Contractor Logo

Project name: Example Project


Project location: Example Location

Daily progress report


Report Date: 11/August/2020

I- Performance follow up:

Daily executed work


Total Planned work Actual work Daily deviation Cumulative
Sr. Area Item Description UOM Comments
Qty for today for today % Actual Qty

1 Block 9 Pile Marking No. 500 100 90 90% 320


2 Block 12 Ramming No. 1 0.5 0.15 30% 0.15
3 Block 9 Pile drilling No. 0%
4 Block 9 Pile Concreting No. 0%

Planned work for next working day


Cumulative Cumulative Planned work
Sr. Area Item Description UOM Total Qty Actual Qty Remaining Qty Actual % for next day Comments

1 Block 9 Pile Marking M 500 320 180 64% 60


2 Block 12 Ramming LS 1 0.15 0.85 15.00% 0.5
3 Block 9 Pile drilling 0%
4 Block 9 Pile Concreting 0%
Contractor Logo

Project name: Example Project


Project location: Example Location

Daily progress report


Report Date: 11/August/2020

II- Manpower and Machinery count:

Indirect manpower Count Sr. Equipment Count


Management 1 Ramming machine 3
1 Project Manager 1 2 Drilling Machine 2
2 Construction Manager 1 3 Telehandler 1
Site supervision

Machinery
3 Civil Engineer 1
4 Electrical Engineer 1
5 Mechanical Engineer 1
Project control
6 Planning Specialist
Quality control
Manpower

7 Quality Engineer 1
Testing and commissioning
8 T&C Engineer 1
Health, safety and environment Total Machinery count 6
9 HSE Manager 1
10 HSE Officer 1
Others
11 Logistics Coordinator 1
12 Store Keeper 1
13 Document Controller 1
14 Admin Officer 1
Total Indirect manpower 13

Direct manpower
Skilled Labors 10
General Labors 50
Total direct manpower 60

Manpower Distribution
Tracker Module Cable Equipment
Area Marking Ramming Drilling Pile Concrete Installation Installaion Cables Laying Termination Intallation
Skilled Labors
General Labors
Overall 0 0 0 0 0 0 0 0 0 0 0
Contractor Logo

Project name: Example Project


Project location: Example Location

Daily progress report


Report Date: 11/August/2020

II- Site Progress Pictures