,683.14


G. Direct Unit Cost (E + F) 302,390.63
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 36,286.88
I. Contractor's Profit (CP) 8% of G 24,191.25
J. Value Added Tax (VAT) 5% of (G + H + I) 18,143.44
K. Total Unit Cost (G + H + I + J) 381,012.19
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 150.00 91.41 13,711.50


b. Skilled Laborer 1 150.00 66.06 9,909.00
c. Unskilled Laborer 1 150.00 50.86 7,629.00

Sub - Total for A 31,249.50

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 3,124.95

Sub - Total for B 3,124.95


C. Total (A + B) 34,374.45
D. Output per Hour = 1 l.s.
E. Direct Unit Cost (C ÷ D) 34,374.45

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 25.92 4,478.57 116,084.53


b. Hallow Core Flush Door m2 11.76 890.71 10,474.75
c. Door Frames set 24.00 2,000.00 48,000.00
d. Bar Door m2 3.60 890.71 3,206.56
d. Consumbale (5% of Material Cost of Door 2,400.00
Frames)

Sub - Total for F 180,165.84


G. Direct Unit Cost (E + F) 214,540.29
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 25,744.83
I. Contractor's Profit (CP) 8% of G 17,163.22
J. Value Added Tax (VAT) 5% of (G + H + I) 12,872.42
K. Total Unit Cost (G + H + I + J) 270,320.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 85.00 91.41 7,769.85


b. Skilled Laborer 1 85.00 66.06 5,615.10
c. Unskilled Laborer 1 85.00 50.86 4,323.10

Sub - Total for A 17,708.05

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,770.81

Sub - Total for B 1,770.81


C. Total (A + B) 19,478.86
D. Output per Hour = 1 l.s.
E. Direct Unit Cost (C ÷ D) 19,478.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Wood Panel Doors m2 8.64 4,478.57 38,694.84


b. Hallow Core Flush Door m2 11.76 890.71 10,474.75
c. Door Frames set 16.00 2,000.00 32,000.00
d. Bar Door m2 3.60 890.71 3,206.56
e. Consumbale (5% of Material Cost of Door 1,600.00
Frames)

Sub - Total for F 85,976.15


G. Direct Unit Cost (E + F) 105,455.01
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 12,654.60
I. Contractor's Profit (CP) 8% of G 8,436.40
J. Value Added Tax (VAT) 5% of (G + H + I) 6,327.30
K. Total Unit Cost (G + H + I + J) 132,873.31
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 13.25 91.41 1,211.18


b. Skilled Laborer 1 13.25 66.06 875.30
c. Unskilled Laborer 2 13.25 50.86 1,347.79

Sub - Total for A 3,434.27

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 343.43
Sub - Total for B 343.43
C. Total (A + B) 3,777.69
D. Output = 1
E. Direct Unit Cost (C ÷ D) 3,777.69

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. uPVC pipe, 100mm dia.x3m, S-1000 lengths 9.00 715.00 6,435.00


b. uPVC pipe, 75mm dia.x3m, S-1000 lengths 2.00 390.00 780.00
c. uPVC, 50mm dia.x3m, S-1000 (Vent) lengths 14.00 190.00 2,660.00
d. Elbow, 100mm dia-90 degr bend pcs 9.00 81.00 729.00
e. Elbow, 50mm dia-90 deg bend pcs 4.00 26.00 104.00
f.Wye, 100mm dia. pcs 6.00 126.00 756.00
g. Wye Reducer, 100mm dia.-75mm dia pcs 1.00 120.00 120.00
h. Wye Reducer, 100mm dia.-50mm dia. pcs 9.00 100.00 900.00
i. uPVC Tee 100mm dia.x 100mm dia. pcs 4.00 135.00 540.00
j. uPVC Tee 50mm dia.x50mm dia. pcs 11.00 37.00 407.00
k.uPVC Tee Reducer, 75mm dia.x 50mm dia. pcs 1.00 94.00 94.00
l. Clean out with cover, 100mm dia. pcs 9.00 59.00 531.00
m. Clean out with cover, 75mm dia. pcs 1.00 36.00 36.00
n. uPVC P-trap, 50mm dia. pcs 20.00 107.00 2,140.00
o. PVC cement can 5.00 190.00 950.00
p. Consumables (5% of Materials) 493.75

Sub - Total for F 17,675.75


G. Direct Unit Cost (E + F) 21,453.44
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,574.41
I. Contractor's Profit (CP) 8% of G 1,716.28
J. Value Added Tax (VAT) 5% of (G + H + I) 1,287.21
K. Total Unit Cost (G + H + I + J) 27,031.34
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works


Unit of Measurement : pc
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.75 91.41 434.20


b. Skilled Laborer 1 4.75 66.06 313.79
c. Unskilled Laborer 2 4.75 50.86 483.17

Sub - Total for A 1,231.15

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 123.12

Sub - Total for B 123.12


C. Total (A + B) 1,354.27
D. Output = 1
E. Direct Unit Cost (C ÷ D) 1,354.27

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 32mm dia. X 4m, PN 16 length 4.00 736.28 2,945.12


b. PPRC Pipe, 25mm dia. X 4m, PN 16 length 2.00 425.92 851.84
c. PPRC Pipe, 20mm dia. X 4m, PN 16 length 5.00 275.50 1,377.50
d. PP-R Coupling Reducer 32x25mm dia. pcs 2.00 15.80 31.60
e.PP-R Coupling Reducer 32x20mm dia. pcs 5.00 14.22 71.10
f.PP-R Elbow 25mm dia.-90 deg pcs 1.00 20.54 20.54
g. PP-R Elbow 20mm dia.- 90 deg pcs 4.00 12.64 50.56
h.PP-R Tee 20mm dia. pcs 5.00 14.80 74.00
i. PPR-Tee Reducer 32x20mm dia. pcs 2.00 32.52 65.04
j.PPR-Tee Reducer 25x20mm dia. pcs 2.00 26.86 53.72
k. Consumables (5% of Materials) 258.72

Sub - Total for F 5,799.74


G. Direct Unit Cost (E + F) 7,154.01
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 858.48
I. Contractor's Profit (CP) 8% of G 572.32
J. Value Added Tax (VAT) 5% of (G + H + I) 429.24
K. Total Unit Cost (G + H + I + J) 9,014.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 26.00 91.41 2,376.66


b. Skilled Laborer 2 26.00 66.06 3,435.12
c. Unskilled Laborer 4 26.00 50.86 5,289.44

Sub - Total for A 11,101.22

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 1,110.12


b. Plate Compactor (5hp) 1 0.00 123.00 -

Sub - Total for B 1,110.12


C. Total (A + B) 12,211.34
D. Output = 1
E. Direct Unit Cost (C ÷ D) 12,211.34

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. uPVC Drain Pipe, 150mm dia.x3m pcs 15.00 1,975.29 29,629.35


b. Roof Drain (Dome-type strainer) pcs 8.00 1,500.00 12,000.00
c.uPVC Sanitary Pipe, 75mm dia.x 3m, S-1000 lengths 20.00 390.00 7,800.00
d.Elbow, 75mm dia.-45 deg bend pcs 18.00 38.00 684.00
e. PVC solvent, 400cc cans 2.00 190.00 380.00
f. Consumables 5% 2,524.67

Sub - Total for F 53,018.02


G. Direct Unit Cost (E + F) 65,229.36
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 7,827.52
I. Contractor's Profit (CP) 8% of G 5,218.35
J. Value Added Tax (VAT) 5% of (G + H + I) 3,913.76
K. Total Unit Cost (G + H + I + J) 82,188.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 80.75 91.41 7,381.36


b. Skilled Laborer 1 80.75 66.06 5,334.35
c. Unskilled Laborer 1 80.75 50.86 4,106.95

Sub - Total for A 16,822.65

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,682.26

Sub - Total for B 1,682.26


C. Total (A + B) 18,504.91
D. Output = 1
E. Direct Unit Cost (C ÷ D) 18,504.91

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 6.00 6,850.00 41,100.00
b. Urinal sets 2.00 4,800.00 9,600.00
c. Concrete Counter Sink (1 Faucet) sets 3.00 2,895.00 8,685.00
d. Concrete Counter Sink (3 Faucet) sets 1.00 6,028.00 6,028.00
e. Wall Hung Lavatory, complete w/ fittings & accs. sets 1.00 6,500.00 6,500.00
f. Gate Valve, 32mm dia pcs 2.00 627.00 1,254.00
g. Gate Valve 20mm dia pcs 2.00 330.00 660.00
h. Gate Valve, 50mm dia pcs 2.00 980.00 1,960.00
i. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k.S.S. Floor Drain 4'x4'' pcs 20.00 280.00 5,600.00
l. Mirror m2 12.00 5,379.20 64,550.40
m. Handrail (PWD) sets 1.00 4,500.00 4,500.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 6.00 165.00 990.00
o. Consumables (5% of Materials) 7,619.07

Sub - Total for F 160,000.47


G. Direct Unit Cost (E + F) 178,505.38
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 21,420.65
I. Contractor's Profit (CP) 8% of G 14,280.43
J. Value Added Tax (VAT) 5% of (G + H + I) 10,710.32
K. Total Unit Cost (G + H + I + J) 224,916.78
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(24) Fire Extinguisher (10 lbs.) 2CL


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 84.25 91.41 7,701.29


b. Skilled Laborer 2 84.25 66.06 11,131.11
c. Unskilled Laborer 4 84.25 50.86 17,139.82

Sub - Total for A 35,972.22

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 3,597.22

Sub - Total for B 3,597.22


C. Total (A + B) 39,569.44
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 39,569.44

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 65mm dia lm 20.00 708.00 14,160.00


b. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 1,416.00 1,416.00
c. Fire Extinguisher, 10 lbs Capacity, Wall set 2.00 6,825.00 13,650.00
Mounted, HCFC 123
d. Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
f. Concrete m³ 15.45 3,475.00 53,688.75
g. Rebar kg 648.90 31.00 20,115.90
h. Plaster Finish m² 66.00 84.25 5,560.50
i. Cement Based Waterproofing bag 159.00 45.00 7,155.00
j. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
k. End-Suction Centrifugal Water Pump, TDH 9m,
0.5HP, 60GPM unit 2.00 23,500.00 47,000.00

Sub - Total for F 371,746.15


G. Direct Unit Cost (E + F) 411,315.59
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 49,357.87
I. Contractor's Profit (CP) 8% of G 32,905.25
J. Value Added Tax (VAT) 5% of (G + H + I) 24,678.94
K. Total Unit Cost (G + H + I + J) 518,257.65

* Please Check the Summation of Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 17.75 91.41 1,622.53


b. Skilled Laborer 2 17.75 66.06 2,345.13
c. Unskilled Laborer 4 17.75 50.86 3,611.06

Sub - Total for A 7,578.72

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 757.87

Sub - Total for B 757.87


C. Total (A + B) 8,336.59
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 8,336.59

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 3.11 3,475.00 10,807.25


b. Reinforcement Steel Bars kgs 405.02 31.00 12,555.62
c. Plaster Finish m2 41.10 84.25 3,462.68
d. Cement-Base Waterproofing-Sahara bags 100.00 45.00 4,500.00
e.6" CHB m2 4.00 122.50 490.00
f. 4"CHB m2 2.00 101.38 202.75
-
-

Sub - Total for F 32,018.30


G. Direct Unit Cost (E + F) 40,354.88
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,842.59
I. Contractor's Profit (CP) 8% of G 3,228.39
J. Value Added Tax (VAT) 5% of (G + H + I) 2,421.29
K. Total Unit Cost (G + H + I + J) 50,847.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 91.41 91.41


b. Skilled Laborer 1 1.00 66.06 66.06
c. Unskilled Laborer 1 1.00 50.86 50.86

Sub - Total for A 208.33

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 20.83

Sub - Total for B 20.83


C. Total (A + B) 229.16
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 229.16

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 0.07 3,475.00 243.25


b.Reinforcement kgs 8.63 31.00 267.53
c.Masonry m2 0.80 101.38 81.10
d. Finishing Works m2 0.18 84.25 14.83
-

Sub - Total for F 606.71


G. Direct Unit Cost (E + F) 835.87
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 100.30
I. Contractor's Profit (CP) 8% of G 66.87
J. Value Added Tax (VAT) 5% of (G + H + I) 50.15
K. Total Unit Cost (G + H + I + J) 1,053.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 15.00 91.41 1,371.15


b. Skilled Laborer 1 15.00 66.06 990.90
c. Unskilled Laborer 2 15.00 50.86 1,525.80

Sub - Total for A 3,887.85

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 388.79

Sub - Total for B 388.79


C. Total (A + B) 4,276.64
D. Output = 1
E. Direct Unit Cost (C ÷ D) 4,276.64

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. uPVC pipe, 100mm dia.x3m, S-1000 lengths 9.00 715.00 6,435.00


b. uPVC pipe, 75mm dia.x3m, S-1000 lengths 2.00 390.00 780.00
c. uPVC, 50mm dia.x3m, S-1000 (Vent) lengths 14.00 190.00 2,660.00
d. Elbow, 100mm dia-90 degr bend pcs 9.00 81.00 729.00
e. Elbow, 50mm dia-90 deg bend pcs 4.00 26.00 104.00
f.Wye, 100mm dia. pcs 6.00 126.00 756.00
g. Wye Reducer, 100mm dia.-75mm dia pcs 1.00 120.00 120.00
h. Wye Reducer, 100mm dia.-50mm dia. pcs 9.00 100.00 900.00
i. uPVC Tee 100mm dia.x 100mm dia. pcs 4.00 135.00 540.00
j. uPVC Tee 50mm dia.x50mm dia. pcs 11.00 37.00 407.00
k.uPVC Tee Reducer, 75mm dia.x 50mm dia. pcs 1.00 94.00 94.00
l. Clean out with cover, 100mm dia. pcs 9.00 59.00 531.00
m. Clean out with cover, 75mm dia. pcs 1.00 36.00 36.00
n. uPVC P-trap, 50mm dia. pcs 28.00 107.00 2,996.00
o. PVC cement can 5.00 190.00 950.00
p. Consumables (5% of Material Cost) 493.75

Sub - Total for F 18,531.75


G. Direct Unit Cost (E + F) 22,808.39
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,737.01
I. Contractor's Profit (CP) 8% of G 1,824.67
J. Value Added Tax (VAT) 5% of (G + H + I) 1,368.50
K. Total Unit Cost (G + H + I + J) 28,738.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works


Unit of Measurement : pc
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.75 91.41 434.20


b. Skilled Laborer 1 4.75 66.06 313.79
c. Unskilled Laborer 2 4.75 50.86 483.17

Sub - Total for A 1,231.15

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 123.12

Sub - Total for B 123.12


C. Total (A + B) 1,354.27
D. Output = 1
E. Direct Unit Cost (C ÷ D) 1,354.27

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 32mm dia. X 4m, PN 16 length 4.00 736.28 2,945.12


b. PPRC Pipe, 25mm dia. X 4m, PN 16 length 2.00 425.92 851.84
c. PPRC Pipe, 20mm dia. X 4m, PN 16 length 5.00 275.50 1,377.50
d. PP-R Coupling Reducer 32x25mm dia. pcs 2.00 15.80 31.60
e.PP-R Coupling Reducer 32x20mm dia. pcs 5.00 14.22 71.10
f.PP-R Elbow 25mm dia.-90 deg pcs 1.00 20.54 20.54
g. PP-R Elbow 20mm dia.- 90 deg pcs 4.00 12.64 50.56
h.PP-R Tee 20mm dia. pcs 5.00 14.80 74.00
i. PPR-Tee Reducer 32x20mm dia. pcs 2.00 32.52 65.04
j.PPR-Tee Reducer 25x20mm dia. pcs 2.00 26.86 53.72
k. Consumables (5% of Materials) 258.72

Sub - Total for F 5,799.74


G. Direct Unit Cost (E + F) 7,154.01
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 858.48
I. Contractor's Profit (CP) 8% of G 572.32
J. Value Added Tax (VAT) 5% of (G + H + I) 429.24
K. Total Unit Cost (G + H + I + J) 9,014.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 34.50 91.41 3,153.65


b. Skilled Laborer 2 34.50 66.06 4,558.14
c. Unskilled Laborer 4 34.50 50.86 7,018.68

Sub - Total for A 14,730.47

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 1,473.05

Sub - Total for B 1,473.05


C. Total (A + B) 16,203.51
D. Output = 1
E. Direct Unit Cost (C ÷ D) 16,203.51

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PVC Drain Pipe, 150mm dia.x3m pcs 15.00 1,975.29 29,629.35


b. Roof Drain (Dome-type strainer) pcs 16.00 1,500.00 24,000.00
c.uPVC Sanitary Pipe, 75mm dia.x 3m, S-1000 lengths 33.00 390.00 12,870.00
d.Elbow, 75mm dia.-45 deg bend pcs 30.00 38.00 1,140.00
e. PVC solvent, 400cc cans 2.00 190.00 380.00
f. Consumables 5% 2,124.97

Sub - Total for F 70,144.32


G. Direct Unit Cost (E + F) 86,347.83
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 10,361.74
I. Contractor's Profit (CP) 8% of G 6,907.83
J. Value Added Tax (VAT) 5% of (G + H + I) 5,180.87
K. Total Unit Cost (G + H + I + J) 108,798.26
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 82.00 91.41 7,495.62


b. Skilled Laborer 1 82.00 66.06 5,416.92
c. Unskilled Laborer 1 82.00 50.86 4,170.52

Sub - Total for A 17,083.06

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,708.31

Sub - Total for B 1,708.31


C. Total (A + B) 18,791.37
D. Output = 1
E. Direct Unit Cost (C ÷ D) 18,791.37

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 6.00 6,850.00 41,100.00
b. Urinal sets 2.00 4,800.00 9,600.00
c. Concrete Counter Sink (1 Faucet) sets 3.00 2,895.00 8,685.00
d. Concrete Counter Sink (3 Faucet) sets 1.00 6,028.00 6,028.00
e. Wall Hung Lavatory, complete w/ fittings & accs. sets 1.00 6,500.00 6,500.00
f. Gate Valve, 32mm dia pcs 2.00 627.00 1,254.00
g. Gate Valve 20mm dia pcs 2.00 330.00 660.00
h. Gate Valve, 50mm dia pcs 2.00 980.00 1,960.00
i. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k.S.S. Floor Drain 4'x4'' pcs 28.00 280.00 7,840.00
l. Mirror ft2 12.00 5,379.20 64,550.40
m. Handrail (PWD) sets 1.00 4,500.00 4,500.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 6.00 165.00 990.00
o. Consumables 5% 7,731.07

Sub - Total for F 162,352.47


G. Direct Unit Cost (E + F) 181,143.84
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 21,737.26
I. Contractor's Profit (CP) 8% of G 14,491.51
J. Value Added Tax (VAT) 5% of (G + H + I) 10,868.63
K. Total Unit Cost (G + H + I + J) 228,241.23
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-2 Dry Stand Pipe System


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 105.25 91.41 9,620.90


b. Skilled Laborer 2 105.25 66.06 13,905.63
c. Unskilled Laborer 4 105.25 50.86 21,412.06

Sub - Total for A 44,938.59

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 4,493.86

Sub - Total for B 4,493.86


C. Total (A + B) 49,432.45
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 49,432.45

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 75mm dia lm 12.00 984.00 11,808.00


b. B.I. Pipe 65mm dia lm 25.00 708.00 17,700.00
c. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 2,950.80 2,950.80
d. Fire Hose Cabinet with Fire Extinguisher set 2.00 24,000.00 48,000.00
e. Fire Extinguisher, 10 lbs Capacity, Wall
set 6.00 6,825.00 40,950.00
Mounted, HCFC 123
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
i. Concrete m³ 15.45 3,475.00 53,688.75
j. Rebar kg 648.90 31.00 20,115.90
k. Plaster Finish m² 66.00 84.25 5,560.50
l. Cement Based Waterproofing bag 159.00 45.00 7,155.00
m. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
n. End-Suction Centrifugal Water Pump, TDH 9m,
1.0HP, 60GPM unit 2.00 27,800.00 55,600.00

Sub - Total for F 479,028.95


G. Direct Unit Cost (E + F) 528,461.40
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 63,415.37
I. Contractor's Profit (CP) 8% of G 42,276.91
J. Value Added Tax (VAT) 5% of (G + H + I) 31,707.68
K. Total Unit Cost (G + H + I + J) 665,861.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 30.00 91.41 2,742.30


b. Skilled Laborer 2 30.00 66.06 3,963.60
c. Unskilled Laborer 4 30.00 50.86 6,103.20

Sub - Total for A 12,809.10

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,280.91

Sub - Total for B 1,280.91


C. Total (A + B) 14,090.01
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 14,090.01

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 6.79 3,475.00 23,595.25


b. Reinforcement Steel Bars kgs 583.68 31.00 18,094.08
c. Plaster Finish m2 70.18 84.25 5,912.67
d. Cement-Base Waterproofing-Sahara bags 170.00 45.00 7,650.00
e.6" CHB m2 5.00 122.50 612.50
f. 4"CHB m2 2.00 101.38 202.75
-
-

Sub - Total for F 56,067.25


G. Direct Unit Cost (E + F) 70,157.26
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 8,418.87
I. Contractor's Profit (CP) 8% of G 5,612.58
J. Value Added Tax (VAT) 5% of (G + H + I) 4,209.44
K. Total Unit Cost (G + H + I + J) 88,398.14
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 91.41 91.41


b. Skilled Laborer 1 1.00 66.06 66.06
c. Unskilled Laborer 1 1.00 50.86 50.86

Sub - Total for A 208.33

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 20.83

Sub - Total for B 20.83


C. Total (A + B) 229.16
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 229.16

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 0.07 3,475.00 243.25


b.Reinforcement kgs 8.63 31.00 267.53
c.Masonry m2 0.80 101.38 81.10
d. Finishing Works m2 0.18 84.25 14.83
-

Sub - Total for F 606.71


G. Direct Unit Cost (E + F) 835.87
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 100.30
I. Contractor's Profit (CP) 8% of G 66.87
J. Value Added Tax (VAT) 5% of (G + H + I) 50.15
K. Total Unit Cost (G + H + I + J) 1,053.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 32.00 91.41 2,925.12


b. Skilled Laborer 1 32.00 66.06 2,113.92
c. Unskilled Laborer 2 32.00 50.86 3,255.04

Sub - Total for A 8,294.08

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 829.41
Sub - Total for B 829.41
C. Total (A + B) 9,123.49
D. Output = 1
E. Direct Unit Cost (C ÷ D) 9,123.49

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
-
a. uPVC pipe, 100mm dia.x3m, S-1000 lengths 26.00 715.00 18,590.00
b. uPVC pipe, 75mm dia.x3m, S-1000 lengths 5.00 390.00 1,950.00
c. uPVC, 75mm dia.x3m, S-1000 (Vent) lengths 5.00 390.00 1,950.00
d. uPVC, 50mm dia.x3m, S-1000 (Vent) lengths 15.00 190.00 2,850.00
e. Elbow, 100mm dia-90 degr bend pcs 8.00 81.00 648.00
f. Elbow, 75mm dia-90 deg bend pcs 4.00 26.00 104.00
g. Elbow, 50mm dia-90 deg bend pcs 16.00 126.00 2,016.00
h.Wye, 100mm dia. pcs 18.00 120.00 2,160.00
i. Wye Reducer, 100mm dia.-75mm dia pcs 2.00 100.00 200.00
j. uPVC Tee 100mm dia.x 100mm dia. pcs 4.00 135.00 540.00
k. uPVC Tee 100mm dia.x 75mm dia. pcs 4.00 37.00 148.00
l. uPVC Tee 50mm dia.x50mm dia. pcs 8.00 94.00 752.00
m. Clean out with cover, 100mm dia. pcs 13.00 59.00 767.00
n. Clean out with cover, 75mm dia. pcs 4.00 36.00 144.00
o. uPVC P-trap, 50mm dia. pcs 40.00 107.00 4,280.00
p. PVC cement cans 6.00 190.00 1,140.00
q. Consumables (5% of Materials) 1,267.00
Sub - Total for F 39,506.00
G. Direct Unit Cost (E + F) 48,629.49
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 5,835.54
I. Contractor's Profit (CP) 8% of G 3,890.36
J. Value Added Tax (VAT) 5% of (G + H + I) 2,917.77
K. Total Unit Cost (G + H + I + J) 61,273.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works


Unit of Measurement : pc
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 21.00 91.41 1,919.61


b. Skilled Laborer 1 21.00 66.06 1,387.26
c. Unskilled Laborer 2 21.00 50.86 2,136.12

Sub - Total for A 5,442.99

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 544.30

Sub - Total for B 544.30


C. Total (A + B) 5,987.29
D. Output = 1
E. Direct Unit Cost (C ÷ D) 5,987.29

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 38mm dia. X 4m, PN 16 length 16.00 1,117.85 17,885.60


b. PPRC Pipe, 25mm dia. X 4m, PN 16 length 8.00 425.92 3,407.36
c. PPRC Pipe, 20mm dia. X 4m, PN 16 length 6.00 275.50 1,653.00
d. PP-R Coupling 38mm dia. pcs 9.00 30.81 277.29
e. PP-R Coupling 25mm dia. pcs 3.00 12.64 37.92
f. PP-R Coupling 20mm dia. pcs 3.00 8.69 26.07
g.PP-R Elbow 38mm dia.-90 deg pcs 2.00 53.91 107.82
h.PP-R Elbow 25mm dia.-90 deg pcs 4.00 20.54 82.16
i. PP-R Elbow 20mm dia.- 90 deg pcs 4.00 12.64 50.56
j.PP-R Elbow Reducer 38mmx25mm pcs 2.00 50.00 100.00
k.PP-R Elbow Reducer 25mmx 20mm pcs 2.00 163.07 326.14
l. PP-R Tee 38mm dia. pcs 2.00 72.34 144.68
m. PP-R Tee 25mm dia. pcs 14.00 26.86 376.04
n. PP-R Tee 20mm dia. pcs 12.00 14.80 177.60
-
-
-
-
-
-

1,147.30

Sub - Total for F 25,799.54


G. Direct Unit Cost (E + F) 31,786.83
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,814.42
I. Contractor's Profit (CP) 8% of G 2,542.95
J. Value Added Tax (VAT) 5% of (G + H + I) 1,907.21
K. Total Unit Cost (G + H + I + J) 40,051.40
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 72.25 91.41 6,604.37


b. Skilled Laborer 2 72.25 66.06 9,545.67
c. Unskilled Laborer 4 72.25 50.86 14,698.54

Sub - Total for A 30,848.58

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 3,084.86

Sub - Total for B 3,084.86


C. Total (A + B) 33,933.44
D. Output = 1
E. Direct Unit Cost (C ÷ D) 33,933.44

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PVC Drain Pipe, 200mm dia.x3m pcs 23.00 3,029.03 69,667.69


a. PVC Drain Pipe, 150mm dia.x3m pcs 13.00 1,975.29 25,678.77
b. Roof Drain (Dome-type strainer) lengths 20.00 1,500.00 30,000.00
c.uPVC Sanitary Pipe, 75mm dia.x 3m, S-1000 pcs 38.00 390.00 14,820.00
d.Elbow, 75mm dia.-45 deg bend pcs 36.00 38.00 1,368.00
e. PVC solvent, 400cc cans 2.00 190.00 380.00
f. Consumables 5% 5,508.32

Sub - Total for F 147,422.78


G. Direct Unit Cost (E + F) 181,356.22
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 21,762.75
I. Contractor's Profit (CP) 8% of G 14,508.50
J. Value Added Tax (VAT) 5% of (G + H + I) 10,881.37
K. Total Unit Cost (G + H + I + J) 228,508.84
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 163.25 91.41 14,922.68


b. Skilled Laborer 1 163.25 66.06 10,784.30
c. Unskilled Laborer 1 163.25 50.86 8,302.90

Sub - Total for A 34,009.87

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 3,400.99

Sub - Total for B 3,400.99


C. Total (A + B) 37,410.86
D. Output = 1
E. Direct Unit Cost (C ÷ D) 37,410.86

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 10.00 6,850.00 68,500.00
b. Urinal sets 2.00 4,800.00 9,600.00
d. Concrete Counter Sink (3 Faucet) sets 9.00 6,028.00 54,252.00
e. Wall Hung Lavatory, complete w/ fittings & accs. sets 3.00 6,500.00 19,500.00
f. Gate Valve, 50mm dia pcs 2.00 627.00 1,254.00
g. Gate Valve 32mm dia pcs 4.00 330.00 1,320.00
h. Gate Valve, 20mm dia pcs 2.00 980.00 1,960.00
i. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k.S.S. Floor Drain 4'x4'' pcs 40.00 280.00 11,200.00
l. Mirror ft2 24.00 5,379.20 129,100.80
m. Handrail (PWD) sets 2.00 4,500.00 9,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 9.00 165.00 1,485.00
o. Consumables 5% 15,406.29

Sub - Total for F 323,532.09


G. Direct Unit Cost (E + F) 360,942.95
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 43,313.15
I. Contractor's Profit (CP) 8% of G 28,875.44
J. Value Added Tax (VAT) 5% of (G + H + I) 21,656.58
K. Total Unit Cost (G + H + I + J) 454,788.12
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-2 Dry Stand Pipe System 8CL


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 163.25 91.41 14,922.68


b. Skilled Laborer 2 163.25 66.06 21,568.59
c. Unskilled Laborer 4 163.25 50.86 33,211.58

Sub - Total for A 69,702.85

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 6,970.29

Sub - Total for B 6,970.29


C. Total (A + B) 76,673.14
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 76,673.14

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 75mm dia lm 54 984.00 53,136.00


b. B.I. Pipe 65mm dia lm 20.00 708.00 14,160.00
c. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 6,729.60 6,729.60
d. Fire Hose Cabinet with Fire Extinguisher set 4.00 24,000.00 96,000.00
e. Fire Extinguisher, 10 lbs Capacity, Wall set 8.00 6,825.00 54,600.00
Mounted, HCFC 123
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
i. Concrete m³ 15.45 3,475.00 53,688.75
j. Rebar kg 648.90 31.00 20,115.90
k. Plaster Finish m² 66.00 84.25 5,560.50
l. Cement Based Waterproofing bag 159.00 45.00 7,155.00
m. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
n. End-Suction Centrifugal Water Pump, TDH 10m,
1.5HP, 80GPM unit 2.00 29,800.00 59,600.00
o. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00

Sub - Total for F 792,545.75


G. Direct Unit Cost (E + F) 869,218.89
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 104,306.27
I. Contractor's Profit (CP) 8% of G 69,537.51
J. Value Added Tax (VAT) 5% of (G + H + I) 52,153.13
K. Total Unit Cost (G + H + I + J) 1,095,215.80
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 34.75 91.41 3,176.50


b. Skilled Laborer 2 34.75 66.06 4,591.17
c. Unskilled Laborer 4 34.75 50.86 7,069.54

Sub - Total for A 14,837.21

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,483.72

Sub - Total for B 1,483.72


C. Total (A + B) 16,320.93
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 16,320.93

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 8.27 3,475.00 28,738.25


b. Reinforcement Steel Bars kgs 655.79 31.00 20,329.49
c. Plaster Finish m2 82.44 84.25 6,945.57
d. Cement-Base Waterproofing-Sahara bags 200.00 45.00 9,000.00
e.6" CHB m2 5.00 122.50 612.50
f. 4"CHB m2 2.50 101.38 253.44
-
-

Sub - Total for F 65,879.25


G. Direct Unit Cost (E + F) 82,200.18
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 9,864.02
I. Contractor's Profit (CP) 8% of G 6,576.01
J. Value Added Tax (VAT) 5% of (G + H + I) 4,932.01
K. Total Unit Cost (G + H + I + J) 103,572.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 91.41 91.41


b. Skilled Laborer 1 1.00 66.06 66.06
c. Unskilled Laborer 1 1.00 50.86 50.86

Sub - Total for A 208.33

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 20.83

Sub - Total for B 20.83


C. Total (A + B) 229.16
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 229.16

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 0.07 3,475.00 243.25


b.Reinforcement kgs 8.63 31.00 267.53
c.Masonry m2 0.80 101.38 81.10
d. Finishing Works m2 0.18 84.25 14.83
-

Sub - Total for F 606.71


G. Direct Unit Cost (E + F) 835.87
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 100.30
I. Contractor's Profit (CP) 8% of G 66.87
J. Value Added Tax (VAT) 5% of (G + H + I) 50.15
K. Total Unit Cost (G + H + I + J) 1,053.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 35.00 91.41 3,199.35


b. Skilled Laborer 1 35.00 66.06 2,312.10
c. Unskilled Laborer 2 35.00 50.86 3,560.20

Sub - Total for A 9,071.65

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 907.17
Sub - Total for B 907.17
C. Total (A + B) 9,978.82
D. Output = 1
E. Direct Unit Cost (C ÷ D) 9,978.82

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
-
a. uPVC pipe, 100mm dia.x3m, S-1000 lengths 30.00 715.00 21,450.00
b. uPVC pipe, 75mm dia.x3m, S-1000 lengths 5.00 390.00 1,950.00
c. uPVC, 75mm dia.x3m, S-1000 (Vent) lengths 5.00 390.00 1,950.00
d. uPVC, 50mm dia.x3m, S-1000 (Vent) lengths 15.00 190.00 2,850.00
e. Elbow, 100mm dia-90 degr bend pcs 8.00 81.00 648.00
f. Elbow, 75mm dia-90 deg bend pcs 4.00 26.00 104.00
g. Elbow, 50mm dia-90 deg bend pcs 16.00 126.00 2,016.00
h.Wye, 100mm dia. pcs 18.00 120.00 2,160.00
i. Wye Reducer, 100mm dia.-75mm dia pcs 2.00 100.00 200.00
j. uPVC Tee 100mm dia.x 100mm dia. pcs 4.00 135.00 540.00
k. uPVC Tee 100mm dia.x 75mm dia. pcs 4.00 37.00 148.00
l. uPVC Tee 50mm dia.x50mm dia. pcs 8.00 94.00 752.00
m. Clean out with cover, 100mm dia. pcs 13.00 59.00 767.00
n. Clean out with cover, 75mm dia. pcs 4.00 36.00 144.00
o. uPVC P-trap, 50mm dia. pcs 46.00 107.00 4,922.00
p. PVC cement cans 6.00 190.00 1,140.00
q. Consumables (5% of Materials) 1,410.00
Sub - Total for F 43,151.00
G. Direct Unit Cost (E + F) 53,129.82
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6,375.58
I. Contractor's Profit (CP) 8% of G 4,250.39
J. Value Added Tax (VAT) 5% of (G + H + I) 3,187.79
K. Total Unit Cost (G + H + I + J) 66,943.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works


Unit of Measurement : l.s
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 23.75 91.41 2,170.99


b. Skilled Laborer 1 23.75 66.06 1,568.93
c. Unskilled Laborer 2 23.75 50.86 2,415.85

Sub - Total for A 6,155.76

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 615.58

Sub - Total for B 615.58


C. Total (A + B) 6,771.34
D. Output = 1
E. Direct Unit Cost (C ÷ D) 6,771.34

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 38mm dia. X 4m, PN 16 length 19.00 1,117.85 21,239.15


b. PPRC Pipe, 25mm dia. X 4m, PN 16 length 8.00 425.92 3,407.36
c. PPRC Pipe, 20mm dia. X 4m, PN 16 length 6.00 275.50 1,653.00
d. PP-R Coupling 38mm dia. pcs 9.00 30.81 277.29
e. PP-R Coupling 25mm dia. pcs 3.00 12.64 37.92
f. PP-R Coupling 20mm dia. pcs 3.00 8.69 26.07
g.PP-R Elbow 38mm dia.-90 deg pcs 2.00 53.91 107.82
h.PP-R Elbow 25mm dia.-90 deg pcs 4.00 20.54 82.16
i. PP-R Elbow 20mm dia.- 90 deg pcs 4.00 12.64 50.56
j.PP-R Elbow Reducer 38mmx25mm pcs 2.00 50.00 100.00
k.PP-R Elbow Reducer 25mmx 20mm pcs 2.00 163.07 326.14
l. PP-R Tee 38mm dia. pcs 2.00 72.34 144.68
m. PP-R Tee 25mm dia. pcs 14.00 26.86 376.04
n. PP-R Tee 20mm dia. pcs 12.00 14.80 177.60
-
-
-
-

1,314.98

Sub - Total for F 29,320.77


G. Direct Unit Cost (E + F) 36,092.10
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,331.05
I. Contractor's Profit (CP) 8% of G 2,887.37
J. Value Added Tax (VAT) 5% of (G + H + I) 2,165.53
K. Total Unit Cost (G + H + I + J) 45,476.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 84.75 91.41 7,747.00


b. Skilled Laborer 2 84.75 66.06 11,197.17
c. Unskilled Laborer 4 84.75 50.86 17,241.54

Sub - Total for A 36,185.71

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 3,618.57


b. Plate Compactor (5hp) 1 0.00 123.00 -

Sub - Total for B 3,618.57


C. Total (A + B) 39,804.28
D. Output = 1
E. Direct Unit Cost (C ÷ D) 39,804.28

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PVC Drain Pipe, 200mm dia.x3m pcs 23.00 3,029.03 69,667.69


a. PVC Drain Pipe, 150mm dia.x3m pcs 19.00 1,975.29 37,530.51
b. Roof Drain (Dome-type strainer) lengths 26.00 1,500.00 39,000.00
c.uPVC Sanitary Pipe, 75mm dia.x 3m, S-1000 pcs 45.00 390.00 17,550.00
d.Elbow, 75mm dia.-45 deg bend pcs 42.00 38.00 1,596.00
e. PVC solvent, 400cc cans 2.00 190.00 380.00
f. Consumables 5% 7,114.91
-
Sub - Total for F 172,839.11
G. Direct Unit Cost (E + F) 212,643.39
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 0.12 of G 25,517.21
I. Contractor's Profit (CP) 0.08 of G 17,011.47
J. Value Added Tax (VAT) 0.05 of (G + H + I) 12,758.60
K. Total Unit Cost (G + H + I + J) 267,930.67
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures


Unit of Measurement : l.s.
Output : 1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 164.00 91.41 14,991.24


b. Skilled Laborer 1 164.00 66.06 10,833.84
c. Unskilled Laborer 1 164.00 50.86 8,341.04

Sub - Total for A 34,166.12

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 3,416.61

Sub - Total for B 3,416.61


C. Total (A + B) 37,582.73
D. Output = 1
E. Direct Unit Cost (C ÷ D) 37,582.73

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 10.00 6,850.00 68,500.00
b. Urinal sets 2.00 4,800.00 9,600.00
d. Concrete Counter Sink (3 Faucet) sets 9.00 6,028.00 54,252.00
e. Wall Hung Lavatory, complete w/ fittings & accs. sets 3.00 6,500.00 19,500.00
f. Gate Valve, 50mm dia pcs 2.00 627.00 1,254.00
g. Gate Valve 32mm dia pcs 4.00 330.00 1,320.00
h. Gate Valve, 20mm dia pcs 2.00 980.00 1,960.00
i. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k.S.S. Floor Drain 4'x4'' pcs 46.00 280.00 12,880.00
l. Mirror ft2 24.00 5,379.20 129,100.80
m. Handrail (PWD) sets 2.00 4,500.00 9,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 9.00 165.00 1,485.00
o. Consumables 5% 15,490.29

Sub - Total for F 325,296.09


G. Direct Unit Cost (E + F) 362,878.82
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 43,545.46
I. Contractor's Profit (CP) 8% of G 29,030.31
J. Value Added Tax (VAT) 5% of (G + H + I) 21,772.73
K. Total Unit Cost (G + H + I + J) 457,227.32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-2 Dry Stand Pipe System 10CL


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 179.25 91.41 16,385.24


b. Skilled Laborer 2 179.25 66.06 23,682.51
c. Unskilled Laborer 4 179.25 50.86 36,466.62

Sub - Total for A 76,534.37

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 7,653.44

Sub - Total for B 7,653.44


C. Total (A + B) 84,187.81
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 84,187.81

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 75mm dia lm 60 984.00 59,040.00


b. B.I. Pipe 65mm dia lm 66.00 708.00 46,728.00
c. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 10,576.80 10,576.80
d. Fire Hose Cabinet with Fire Extinguisher set 4.00 24,000.00 96,000.00
e. Fire Extinguisher, 10 lbs Capacity, Wall
set 10.00 6,825.00 68,250.00
Mounted, HCFC 123
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
i. Concrete m³ 15.45 3,475.00 53,688.75
j. Rebar kg 648.90 31.00 20,115.90
k. Plaster Finish m² 66.00 84.25 5,560.50
l. Cement Based Waterproofing bag 159.00 45.00 7,155.00
m. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
n. End-Suction Centrifugal Water Pump, TDH 10m,
1.5HP, 80GPM unit 2.00 29,800.00 59,600.00

o. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00
Sub - Total for F 848,514.95
G. Direct Unit Cost (E + F) 932,702.76
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 111,924.33
I. Contractor's Profit (CP) 8% of G 74,616.22
J. Value Added Tax (VAT) 5% of (G + H + I) 55,962.17
K. Total Unit Cost (G + H + I + J) 1,175,205.48

* Please Check the Summation of Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 38.25 91.41 3,496.43


b. Skilled Laborer 2 38.25 66.06 5,053.59
c. Unskilled Laborer 4 38.25 50.86 7,781.58

Sub - Total for A 16,331.60

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,633.16

Sub - Total for B 1,633.16


C. Total (A + B) 17,964.76
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 17,964.76

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 9.65 3,475.00 33,533.75


b. Reinforcement Steel Bars kgs 746.90 31.00 23,153.90
c. Plaster Finish m2 95.92 84.25 8,081.26
d. Cement-Base Waterproofing-Sahara bags 132.00 45.00 5,940.00
e.6" CHB m2 6.00 122.50 735.00
f. 4"CHB m2 3.00 101.38 304.13
-
-

Sub - Total for F 71,748.04


G. Direct Unit Cost (E + F) 89,712.80
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 10,765.54
I. Contractor's Profit (CP) 8% of G 7,177.02
J. Value Added Tax (VAT) 5% of (G + H + I) 5,382.77
K. Total Unit Cost (G + H + I + J) 113,038.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 91.41 91.41


b. Skilled Laborer 1 1.00 66.06 66.06
c. Unskilled Laborer 1 1.00 50.86 50.86

Sub - Total for A 208.33

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 20.83

Sub - Total for B 20.83


C. Total (A + B) 229.16
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 229.16

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 0.07 3,475.00 243.25


b.Reinforcement kgs 8.63 31.00 267.53
c.Masonry m2 0.80 101.38 81.10
d. Finishing Works m2 0.18 84.25 14.83
-

Sub - Total for F 606.71


G. Direct Unit Cost (E + F) 835.87
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 100.30
I. Contractor's Profit (CP) 8% of G 66.87
J. Value Added Tax (VAT) 5% of (G + H + I) 50.15
K. Total Unit Cost (G + H + I + J) 1,053.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 37.00 91.41 3,382.17


b. Skilled Laborer 1 37.00 66.06 2,444.22
c. Unskilled Laborer 2 37.00 50.86 3,763.64

Sub - Total for A 9,590.03

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Minor Tools (10% of labor cost) 959.00
Sub - Total for B 959.00
C. Total (A + B) 10,549.03
D. Output = 1
E. Direct Unit Cost (C ÷ D) 10,549.03

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
-
a. uPVC pipe, 100mm dia.x3m, S-1000 lengths 33.00 715.00 23,595.00
b. uPVC pipe, 75mm dia.x3m, S-1000 lengths 5.00 390.00 1,950.00
c. uPVC, 75mm dia.x3m, S-1000 (Vent) lengths 5.00 390.00 1,950.00
d. uPVC, 50mm dia.x3m, S-1000 (Vent) lengths 15.00 190.00 2,850.00
e. Elbow, 100mm dia-90 degr bend pcs 8.00 81.00 648.00
f. Elbow, 75mm dia-90 deg bend pcs 4.00 26.00 104.00
g. Elbow, 50mm dia-90 deg bend pcs 16.00 126.00 2,016.00
h.Wye, 100mm dia. pcs 18.00 120.00 2,160.00
i. Wye Reducer, 100mm dia.-75mm dia pcs 2.00 100.00 200.00
j. uPVC Tee 100mm dia.x 100mm dia. pcs 4.00 135.00 540.00
k. uPVC Tee 100mm dia.x 75mm dia. pcs 4.00 37.00 148.00
l. uPVC Tee 50mm dia.x50mm dia. pcs 8.00 94.00 752.00
m. Clean out with cover, 100mm dia. pcs 13.00 59.00 767.00
n. Clean out with cover, 75mm dia. pcs 4.00 36.00 144.00
o. uPVC P-trap, 50mm dia. pcs 50.00 107.00 5,350.00
p. PVC cement cans 6.00 190.00 1,140.00
q. Consumables (5% of Materials) 1,517.25
Sub - Total for F 45,831.25
G. Direct Unit Cost (E + F) 56,380.28
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 6,765.63
I. Contractor's Profit (CP) 8% of G 4,510.42
J. Value Added Tax (VAT) 5% of (G + H + I) 3,382.82
K. Total Unit Cost (G + H + I + J) 71,039.16
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(6) Waterline Works


Unit of Measurement : pc
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 25.75 91.41 2,353.81


b. Skilled Laborer 1 25.75 66.06 1,701.05
c. Unskilled Laborer 2 25.75 50.86 2,619.29

Sub - Total for A 6,674.14

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 667.41

Sub - Total for B 667.41


C. Total (A + B) 7,341.56
D. Output = 1
E. Direct Unit Cost (C ÷ D) 7,341.56

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PPRC Pipe, 38mm dia. X 4m, PN 16 length 21.00 1,117.85 23,474.85


b. PPRC Pipe, 25mm dia. X 4m, PN 16 length 8.00 425.92 3,407.36
c. PPRC Pipe, 20mm dia. X 4m, PN 16 length 6.00 275.50 1,653.00
d. PP-R Coupling 38mm dia. pcs 9.00 30.81 277.29
e. PP-R Coupling 25mm dia. pcs 3.00 12.64 37.92
f. PP-R Coupling 20mm dia. pcs 3.00 8.69 26.07
g.PP-R Elbow 38mm dia.-90 deg pcs 2.00 53.91 107.82
h.PP-R Elbow 25mm dia.-90 deg pcs 4.00 20.54 82.16
i. PP-R Elbow 20mm dia.- 90 deg pcs 4.00 12.64 50.56
j.PP-R Elbow Reducer 38mmx25mm pcs 2.00 50.00 100.00
k.PP-R Elbow Reducer 25mmx 20mm pcs 2.00 163.07 326.14
l. PP-R Tee 38mm dia. pcs 2.00 72.34 144.68
m. PP-R Tee 25mm dia. pcs 14.00 26.86 376.04
n. PP-R Tee 20mm dia. pcs 12.00 14.80 177.60
-
-
-
-

1,426.76

Sub - Total for F 31,668.25


G. Direct Unit Cost (E + F) 39,009.81
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,681.18
I. Contractor's Profit (CP) 8% of G 3,120.78
J. Value Added Tax (VAT) 5% of (G + H + I) 2,340.59
K. Total Unit Cost (G + H + I + J) 49,152.36
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 94.50 91.41 8,638.25


b. Skilled Laborer 2 94.50 66.06 12,485.34
c. Unskilled Laborer 4 94.50 50.86 19,225.08

Sub - Total for A 40,348.67

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Minor Tools (10% of labor cost) 4,034.87

Sub - Total for B 4,034.87


C. Total (A + B) 44,383.53
D. Output = 1
E. Direct Unit Cost (C ÷ D) 44,383.53

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PVC Drain Pipe, 200mm dia.x3m pcs 23.00 3,029.03 69,667.69


a. PVC Drain Pipe, 150mm dia.x3m pcs 25.00 1,975.29 49,382.25
b. Roof Drain (Dome-type strainer) lengths 30.00 1,500.00 45,000.00
c.uPVC Sanitary Pipe, 75mm dia.x 3m, S-1000 pcs 51.00 390.00 19,890.00
d.Elbow, 75mm dia.-45 deg bend pcs 48.00 38.00 1,824.00
e. PVC solvent, 400cc cans 2.00 190.00 380.00
f. Consumables 5% 6,947.00
-
Sub - Total for F 193,090.94
G. Direct Unit Cost (E + F) 237,474.47
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 28,496.94
I. Contractor's Profit (CP) 8% of G 18,997.96
J. Value Added Tax (VAT) 5% of (G + H + I) 14,248.47
K. Total Unit Cost (G + H + I + J) 299,217.83
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Sanitary/Plumbing Fixtures


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 164.75 91.41 15,059.80


b. Skilled Laborer 1 164.75 66.06 10,883.39
c. Unskilled Laborer 1 164.75 50.86 8,379.19

Sub - Total for A 34,322.37

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 3,432.24

Sub - Total for B 3,432.24


C. Total (A + B) 37,754.60
D. Output = 1
E. Direct Unit Cost (C ÷ D) 37,754.60

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet complete w/ fittings & accs. sets 10.00 6,850.00 68,500.00
b. Urinal sets 2.00 4,800.00 9,600.00
d. Concrete Counter Sink (3 Faucet) sets 9.00 6,028.00 54,252.00
e. Wall Hung Lavatory, complete w/ fittings & accs. sets 3.00 6,500.00 19,500.00
f. Gate Valve, 50mm dia pcs 2.00 627.00 1,254.00
g. Gate Valve 32mm dia pcs 4.00 330.00 1,320.00
h. Gate Valve, 20mm dia pcs 2.00 980.00 1,960.00
i. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k.S.S. Floor Drain 4'x4'' pcs 50.00 280.00 14,000.00
l. Mirror ft2 24.00 5,379.20 129,100.80
m. Handrail (PWD) sets 2.00 4,500.00 9,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 9.00 165.00 1,485.00
o. Consumables 5% 15,546.29

Sub - Total for F 326,472.09


G. Direct Unit Cost (E + F) 364,226.69
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 43,707.20
I. Contractor's Profit (CP) 8% of G 29,138.14
J. Value Added Tax (VAT) 5% of (G + H + I) 21,853.60
K. Total Unit Cost (G + H + I + J) 458,925.63
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-2 Dry Stand Pipe System 12CL


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 185.75 91.41 16,979.41


b. Skilled Laborer 2 185.75 66.06 24,541.29
c. Unskilled Laborer 4 185.75 50.86 37,788.98

Sub - Total for A 79,309.68

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 7,930.97

Sub - Total for B 7,930.97


C. Total (A + B) 87,240.65
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 87,240.65

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. Pipe 75mm dia lm 72.00 984.00 70,848.00


b. B.I. Pipe 65mm dia lm 66.00 708.00 46,728.00
c. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 11,757.60 11,757.60
d.
e. Fire
Fire Hose Cabinet10
Extinguisher, with
lbsFire Extinguisher
Capacity, Wall set 4.00 24,000.00 96,000.00
Mounted, HCFC 123 set 12.00 6,825.00 81,900.00
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
i. Concrete m³ 15.45 3,475.00 53,688.75
j. Rebar kg 648.90 31.00 20,115.90
k. Plaster Finish m² 66.00 84.25 5,560.50
l. Cement Based Waterproofing bag 159.00 45.00 7,155.00
m. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
n. End-Suction Centrifugal Water Pump, TDH 10m,
unit 2.00 29,800.00 59,600.00
1.5HP, 80GPM
o. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00
Sub - Total for F 875,153.75
G. Direct Unit Cost (E + F) 962,394.40
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 115,487.33
I. Contractor's Profit (CP) 8% of G 76,991.55
J. Value Added Tax (VAT) 5% of (G + H + I) 57,743.66
K. Total Unit Cost (G + H + I + J) 1,212,616.94

* Please Check the Summation of Sub-Total A, B,


and F
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL-3 Septic Vault Type E


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 44.50 91.41 4,067.75


b. Skilled Laborer 2 44.50 66.06 5,879.34
c. Unskilled Laborer 4 44.50 50.86 9,053.08

Sub - Total for A 19,000.17

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 1,900.02

Sub - Total for B 1,900.02


C. Total (A + B) 20,900.18
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 20,900.18

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 11.01 3,475.00 38,259.75


b. Reinforcement Steel Bars kgs 790.00 31.00 24,490.00
c. Plaster Finish m2 107.00 84.25 9,014.75
d. Cement-Base Waterproofing-Sahara bags 259.00 45.00 11,655.00
e.6" CHB m2 6.00 122.50 735.00
f. 4"CHB m2 3.00 101.38 304.13
-
-

Sub - Total for F 84,458.63


G. Direct Unit Cost (E + F) 105,358.81
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 12,643.06
I. Contractor's Profit (CP) 8% of G 8,428.70
J. Value Added Tax (VAT) 5% of (G + H + I) 6,321.53
K. Total Unit Cost (G + H + I + J) 132,752.10
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(6)b1 Catch Basin -1


Unit of Measurement : ea
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 91.41 91.41


b. Skilled Laborer 1 1.00 66.06 66.06
c. Unskilled Laborer 1 1.00 50.86 50.86

Sub - Total for A 208.33

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost) 20.83

Sub - Total for B 20.83


C. Total (A + B) 229.16
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D) 229.16

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete m3 0.07 3,475.00 243.25


b.Reinforcement kgs 8.63 31.00 267.53
c.Masonry m2 0.80 101.38 81.10
d. Finishing Works m2 0.18 84.25 14.83
-

Sub - Total for F 606.71


G. Direct Unit Cost (E + F) 835.87
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 100.30
I. Contractor's Profit (CP) 8% of G 66.87
J. Value Added Tax (VAT) 5% of (G + H + I) 50.15
K. Total Unit Cost (G + H + I + J) 1,053.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 9.00 91.41 822.69


b. Skilled Laborer 1 11.00 66.06 726.66
c. Unskilled Laborer 1 11.00 50.86 559.46

Sub - Total for A 2,108.81

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 210.88

Sub - Total for B 210.88


C. Total (A + B) 2,319.69
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 2,319.69

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 95.00 69.00 6,555.00


b. 25mmØ PVC conduit length 2.00 92.00 184.00
c. 32mmØ RSC conduit length 4.00 883.75 3,535.00
d. 20mmØ PVC adpater pc 190.00 8.00 1,520.00
e. 25mmØ PVC adapter pc 2.00 14.00 28.00
f. 20mmØ locknut and bushing pr 190.00 8.00 1,520.00
c. 32mmØ RSC elbow pr 2.00 320.00 640.00
h. 25mmØ locknut and bushing pr 2.00 14.00 28.00
i. 20mmØ liquidtight flexible metal conduit m 3.00 20.00 60.00
j. 20mmØ connector pc 2.00 10.00 20.00
k. Ulitiity box, deep type pc 35 30.00 1,050.00
l. junction box, deep type pc 40 31.00 1,240.00
m.32mmØ entrance cap pc 1 243.20 243.20
n. 16mmØx2.4m ground rod pc 2 1,200.00 2,400.00

Sub - Total for F 19,023.20


G. Direct Unit Cost (E + F) 21,342.89
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,561.15
I. Contractor's Profit (CP) 8% of G 1,707.43
J. Value Added Tax (VAT) 5% of (G + H + I) 1,280.57
K. Total Unit Cost (G + H + I + J) 26,892.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 9.00 91.41 822.69


b. Skilled Laborer 1 22.00 66.06 1,453.32
c. Unskilled Laborer 1 22.00 50.86 1,118.92

Sub - Total for A 3,394.93

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 339.49

Sub - Total for B 339.49


C. Total (A + B) 3,734.42
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 3,734.42

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3.5mm2 THHN wire,stranded m 640.00 23.00 14,720.00


b. 5.5mm2 THHN wire,stranded m 18.00 24.00 432.00
c. 22.0mm2 THHN, wire, stranded m 24.00 156.00 3,744.00
d. 2.0mm2 TW wire, stranded m 48.00 24.00 1,152.00
e. 3.5mm2 TW wire, stranded m 320.00 23.00 7,360.00
f. 5.5mm2 TW wire stranded m 33.00 24.00 792.00
g. 8.0mm2 TW wire stranded m 12.00 65.00 780.00
h. one gang switch set 7.00 92.00 644.00
i. two gang switch set 5.00 126.00 630.00
j. three way switch set 6.00 145.00 870.00
k. Duplex C.O. grounding type, 15A, 250V set 4.00 330.00 1,320.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 2.00 420.00 840.00

m. KWHR meter set 1.00 2,200.00 2,200.00


n. Tape, bolt&nut, mica tube, terminal lugs, JB lot 1.00 1,774.20 1,774.20
cover clamps, screw and anchors

Sub - Total for F 37,258.20


G. Direct Unit Cost (E + F) 40,992.62
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,919.11
I. Contractor's Profit (CP) 8% of G 3,279.41
J. Value Added Tax (VAT) 5% of (G + H + I) 2,459.56
K. Total Unit Cost (G + H + I + J) 51,650.70
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards
Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 7.00 91.41 639.87


b. Skilled Laborer 1 7.00 66.06 462.42
c. Unskilled Laborer 2 7.00 50.86 712.04

Sub - Total for A 1,814.33

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 181.43

Sub - Total for B 181.43


C. Total (A + B) 1,995.76
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 1,995.76

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

LPA - Flush Mounted, NEMA 1 Enclosure w/ Ground Ter set 1.00 14,790.10 14,790.10
Main: 70at, 100af, 2p, 240v ,18KAIC
Branches: 3 - 15at, 50af, 2p, 240v
4 - 20at, 50af, 2p, 240v
2 - 30at, 50af, 2p, 240v
1 - 30at, 50af, 2p, 240v

40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
Sub - Total for F 18,390.10
G. Direct Unit Cost (E + F) 20,385.86
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,446.30
I. Contractor's Profit (CP) 8% of G 1,630.87
J. Value Added Tax (VAT) 5% of (G + H + I) 1,223.15
K. Total Unit Cost (G + H + I + J) 25,686.19
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 9.00 91.41 822.69


b. Skilled Laborer 1 9.00 66.06 594.54
c. Unskilled Laborer 2 9.00 50.86 915.48

Sub - Total for A 2,332.71

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 233.27

Sub - Total for B 233.27


C. Total (A + B) 2,565.98
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 2,565.98

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture, box type set 4.00 723.00 2,892.00


b. 2 x 36 watts FL fixture box type w/ canopy base set 8.00 1,173.00 9,384.00
and stem set -
c. 1 x 36 watts FL fixture box type. set 9.00 381.00 3,429.00
d. 1 - 18 watts CFL w/ medium base keyless type set 9.00 320.00 2,880.00
porcelain
e. wall fanreceptacle
w/ control switch set 4.00 1,200.00 4,800.00

Sub - Total for F 23,385.00


G. Direct Unit Cost (E + F) 25,950.98
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,114.12
I. Contractor's Profit (CP) 8% of G 2,076.08
J. Value Added Tax (VAT) 5% of (G + H + I) 1,557.06
K. Total Unit Cost (G + H + I + J) 32,698.24
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

b. Skilled Laborer 1 24.00 66.06 1,585.44


c. Unskilled Laborer 1 24.00 50.86 1,220.64

Sub - Total for A 2,806.08

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 280.61

Sub - Total for B 280.61


C. Total (A + B) 3,086.69
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,086.69

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Manual Pull Switch set 2.00 1,250.00 2,500.00
c. Bell, Vibrating Type set 2.00 1,300.00 2,600.00

Sub - Total for F 18,990.00


G. Direct Unit Cost (E + F) 22,076.69
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,649.20
I. Contractor's Profit (CP) 8% of G 1,766.14
J. Value Added Tax (VAT) 5% of (G + H + I) 1,324.60
K. Total Unit Cost (G + H + I + J) 27,816.63
ESTIMATE SYSTEM:

PROJECT : MULTI-PURPOSE
LOCATION : SIMPATUYO

EXCAVATION OF FOOTING EMBANKMENT


EXCAVATION Dimension Qty. Excavation EMBANKMENT
Member WIDTH LENGTH HEIGHT per Volume Member
Description (m) (m) (m) Unit (cu.m.) Description
C1-F1 1.50 1.50 1.25 6.00 16.88
C1-F1 1.50 1.50 2.25 2.00 10.13
FTB-1 0.25 5.15 0.30 4.00 1.55
STAIR FOOTING 0.50 1.20 0.70 1.00 0.42

0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00
0.00
0.00
0.00
0.00
0.00
0.00

Volume of footing cu.m


Total Volume of Exacavation 28.97 cu.m
Embankment from structure Excavation 0.00 cu.m
Embankment from common borrow 22.50 cu.m

EMBANKMEN
EMBANKMENT
Member
Description
C1-F1
C1-F1
EMBANKMENT from structure excavation GRAVEL FILL
Dimension Qty. EMBANKMENT EMBANKMENT Dimension
WIDTH LENGTH HEIGHT per Volume Member WIDTH
(m) (m) (m) Unit (cu.m.) Description (m)
F1 1.50
tie beam 1.50
WF 0.40
WF 0.40
WF 0.40
WF 0.40
WF 0.40
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00
0.00
0.00
TOTAL 0.00

EMBANKMENT from common borrow


Dimension Qty. EMBANKMENT
WIDTH LENGTH HEIGHT per Volume
(m) (m) (m) Unit (cu.m.)
1.50 1.50 1.00 6.00 13.50
1.50 1.50 2.00 2.00 9.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL 22.50
GRAVEL FILL
Dimension Qty. EMBANKMENT
LENGTH HEIGHT per Volume
(m) (m) Unit (cu.m.)
1.50 0.10 6.00 1.35
1.50 0.10 2.00 0.45
1.90 0.10 1.00 0.08
0.80 0.10 1.00 0.03
5.00 0.10 1.00 0.20
5.00 0.10 1.00 0.20
2.90 0.10 1.00 0.12
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00
0.00
0.00
TOTAL 2.42
Total Volume of Footing 4.50 cu.m.
AGGREGATE, crushed gravel 1" 5.00 cu.m.
AGGREGATE, washed sand 3.00 cu.m.
CEMENT, Portland ordinary @ 40kg. 41.00 bag
REBAR, 10mm x 6.0m grade 33 - lg.
REBAR, 10mm x 9.0m grade 33 - lg.
REBAR, 12mm x 6.0m grade 33 - lg.
REBAR, 12mm x 9.0m grade 33 - lg.
REBAR, 16mm x 6.0m grade 40 37.00 lg.
REBAR, 16mm x 9.0m grade 40 - lg.
REBAR, 20mm x 6.0m grade 40 - lg.
REBAR, 20mm x 9.0m grade 40 - lg.
REBAR, 25mm x 6.0m grade 40 - lg.
REBAR, 25mm x 9.0m grade 40 - lg.
WIRE, GI tie #16 5.00 kg.
Total Volume of Colums 3.02 cu.m.
Total Lateral Surface Area 40.32 sq.m.
Total Length of Columns 33.60 m.
No. of cycle of Forms 3.00 cycles
No. of cycle of Scaffoldings 5.00 cycles
AGGREGATE, crushed gravel 3/4" 4.00 cu.m.
AGGREGATE, washed sand 3.00 cu.m.
CEMENT, Portland ordinary @ 40kg. 31.00 bag
CEMENT, Masonry @ 40kg. 5.00

REBAR, 6mm x 6.0m grade 33 - lg.


REBAR, 10mm x 6.0m grade 33 68.00 lg.
REBAR, 10mm x 9.0m grade 33 - lg.
REBAR, 12mm x 6.0m grade 33 - lg.
REBAR, 12mm x 9.0m grade 33 - lg.
REBAR, 16mm x 6.0m grade 40 64.00 lg.
REBAR, 16mm x 9.0m grade 40 - lg.
REBAR, 20mm x 6.0m grade 40 - lg.
REBAR, 20mm x 9.0m grade 40 - lg.
REBAR, 25mm x 6.0m grade 40 - lg.
REBAR, 25mm x 9.0m grade 40 - lg.
SPACER, PVC bar #234 68.00 pc.
WIRE, GI tie #16 12.00 kg.
FORMWORKS, Marine plywood 1/2" x 4' x 8' 5.00 sht.
FORMWORK, good lumber 2" x 2" x 12' 33.00 pc.
SCAFFOLD, good lumber 2" x 4" x 12' 32.00 pc.
NAIL, CWN 1-1/2" 2.00 kg.
NAIL, CWN 2" 2.00 kg.
NAIL, CWN 3" 7.00 kg.
NAIL, CWN 4" 4.00 kg.
RELEASING AGENT, formoil Houston 1.00 gal.
SLABS Dimension Qty. Concrete Surface Main Bar (Short Direction)
Member Width Length Thk. per Volume Area Cut Qty. Bar-Dia. Bar-lg.
Description (m) (m) (m) Unit (cu.m.) (sq.m.) (pc.) (mm) (m)
ON-FILL
SOF 5.00 5.50 0.10 1 2.75 27.50 14 10 6
ramp 1.20 5.50 0.10 1 0.66 6.60 4 10 6
ramp 1.20 0.70 0.10 1 0.08 0.84 4 10 6
step 0.30 4.00 0.10 1 0.12 1.20 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0.00 0.00 0 0 0
ELEVATED
ELEC SLAB 5.00 5.50 0.12 1 3.30 27.50 21 10 6
STAIR SLAB 1.20 2.25 0.10 1 0.27 2.70 5 10 6
STAIR 1.00 2.20 0.18 1 0.40 2.20 15 12 6
STAIR 1.00 2.70 0.18 1 0.49 2.70 15 12 6
canopy 0.40 1.90 0.10 2 0.15 1.52 4 10 6
canopy door 1.00 1.94 0.15 1 0.29 1.94 6 10 6
0.00 0.00 0.00 0 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0 0 0

Total Volume of Slab on Fill 3.61 cu.m.


Total Volume of Elev. Slabs 4.89 cu.m.
Total Area of Elev. Slab 38.56 sq.m. forms
No. of cycle of Forms 3.00 cycles
No. of cycle of Scaffoldings 5.00 cycles
AGGREGATE, crushed gravel 1" 4.00 cu.m.
AGGREGATE, crushed gravel 3/4" 5.00 cu.m.
AGGREGATE, washed sand 6.00 cu.m.
CEMENT, Portland ordinary @ 40kg. 90.00 bag
FIBRIN, micro-fiber element @ 40g. 47.00 sachet
REBAR, 6mm x 6.0m plain - lg. Weight of RSB
REBAR, 10mm x 6.0m grade 33 163.00 lg. 606.36
REBAR, 10mm x 9.0m grade 33 - lg. - kg
REBAR, 12mm x 6.0m grade 33 19.00 lg. 101.46 kg
REBAR, 12mm x 9.0m grade 33 - lg. - kg
REBAR, 16mm x 6.0m grade 40 - lg. - kg
REBAR, 16mm x 9.0m grade 40 - lg. - kg
REBAR, 20mm x 6.0m grade 40 - lg. - kg
REBAR, 20mm x 9.0m grade 40 - lg. - kg
REBAR, 25mm x 6.0m grade 40 - lg. - kg
REBAR, 25mm x 9.0m grade 40 - lg. - kg
SPACER, PVC bar #232 39.00 pc.
WIRE, GI tie #16 10.00 kg.
FORMWORKS, Marine plywood 1/2" x 4' x 8' 5.00 sht.
SCAFFOLD, good lumber 2" x 4" x 12' 20.00 pc.
NAIL, CWN 1-1/2" 1.00 kg.
NAIL, CWN 3" 4.00 kg.
NAIL, CWN 4" 6.00 kg.
RELEASING AGENT, formoil Houston 2.00 gal.
Weight Of Rebars 707.82 kg.
ain Bar (Short Direction) Main Bar (Long Direction) Temperature Bar (Short Direction)
Cut-lg. Bar-Qty. Cut Qty. Bar-Dia. Bar-lg. Cut-lg. Bar-Qty. Spacing Cut Qty. Bar-Dia.
(m) (lg.) (pc.) (mm) (m) (m) (lg.) (m) (pc.) (mm)

5.51 14.00 10 x 6 15 10 6 5.30 15.00 10 x 6 - 0 0


5.51 4.00 10 x 6 15 10 6 1.30 3.75 10 x 6 - 0 0
0.71 0.50 10 x 6 3 10 6 1.30 0.75 10 x 6 - 0 0
4.01 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0

5.80 21.00 10 x 6 23 10 6 6.00 23.00 10 x 6 - 21 10


2.55 2.50 10 x 6 9 10 6 2.50 4.50 10 x 6 - 5 10
2.50 7.50 12 x 6 17 10 6 1.20 3.40 10 x 6 - 6 10
3.00 7.50 12 x 6 21 10 6 1.20 4.20 10 x 6 - 7 10
2.20 4.00 10 x 6 13 10 6 0.60 2.60 10 x 6 - 0 0
2.24 3.00 10 x 6 15 12 6 1.30 3.75 12 x 6 - 4 10
0.30 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.30 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.30 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
0.30 0.00 0.00 0 0 0 0.00 0.00 0.00 - 0 0
Temperature Bar (Short Direction) Temperature Bar (Long Direction)
Bar-lg. Cut-lg. Bar-Qty. Spacing Cut Qty. Bar-Dia. Bar-lg. Cut-lg. Bar-Qty.
(m) (m) (lg.) (m) (pc.) (mm) (m) (m) (lg.)

0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00


0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00

6 5.80 21.00 10 x 6 - 23 10 6 6.00 23.00 10 x 6


6 2.55 2.50 10 x 6 - 9 10 6 2.50 4.50 10 x 6
6 0.75 0.75 10 x 6 - 0 0 0 0.00 0.00 0.00
6 0.75 0.88 10 x 6 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
6 2.00 1.33 10 x 6 - 15 10 6 1.00 2.50 10 x 6
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
0 0.00 0.00 0.00 - 0 0 0 0.00 0.00 0.00
MORTAR BINDER & FILLER Masonry Rebar
Member Vert. Hor. Unit Area CHB Cement Sand Grv.3/8" Bar-Qty. Tie Wire
Description (m) (m) Qty. (sq.m.) Qty. Size (bag) (cu.m.) (cu.m.) (lg.) (kg.)
SOUTH 3.55 21.80 1 57.99 740.00 0 0.00 0.00 0.00 0.00 0 0.00

EAST 3.55 8.53 1 23.73 303.00 0 0.00 0.00 0.00 0.00 0 0.00
NORTH 3.55 26.37 1 75.15 959.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00
WEST 3.55 8.53 1 30.28 387.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
PHARMACY 3.55 5.20 1 18.46 236.00 0 0.00 0.00 0.00 0.00 0 0.00
3.55 3.54 1 10.76 138.00 0 0.00 0.00 0.00 0.00 0 0.00
STOCK ROOM 3.55 3.54 1 10.76 138.00 0 0.00 0.00 0.00 0.00 0 0.00
3.55 3.42 1 12.14 155.00 0 0.00 0.00 0.00 0.00 0 0.00
3.55 1.50 1 5.33
NUTRITION ROOM 3.55 8.53 1 28.40 363.00 0 0.00 0.00 0.00 0.00 0 0.00
DENTAL ROOM 3.55 8.53 1 28.76 367.00 0 0.00 0.00 0.00 0.00 0 0.00
1.60 2.40 1 3.84 49.00 4" 1.80 0.24 0.27 1.60 10 x 9 0.12
CR 3.55 2.60 1 9.23 118.00 0 0.00 0.00 0.00 0.00 0 0.00
3.55 2.40 1 7.27 93.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
CHB 100MM THCK
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
0.00 0.00 0 0.00 0.00 0 0.00 0.00 0.00 0.00 0 0.00
Glazed Tiles and Trims Unglazed Tiles
Dimesion(m) Dimesion(m)
Location QTY Area Location QTY Area
L W/h L W/h
cr wall rear 0 0 0 0 cr floor 0 0 0 0
cr wall L&R 0 0 0 0
cr wall F 0 0 0 0

total 0 total 0
LUMBER Area of Ceiling
Description
Quantity Unit Exterior Interior
Compute & Enter Area here >> 68.76 229.94
102.00 sht. CEIL. PANEL, Flexboard 4.5mm x 4' x 8' 24.00 78.00
420.00 bd.ft. CEIL. FRAME, aptg. trd. 70pc. 2" x 3" x 12' 16.00 54.00
1,224.00 bd.ft. CEIL. JOIST, aptg. trd. 306pc. 2" x 2" x 12' 72.00 234.00
378.00 bd.ft. CEIL. PLATE, aptg. trd. 63pc. 2" x 3" x 12' 15.00 48.00
104.00 bd.ft. CEIL. HANGER, aptg. trd. 26pc. 2" x 2" x 12' 6.00 20.00
7.00 sht. FACIA PANEL, Flexboard 4.5mm x 4' x 8' - -
168.00 bd.ft. FACIA FRAME, aptg. trd. 42pc. 2" x 2" x 12' - -
0.00 sht. WALL PANEL, Flexboard 6mm x 4' x 8' - -
0.00 sht. WALL PANEL, Flexboard 9.0mm x 4' x 8' - -
0.00 bd.ft. WALL STUD, aptg. trd. 0pc. 2" x 4" x 12' - -
3.00 4-lt. WOOD PROTECTANT, coaltar Tru-coat 0.62 1.98
7.00 100ml. WOOD PROTECTANT, Cislin or Solig.= 21 gal. 1.53 5.11
10.00 kg. NAIL, Flexboard 1" 2.16 7.02
18.00 kg. NAIL, CWN 1-1/2" 3.98 13.02
11.00 kg. NAIL, CWN 2" 2.26 7.35
8.00 kg. NAIL, CWN 3" 1.63 5.31
4.00 kg. NAIL, CWN 4" 0.75 2.45
Windows(Steel casement)
Dimensions
Description QTY Area(m²)
L (m) H(m)
w-1 1.60 1.20 3.00 5.76
W-2 1.20 1.20 1.00 1.44
0
0
0
0
0
0
0
0
0
0
0
0
total 7.2
BEAMS Dimension Qty. Concrete Surface Total Main Bar
Member Width Depth Length per Volume Area Length Cut Qty. Bar-Dia. Bar-lg.
Description (m) (m) (m) Unit (cu.m.) (sq.m.) (m) (pc.) (mm) (m)
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
TIE BEAMS
TIE BEAM 0.20 0.30 5.15 4 1.24 12.36 20.60 0 0 0
TIE BEAM 0.20 0.30 2.10 4 0.50 5.04 8.40 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0
0.00 0.00 0.00 0 0.00 0.00 0.00 0 0 0

Total Volume of Beams 1.74 cu.m.


Total Volume of Roof/ Beams - cu.m.
Total Volume of Tie Beams 1.74 cu.m.
Total Lateral Surface Area - sq.m. FORMS
area to be plastered 17.40 sq.m.
Total Length of Beams 29.00 m.
No. of cycle of Forms 3.00 cycles
No. of cycle of Scaffoldings 5.00 cycles
AGGREGATE, crushed gravel 3/4" 2.00 cu.m.
AGGREGATE, washed sand 2.00 cu.m.
CEMENT, Portland ordinary @ 40kg. 16.00 bag 15.66 bags
CEMENT, masonry @ 40kg. - bag - bags
Weight of RSB
REBAR, 6mm x 6.0m plain - lg. - kg
REBAR, 10mm x 6.0m grade 33 - lg. - kg
REBAR, 10mm x 9.0m grade 33 - lg. - kg
REBAR, 12mm x 6.0m grade 33 - lg. - kg
REBAR, 12mm x 9.0m grade 33 - lg. - kg
REBAR, 16mm x 6.0m grade 40 - lg. - kg
REBAR, 16mm x 9.0m grade 40 - lg. - kg
REBAR, 20mm x 6.0m grade 40 - lg. - kg
REBAR, 20mm x 9.0m grade 40 - lg. - kg
REBAR, 25mm x 6.0m grade 40 - lg. - kg
REBAR, 25mm x 9.0m grade 40 - lg. - kg
SPACER, PVC bar #232 39.00 pc.
WIRE, GI tie #16 - kg.
FORMWORKS, Marine plywood 1/2" x 4' x 8' - sht.
FORMWORK, good lumber 2" x 2" x 12' - pc.
SCAFFOLD, good lumber 2" x 4" x 12' 6.50 pc.
NAIL, CWN 1-1/2" - kg.
NAIL, CWN 2" - kg.
NAIL, CWN 3" 2.00 kg.
NAIL, CWN 4" 1.00 kg.
RELEASING AGENT, formoil Houston - gal.
Weight of Rebar - kg.
Main Bar Extra Bars Closed Stirrups
Cut-lg. Bar-Qty. Cut Qty. Bar-Dia. Bar-lg. Cut-lg. Bar-Qty. Spacing Cut Qty. Bar-Dia. Bar-lg.
(m) (lg.) (pc.) (mm) (m) (m) (lg.) (m) (pc.) (mm) (m)
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0.00 0.00 0.000
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0

0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0


0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0
0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.000 0 0 0

Qty. Space Equiv.


1 0.05 0.10
2 0.10 0.40
0.00

0.00
0 0.00 0.00
6 0.125 8
1 2.00 0.50 0.25 Bal.

0
Closed Stirrups Cut Bars/Open Stirrups
Cut-lg. Bar-Qty. Spacing Cut Qty. Bar-Dia. Bar-lg. Cut-lg. Bar-Qty.
(m) (lg.) (m) (pc.) (mm) (m) (m) (lg.)

0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00


0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00

0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00


0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
0.00 0.00 0.00 0.000 0 0 0 0.00 0.00 0.00
Republic of the Philippines
Province of Cagayan
MUNICIPALITY OF STA. TERESITA
OFFICE OF THE MUNICIPAL ENGINEER/BUILDING OFFICIAL
November 20, 2020
Date
PROGRAM OF WORK BUDGET/COST FOR PUBLIC
WORK USING EQUIPT. LABOR TECHNOLOGY

Name of Project : INSTALLATION OF GYM SHADE (PHASE III) Type of Project:


Project Length :
Project Number : No. of Culverts :
Location : BRGY. CENTRO EAST, STA. TERESITA, CAGAYAN RCCP :
Appropriation : P 68,000.00 No. of Span/Storey :
Source of Fund : Time for Completion :
Starting Date :
DESCRIPTION OF WORK % OF LABOR/EQUIPTMENT REQUIREMENTSNEEDED AVAILABLE
TO BE DONE TOTAL DESCRIPTION

ITEM D E S C R I P T I O N UNIT QUANTITY ESTIMATED COST OF WORKS


NO. UNIT COST
I ROOFING WORKS L.S ALL 68,000.00 68,000.00

BREAKDOWN OF ESTIMATED COST % OF A. DIRECT & INDIRECT COST P 68,000.00


EXPENDITURES Pesos TOTAL B. COST OF ENG'G. 3%
1.Labor-skilled(Mandays) P 17,629.63 26% C. QUALITY CONTROL
2.Materials 50,370.37 74% D. ADVERTISEMENT 1%
3.Hand-tools E. TOTAL ESTIMATED COST P 68,000.00
4.Rental Equipment
5.POL & Maintenance
Direct Cost - Total P 68,000.00 100%

PREPARED BY:

ENGR. LIEZEL S. UDAUNDO


OIC-Municipal Engineer

APPROVED BY: NOTED BY:

ENGR. WINIFRED P. DE GRACIA ATTY. RODRIGO P. DE GRACIA, CESE


Punong barangay Municipal Mayor
BACKSTAGE

90
SIA HARDWARE

ITEM NO. DESCRIPTION UNIT QUANTITY


1 CONCRETE WORKS
Portland Cement, 40kg bag 1
16mm Ø RSB x 6m long (Grade 40) pc 1
12mm Ø RSB x 6m long (Grade 40) pc 1
10mm Ø RSB x 6m long (Grade 40) pc 1
9mm Ø RSB x 6m long (Grade 40) pc 1
G1 , (6 cu.m) load 1
S1 , (6 cu.m) load 1
Mixed Gravel Sand , (6 cu.m) load 1
1/4" Marine Plywood pc 1
C.W.N all Sizes kg 1
#16 Annealed tie Wire kg 1
PRICE

245 PHP
310 PHP
175 PHP
118 PHP
95 PHP
1800 PHP
1800 PHP
1800 PHP
350 PHP
70 PHP
70 PHP
Soil Poisoning – Termicide
Gravel
Wash Sand
Portland Cement, 40kg
Pozzolan Cement, 40kg
Steel Bars
 10mm Diameter Deformed Bars
 12mm Diameter Deformed Bars
 16mm Diameter Deformed Bars
 20mm Diameter Deformed Bars
 #16 G.I. Tie Wire
Formworks
 2 x 3 x 10′ Coco lumber
 2 x 4 x 10 Coco lumber
 1/2″ x 4′ x 8′ Plywood
 6mm thk. Lawanit board
 6mm thk. Ordinary Plywood
 1″x2″x8′ Wood
 2″x2″x8′ Wood
 2″x3″x8′ Wood
 2″x4″x8′ Wood
Liter
cu.m
cu.m
Bag
Bag

pc
pc
pc
pc
kg

pc
pc
pc
pc
pc
pc
pc
pc
pc
       325.00
    1,310.00
    1,435.00
       259.00
       261.00

       156.00
       221.00
       392.00
       642.00
         16.00

       270.00
       270.00
       656.00
       201.00
       323.00
         75.00
         95.00
         105.00
         125.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 19.00 91.41 1,736.79


b. Skilled Laborer 1 60.00 66.06 3,963.60
c. Unskilled Laborer 1 60.00 50.86 3,051.60

Sub - Total for A 8,751.99

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 875.20

Sub - Total for B 875.20


C. Total (A + B) 9,627.19
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 9,627.19

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 175.00 69.00 12,075.00


b. 25mmØ PVC conduit length 4.00 92.00 368.00
c. 32mmØ PVC conduit length 2.00 120.00 240.00
d. 40mmØ RSC conduit length 4.00 1,069.50 4,278.00
e. 20mmØ PVC adpater pc 350.00 8.00 2,800.00
f. 25mmØ PVC adapter pc 4.00 14.00 56.00
g. 32mmØ PVC adapter pc 2.00 16.00 32.00
h. 20mmØ locknut and bushing pr 350.00 8.00 2,800.00
d. 40mmØ RSC elbow pr 4.00 289.80 1,159.20
j. 25mmØ locknut and bushing pr 4.00 14.00 56.00
k. 20mmØ liquidtight flexible metal conduit m 3.00 20.00 60.00
l. 20mmØ connector pc 2.00 10.00 20.00
m. Ulitiity box, deep type pc 60.00 30.00 1,800.00
n. junction box, deep type pc 80.00 31.00 2,480.00
o. 40mmØ entrance cap pc 1.00 304.00 304.00
p. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for F 30,928.20


G. Direct Unit Cost (E + F) 40,555.39
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,866.65
I. Contractor's Profit (CP) 8% of G 3,244.43
J. Value Added Tax (VAT) 5% of (G + H + I) 2,433.32
K. Total Unit Cost (G + H + I + J) 51,099.79
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 26.00 91.41 2,376.66


b. Skilled Laborer 1 40.00 66.06 2,642.40
c. Unskilled Laborer 1 40.00 50.86 2,034.40

Sub - Total for A 7,053.46

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 705.35

Sub - Total for B 705.35


C. Total (A + B) 7,758.81
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 7,758.81

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3.5mm2 THHN wire,stranded m 1100.00 23.00 25,300.00


b. 5.5mm2 THHN wire,stranded m 60.00 24.00 1,440.00
c.8.0mm2 THHN, wire, stranded m 6.00 65.00 390.00
c.38.0mm2 THHN, wire, stranded m 24.00 292.60 7,022.40
d.2.0mm2 TW wire, stranded m 72.00 24.00 1,728.00
e. 3.5mm2 TW wire, stranded m 550.00 23.00 12,650.00
f.5.5mm2 TW wire stranded m 18.00 24.00 432.00
g.8.0mm2 TW wire stranded m 24.00 65.00 1,560.00
h. one gang switch set 11.00 92.00 1,012.00
i. two gang switch set 9.00 126.00 1,134.00
j. three way switch set 4.00 145.00 580.00
j. 2- gang ,three way switch set 4.00 175.00 700.00
k. Duplex C.O. grounding type, 15A, 250V set 12.00 330.00 3,960.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 2.00 420.00 840.00
-
m. KWHR meter set 1.00 2,200.00 2,200.00
n. Tape, bolt&nut, mica tube, terminal lugs, JB lot 1.00 3,047.42 3,047.42
cover clamps, screw and anchors

Sub - Total for F 63,995.82


G. Direct Unit Cost (E + F) 71,754.63
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 8,610.56
I. Contractor's Profit (CP) 8% of G 5,740.37
J. Value Added Tax (VAT) 5% of (G + H + I) 4,305.28
K. Total Unit Cost (G + H + I + J) 90,410.83
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards
Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 11.00 91.41 1,005.51


b. Skilled Laborer 1 11.00 66.06 726.66
c. Unskilled Laborer 2 11.00 50.86 1,118.92

Sub - Total for A 2,851.09

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 285.11

Sub - Total for B 285.11


C. Total (A + B) 3,136.20
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,136.20

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MDP set 1.00 8,800.00 8,800.00


Main: 100at, 100af, 2p, 240v, 18 KAIC
Br.: 1 - 30at, 50af, 2p, 240v
1 - 40at, 50af, 2p, 240v
1 - 50at, 50af, 2p, 240v

a. LPA set 1.00 14,255.00 14,255.00


Main: 50at, 50af, 2p, 240v (lugs only)
Br.: 2 - 15at, 50af, 2p, 240v
5 - 20at, 50af, 2p, 240v
1 - 30at, 50af, 2p, 240v

a. LPB set 1.00 9,800.00 9,800.00


Main: 40at, 50af, 2p, 240v, 10KAIC
Br.: 2 - 15at, 50af, 2p, 240v
4 - 20at, 50af, 2p, 240v

40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
Sub - Total for F 36,455.00
G. Direct Unit Cost (E + F) 39,591.20
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 4,750.94
I. Contractor's Profit (CP) 8% of G 3,167.30
J. Value Added Tax (VAT) 5% of (G + H + I) 2,375.47
K. Total Unit Cost (G + H + I + J) 49,884.91
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 19.00 91.41 1,736.79


b. Skilled Laborer 1 19.00 66.06 1,255.14
c. Unskilled Laborer 2 19.00 50.86 1,932.68

Sub - Total for A 4,924.61

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 492.46

Sub - Total for B 492.46


C. Total (A + B) 5,417.07
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 5,417.07

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture, box type set 12.00 723.00 8,676.00


b. 2 x 36 watts FL fixture box type w/ canopy base set 24.00 1,173.00 28,152.00
and stem -
c. 1 x 36 watts FL fixture box type. set 17.00 381.00 6,477.00
d. 1 - 18 watts CFL w/ medium base keyless type set 9.00 320.00 2,880.00
porcelain
e. wall fanreceptacle
w/ control switch set 12.00 1,200.00 14,400.00

Sub - Total for F 60,585.00


G. Direct Unit Cost (E + F) 66,002.07
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 7,920.25
I. Contractor's Profit (CP) 8% of G 5,280.17
J. Value Added Tax (VAT) 5% of (G + H + I) 3,960.12
K. Total Unit Cost (G + H + I + J) 83,162.61
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

b. Skilled Laborer 1 24.00 66.06 1,585.44


c. Unskilled Laborer 1 24.00 50.86 1,220.64

Sub - Total for A 2,806.08

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 280.61

Sub - Total for B 280.61


C. Total (A + B) 3,086.69
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,086.69

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Manual Pull Switch set 2.00 1,250.00 2,500.00
c. Bell, Vibrating Type set 2.00 1,300.00 2,600.00

Sub - Total for F 18,990.00


G. Direct Unit Cost (E + F) 22,076.69
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 2,649.20
I. Contractor's Profit (CP) 8% of G 1,766.14
J. Value Added Tax (VAT) 5% of (G + H + I) 1,324.60
K. Total Unit Cost (G + H + I + J) 27,816.63
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 40.00 91.41 3,656.40


b. Skilled Laborer 1 68.00 66.06 4,492.08
c. Unskilled Laborer 1 68.00 50.86 3,458.48

Sub - Total for A 11,606.96

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,160.70

Sub - Total for B 1,160.70


C. Total (A + B) 12,767.66
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 12,767.66

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 310.00 69.00 21,390.00


b. 25mmØ PVC conduit length 4.00 92.00 368.00
c. 32mmØ PVC conduit length 12.00 120.00 1,440.00
d. 65mmØ RSC conduit length 8.00 2,233.35 17,866.80
d. 90mmØ RSC conduit length 4.00 3,580.46 14,321.84
d. 32mmØ RSC elbow pc 2.00 320.00 640.00
e. 20mmØ PVC adpater pc 500.00 8.00 4,000.00
f. 25mmØ PVC adapter pc 4.00 14.00 56.00
g. 32mmØ PVC adapter pc 2.00 16.00 32.00
h. 20mmØ locknut and bushing pr 500.00 8.00 4,000.00
j. 25mmØ locknut and bushing pr 2.00 14.00 28.00
j. 32mmØ locknut and bushing pr 2.00 16.00 32.00
k. 20mmØ liquidtight flexible metal conduit pc 3.00 20.00 60.00
l. 20mmØ connector m 2.00 10.00 20.00
m. Ulitiity box, deep type pc 85.00 30.00 2,550.00
n. junction box, deep type pc 115.00 31.00 3,565.00
o. 90mmØ entrance cap pc 1.00 684.00 684.00
p. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00
Sub - Total for F 73,453.64
G. Direct Unit Cost (E + F) 86,221.30
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 10,346.56
I. Contractor's Profit (CP) 8% of G 6,897.70
J. Value Added Tax (VAT) 5% of (G + H + I) 5,173.28
K. Total Unit Cost (G + H + I + J) 108,638.83
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 45.00 91.41 4,113.45


b. Skilled Laborer 1 65.00 66.06 4,293.90
c. Unskilled Laborer 1 65.00 50.86 3,305.90

Sub - Total for A 11,713.25

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,171.33

Sub - Total for B 1,171.33


C. Total (A + B) 12,884.58
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 12,884.58

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3.5mm2 THHN wire,stranded m 1940.00 23.00 44,620.00


b. 5.5mm2 THHN wire,stranded m 60.00 24.00 1,440.00
c.14.0mm2 THHN, wire, stranded m 18.00 86.00 1,548.00
c.100.0mm2 THHN, wire, stranded m 14.00 691.00 9,674.00
c.200.0mm2 THHN, wire, stranded m 24.00 1,336.00 32,064.00
d.2.0mm2 TW wire, stranded m 216.00 24.00 5,184.00
e. 3.5mm2 TW wire, stranded m 970.00 23.00 22,310.00
f.5.5mm2 TW wire stranded m 30.00 24.00 720.00
g.8.0mm2 TW wire stranded m 8.00 65.00 520.00
g.22.0mm2 TW wire stranded m 7.00 156.00 1,092.00
g.30.0mm2 TW wire stranded m 12.00 210.00 2,520.00
h. one gang switch set 17.00 92.00 1,564.00
i. two gang switch set 12.00 126.00 1,512.00
j. three way switch set 4.00 145.00 580.00
j. 2- gang ,three way switch set 4.00 175.00 700.00
k. Duplex C.O. grounding type, 15A, 250V set 16.00 330.00 5,280.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 4.00 420.00 1,680.00
-
m. KWHR meter set 1.00 2,200.00 2,200.00
n. Tape, bolt&nut, mica tube, terminal lugs, JB lot 1.00 6,760.40 6,760.40
cover clamps, screw and anchors

Sub - Total for F 141,968.40


G. Direct Unit Cost (E + F) 154,852.98
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 18,582.36
I. Contractor's Profit (CP) 8% of G 12,388.24
J. Value Added Tax (VAT) 5% of (G + H + I) 9,291.18
K. Total Unit Cost (G + H + I + J) 195,114.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards
Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 15.00 91.41 1,371.15


b. Skilled Laborer 1 15.00 66.06 990.90
c. Unskilled Laborer 2 15.00 50.86 1,525.80

Sub - Total for A 3,887.85

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 388.79

Sub - Total for B 388.79


C. Total (A + B) 4,276.64
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 4,276.64

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MDP set 1.00 37,602.50 37,602.50


Main: 500at, 600af, 3p, 240v, 42 KAIC
Br.: 1 - 60at, 100af, 2p, 240v
2 - 50at, 100af, 2p, 240v
1 - 400at, 400af, 3p, 240v

a. LPA set 1.00 14,008.80 14,008.80


Main: 60at, 2p(lugs only)
Br.: 3 - 15at, 50af, 2p, 240v
8 - 20at, 50af, 2p, 240v
1 - 30at, 50af, 2p, 240v

a. LPB set 1.00 14,346.80 14,346.80


Main: 50at, 50af, 2p, 240v, 10KAIC
Br.: 3 - 15at, 50af, 2p, 240v
7 - 20at, 50af, 2p, 240v

FPP set 1.00 46,597.20 46,597.20


Main:400AT,400AF,,240V, 22KAIC, 3p
Br.: 3 - 400at, 100af, 2p
1 - 40at, 100af, 3p
1 - 400at, 400af, 3p

Automatic Transfer switch set 1.00 128,000.00 128,000.00


Main 500AT,600AF,,240V, 42KAIC, 3p
in NEMA 3R Enclosure
40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
Sub - Total for F 244,155.30
G. Direct Unit Cost (E + F) 248,431.94
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 29,811.83
I. Contractor's Profit (CP) 8% of G 19,874.55
J. Value Added Tax (VAT) 5% of (G + H + I) 14,905.92
K. Total Unit Cost (G + H + I + J) 313,024.24
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 26.00 91.41 2,376.66


b. Skilled Laborer 1 26.00 66.06 1,717.56
c. Unskilled Laborer 2 26.00 50.86 2,644.72

Sub - Total for A 6,738.94

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 673.89

Sub - Total for B 673.89


C. Total (A + B) 7,412.83
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 7,412.83

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture, box type set 16.00 723.00 11,568.00


b. 2 x 36 watts FL fixture box type w/ canopy base set 32.00 1,173.00 37,536.00
and stem -
c. 1 x 36 watts FL fixture box type. set 34.00 381.00 12,954.00
d. 1 - 18 watts CFL w/ medium base keyless type set 5.00 320.00 1,600.00
porcelain
e. wall fanreceptacle
w/ control switch set 16.00 1,200.00 19,200.00

Sub - Total for F 82,858.00


G. Direct Unit Cost (E + F) 90,270.83
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 10,832.50
I. Contractor's Profit (CP) 8% of G 7,221.67
J. Value Added Tax (VAT) 5% of (G + H + I) 5,416.25
K. Total Unit Cost (G + H + I + J) 113,741.25
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 31.00 66.06 2,047.86


b. Unskilled Laborer 1 31.00 50.86 1,576.66

Sub - Total for A 3,624.52

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 362.45

Sub - Total for B 362.45


C. Total (A + B) 3,986.97
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,986.97

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Manual Pull Switch set 4.00 1,250.00 5,000.00
c. Bell, Vibrating Type set 4.00 1,300.00 5,200.00

Sub - Total for F 24,090.00


G. Direct Unit Cost (E + F) 28,076.97
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,369.24
I. Contractor's Profit (CP) 8% of G 2,246.16
J. Value Added Tax (VAT) 5% of (G + H + I) 1,684.62
K. Total Unit Cost (G + H + I + J) 35,376.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 44.00 91.41 4,022.04


b. Skilled Laborer 1 76.00 66.06 5,020.56
c. Unskilled Laborer 1 76.00 50.86 3,865.36

Sub - Total for A 12,907.96

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,290.80

Sub - Total for B 1,290.80


C. Total (A + B) 14,198.76
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 14,198.76

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 380.00 69.00 26,220.00


b. 25mmØ PVC conduit length 2.00 92.00 184.00
c. 32mmØ PVC conduit length 3.00 120.00 360.00
d. 65mmØ RSC conduit length 6.00 2,233.35 13,400.10
d. 90mmØ RSC conduit length 4.00 3,580.46 14,321.84
d. 90mmØ RSC elbow pc 2.00 2,348.15 4,696.30
d. 65mmØ RSC elbow pc 2.00 889.45 1,778.90
e. 20mmØ PVC adpater pc 575.00 8.00 4,600.00
f. 25mmØ PVC adapter pc 2.00 14.00 28.00
g. 32mmØ PVC adapter pc 4.00 16.00 64.00
h. 20mmØ locknut and bushing pr 575.00 8.00 4,600.00
j. 25mmØ locknut and bushing pr 4.00 14.00 56.00
j. 32mmØ locknut and bushing pr 2.00 16.00 32.00
k. 20mmØ liquidtight flexible metal conduit pc 3.00 20.00 60.00
l. 20mmØ connector m 2.00 10.00 20.00
m. Ulitiity box, deep type pc 95.00 30.00 2,850.00
n. junction box, deep type pc 135.00 31.00 4,185.00
o. 90mmØ entrance cap pc 1.00 684.00 684.00
p. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00
Sub - Total for F 80,540.14
G. Direct Unit Cost (E + F) 94,738.90
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 11,368.67
I. Contractor's Profit (CP) 8% of G 7,579.11
J. Value Added Tax (VAT) 5% of (G + H + I) 5,684.33
K. Total Unit Cost (G + H + I + J) 119,371.01
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 65.00 91.41 5,941.65


b. Skilled Laborer 1 82.00 66.06 5,416.92
c. Unskilled Laborer 1 82.00 50.86 4,170.52

Sub - Total for A 15,529.09

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,552.91

Sub - Total for B 1,552.91


C. Total (A + B) 17,082.00
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 17,082.00

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3.5mm2 THHN wire,stranded m 2350.00 23.00 54,050.00


b. 8.0mm2 THHN wire,stranded m 12.00 65.00 780.00
c.14.0mm2 THHN, wire, stranded m 6.00 86.00 516.00
c.80.0mm2 THHN, wire, stranded m 24.00 549.89 13,197.24
c.100.0mm2 THHN, wire, stranded m 30.00 691.00 20,730.00
c.200.0mm2 THHN, wire, stranded m 36.00 1,336.00 48,096.00
d.2.0mm2 TW wire, stranded m 264.00 24.00 6,336.00
e. 3.5mm2 TW wire, stranded m 1170.00 23.00 26,910.00
f.5.5mm2 TW wire stranded m 6.00 24.00 144.00
g.8.0mm2 TW wire stranded m 27.00 65.00 1,755.00
g.22.0mm2 TW wire stranded m 10.00 156.00 1,560.00
g.30.0mm2 TW wire stranded m 12.00 210.00 2,520.00
h. one gang switch set 19.00 92.00 1,748.00
i. two gang switch set 14.00 126.00 1,764.00
j. three way switch set 4.00 145.00 580.00
j. 2- gang ,three way switch set 4.00 175.00 700.00
k. Duplex C.O. grounding type, 15A, 250V set 20.00 330.00 6,600.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 6.00 420.00 2,520.00

m. KWHR meter set 1.00 2,200.00 2,200.00


n. Tape, bolt&nut, mica tube, terminal lugs, JB lot 1.00 9,635.31 9,635.31
cover clamps, screw
Suband anchors
- Total for F 202,341.55
G. Direct Unit Cost (E + F) 219,423.55
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 26,330.83
I. Contractor's Profit (CP) 8% of G 17,553.88
J. Value Added Tax (VAT) 5% of (G + H + I) 13,165.41
K. Total Unit Cost (G + H + I + J) 276,473.67
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards
Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor CF
###
a. Construction Foreman 1 24.00 91.41 2,193.84
b. Skilled Laborer 1 24.00 66.06 1,585.44
c. Unskilled Laborer 2 24.00 50.86 2,441.28

Sub - Total for A 6,220.56

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment ###

Minor Tools (10% of Labor Cost) 622.06

Sub - Total for B 622.06


C. Total (A + B) 6,842.62
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 6,842.62

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MDP set 1.00 37,602.50 37,602.50


Main: 500at, 600af, 3p, 240v, 42 KAIC ###
Br.: 1 - 60at, 100af, 2p, 240v ###
2 - 50at, 100af, 2p, 240v ###
1 - 400at, 400af, 3p, 240v ###

a. LPA set 1.00 14,008.80 14,008.80


Main: 60at, 2p(lugs only)
Br.: 3 - 15at, 50af, 2p, 240v ###
8 - 20at, 50af, 2p, 240v ###
1 - 30at, 50af, 2p, 240v ###

a. LPB set 1.00 14,346.80 14,346.80


Main: 50at, 50af, 2p, 240v, 10KAIC 0.00
Br.: 3 - 15at, 50af, 2p, 240v ###
7 - 20at, 50af, 2p, 240v ###

FPP set 1.00 46,597.20 46,597.20


Main:400AT,400AF,,240V, 22KAIC, 3p 0.00
Br.: 3 - 40at, 100af, 2p ###
1 - 40at, 100af, 3p ###
1 - 400at, 400af, 3p ###

Automatic Transfer Switch (ATS) set 1.00 128,000.00 128,000.00


Main:500AT, 600 AF, 3P, 240V, 42 KAIC
in NEMA 2r Closure
40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
###
Sub - Total for F 244,155.30
G. Direct Unit Cost (E + F) 250,997.92
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 30,119.75
I. Contractor's Profit (CP) 8% of G 20,079.83
J. Value Added Tax (VAT) 5% of (G + H + I) 15,059.87
K. Total Unit Cost (G + H + I + J) 316,257.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 31.00 91.41 2,833.71


b. Skilled Laborer 1 31.00 66.06 2,047.86
c. Unskilled Laborer 2 31.00 50.86 3,153.32

Sub - Total for A 8,034.89

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 803.49

Sub - Total for B 803.49


C. Total (A + B) 8,838.38
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 8,838.38

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture, box type set 20.00 723.00 14,460.00


b. 2 x 36 watts FL fixture box type w/ canopy base set 40.00 1,173.00 46,920.00
and stem
c. 1 x 36 watts FL fixture box type. set 38.00 381.00 14,478.00
d. 1 - 18 watts CFL w/ medium base keyless type set 5.00 320.00 1,600.00
porcelain
e. wall fanreceptacle
w/ control switch set 20.00 1,200.00 24,000.00

Sub - Total for F 101,458.00


G. Direct Unit Cost (E + F) 110,296.38
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 13,235.57
I. Contractor's Profit (CP) 8% of G 8,823.71
J. Value Added Tax (VAT) 5% of (G + H + I) 6,617.78
K. Total Unit Cost (G + H + I + J) 138,973.44
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : l.s.
Output per hour : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 31.00 66.06 2,047.86


b. Unskilled Laborer 1 31.00 50.86 1,576.66

Sub - Total for A 3,624.52

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 362.45

Sub - Total for B 362.45


C. Total (A + B) 3,986.97
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,986.97

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Manual Pull Switch set 4.00 1,250.00 5,000.00
c. Bell, Vibrating Type set 4.00 1,300.00 5,200.00

Sub - Total for F 24,090.00


G. Direct Unit Cost (E + F) 28,076.97
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,369.24
I. Contractor's Profit (CP) 8% of G 2,246.16
J. Value Added Tax (VAT) 5% of (G + H + I) 1,684.62
K. Total Unit Cost (G + H + I + J) 35,376.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(19) Conduit, Boxes, and Fittings


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 54.00 91.41 4,936.14


b. Skilled Laborer 1 91.00 66.06 6,011.46
c. Unskilled Laborer 1 91.00 50.86 4,628.26

Sub - Total for A 15,575.86

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,557.59

Sub - Total for B 1,557.59


C. Total (A + B) 17,133.45
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 17,133.45

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 20mmØ PVC conduit length 485.00 69.00 33,465.00


b. 25mmØ PVC conduit length 2.00 92.00 184.00
c. 32mmØ PVC conduit length 3.00 120.00 360.00
d. 65mmØ RSC conduit length 6.00 2,233.35 13,400.10
d. 90mmØ RSC conduit length 4.00 3,580.46 14,321.84
d. 90mmØ RSC elbow pc 2.00 2,348.15 4,696.30
d. 65mmØ RSC elbow pc 2.00 889.45 1,778.90
e. 20mmØ PVC adpater pc 675.00 8.00 5,400.00
f. 25mmØ PVC adapter pc 2.00 14.00 28.00
g. 32mmØ PVC adapter pc 4.00 16.00 64.00
h. 20mmØ locknut and bushing pr 675.00 8.00 5,400.00
j. 25mmØ locknut and bushing pr 4.00 14.00 56.00
j. 32mmØ locknut and bushing pr 2.00 16.00 32.00
k. 20mmØ liquidtight flexible metal conduit pc 3.00 20.00 60.00
l. 20mmØ connector m 2.00 10.00 20.00
m. Ulitiity box, deep type pc 115.00 30.00 3,450.00
n. junction box, deep type pc 155.00 31.00 4,805.00
o. 90mmØ entrance cap pc 1.00 684.00 684.00
p. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for F 90,605.14


Direct Unit Cost (E + F) 107,738.59
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 12,928.63
I. Contractor's Profit (CP) 8% of G 8,619.09
J. Value Added Tax (VAT) 5% of (G + H + I) 6,464.32
K. Total Unit Cost (G + H + I + J) 135,750.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(18) Wires and Wiring Devices


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 76.00 91.41 6,947.16


b. Skilled Laborer 1 96.00 66.06 6,341.76
c. Unskilled Laborer 1 96.00 50.86 4,882.56

Sub - Total for A 18,171.48

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 1,817.15

Sub - Total for B 1,817.15


C. Total (A + B) 19,988.63
D. Output = 1 l.s. .
E. Direct Unit Cost (C ÷ D) 19,988.63

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3.5mm2 THHN wire,stranded m 3000.00 23.00 69,000.00


b. 5.5mm2 THHN wire,stranded m 60.00 24.00 1,440.00
c.8.0mm2 THHN, wire, stranded m 12.00 65.00 780.00
c.22.0mm2 THHN, wire, stranded m 8.00 156.00 1,248.00
c.100.0mm2 THHN, wire, stranded m 24.00 691.00 16,584.00
c.200.0mm2 THHN, wire, stranded m 36.00 1,336.00 48,096.00
d.2.0mm2 TW wire, stranded m 300.00 24.00 7,200.00
e. 3.5mm2 TW wire, stranded m 1500.00 23.00 34,500.00
f.5.5mm2 TW wire stranded m 30.00 24.00 720.00
g.8.0mm2 TW wire stranded m 27.00 65.00 1,755.00
g.30.0mm2 TW wire stranded m 12.00 210.00 2,520.00
h. one gang switch set 21.00 92.00 1,932.00
i. two gang switch set 16.00 126.00 2,016.00
j. three way switch set 4.00 145.00 580.00
j. 2- gang ,three way switch set 8.00 175.00 1,400.00
k. Duplex C.O. grounding type, 15A, 250V set 24.00 330.00 7,920.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 6.00 420.00 2,520.00
-
m. KWHR meter set 1.00 2,200.00 2,200.00
n. Tape, bolt&nut, mica tube, terminal lugs, JB lot 1.00 10,120.55 10,120.55
cover clamps, screw and anchors -
Sub - Total for F 212,531.55
G. Direct Unit Cost (E + F) 232,520.18
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 27,902.42
I. Contractor's Profit (CP) 8% of G 18,601.61
J. Value Added Tax (VAT) 5% of (G + H + I) 13,951.21
K. Total Unit Cost (G + H + I + J) 292,975.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(21) Power Load Center, Switchgear, and Panel Boards
Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 15.00 91.41 1,371.15


b. Skilled Laborer 1 15.00 66.06 990.90
c. Unskilled Laborer 2 15.00 50.86 1,525.80

Sub - Total for A 3,887.85

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 388.79

Sub - Total for B 388.79


C. Total (A + B) 4,276.64
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 4,276.64

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MDP set 1.00 40,718.60 40,718.60


Main: 500at, 600af, 3p, 240v, 42 KAIC
Br.: 1-70AT, 100AF, 2P, 240V
2 - 50at, 100af, 2p, 240v
1 - 60at, 100af, 2p, 240v
1 - 400at, 400af, 3p, 240v

a. LPA set 1.00 16,343.60 16,343.60


Main: 70at, 2p(lugs only)
Br.: 5 - 15at, 50af, 2p, 240v
8 - 20at, 50af, 2p, 240v
1 - 30at, 50af, 2p, 240v

a. LPB set 1.00 16,681.60 16,681.60


Main: 50at, 50af, 2p, 240v, 10KAIC
Br.: 5 - 15at, 50af, 2p, 240v
7 - 20at, 50af, 2p, 240v

FPP set 1.00 46,597.20 46,597.20


Main:400AT,400AF,,240V, 22KAIC, 3p
Br.: 3 - 40at, 100af, 2p
1 - 40at, 100af, 3p
1 - 400at, 400af, 3p

Automatic Transfer Switch (ATS) set 1.00 128,000.00 128,000.00


Main:500AT, 600 AF, 3P, 240V, 42 KAIC
in NEMA 2r Closure
40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00

Sub - Total for F 251,941.00


G. Direct Unit Cost (E + F) 256,217.64
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 30,746.12
I. Contractor's Profit (CP) 8% of G 20,497.41
J. Value Added Tax (VAT) 5% of (G + H + I) 15,373.06
K. Total Unit Cost (G + H + I + J) 322,834.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 36.00 91.41 3,290.76


b. Skilled Laborer 1 36.00 66.06 2,378.16
c. Unskilled Laborer 2 36.00 50.86 3,661.92

Sub - Total for A 9,330.84

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 933.08

Sub - Total for B 933.08


C. Total (A + B) 10,263.92
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 10,263.92

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 x 36 watts FL fixture, box type set 24.00 723.00 17,352.00


b. 2 x 36 watts FL fixture box type w/ canopy base set 48.00 1,173.00 56,304.00
and stem 0.00
c. 1 x 36 watts FL fixture box type. set 42.00 381.00 16,002.00
d. 1 - 18 watts CFL w/ medium base keyless type set 5.00 320.00 1,600.00
porcelain
e. wall fanreceptacle
w/ control switch set 24.00 1,200.00 28,800.00

Sub - Total for F 120,058.00


G. Direct Unit Cost (E + F) 130,321.92
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 15,638.63
I. Contractor's Profit (CP) 8% of G 10,425.75
J. Value Added Tax (VAT) 5% of (G + H + I) 7,819.32
K. Total Unit Cost (G + H + I + J) 164,205.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 31.00 66.06 2,047.86


b. Unskilled Laborer 1 31.00 50.86 1,576.66

Sub - Total for A 3,624.52

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost) 362.45

Sub - Total for B 362.45


C. Total (A + B) 3,986.97
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D) 3,986.97

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Alarm Control Panel set 1.00 13,890.00 13,890.00


b. Manual Pull Switch set 4.00 1,250.00 5,000.00
c. Bell, Vibrating Type set 4.00 1,300.00 5,200.00

Sub - Total for F 24,090.00


G. Direct Unit Cost (E + F) 28,076.97
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 3,369.24
I. Contractor's Profit (CP) 8% of G 2,246.16
J. Value Added Tax (VAT) 5% of (G + H + I) 1,684.62
K. Total Unit Cost (G + H + I + J) 35,376.98