The document provides a cost estimate for proposed reconstruction of 20 hume pipe culverts along a road in Mawmaram Nongthliew Mawmih Mawlyndep. The estimate includes 8 items related to excavation, concrete work, stone pitching, filter material, and laying 1200mm diameter RCC pipes. The total estimated cost is Rs. 78,80,427.
The document provides a cost estimate for proposed reconstruction of 20 hume pipe culverts along a road in Mawmaram Nongthliew Mawmih Mawlyndep. The estimate includes 8 items related to excavation, concrete work, stone pitching, filter material, and laying 1200mm diameter RCC pipes. The total estimated cost is Rs. 78,80,427.
The document provides a cost estimate for proposed reconstruction of 20 hume pipe culverts along a road in Mawmaram Nongthliew Mawmih Mawlyndep. The estimate includes 8 items related to excavation, concrete work, stone pitching, filter material, and laying 1200mm diameter RCC pipes. The total estimated cost is Rs. 78,80,427.
Upgradation of Mawmaram Nongthliew Mawmih Mawlyndep Road (Km 0+000 to Km 41+527)
Cost Estimate for Proposed Hume Pipe Culverts (Reconstruction)
(1 Row 1200 mm with 12 m Width) - 20 Nos. Sr. Item No. of Total Rate Amount Description Nos. Length Width Depth Quantity Unit No. No. Str. Quantity (Rs.) (Rs.) 1. 46.30 Removing Np2 and Np3 class pipes including stacking at road side as directed by the Engineer in charge. Upto 900mm dia. etc. complete. 1 10.00 10.00 20 200.00 metre 150.00 30000 2. 46.31 Removing Np2 and Np3 class pipes including stacking at road side as directed by the Engineer in charge. 900mm dia. and above. etc. complete. 0 0.00 0.00 20 0.00 metre 175.00 0 3. 12.02 Excavation for foundation by mechanical means in earth, soils of all types, sand, gravel, soft murum including shoring and strutting as necessary and disposing off excavated stuff as directed etc. complete.
Head walls 2 6.50 1.50 1.10 21.45
Pipe 1 1.85 11.78 0.52 11.33 Stone pitching for Apron on u/s side 1 2.16 1.50 0.64 2.06 Stone pitching for Apron on d/s side 1 3.61 3.00 0.64 6.88 Sub Total 41.72 20 834.36 cum 103.00 85939 4. 24.04 Providing and casting in situ cement concrete in M15 of trap/ granite/quartzite/gneiss metal for steps including steel centering, plywood/steel formwork, compacting, roughening them if special finish is to be provided, finishing uneven and honeycombed s
Below Head walls 2 6.50 1.50 0.15 2.93
Below Pipe 1 1.85 12.38 0.52 11.91 Sub Total 14.83 20 296.69 cum 4588.00 1361219 5. 24.06 Providing and casting in situ cement concrete in M20of trap/ granite/quartzite/gneiss metal for steps including steel centering, plywood/steel formwork, compacting, roughening them if special finish is to be provided, finishing uneven and honeycombed su
Head walls 2 6.40 0.88 2.99 33.43
Deduction for Pipe 2 1.45 0.88 1.14 2.89 Parapet Walls 2 6.40 0.40 1.00 5.12 Sub Total 35.66 20 713.24 cum 5729.00 4086178 6. 15.79 Providing and laying pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and technical specifications etc. complete. (by stone/boulder) For Apron on u/s side 1 2.16 1.50 0.30 0.97 For Apron on d/s side 1 3.61 3.00 0.30 3.25 For Slopes 4 2.30 1.15 0.67 7.06 Sub Total 11.29 20 225.72 cum 1134.00 255967 7. 15.83 Providing and laying filter material underneath pitching in slopes as per drawings and technical specifications etc. complete. For Apron on u/s side 1 2.16 1.50 0.15 0.49 For Apron on d/s side 1 3.61 3.00 0.15 1.63 For Slopes 4 2.30 1.15 0.15 1.59 Sub Total 3.70 20 73.98 cum 1421.00 105124 8. 11.21 Providing and laying cement concrete pipe of IS 458:2003 NP 4 class of 1200mm diameter in proper line, level and slope including providing and fixing collars in cement mortar 1:2 and curing etc. complete. 24/269 RCC Pipe Np4 heavy duty non presure pipe 1 10.00 10.00 20 200.00 metre 9780.00 1956000 TOTAL 7880427
Intermediate Lane Highway (Re-Construction/New Construction Section) (Open Country & Isoiated Built-Up Aera:Plane/Rolling Terrain) (Modified Figure 2.3 of IRC:SP:73:2015)