ACLAN, DEREK JOHN JAIME P.

1804578
1.

ESTIMATED TRIP ACTUAL TRIP


ZONE GROWTH FACTOR
GENERATION GENERATION
A 693 720 1.04
B 800 770 0.96
C 943 980 1.04
D 554 520 0.94

𝐸𝑋𝑃𝐸𝐶𝑇𝐸𝐷 𝑇𝑅𝐼𝑃 𝐺𝐸𝑁𝐸𝑅𝐴𝑇𝐼𝑂𝑁


𝐺𝑅𝑂𝑊𝑇𝐻 𝐹𝐴𝐶𝑇𝑂𝑅 =
𝑇𝐻𝐸 𝑇𝑅𝐼𝑃 𝐺𝐸𝑁𝐸𝑅𝐴𝑇𝐼𝑂𝑁 𝐼𝑁 𝑃𝑅𝐸𝐶𝐸𝐸𝐷𝐼𝑁𝐺 𝐶𝐴𝐿𝐶𝑈𝐿𝐴𝑇𝐼𝑂𝑁 𝑂𝑅 𝐼𝑇𝐸𝑅𝐴𝑇𝐼𝑂𝑁

EXPECTED TRIP GENERATION FOR SECOND ITERATION

FOR ZONE A = GROWTH FACTOR FOR A x EXPECTED TRIP IN THE FIRST ITERATION

= 1.04 x 693

= 720.72

FOR ZONE B = GROWTH FACTOR FOR A x EXPECTED TRIP IN THE FIRST ITERATION

= 0.96 x 800

= 768

FOR ZONE C = GROWTH FACTOR FOR A x EXPECTED TRIP IN THE FIRST


ITERATION

= 1.04 x 943

= 980.72

FOR ZONE D = GROWTH FACTOR FOR A x EXPECTED TRIP IN THE FIRST


ITERATION

= 0.94 x 554

= 520.76

Hence, it can be easily seen that the estimated trip generation on second iteration is closer to
actual trip generation.
2. ADJUSTED VALUES:
300
ZONE 1: A12 = 300 𝑋 379
= 237

270
ZONE 2: A22 = 270 𝑋 210
= 347

180
ZONE 3: A32 = 180 𝑋 161
= 201

ZONE 1 2 3 COMPUTED GIVEN P


P
1 34 68 38 140 140
2 153 112 65 330 330
3 116 88 76 280 280
COMPUTED 303 268 179 750 750
A
GIVEN A 300 270 180 750

𝐴𝑗 𝐹𝑖𝑗 𝐾𝑖𝑗
𝑇𝑖𝑗 = 𝑃𝑖 [ ]
∑𝑗 𝐴𝑗 𝐹𝑖𝑗 𝐾𝑖𝑗

Perform a second iteration using the adjusted attraction values.


237 𝑥 39
𝑇1−1 = 140 𝑥 = 𝟑𝟒
(237 𝑥 39) + (347 𝑥 52) + (201 𝑥 50)

347 𝑥 52
𝑇1−2 = 140 𝑥 = 𝟔𝟖
(237 𝑥 39) + (347 𝑥 52) + (201 𝑥 50)

201 𝑥 50
𝑇1−3 = 140 𝑋 = 𝟑𝟖
(237 𝑥 39) + (347 𝑥 52) + (201 𝑥 50)

P1 = 140

Make a similar calculation for zone 2 and zone 3:

T2- 1 = 153 T2- 2 = 112 T2- 3 = 65 P2 = 330

T3- 1 = 116 T3- 2 = 88 T3- 3 = 76 P3 = 280

The sum of the attractions is now much closer to the given value. The process will be continued until
there is a reasonable agreement (within 5%) between the A that is estimated using the gravity model and
the values that are furnished in the trip generation phase.