Reduce level of the ground along the centerline of the proposed road from chainage 1 to 9 are given below.

The formation level at 0 th


chainage is 53m and road is in downward, formation width of road is 12m and side slope of bank is 2:1. length of chain is 40m. draw
longitudnal section of the road .
assume fall in slope of road is to be 1 in 100
Also calculate quantity of earthwork ?

chainage length R.L.(ground) R.L.(formation) chainage slope


1 40 50 54.000 20-25 1 100
2 80 50.3 53.600 25-30 1 100
3 120 50.8 53.200
4 160 50.2 52.800 B 12
4 200 48.5 52.800
Assignment 2 S
5 240 48 52.400
6
7
280
320
48.2
48.1
52.000
51.600
Submission Date: 21-05-2014
8 360 48.2 51.200
9 400 48.25 50.800