Professional Documents
Culture Documents
Deeti Math
Deeti Math
2 D(4) 3
A(3)
H(2)
E(4) I(5)
1 4 6
B(2) 8 K(3) 9
F(7)
C(2)
5 6 J(6)
G(4)
Solution: To determine earliest start time, Ej and latest finish time, Lj for each time, proceed as
follows:
E1= 0
E4=E1+t1,4 =0+2= 2
=max{2+7, 2+4}=9
=max{11+3, 9+6}=15
L9= l9= 15
=min[9-7 ; 7-4} = 2
3 7
6 10
D(4)
2 3
0 11 15
0 A(3) 6
2 H(2) 12 15
7
2 E(4)
1 4 7 I(5)
B(2) 8 K(3) 9
F(7)
C(2)
5 6 J(6)
G(4)
2 9
5 9
The critical path shown by double lines in the network is the longest time path throughout the
network or path B-F-J, where E-values are equal to the L-values. Thus, there is no spare (slack)
time and the events must be completed exactly as scheduled to meet completion time of 15(2+7+6)
days.
Draw a network of the following activities and tabulate earliest and latest starting and finishing
times of each activity and the total and free floats of them:
Solution: The graphical representation of network and time schedule is shown below:
16
16
6 4
6 38
C(10) 58
E(10)
3
0 6 80
62
0 B(4) D(4) J(4) 62 86
A(2)
A(2) M(12)
F(5) L(6)
1 2 5 8 9 10
G(36)
26 I(12) 68
2
26 7 K(3) 68
2
38
54
The critical path is: A-B-C-E-G-L-M