Professional Documents
Culture Documents
Paper - NEW METHOD FOR IN-SERVICE PARTIAL DISCHARGE MEASUREMENT ON SOLID DIELECTRIC SWITCH
Paper - NEW METHOD FOR IN-SERVICE PARTIAL DISCHARGE MEASUREMENT ON SOLID DIELECTRIC SWITCH
Paper - NEW METHOD FOR IN-SERVICE PARTIAL DISCHARGE MEASUREMENT ON SOLID DIELECTRIC SWITCH
Paper 1436
INTRODUCTION
The term “partial discharge” is defined by IEC 60270 as a
localized electrical discharge that only partially bridges
the insulation between conductors and which may or may
not occur adjacent to a conductor [1]. PD can result from
a number of different sources; breakdown of gas in
cavity, breakdown along the interface, breakdown
between energized electrode and a floating conductor, to
name the few [2]. In the SD insulation, among the most Fig. 1: Physical phenomena of PD occurrence
common sources of PD are cavities – sometimes called
“voids” [3]. There are many diagnostic techniques • Electrical (THV - transient high voltage, TEF – transient
available today for the condition assessment of medium electrical field, CP – current pulse, TEV – transient earth
voltage (MV) switchgear, able to find voids [4], [5], [6]. voltage, TEM – transient electromagnetic, RF – radio
frequency wave).
Unfortunately, in many cases these techniques are
• Acoustical (acoustic wave)
intrusive since they require scheduled outages as the • Optical (UV and IR radiation)
switchgear must be isolated of the network. Also, • Chemical (decomposition of the material).
utilizing these diagnostic techniques on outdoor MV
equipment is very limited. Taking into account that the
MV switchgear designs are rapidly moving from SF6 After qualitative comparison of benefits and limitations
insulation to SD insulation, the importance of applying (Table 1) and considering characteristics of a test object -
condition assessment methods on SD equipment in the MV switch with solid epoxy polymer system insulation -
field is increasing. This subject is currently being the Authors selected electrical methods for further
investigated by joint CIGRE/CIRED A3.32 working investigation.
group “Non-intrusive methods for condition assessment
CIRED2015 1/5
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1436
CIRED2015 2/5
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1436
sandwiched between two conductors. The insulation has As it can be seen in Table 2, PD sensors 5-8 have very
an internal void (as showed in Figure 5) and in presence low sensitivity coefficient. Thus, they were eliminated
of High Voltage, PD is generated inside of the insulation from further consideration.
void. Two tests were conducted: In the first one, PD On the contrary, PD sensors 1 (upper external conductive
spark was applied on the HV contacts (Position A), and foil) and 4 (source side internal capacitive sensor) have
in the second test, PD spark was applied on the surface of even higher sensitivity than 1(C) standard measurement
the solid dielectric epoxy module (Position B). PD was (S1(foil)>1, S4(VDC)>1). This suggests that the transient
measured using IEC 60270 standard and using alternative voltage is better coupled with alternative PD sensors 1
PD sensors, as depicted in Figure 4. Results of this test and 4 than the standard PD measurement 1(C).
are presented in Table 2 below. Relative sensitivity Lastly, PD sensors 2 (bottom external conductive foil)
measurement (Sensitivity coefficient - Si) was derived by and 3 (load side internal capacitive sensor) have
comparison of PD values between alternate PD sensors sensitivity index Si is below 1, but still reasonably
and PD measurement described by IEC 60270 attenuated.
(measuring point 1C). Based on these results, authors decided to continue
testing of PD sensors 1-4. Next, the PD test was
conducted on the fully assembled 3 phase SD switch in
the High Voltage lab with low background noise. Two
phases assembled on the SD switch were in “good
condition” – they’ve had PD readings within
manufacturer’s limits. Third phase was purposely
selected with high PD readings as a controlled sample in
order to verify the accuracy of measurement.
CIRED2015 3/5
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1436
1 (foil)
2 (foil)
3 (VDC)
4 (VDC)
Fig. 7: PD pattern of Phase 1 and 3 (standardized and
additional measurements).
Table 4: PD pattern of Phase 1 and 3 (standardized and First the background noise was measured on each phase
additional measurements). prior to installation of SD switch. Results are reported in
Table 6. Then SD switch was installed and the test was
Table 4 summarizes results on Phase 1 (module with high repeated in two configurations: A) without the gating
PD levels) and Phase 3 (module with acceptable PD principle B) with gating principle. Results are reported in
levels). It can be seen that in the lab with the low Table 7.
background noise PD sensors 1-4 closely replicated
results from the reference PD test. Although the lab had a
low background noise, a crosstalk noise was generated by
Phase 1 and received on Phase 2 (in nC range) and Phase
3 (hundreds of pC). A principle of coincidence (or gating
concept) [1], was used to eliminate the noise.
IN-SERVICE TESTING
CIRED2015 4/5
23rdInternational Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1436
CIRED2015 5/5